Académique Documents
Professionnel Documents
Culture Documents
Printed In Svvltzerland
Preface
Fires, explosions and the release of toxic gases can therefore not covered in this manual. Also not taken
cause deaths and injuries to workers and the into account are hazards associated with nuclear
public, result in the evacuation of communities and industrial activities and national and international
adversely affect the environment as a whole. transport of dangerous goods, because the
Disasters that have come to be known as " Base1 ", management and legislative control of these
" Bhopal ", " Flixborough ", " Mexico City and
" activities are generally treated separately.
" Seveso gave rise to the terms " major hazards "
"
The manual aims at assisting all countries
and " major hazard control" ; the prevention and
which are considering major hazard control. The
control of major hazards have subsequently become
system described is applicable to countries where
a pressing issue in all parts of the world. This
certain aspects of major hazard control are already
manual on major hazard control is a response to the
in operation and to those which intend, for the first
public discussion on how to prevent major
time, to develop a programme for controlling major
accidents. Its preparation was recommended by a
hazards. In particular, factory inspectorates,
tripartite ad hoc meeting of special consultants
managements of major hazard installations, trade
convened by the International Labour Office in
unions and local authorities, as well as the police,
1985, after the major accident in Bhopal.
fire stations, hospitals and emergency units, will
The potential for major accidents caused by the find this manual indispensable.
increasing production, storage and use of
This book is the result of a collaborative effort
dangerous substances implies that a well-defined
on the part of the ILO and several experts. The
and systematic approach is required if major
Office wishes to thank the consultants, Dr.-Ing.
disasters are to be avoided. This manual is
D. Hesel, TUV Rheinland, Federal Republic of
therefore designed to deal with the safety aspects
Germany ; Dr. C. A. W. A. Husmann, Directorate
of siting, planning, design, construction and
General of Labour, Ministry of Social Affairs and
operation of plants. It explains how to identify
Employment, the Netherlands ; and Dr. A. F. Ellis,
major hazard installations and describes all the
United Kingdom, in his capacity a s an ILO expert
components of a major hazard control system.
in the field of major hazard control.
Because of the potential adverse effects of major
accidents on both workers and the community,
extensive information is provided on planning for
emergencies, both on site and in the surrounding
neighbourhood. G. R. Kliesch,
The day-to-day application of safety and health Director,
practices is part of normal plant operation and is Worlang Conditions and Environment Department
This manual identifies and discusses the various The manual recognises that the achievement of
components of a major hazard control system. It is major hazard control is usually the result of a step-
written particularly for those countries which are by-step approach, and priorities for progress are
considering such controls for the first time. identified consistent with this policy.
However, it should be useful for many other
These priorities will involve government
countries with major hazard works that have some
authorities and factory inspectorates both centrally
degree of major hazard control already in operation,
and locally, works managements and trade unions,
although not yet representing the comprehensive
in addition to the various organisations which may
package which is now part of the legislation
be involved with emergency planning - police, fire
adopted by the member States of the European
authorities, hospitals, and so on.
Communities (EC).
vii
Contents
6.3.9 Role of the government safety authority 37 3. A guide to hazard and operability studies 71
6.4 Rehearsals and exercises m off-site emergency 4. Consequence calculation methods 119
planning 37
5. (a) The storage of LPG at fixed installations 129
7. Implementation of major hazard control (b) Safety advice for bulk chlorine installations 171
systems 39 (c) Storage of anhydrous ammonia under pressure in the
7.1 Introduction 39 United Kingdom 221
7.2 Identification of major hazards 39 6. Example of a safety report 253
7.3 Setting priorities 39 7. Example of accidents reporting form (derived from Annex
VI to EC Directive (82/501/EEC)) 289
7.3.1 Establishment of a group of experts 39
8. Land-use near to malor hazard works 293
7.3.2 Emergency planning on site 40
7.3.3 Emergency planning off site 40
7 3.4 Siting 41
7.3.5 Training of factory inspectors 41
Figures
7.3.6 Preparation of check-lists 41
1. The role of management in major hazard control
7.3.7 Inspection of works by factory mspectors 42 systems 11
7.3.8 Inspection of works by specialists 42 2. An example of a simple flowsheet 14
7.3.9 Evaluation of major hazards 43 3. Sketch of the operation of safety devices 17
7.3.10 Actions arising from evaluation 43
7.3.11 Information to the public 43
8. Prerequisites for a major hazard control system 45
8.1 Manpower requirements 45
Tables
1 Examples of industrial explosions 3
8.2 Equipment 45
2. Examples of major fires 4
8.3 Sources of information 45 3. Examples of major toxic releases 5
Bibliography 47 4. EC Directive criteria for major hazard installations 8
Appendices 5. Priority chemicals used in identifying major hazard
installations 8
1. List of dangerous substances and threshold quantities
(derived from Annex I11 to EC Directive (82/501/EEC)) 49 6. Working methods for hazard assessment 12
7. Preliminary hazard analysis in an LPG storage plant 13
2. Example of a rapid ranking method for the classification of
units/plant elements 55 8. Effects of blast over-pressure on structures 30
(a) Hazard figures and material factors as derived from 9. Effects of thermal radiation on unprotected skin 30
National Fire Protection Association data 65 10. Effects of chlorme gas concentrations on people 31
1. Introduction
The rapid growth in the use of hazardous chemicals evacuated from local villages when a process
in industry and trade has brought about a very malfunction resulted in a small release of the
significant increase in the number of people, both chemical dioxin in Seveso, Italy. A cyclohexane
workers and members of the general public, whose explosion at Flixborough in the United Kingdom in
life could be endangered at any one time by an 1974 killed 28, and injured 89, persons. The
accident involving these chemicals. The rapid pace economic damage resulting from all these events
of progress in modern technology allows less and many others is huge.
