I-EARTHWORKS
1. Excavation
a. Columns and Column Footing
1#
(2m x 2m)(3m)= 12 cu.m/CF
12 cu.m x 24 column footings= 228cu.m
2#
(1.5m x 1.5m)(3m)= 6.75 cu.m/CF
6.75 cu.m x 6 column footings= 40.5 cu.m
3#
(2m x 2m)(3m)= 12 cu.m/CF
12 cu.m x 2 column footings= 24cu.m
b. Wall Footing
Total Perimeter - Size of Column Footing= 121.80m
V= 121.80m (0.40m)(0.80m)
Vt= 38.976 cu.m
c. Footing Tie-Beam
Total Perimeter - Size of Column Footing= 188.364m
V= 188.364m (0.30m)(1.5m)
Vt= 84.76 cu.m
Volume Excavation:
416.236 cu.m
2. Backfill
a. Columns and Column Footing
1#
(2m x 2m)(.35m)= 1.4 cu.m/CF
1.4 cu.m x 24 column footings= 33.6cu.m
(1m x 0.50m)(2.5m) = 1.25cu.m
1.25cu.m x 23 = 30 cu. m
2#
(1.5m x 1.5m)(.35m)= 0.785cu.m/CF
0.785 cu.m x 6 column footings= 4.71cu.m
(0.80m x 0.40m)(2.5m) = 0.80cu.m
0.80cu.m x 6 = 4.8 cu. m
3#
(2m x 2m)(.35m)= 1.4 cu.m/CF
1.4 cu.m x 2 column footings= 2.80cu.m
(0.80m x 0.50m)(2.5m) = 1cu.m
Detailed Estimate Take-of
1cu.m x 2 = 2 cu. m
Vt = 77.91cu.m
b. Wall Footing
Wall depth: 3xCHB = 0.6m
x0.15 = 9cu.m
Total Perimeter - Size of Column Footing= 121.80m
V= 121.80m (0.40m)(0.20m)
Vt= 9.774 cu.m
c. Footing Tie-beam
Total Perimeter - Size of Column Footing= 188.364m
V= 188.364m (0.3m)(0.45m)
Vt= 9.774 cu.m
Backfill:
(416.236 - 113.11 )(1.25)= 378.9 cu. m.
378.9 cu. m.
3. Earth Fill:
4. Gravel Fill:
560m(0.10m) = 56 cu m. 56 cu.m .
5. Soil Poisoning
Area=850 sq.m.
850(2)/70 = 24.285 say 25L
SUMMARY OF MATERIALS
Description Quantity
Backfill 378.9 cu.m.
Earth Fill 84 cu. m.
Gravel Fill 56 cu. m.
Detailed Estimate Take-of
II- FORMWORKS AND SCAFFOLDING
A. Formworks
1. Column
P= 2(a+b) + 0.20
where:
P= Lateral Perimeter
a= Shorter side of the column
b= Longer side of the column
0.20= Constant value for the lapping of form joint
#1
P= 2(1m + 0.50m) + 0.20
P= 3.20m
A= 3.20m x 18.05 m. x 24
A= 1386.24 sq. m.
No.of Plywood: 1386.24= 481.33 482 pcs 1/2" 4' x 8' plywood
2.88
Wood Frame:
482 x 29.67= 14300.94 14301 bd.f 2" x 2" CCL
#2
P= 2(0.80 m + 0.40m) + 0.20
P= 2.60m
A= 2.60 m x 18.05 m. x 6
A= 281.58 sq. m.
Wood Frame:
98 x 29.67= 2907.66 2908 bd.f 2" x 2" CCL
#3
P= 2(0.80 m + 0.50m) + 0.20
P= 2.80m
A= 2.80 m x 18.05 m. x 2
A= 101.08 sq. m.
