Académique Documents
Professionnel Documents
Culture Documents
REPORT
MCA-I Deliverable Review for
3rd Deliverable, R. 3.5 Detail Improvement of Project
Development
PT. Selo Kencana Energi
i
1. Executive Summary
PROJECT DETAILS
Project Name: Lubuk Gadang Hydro Power Plant
Proposal Number: W3B1-17
Grant Agreement Number: 2015/Grant /015
Grantee Name: PT. Selo Kencana Energi
Project Location: Sangir, West Sumatera
Project Phase: TAPP of Full Grant
TECHNICAL REVIEW SUMMARY/ RECOMMENDATION
Portfolio Lead Name: Gina Veronese
Date Received from GAST: 5 June 2017
Date Submitted to GAST: 14 June 2017
Deliverable Reviewed: 3rd Deliverable R3.5
Deliverable Quality Assessment Strengths, Weaknesses, Gaps and Risks:
1. Several errors that were identified in previous submittals regarding the slope
stabilization calculations and design have not been addressed in this submittal. Please
provide corrections to the slope stabilization analysis which, at a minimum address
the following:
a. Please review and revise the soil parameters used throughout the slope
stability calculations. The following errors and inconsistencies were identified
for the selected soil parameters in the slope and soil nail/shotcrete retaining
wall stability calculations:
i. Silt layers have been labelled as cohesive soil and have been assigned
cohesion values ranging from 31 to 56 kN/m2. Generally, silt does not
have cohesive strength for drained conditions. It is erroneous to
consider any cohesion from silt soils.
ii. Soil properties are not consistent between calculations. For example,
the unit weight of the soil used for the sliding stability analysis, on
page 28 (19.43 kN/m3) is different than the unit weight of the soil used
to calculate the maximum tension in the soil nail, on page 32 (18.39
kN/m3).
b. Drawings for the proposed shotcrete/soil nail wall are not complete. Please
provide, at a minimum, the following:
1
v. Details for drainage discharge for geocomposite strip drain behind
wall.
c. Please perform a global slope stability analysis for the proposed slope
protection under normal loading conditions.
e. It appears that the maximum tensile force at the wall facing (Tmax) has been
calculated incorrectly. The following errors were identified:
iii. Tmax has been calculated irrespective of tributary area around the soil
nails. Per FHWA, Tensile forces may be estimatedconsidering an
influence area around individual nails.
3. The following errors and technical gaps were identified on the submitted drawings:
b. Please provide match lines for all drawings which span more than one page.
This comment applies to all drawings.
2
h. Please include a north arrow on all applicable drawings. North arrows were
not found on MHPP-LBG-02-001, MHPP-LBG-05-001 through MHPP-LBG-05-
002, MHPP-LBG-07-001 through MHPP-LBG-07-004, MHPP-LBG-08-001,
MHPP-LBG-08-002, MHPP-LBG-08-004, MHPP-LBG-08-005, and MHPP-LBG-
08-008.
i. Please provide labels for all major features. This comment applies to all
drawings.
5. Cross-section at station 0+600 and similar sections show a steep slope adjacent to the
river normalization and proposed gabion wall. Please provide information regarding
excavation of slope adjacent to the proposed improvements. Please evaluate slope
stability and design of drainage structure for imposed loading from slope.
6. Please clarify how the earthquake seismic coefficient was calculated for the river
normalization and retaining wall analyses. The kh coefficient is not consistent with the
seismic coefficients presented in the 2nd deliverable, 3rd deliverable report submitted
on 20 March 2017, and the retaining wall stability analysis.
7. Two cross-sections were analyzed for the river normalization stability calculations.
Please perform analyses for all unique river normalization cross-sections including
but not limited to:
b. Many of the cross-sections show the stone masonry drainage channel abutting
the gabion basket retaining wall. Please provide a stability analysis for this
condition.
9. Please provide cofferdam layout, Cofferdam layout shall provide upstream and
downstream flood protection to facilitate construction of weir.
10. Please provide drawings, details, and calculations for proposed waterway cover.
11. The dimensions shown in the Drainage channel along of river normalization
calculations do not reflect the dimensions shown on the drawings. Please review and
revise.
13. Please review/revise or confirm the hydraulic analysis for the weir under normal and
spillway design flood (SDF) conditions.