opportunity for learning by trial and error, making it Although these cases may have differed in the
increasingly necessary to get design and operating way they happened and the chemicals that were
procedures right the first time. However, involved, they shared a common feature : they were
safeguards in the chemical industry are not limited uncontrolled events involving fires, explosions or
to the factory floor alone. Public concern at multiple releases of toxic substances that either resulted in
injuries and deaths from spectacular events such as the death and injury of a large number of people
a major explosion invariably leads to calls for inside and outside the plant or caused extensive
additional controls at national and international property and environmental damage, or both. The
levels. It is therefore important, particularly for storage and use of flammable, explosive or toxic
projects involving the storage and use of hazardous chemicals having the potential to cause such
chemicals, to address both on-site and off-site disasters are generally referred to as major hazards.
safety when deciding on the safety measures to be This potential, therefore, is a function both of the
applied. inherent nature of the chemical and the quantity
This chapter discusses the definition of major that is present on site.
industrial hazards, their types and consequences In recent years much effort has been devoted to
and the components of their control systems. the development of legislation controlling major
Mention is made of the types of industrial activities hazards. Most notable is that of the Council of the
that are excluded from the scope of this manual. European Communities (EC) which in 1982 issued a
Directive on major accident hazards of certain
industrial activities. This defined the term " major
1.1. Major industrial hazards accident " as " an occurrence such as a major
Sixty thousand inhabitants were evacuated as emission, fire or explosion resulting from
a result of fire involving ammonium nitrate in uncontrolled developments in the course of an
France in October 1987. Fire involving methane industrial activity, leading to a serious danger to
caused four fatalities and one injury in Italy in April man, immediate or delayed, inside or outside the
1987. In Bulgaria a vinyl chloride explosion resulted establishment, and to the environment, and
in 17 deaths and 19 injuries in November 1986. An involving one or more dangerous substances ".
explosion involving fireworks killed 11 and injured
eight in the Philippines in April 1986. In February 1.2. Types and consequences of
1986 a chlorine leak in the United States injured 76
persons. These cases are but a sample of recent
major industrial hazards
reported events. Major industrial hazards are generally
More disastrous events may also be cited. associated with the potential for fire, explosion or
These include the release of the chemical methyl dispersion of toxic chemicals and usually involve
isocyanate in Bhopal, India, in 1984, resulting in the release of material from containment followed,
over 2,000 fatalities and 200,000 injuries. Two in the case of volatile materials, by its vaporisation
weeks earlier was the explosion of liquefied and dispersion. Accidents involving major hazards
petroleum gas (LPG) in Mexico City, resulting in could include :
650 deaths and several thousand injuries. An - leakage of flammable material, mixing of the
explosion of propane gas in Ortuella, Spain, also material with air, formation of a flammable
resulted in 51 fatalities and many injuries in 1980. In vapour cloud and drifting of the cloud to a
1976, 30 people were injured and 220,000 persons source of ignition, leading to a fire or an
Major hazard control
generally accepted that a vapour phase explosion Table 1. Examples of industrial explosions
requires some degree of confinement for a Chemical Consequences Place and date
detonation to take place. mvolved
Deaths Inlunes
the fumes generated as a result of fire. These fumes between a fire and an explosion. Quite often an
may include toxic gases, such as sulphur dioxide explosion is followed by a fire, and the casualties
from the combustion of carbon disulphide and are caused by both phenomena.
nitrous oxides from a fire involving ammonium
nitrate. 1.2.3. Toxic releases
1.2.2.1. Boiling liquid expanding vapour There are large numbers of chemicals with
explosion (BLEVE) which particular care needs to be taken to prevent
them from having harmful effects on workers. The
Sometimes referred to as a fireball, a BLEVE is major discipline of occupational hygiene exists to
a combination of fire and explosion with an intense develop the methods necessary to control exposure
radiant heat emission within a relatively short time to these chemicals, possibly over as long a period
interval. As implied by the term, the phenomenon as the working lifetime of a plant operator. This is
can occur within a vessel or tank in which a of fundamental importance to workers' safety. The
liquefied gas is kept above its atmospheric boiling- effects of toxic chemicals when considering major
point. If a pressure-vessel fails as a result of a hazards, on the other hand, are quite different and
weakening of its structure, the contents are are concerned with acute exposure during and soon
instantaneously released from the vessel as a after a major accident rather than with long-term
turbulent mixture of liquid and gas, expanding chronic exposure. In other words, this manual
rapidly and dispersing in air as a cloud. When this considers the storage and use of toxic chemicals,
cloud is ignited, a fireball occurs, causing an often in very large quantities which, if released,
enormous heat-radiation intensity within a few would disperse with the wind and have the
seconds. This heat intensity is sufficient to cause potential to kill or injure people living many
severe skin burns and deaths at several hundred hundreds of metres away from the plant, and being
metres from the vessel, depending on the quantity unable to escape or find shelter.
of the gas involved. A BLEVE can therefore be The toxicity of chemicals is commonly
caused by a physical impact on a vessel or tank determined by using four major methods. These are
which is already overstressed or damaged, for incident studies, epidemiological studies, animal
example from a traffic accident with a tank-car or a experiments and micro-organism tests. Despite
derailment of a tank-wagon, or it can be caused by their obvious value, these methods all suffer from
fire impinging upon or engulfing a vessel and thus weaknesses which are outside the scope of this
weakening its structure. A BLEVE involving a manual, but which mean that caution should be
50-tonne propane tank can cause third-degree exercised in the interpretation of results. Other
injuries at distances of approximately 200 metres factors also affect the toxicity of chemicals - for
and blisters at approximately 400 metres. instance age, sex, genetic background, ethnic
A list of some major fires is given in table 2 grouping, nutrition, fatigue, diseases, exposure to
other substances with synergistic effects, and
Sometimes it is difficult to make a distinction hours and patterns of work.
