Académique Documents
Professionnel Documents
Culture Documents
Perlite Management Services Ltd was recently requested to inspect a 50m high cold box in Toulouse,
France which was showing signs of ice formation around
the top 5 metres.
PMS were then requested to provide on-site supervision to help oversee the project. PMS director
Paul Brown was on site for 10 days supervising the night shift and providing technical advice as
required to the Linde engineers.
It was necessary to initially enter the cold
box from the top, using rope access, to
break up the frozen perlite. The perlite was
removed manually and transferred to
ground level by a temporary lift which was
installed up the side of the cold box.
This perlite had to be completely removed
before it was safe to extract the remaining
dry perlite using tankers extracting through
the top manway.