No.of Plywood: 101.08 35.09 say 36 pcs 1/2" 4' x 8' plywood
2.88
Detailed Estimate Take-of
Wood Frame:
36 x 29.67= 1068.12 1069 bd.f 2" x 2" CCL
2. Beam
P= 2(d) + b +0.10
where:
P= Perimeter of two sides form
d= 2 sides form
b= the bottom form
0.10= constant value for the lapping of forms
#1
P= 2(0.3 + 0.45) + 0.10
P= 1.60m
A= 1.60m x 191.664 m x 3
A= 920 sq.m
Wood Frame:
320 x 25.06= 820 bd ft. 2" x 2" CCL
#2
P= 2(0.25 + 0.40) + 0.10
P=1.40 m
A= 1.40m x 191.664 m x 3
A= 805 sq.m
Wood Frame:
280 x 25.06= 7017 bd ft. 2" x 2" CCL
3. Floor Slab
Detailed Estimate Take-of
4. Roof Slab
Area=560 sq m
560 = 194.44 pcs. 195 pcs. 4' x 8' marine plywood
2.88
5. Stairs
Area= 38.91 sq m
38.91= 13.5 pcs. 14 pcs. 4' x 8' plywood
2.88
B. Scaffoldings
1. Beam
P= 191.664 x 5 = 958.32
2. Column
Total length = 18.05 m x 32 = 577.6
4. Roof Slab
Area= 560 sq m
560 x 9.10= 5096 bd ft. (2" x 3" CCL)
5096 x 2= 10,192 bd ft. (2" x 3" CCL)
SUMMARY OF MATERIALS
Description Quantity
1/2" 4' x 8' plywood 1230 pcs
2" x 2" CCL 6758 bd ft.
2" x 3" CCL 78165 bd. Ft
2" x 4" CCL 16174 bd. Ft
marine plywood 1168 pcs
a. Column Footing
#1 & #3
(2m x 2m)(0.35m)= 1.4 cu.m/CF
1.4 cu.m x 26 column footings= 36.4 cu.m
#2
(1.50m x 1.50m)(0.35m)= 1.4 cu.m/CF
0.7875 cu.m x 6 column footings= 4.725 cu.m
Class 'A' Concrete Mixture
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 41.125 9 370.125
Sand 41.125 0.5 20.5625
Gravel 41.125 1 41.125
b. Columns
#1
Detailed Estimate Take-of
(1m x 0.50m)(18.05m X 24)=216.60 cu.m
216.60 cu.m
#2
(0.8m x 0.40m)(18.05m x 6)=34.656cu.m
34.656 cu.m
#3
(0.8m x 0.50m)(18.05m x 2)=14.44cu.m
14.44 cu.m
Class 'A' Concrete Mixture
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 265.7 9 2391.3
Sand 265.7 0.5 132.85
Gravel 265.7 1 265.7
c. Wall Footing
V=121.80m (0.40m)(0.20m)
V= 9.744 cu.m
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 9.744 9 87.696
Sand 9.744 0.5 4.872
Gravel 9.744 1 9.744
d. Beams
(0.30m x 0.45m)(191.664m x 3)= 75.21 cu.m
(0.25m x 0.40m)(191.664m x 3) = 57.5 cu. M
Class 'A' Concrete Mixture
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 132.71 9 1194.39
Sand 132.71 0.5 66.355
Gravel 132.71 1 132.71
g. Roofing Slab
Area= 560 sq.m
560 x 0.10m= 56 cu.m
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 448 9 4032
Sand 448 0.5 224
Gravel 448 1 448
g. Stairs
Volume= 21.3 cu m
Cement in Bags
Description Volume Quantity
Sand/Gravel in cu.m
Cement 21.3 9 191.7
Sand 21.3 0.5 10.65
Gravel 21.3 1 21.3
SUMMARY OF MATERIALS
Description Quantity
Cement 8,213 bags
Sand 458 cu. m.
Gravel 916 cu. m.
a. CHB Wall
Total Area= 1948.8 sq m
for vertical
1948.8 x 1.60= 3116.92
for horizontal
Detailed Estimate Take-of
1459.90 x 2.15= 4188.37
total length= 3116.92 + 4188.37
total length= 7305.23
b. Column Footing
#1 
Total Length per Footing = 40m
40 x 26 column footings =1040 m
#2
Total Length per Footing = 21m
21 x 6 column footings =126 m
c. Wall Footing
Total length of perimeter wall= 121.8
No. of Traverse bar per 6.00 full-length bar= 9 pcs
No. of Full length bars required=
121.8 = 46 pcs. 16mm x 6.0m
0.30 x 9
Longitudinal Bars=
No. of Full length bars required=
121.8 (6) (1.20)= 146.16 147 pcs.