Table 2. Examples of major fires Although toxicity data are not abundant, the
toxicity of certain chemicals has been established.
Chem~cal Consequences Place and date
involved Chlorine, for example, is known to be dangerous to
Deaths Injur~es
human health at concentrations of 10-20 parts per
Methane 136 77 Cleveland, Ohio, United million (ppm) for an exposure of 30 minutes. The
States, 1944 gas becomes fatal at concentrations of 100-150 ppm
LPG 1 (BLEVE) 18 90 Feyzin, France, 1966 with exposure durations of 5-10 minutes. Exposure
LNG 40 - Staten Island, New York, to chlorine for shorter periods can be fatal at
Unlted States, 1973
concentrations of 1,000 ppm. As far as the
Methane 52 - Santa Cruz, Mexico, 1978
consequences of a chlorine release are concerned,
LPG (BLEVE) 650 2 500 Mexico Clty, Mexico, 1985
it is known that an instantaneous release of 10
! L~quefiedpetroleum gas 2 Liquefied natural gas
tonnes of this chemical may produce a maximum
Introduction
concentration of 140 ppm at a distance of 2 km The basic components of this system are :
downwind from the source and of 15 ppm at a
distance of 5 km in D5 weather conditions (normal
(a) Identification of major hazard installations. It is
necessary to identify the installations which,
non-inversion weather).
according to the definition, may fall within the
Table 3 lists some major industrial accidents criteria set for the classification of major hazard
involving toxic releases of different chemicals, some installations. Governmental authorities and
of which caused fatalities. Chlorine and ammonia management should institute the identification
are the toxic chemicals most commonly used in of major hazard installations on a priority basis.
major hazard quantities and both have a history of Identification may be done in accordance with
major accidents. None the less, other chemicals, the guidance set out in Chapter 2, which also
such as methyl isocyanate and dioxin, must be provides a shortlist of 20 priority substances for
used with particular care in view of their higher this purpose.
toxicity, even though they may be handled in lesser
quantities. For this reason, a number of these very (b) Information about the installation. Once the
major hazard installations have been identified,
toxic chemicals have been included in the so-called
additional information needs to be collected
" Seveso Directive" of the EC (see Appendix 1).
about their design and operation. In addition,
such information must also describe all other
Table 3. Examples of major toxic releases hazards specific to the installation. Because of
Chemical Consequences Place and date the likely complexity of the installation, the
Involved
Deaths Inlunes information should be gathered and arranged
systematically, and should be accessible to all
Phosgene 10 - Poza Rica, Mexico, 1950 parties concerned within the industry, such as
Chlorlne 7 - Wilsum, Federal Repub- management and workers, and outside the
lic of Germany, 1952
DioxinITCDD - - Seveso, Italy, 1976
industry, such as the governmental bodies
Ammonia 30 25 Cartagena, Colombia, which may require it for licensing and
1977 inspection purposes. In order to achieve a
Sulphur dioxide - 100 Baltimore, Maryland, complete description of the hazards, it may be
United States, 1978 necessary to carry out safety studies and
Hydrogen sulphlde 8 29 Chicago, Illinois, Unlted
States, 1978
hazard assessments to discover possible
Methyl isocyanate 2 000 200 000 Bhopal, India, 1984 process failures and to set priorities during the
process of hazard assessment. Rapid ranking
methods may be used to select the units which
1.3. Components of a major require a more thorough assessment. In section
3.5 and Appendix 6 the contents of such a
hazard control system study are described in the form of a safety
Section 1.2 has described the variety of major report. An example of a rapid ranking method
accidents that can take place, leading to the to classify units according to their hazard
concept of a " major hazard " as an industrial appears in Appendix 2.
activity requiring controls over and above those
(c) Action inside the industrial activity. In addition
applied in normal factory operations, in order to to preparing a report, management has the
protect both workers and people living and working primary responsibility of operating and
outside. These controls form an integrated package
maintaining a safe plant. A sound safety policy
- a major hazard control system - which aims not
is required. Technical inspection, maintenance,
only at preventing accidents but also, and most
plant modification, training and selection of
importantly, at mitigating the consequences of any
suitable personnel must be carried out
accidents which do take place.
according to sound procedures. In addition to
Because of the complexity of the industrial the preparation of the safety report, accidents
activities concerned, major hazard control needs to should be investigated and reports submitted
be based on a systematic approach. to the authorities. Lessons should be learnt
Major hazard control
from accidents and near misses. For further planning, a distinction is made between on-site
details concerning the role of management, and off-site planning. A well-structured and
reference should be made to sections 3.1 to 3.5. clear plan is one which is based on a well-
(d) Actions b y the governmental authorities. prepared safety report and which can be
Assessment of the hazards for the purposes of quickly and effectively employed when a major
licensing, where appropriate, inspection and accident occurs. More details on emergency
enforcement of legislation are the responsibility planning are provided in Chapter 6.
of government in the control of major hazards.
Land-use planning can appreciably reduce the 1.4. Exclusions
potential for a disaster and will probably come
under government control. The training of Although certain parts will be applicable to a
factory inspectors, including chemical wider range of industrial activities, this manual
inspectors, is also an important government considers the control of industrial major hazards a s
role. More on the role of the authorities appears described in section 1.1.The controls necessary for
in Chapter 4. the transport of hazardous chemicals are excluded,
since their control and management are quite
(e) Emergency planning. All previous elements
different from those of static sites.
focus on the prevention of the occurrence of
major accidents. Emergency planning aims at Also excluded from the scope of this manual
the reduction of the consequences of major are nuclear hazards and those of a strictly military
accidents, and assumes that absolute safety nature, both of which are likely to have existing
cannot be guaranteed. In setting up emergency comprehensive controls of their own.