3
14. Please provide design details and calculations for headpond railing.
15. Please provide designs and analyses for all proposed bridges.
16. Please provide inflows to the project for the 1, 3, 5, 10-year precipitation events to
provide information regarding the design of the cofferdam and temporary bypass
system.
Cure Options:
The documents shall be updated as per comments during the Grant Agreement Amendment
phase. The Grant Agreement Amendment is being developed and includes a section in the
Terms of Reference for additional engineering by the Implementer that addresses the gaps
identified in this review.
OVERALL PROJECT ASSESSMENT
Upcoming Milestones and Critical Path: Grant Agreement Amendment completion and
signing
4
2. Detailed Summary
Table 1. Review Result
Project Doc. No. Document Title MCA-I REVIEWS CONTRACTOR REPLIES Result
Drawings MHPP-LBG-01-002 Layout 2 Dimensions are illegible. Please resubmit drawings so all
text is readable.
MHPP-LBG-01-010 Layout 10 Dimensions are illegible. Please resubmit drawings so all
text is readable.
MHPP-LBG-02-001 Weir Layout Please provide a demolition plan which shows limits of
existing conditions to be removed.
5
MHPP-LBG-04-001 Cross Section 1-1, 2-2, 3-3 Drawing shows headpond cross-sections. Please clarify if
additional work is proposed for the headpond. Please
identify existing and proposed construction.
MHPP-LBG-05-002 Inspection Road Layout Sta. Please provide details for inspection road.
1+150 Sta. 1+300
MHPP-LBG-05-004 Cross Section Sta. 1+200 Section shows slope stabilization ends at approximately El.
610.00. Please clarify why slope stabilization does not
extend the full height of the slope.
MHPP-LBG-06-001 River Normalization Layout Please indicate location of river normalization
Sta. 0+000 Sta. 0+150 improvements such as retaining wall and masonry drainage
channel.
MHPP-LBG-06-005 Long Section Sta. 0+000 Please provide elevation labels along the y-axis of the graph
to MHPP-LBG-06- Sta. 0+075 to Long Section for all sheets.
012 Ata. 0+900 Sta. 0+946.251
MHPP-LBG-06-015 Cross Section Sta. 0+200 to Geotextile is hard to see on the drawings due to border with
to MHPP-LBG-06- Cross Section Sta. 0+900 the gabion baskets. Please indicate limits of geotextile fabric.
029
MHPP-LBG-06-030 Detail of Gabion Wire Please clarify material placed below stone masonry drainage
channel. Please provide material type and thickness.
MHPP-LBG-07-008 Slope Stability Cross Section Please provide details for transition from shotcrete soil nail
to MHPP-LBG-07- Sta. 0+650 to Slope Stability wall and area adjacent to the water conveyance.
010 Cross Section Sta. 1+700
Please show the top of the existing slope on the drawings.
MHPP-LBG-08-001 Power House Layout 1 Dimensions are illegible, please resubmit drawing with
legible text.
Technical Calculation Revision Gabion Wall Sta. The top width of the gabion B2 is inconsistent with what is
0+800 shown on the drawings. Please review and revise.
Active pressure coefficient Ka has been neglected from the
active earth force, Pa calculations. This may lead to an over-
estimation of the earth pressures due to the surcharge load.
Please clarify, review and revise.
Please provide definition for Phb and clarify how it is
different from Pabackfill.
Analysis of Gabion It is standard engineering practice to neglect passive
Wire (Sta 0+200) pressure when analyzing retaining wall. Please review and
revise calculations.
Resultant for surcharge loads due to temporary construction
traffic (da2) have been calculated incorrectly for all loading
and soil conditions. Please review and revise.
Stability calculation Water levels behind retaining wall vary depending on the
of retaining wall at loading condition. Please clarify why each water level was
weir area selected. It is generally more conservative to assume ground
water and ground surface.
Unpredictable Loads on the Retaining Wall appear to have
been applied to the resisting forces. Please review and
revise.
Slope of the retaining wall, is not consistent with what is
shown on the drawings. Please review and revise.
Active pressure 3, Pa3 has been calculated incorrectly. An
incorrect unit weight was used to calculate Pa3. Please
review and revise.