6 16mm x 6.0m
use 5kg GI Tie Wire
d. Column (vertical bars)
Detailed Estimate Take-of
Total length of Main Steel Reinforcement
a. Bend at the base footing
b. Length from footing to ground floor
c. Total Height =15.5[6(6)+10(24)+6(2)]
288
5241.6/12 = 434 pcs 32mm x 12.00m
f. Beam
p= 958.32
(4 pcs 16mm x 12.0m)
3833.28/12 = 320 pcs @ 25mm x 12.00m
g. Beam (Stirrups)
no. of stirrups= L(0.30 +1)
no. of stirrups= 958.32m(0.30+1)
no.of stirrups= 1245.82 1246 pcs
4 pcs stirrups in 6.00m
1246/6= 208 pcs @ 16mm x 6.00m
h. Slab
Area= 2800 sq.m
2800 x 3.764= 10595.42 pcs 10,596 pcs 12mm x 6.00m
i. Roofing Slab
Area= 560 sq.m
560 x 2.36= 1321.6 pcs 1322 pcs 12mm x 6.00m
j. Stairs
1(1)(18) = 100m bend bars
0.18
SUMMARY OF MATERIALS
Description Quantity
10mm dia. Reinforcement bars L=6 1218pcs
12mm dia. Reinforcement bars L=6 12128pcs
16mm dia. Reinforcement bars L=6 208pcs
25 mm dia. Reinforcement bars L=12 2371 pcs
28 mm dia. Reinforcement bars L=12 98pcs
Detailed Estimate Take-of
32 mm dia. Reinforcement bars L=12 434pcs
#16 GI Tie Wire 1027kg
V- MASONRY
Cement in Bags
Description Area Quantity
Sand/ in cu.m
Cement 1948.8 2.26 4404.288
Sand 1948.8 0.125 243.6
Cement in Bags
Description Area Quantity
Sand/ in cu.m
Cement 3897.6 0.9 3507.84
Sand 3897.6 0.05 194.88
VI ARCHITECTURAL WORKS
Wall Finish:
300 x 300mm Homogeneous Tiles:
Perimeter x 1.5 = Area
8.38 x 1.5 = 12.57
12.57 x 4 x 5 = 251.40 sq m
Ficem Board:
57.884(13.33 - 0.2 - 0.2 - 0.15 - 0.1) = 733.969 sq m
733.969 / 2.88 = 254.8503 pcs say 255 ficem board
Metal Studs:
@ 0.4m grid
733.969 / (0.4 x 0.4) = 4,587.3062
4587.3062 x 2 (0.4) = 3669.845
3669.845 / 3 = 1223.28 pcs say 1224 pcs
Metal Track:
1223.28 x 0.454 = 555.3691 pcs say 556 pcs
Floor Finish
600 x 600 mm Homogeneous tiles
Area= 1202.25 sq m
1202.25 / (0.6 x 0.6) = 3340pcs
Cement in Bags
Description Area Quantity
Sand/ in cu.m
Cement 253.48 0.45 114.066 115
Sand 253.48 0.025 6.337 7 cu.m
Gypsum Board
144.5/2.88 = 51 pcs
Painting Works
Wall Area for Painting = 1948.8 x 2 = 3897.6 sq m.
for neutralizer : 3897.6 / (30x2.5) = 51.92 quarts = 13 gal
for primer: 3897.6 / 30 = 129.92 gal
for final coating: 130 gal
Detailed Estimate Take-of
Ceiling Area for Painting = 253.48 + 151.28 + 28.96 + 0.3(471.852) = 575.276
gypsum putty = 15
for primer: 575.276/30 = 19. 17 say 20 gal
for final coating: 20 gal
Metal Paint:
Area = [4(0.05 x 6 x 4) + 13(0.05 x 6 x 2)]5 = 63 sq m
for epoxy primer: 63 / 30 = 2.1 say 3 gal
for quick dry enamel: 3 gal
Detailed Estimate Take-of
Detailed Estimate Take-of
Detailed Estimate Take-of
Quantity
370.125
20.5625
41.125
Detailed Estimate Take-of
Quantity
2391.3
132.85
265.7
Quantity
87.696
4.872
9.744
Quantity
1194.39
66.355
132.71
Detailed Estimate Take-of
Quantity
4032
224
448
Quantity
191.7
10.65
21.3
Detailed Estimate Take-of
m x 12.00m
16mm x 6.0m
0.2 (288)
2.5(288)
4464
5241.6m
Quantity
4404.288
243.6
Quantity
3507.84
194.88
Detailed Estimate Take-of
Quantity
2.025
0.1125
Detailed Estimate Take-of
Quantity
114.066 115 bags
6.337 7 cu.m