2. Identification of
major hazard installations
Any major hazard control system is concerned with most commonly chosen, but alternatives - based,
priorities which may reasonably differ from one for example, on factory inspectorate records - may
country to another. Resources are always likely to be appropriate.
be limited both within the various authorities and
within industry, and therefore the special attention The definition of a major hazard for any country
that is demanded for major hazard control should may need to be amended as experience and
be directed at the priority areas. knowledge are accumulated on both existing and
new hazards and on the history of major accidents
It is clearly inappropriate to consider all since the substancelquantity definition was
possible industrial processes which could result in established.
injury or death and to call them all major hazards.
The final list would be enormous and
unmanageable in any country (developed or 2.2. Major hazard installations
developing). under the EC Directive
Major hazards usually need to be defined by Following serious incidents in the chemical
means of a list of hazardous substances with industry in Europe in the last two decades, specific
associated trigger quantities, in such a way that legislation covering major hazard activities was
the industrial installations brought within the scope developed in various countries in Western Europe.
of the definition as major hazard works are A key feature in the legislation was the obligation
recognised as those requiring priority attention, i.e. of the employer of a major hazard industrial activity
they have the potential for causing a very serious to submit information about the activity and its
incident which is likely to affect people both on and hazards based on the results of systematic safety
off site. studies. After the accident in Seveso (Italy)in 1976,
the major hazard regulations in the various
2.1. Identification : Purpose and countries were put together and integrated in an
procedures EC Directive of 24 June 1982. This Directive, on
the major accident hazards of certain industrial
Identification of major hazards is the starting- activities, has been in force since 1984 and is often
point for a system of control and, once such works referred to as the Seveso Directive. It was
have been identified, the agenda is set for amended and updated in 1987 and 1988.
implementing the various components of the
For the purpose of identifying major hazard
system. Identification will show which hazardous
installations, the EC Directive uses certain criteria.
materials are most commonly available in major
These criteria are based on the toxic, flammable,
hazard quantities, therefore requiring priority explosive and oxidising properties of the
attention by the group of experts (subsection 7.3.1).
chemicals, as described in table 4.
Where licences are being sought for new major
hazards, the authorities (the factory inspectorate)
For the selection of specific major hazard
may require sufficient additional information
industrial activities, a list of substances and
(section 3.5) to enable the application to be properly
threshold limits is provided. This list appears in
considered. A start can be made on the other
Appendix 1. An industrial activity is defined by the
components described in later chapters (e.g.
Directive as the aggregate of all installations within
emergency planning).
a distance of 500 metres of each other and
Although a substancelquantity definition of belonging to the same factory/plant. When the
major hazards is likely to be the method of defining quantity of the substances present exceeds the
a major hazard in most if not all countries, the given threshold limit appearing in the list, the
identification of works from this definition will activity is referred to as a major hazard installation.
depend on local circumstances and is discussed in The list of substances consists of 180 chemicals,
section 7.2. Making it a statutory requirement for whereas the threshold limits vary between 1 kg for
the major hazard works management to notify the extremely toxic substances to 50,000 tonnes for
authorities of the activity is likely to be the method highly flammable liquids. For isolated storage of
Major hazard control
Table 4. EC Directive criteria for major hazard shortened so as to give prominence to the more
installations hazardous chemical sites. A suggested list of
Toxic substances (very toxic and toxic) : priorities is given in table 5.
Substances showing the following values of acute toxiclty and With the chemicals shown in table 5 acting as
having phys~caland chemical properties capable of entailing
malor accident hazards a guide, a list of installations can be identified. If
LD50 oral ln rats LD50 cutaneous ~n rats LC50 inhalation (4hours) the list is still too big to be coped with by the
mglkg body weight or rabbits mglkg body In rats mg/l (mhalation)
we~ght authorities, new priorities can be set by means of
1 LD50<5 LD50 5 10 LC50 5 0 1 setting new quantity thresholds. Priority setting
2 5 < LD50 5 25 10 < LD50 5 50 01 <LC50505 can also be used inside the factory to identify the
3 25 < LD50 5 200 50 < LD50 S 400 0 5 < LC5C52
more hazardous parts using rapid ranking methods,
Flammable substances
for example.
1. Flammable gases : substances which in the gaseous state
at normal pressure and muted with air become flammable These are based on a short survey of the
and the boiling-point of which at normal pressure is 20" C
or below.
industrial activity as a whole or in part. This
2. Hlghly flammable liquids, substances which have a flash- establishes numerical factors which are
polnt lower than 21" C and the boiling-point of which at incorporated in the calculation of a "safety index"
normal pressure is above 20" C. giving an indication of the magnitude of the major
3. Flammable liquids substances which have a flash-point
'
hazard. This method is described in Appendix 2. It
lower than 55' C and which remain liquid under pressure,
where particular processing conditions, such as high is somewhat laborious and great care should be
pressure and high temperature, may create malor taken in its interpretation.
accident hazards.
Explosive substances
Substances which may explode under the effect of flame or Table 5. Priority chemicals used in identifying major
which are more sensitive to shocks or friction than hazard installations
dinitrobenzene.
Name of substance Quant~ty(2) EC 1st s e n d
Oxidising substances number
Substances which give rise to highly exothermic reaction
when in contact with other substances, particularly flammable General flammable substances
substances. Flammable gases
Highly flammable liquids
Speclfic flammable substances
substances, a separate list of a few substances is Hydrogen
given. Ethylene oxlde
In addition to flammable gases, liquids and Specific exploswes
explosives, the list contains chemicals such as Ammonlum nitrate 2 500 t 146 (a)
ammonia, chlorine, sulphur dioxide and Nitroglycerine 10 t 132
acrylonitrile. 2 4 6-Trinitrotoluene 50 t 145
Specific toxlc substances
2.3. Scope for priorities Acrylonitrile
Ammoma
For a major hazard control system to achieve its Chlorine
objectives, it must be capable of being applied. In Sulphur dioxlde
order to facilitate the application of the system and Hydrogen sulphide
to encourage the authorities and management to Hydrogen cyanide
apply it, it must be priority-oriented, with attention Carbon disulphide
being focused on the more hazardous installations. Hydrogen fluoride
Hydrogen chloride
Setting of priorities can be achieved by various Sulphur trloxlde
methods and techniques. One way to do this is by Speclfic very toxic substances
concentrating on fewer chemicals than are Methyl isocyanate
currently in the EC definition. The list of chemicals Carbonyl chloride (Phosgene)
appearing in Appendix 1 can therefore be
Identification of major hazard installations
Major hazard installations have to be operated to a management must have answers to the following
very high standard of safety. This is the duty of questions :
management. In addition, management holds a key (a) Do toxic, explosive or flammable substances in
role in the organisation and implementation of a our facility constitute a major hazard?
major hazard control system. In particular,
management has the responsibility to - (b) Which failures or errors can cause abnormal
conditions leading to a major accident?
(a) provide the information required to identify
major hazard installations ; (c) If a major accident occurs, what are the
consequences of a fire, an explosion or a toxic
(b) carry out the hazard assessment ; release for the employees, people living outside
(c) report to the authorities on the results of the the factory, the plant or the environment?
hazard assessment ; (d) What can management do to prevent these
(d) set up an emergency plan ; accidents happening?
(e) take measures to improve plant safety. (e) What can be done to mitigate the
consequences of an accident ?
Figure 1 summarises the duties a manufacturer
has to-fulfil in the major hazard control system.
3.1. Assessment of hazards
First and foremost, the management of an
installation which can cause a major accident has a The most appropriate way of answering these
duty to control this major hazard. To do this, it questions is to carry out a hazard assessment, the
must be aware of the nature of the hazard, of the Purpose of which is to understand why accidents
events that cause accidents and of the potential OCcur and how they can be avoided or at kast
consequences of such accidents. This means that, mitigated.
in order to control a major hazard successfully, A properly conducted assessment will therefore
Figure 1. The role of management in major hazard control systems
I I
NO ACTION
t
Does the quantity
exceed the threshold
in table 5 or
Appendix 1?
Provlde notification Provide information Prepare an on-site Inform the public Notify major accident
to authorities on significant emergency plan about the major hazard to authority
modifications
Prepare and submit Provide further Provide information to Provide information
safety report information on request local authority to enable on major accident
it to draw up an off-site
emergency plan
Major hazard control
analyse the existing safety concept or develop a 3.1.1.1. Preliminary hazard analysis (PHA)
new one ; The PHA is performed as the first step in a
identify the remaining hazards ; and . hazard assessment. It starts with the type of
accident involving toxic, flammable and explosive
develop optimum measures for technical and
materials. The procedure specifies the system
organisational protection in the event of
elements (plant components such as storage tanks,
abnormal plant operation.
reaction vessels) or event (overloading of a tank,
Methods which can be used for an assessment, and runaway reaction) that can lead to a hazardous
their application, are described below. condition.
3.1.1. Methods of hazard assessment Once the hazardous systems have been
To achieve the aims of a hazard assessment, it identified, the events that may lead to the accident
is necessary to follow certain procedures or use must be specified. Events such as "the formation of
certain aids. A number of working methods have an explosive atmosphere outside or inside a storage
vessel" or "the release of a toxic gas " will need to
been developed for this purpose. These are
summarised in table 6. be examined so as to identify the components of
the plant that can cause the accident. The
Of the methods listed in table 6, a detailed components, which include storage tanks, reaction
discussion is given on two which are vessels, pipes, pumps, stirrers, relief valves or other
complementary to one another. These are : systems, will then be singled out for a more
- preliminary hazard analysis (PHA); and detailed examination by other evaluation methods
such as the HAZOP.
-
hazard and operability study (HAZOP).
The results of the PHA are recorded on a form
A brief account will follow of two other methods as shown in table 7.
used to determine the frequency of occurrence of Since the PHA is fast and cost-effective, and
an accident. These are the "fault tree analysis" and since it identifies key problems, hazard evaluation
the " accident sequence analysis " . Their application should always start with this method.
in a hazard assessment should be limited to a small
number of special cases. Its results indicate which systems or
procedures require further analysis and which
This section concludes with a discussion of the systems are of less interest from a major hazard
" accident consequence analysis " , which is used in point of view. In this way it is possible to limit the
describing the damage that would result if an evaluation to key problems, thus avoiding
accident occurred. unnecessary effort.
1. Preliminary hazard analysis 1. Identification of 1. Completeness of safety 1 Use of " thinking aids "
2. Matrix diagrams of interactions hazards concept
3. Use of check-lists
Figure 2. An example of a simple flowsheet accepted as realistic, the consequences are then
considered :
(a) the reaction produces C contaminated with an
excess of A which goes on into the next stage
of the process ;
(b) the excess flow into the reaction vessel means
that some will leave the vessel by the overflow.
Reaction : A B = C +
T
Product C
3.2. Causes of major industrial (a) failure in the monitoring of crucial process
parameters (pressure, temperature, flow,
accidents quantity, mixing ratios) and in the processing
The hazard assessment described in section 3.1 of these parameters ;
eventually leads to the identification of a number of (b) failure in the manual supply of chemical
potential hardware and software failures in and components ;
around the plant. Once these have been identified,
the manufacturer has to determine whether or not (c) failures in the utilities, such as :
something must be done about them. (i) insufficient coolant for exothermal
reactions ;
To help the manufacturer in this procedure, the
following sections give examples of typical failures (ii) insufficient steam or heating medium ;
followed by suitable control measures. (iii) no electricity ;
(iv) no nitrogen ;
3.2.1. Component failure
The fundamental precondition for safe (v) no compressed air (instrument air) ;
operation is that components can withstand the (d) failures in the shut-down or start-up
operational loads and thus enclose any potentially procedures, which could lead to an explosive
hazardous substances. Causes of failure include - atmosphere within the plant ;
(a) inappropriate design against internal pressure, (e) formation of side products, residues or
external forces, corrosive media and impurities which could cause side reactions
temperature ; (polymerisation).
(b) mechanical failure of vessels and pipe-work due The consequences of these failures can be
to corrosion or external impact ; understood only after examination of the behaviour
(c) failure of components such as pumps, of the entire system in the event of such a failure.
compressors, blowers and stirrers ; Counter-measures can be provided by reliable
process control (automatic or manual), good
(d) failure of control systems (pressure and operating procedures and a proper inspection and
temperature sensors, level controllers, flow- testing programme.
meters, control units, process computers) ;
3.2.3. Human and organisational errors
(e) failure of safety systems (safety valves, bursting
discs, pressure-relief systems, neutralisation Human ability to run a major hazard installation
systems, flare towers) ; is of fundamental importance, not only for plants
Major hazard control
which require a lot of manual operation but also for the plant or when designing very sensitive parts
highly automated plants requiring human of it.
intervention only in the case of an emergency.
3.2.5. Natural forces
Errors made by operating personnel, however, Other external impacts may be caused by
can be as diverse as their tasks in running the natural forces. The following are of importance
plant. Some of the most common errors are listed
below : (a) wind ;
(a) operator error (wrong button, wrong valve) ; (b) flooding ;
(b) disconnected safety systems because of (c) earthquakes ;
frequent false alarms ; (d) settlement as the result of mining activities ;
(c) mix-up of hazardous substances (material (e) extreme frost ;
identification check) ; (f) extreme sun ;
(d) communication errors ; (g) lightning
(e) incorrect repair or maintenance work ; If such hazards are known to occur in the
(f) unauthorised welding. natural environment of the installation, precautions
These human errors occur because - should be taken against them.
(a) the operating personnel are not aware of the 3.2.6. Acts of mischief or sabotage
hazards ; Every major hazard installation car, be a target
(b) the operating personnel are insufficiently for mischief or sabotage by plant personnel or from
trained for the job ; or outside. Protection is difficult and will never be
perfect. It should, however, be considered in the
(c) too much is expected from operating personnel. design.
To reduce human and organisational errors, 3.2.7. Additional failures
careful selection of personnel and regular training in
Further information is available in the form of
conjunction with clear operating instructions
check-lists concerning additional failures which
represent essential features in the management of
may cause accidents (American Institute of
personnel on major hazard sites.
Chemical Engineers, 1985).
3.2.4. Outside accidental interferences
A major accident in an installation can be 3.3. Safe operation of major
caused not only by operational failures but also by hazard installations
external events which can influence the plant.
These include accidents involving - Having discussed the evaluation of hazards and
the causes of major accidents, it is necessary to
(a) road and rail transport (especially dangerous give an idea of how the hazards should be
goods) ; controlled. This section therefore summarises the
(b) ship traffic ; most important control systems and organisational
(c) loading stations for flammable/explosive measures which are widely used to control major
substances ; hazards. A fuller description of the state of the art
in the safety of LPG, anhydrous ammonia storage
(d) air traffic ; and bulk chlorine installations is provided in
(e) neighbouring plants, especially those handling Appendix 5.
flammable/explosive substances ; and
3.3.1. Plant component design
(f) mechanical impact such as that caused by a
In view of the accidents that can occur as a
falling crane. result of improper component design, the following
These accidents cannot always be avoided. facts should be kept in mind. A component has to
They should, however, be considered when siting withstand the following :
The role of management
I
device operates system operates a
.*
Limit value of \
protective device -.
_._.-..-.-_..
,.-.....-C;orrectlve
- ;-
. - . actlon. . .-- / \ Permissible
range
-
Monitoring device Monitoring device Time
signals initiates action
Major hazard control
In order to operate such control systems, it is (d) Safety shut-down systems, emergency
necessary to monitor the process variables and shu t-offsystems
active parts of the plant, e.g. pumps, compressors
and blowers, with regard to operation and to These are systems which shut down the plant
dangerous conditions such as excessive pressure. (i.e. cut off pumps and compressors and close or
open quick-acting valves) in order to bring the
To ensure that the operating personnel do not plant into a safe condition. These systems can be
have to rely solely on the functioning of automatic initiated automatically or manually.
systems, these systems should be combined with
acoustic or optical alarms. Moreover, the operating 3.3.3.2. Systems preventing failure of
personnel should be well trained to be aware of the safety-related components
mode of operation and the importance of the Safety-related components may need to be
control systems. specially equipped for additional reliability,
It is most important to realise that any control depending on their importance in the safety
system will have problems in rare operating system. The plant can have different systems
conditions such as start-up and shut-down phases. which take over the function of these components
Special attention must be paid to these phases of (diversity), or there can be a second component for
operation. the same purpose, e.g. a second coolant pump
(redundancy).
3.3.3. Safety systems
3.3.3.3. Utilities
Any major hazard installation will require some
form of safety system. The form and design of the Safety-related utility supplies, such as
system depend on the hazards present in the plant. electricity supply to control systems, compressed
The following gives a survey of available safety air for instruments or nitrogen supply as an inert
systems and their purposes. gas, might need a second source, e.g. batteries, a
buffer-storage tank or an extra set of pressure gas
3.3.3.1. Systems preventing deviation from cylinders in case of a failure in the primary system.
permissible operating conditions
(a) Pressure-relief systems 3.3.3.4. Alarm systems
These are systems which, on the basis of
Rupture discs and safety valves can release
sensors, allow the operator to determine the causes
material into the atmosphere. If the material
of a malfunction as soon as it has occurred. Such
released forms an explosive mixture with air, care
alarm systems are available for -
must be taken that this mixture does not come into
contact with an ignition source before the lower (a) monitoring of process parameters (temperature,
explosive limit is reached. If the material released is pressure, flow rate, quantity, level, mixing ratio,
toxic, it should be led into a secondary system such 0, content) ;
The role of management
detection of failures of safety-related (e) proper communication devices for the plant
components (pumps, compressors, stirrers, personnel ;
blowers) ; (f) safeguarding against inadvertent switching
detection of leaks (gas detectors, actions ;
explosimeters) ; (g) training of personnel.
detection of fire or smoke ;
3.3.4. Maintenance and monitoring
detection of failure of safety devices (closed-
circuit current principle). The safety of a plant and the function of safety-
related systems can only be as good as the
3.3.3.5. Technical ~ r o t e c t i v emeasures maintenance and monitoring of these systems. For
this reason, it is of great importance to establish a
Over and the safety systems which
plant maintenance and monitoring schedule which
to keep the plant in a safe condition, protective
includes the following tasks :
measures can be taken to limit the consequences of
an accident. Such measures are - (a) checking of safety-related operating conditions
(a) gas detectors ; both in the control room and on site ;
(b) water spray systems (to cool tanks or to (b) checking of safety-related parts of the plant on
extinguish a fire) ; site, e.g. by visual inspection or by remote
monitoring ;
(c) water jets ;
(c) monitoring of safety-related utilities (electricity,
(d) steam spray systems ; steam, coolant, compressed air, etc.) ;
(e) collecting tanks and bunds. (d) preparation of a maintenance plan and
documentation of maintenance work specifying
3.3.3.6. Mitigating measures
the different maintenance intervals and the
To mitigate the consequences of an accident, it type of work to be performed.
is important to plan and to take adequate
organisational measures. These are described in In addition, the maintenance and monitoring
section 3.4. schedule must specify the qualifications and
experience required by the personnel to perform
3.3.3.7.Prevention of human and their tasks.
organisational errors
3.3.5. Inspection and repair
As shown in subsection 3.2.3, human errors
can be a source of major accidents. For this reason, It is necessary to establish a plan for on-site
their prevention needs to be addressed as one of inspections which should include a schedule and
the key safety measures. The following preventive the operating conditions to be adhered to during
measures can be taken : inspection work.
(a) use of differently sized connections in loading Repair work can be a major source of accidents.
stations for tank-cars to prevent mixing of For this reason, strict procedures must be specified
reactive substances (e.g. sulphuric acid and for carrying out repair work (e.g. welding of
nitric acid) ; components containing flammable substances).
(b) prevention of material mix-ups by means of These procedures should cover repair work
proper labelling, packaging, receiving requiring shut-down of the plant and cleaning of
inspection and analysis ; tanks, the qualifications required by personnel,
quality requirements of the work to be performed
(c) interlocking of safety-related valves and and requirements for the supervision of repair work.
switches which may not operate Because of the importance of this, many
simultaneously ; manufacturers establish their own standards for
(d) clear marking of switches, knobs and displays repair work over and above what national standards
on control panels ; may require.
Major hazard control
hazards coming within the scope of the additional activities and has provided appropriate
controls described in this manual. measures.
The purpose of the second step, the These objectives will assist both management
preparation of a safety report, is to present the and authorities in the evaluation of plant safety.
entire safety system. This gives the authorities the
opportunity (a) to check adherence to safety In order to fulfil these objectives, a safety report
standards as part of any licensing decisions, (b)to has two basic tasks. Firstly, it gives factual
carry out specific inspection in order to learn about information about the site, the processes and the
hazards arising from these installations, (c) to take surroundings. Secondly, it performs a hazard
proper siting decisions for new plants, and (d) to assessment allowing judgement of the nature,
establish contingency plans. likelihood and scale of potential major accidents
and of the means for controlling such hazards.
Finally, if an accident occurs, this may need to
be reported at once to the authorities. This is in The safety report, an example of which appears
addition to informing the authorities involved in in Appendix 6, should therefore contain the
handling the emergency off site, where immediate following information :
contact will be essential.
A. Description of the installa tion
3.5.2. Contents of reports to the
and the processes
authorities
3.5.2.1. Identification (1) Description of the installation
(d) information about the hazardous substances, (i) materials (only those related to
their names, quantities and physical condition. safety) ;
3.5.2.2. The safety report (ii) design data (pressure, temperature,
volume) ;
If a plant is identified as a major hazard
installation according to the criteria specified in (iii) foundations (stability) ;
Chapter 2, a safety report may have to be prepared. (c) protection zones (explosion protection,
This is to inform the authorities about the separation distances) ;
installation and its hazards, and has the following (d) accessibility of plant -
objectives : (i) escape routes ;
(a) to identify the nature and scale of the use of (ii) routes for emergency services.
hazardous substances in the installation ;
( 2 ) Description of the processes
(b) to give an account of the arrangements for safe
operation of the installation, for control of (a) technical purpose of the installation ;
serious deviations that could lead to a major (b) basic principles of the technological
accident and for emergency procedures at the process -
site ; (i) basic operations ;
(c) to identify the type, relative likelihood and (ii) physical and chemical reactions ;
consequences of malor accidents that might (iii) operational storage ;
occur ; and (iv) discharge, retention, recycling or
(d) to demonstrate that the manufacturer has disposal of waste ;
identified the major hazard potential of his (v) discharge or treatment of off-gases ;
Major hazard control
process conditions : description of the The result of this PHA is a list of those
process and safety-related data components, equipment, safety features and
(pressure, temperature) for the operations that might be linked to the occurrence
individual process stages ; of a major accident. These are called "safety-
process description : this description is relevant units " .
best given by appropriate flow
D . Description of safety-relevant units
diagrams (PI diagrams). They should
contain information on - The safety-relevant parts identified in the PHA
(i) components used in the process ; need to be described in greater detail in order to
(ii) utility supplies ; perform the hazard assessment. The following data
are required :
(iii) characteristic operating conditions ;
(iv) size of vessels and pipe-work (a) function ;
containing hazardous substances ; (b) type and extent of loads ;
(v) press control systems ; (c) importance for safety ;
utility supply : all safety-related types of (d) special design criteria ;
utilities (electricity, steam, coolant,
compressed air, inert gas) and, if (e) controls and alarms ;
available, the emergency supplies (f) pressure-relief systems ;
should be described. (g) quick-acting valves ;
B . Description of the hazardous (h) collecting tanksldump tanks ;
substances (i) sprinkler systems ;
(1) Substances Cjl fire protection.
(a) the process stage in which the E . Hazard assessment
substances are or may be involved ;
(b) quantities of substances ; On the basis of the hazards identified in the
PHA and all the information available about the
(c) substance data (physical and installation, namely the descriptive sections of the
chemical) ; safety report, the next step is to perform the hazard
(d) safety-related data (explosive limits, assessment. To enable the reader to carry out such
flash-point, thermal stability) ; an assessment, this manual contains the following
(e) toxicological data (toxicity, effects, aids :
odour level) ;
(a) the methods used for hazard assessment,
(f) threshold values (TLV, lethal shown in subsection 3.1.1;
concentrations).
(b) the causes of the hazards to be considered,
(2) Form of substances: the form in which the listed in section 3.2 ; and
substances may occur or into which they (c) the major hazard control instrumentation, given
may be transformed in the event of in subsection 3.3.3.
abnormal conditions.
As additional information, the hazard
C . Preliminary hazard analysis (PHA) assessment should include the known accident
history both of the plant in question and of similar
On the basis of the process description and the plants elsewhere.
description of the hazardous substances, it is
possible to identify the hazards and to determine It is recommended that the HAZOP method
which components, safety measures or human should be followed in the safety-relevant units and
interventions may be of importance. This can be that documentation on the HAZOP analysis may be
done according to the procedure described in included in the safety report. For reference, an
subsection 3.1.1.1. example of HAZOP appears in Appendix 3.
The role of management
In cases where the assessment leads to the major accidents may affect the authorities as well.
identification of particularly sensitive features For this reason, it is of great importance that the
(safety devices, control instruments or actions by mitigating measures listed in section 3.4 of this
operating personnel), it is necessary to consider the manual are described in detail and are consistent
reliability of these features. This consideration will with the measures taken by the authorities. This
show whether sufficient precautions have been applies mainly to :
taken to avoid major accidents. If this is not the (a) warning systems ;
case, the identified sensitive features of the plant
will have to be improved. (b) emergency plans ; and
(c) emergency services.
F. Organisation
Organisational systems used for the safe 3.5.2.3. Reporting of accidents
operation of a plant are important factors to
If a major accident occurs on a site, the
consider in the overall assessment of plant safety. manufacturer should immediately notify the
This should include information on the following : authorities of this accident. This notification should
(a) maintenance and inspection schedules ; contain the following information :
(b) guide-lines for the training of personnel ; (a) the circumstances of the accident ;
(c) allocation and delegation of responsibility for (b) the hazardous substances involved ;
plant safety ;
(c) data available for assessing the effects of the
(d) implementation of safety procedures. accident on persons and the environment ;
G. Assessment of the consequences (d) the emergency measures taken.
of major accidents Furthermore, the notification should state the
While sections A to E of the safety report deal steps envisaged :
with technical and operational safety measures, (a) to mitigate medium- or long-term effects of the
this section should provide information on possible accident ; and
accidents. The following information should be
(b) to prevent the recurrence of such an accident.
given :
In notifying the accident, use may be made of
(a) assessment of the possible releases of
hazardous substances or of energy ; forms such as that of the European Communities,
shown in Appendix 7.
(b) possible dispersion of released substances ;
(c) assessment of the effects of the releases (size of
affected area, health effects, property damage). 3.5.3. Updating of reports
Some physical models are available to assist The safety reports may need to be updated in
with these assessments. Several references exist the event of :
that give more details on these models (Havens and (a) major changes in the plant or process ;
Spicer, 1984 ; Netherlands, Directorate General of
(b) relevant new information about the hazardous
Labour, 1979).Further details appear in Appendix 4. substances ; or
H . Lnformation on the mitigation (c) substantial improvements available in safety
of major accidents engineering.
While in-plant safety measures are solely within In general, reports should be updated regularly
the manufacturer's responsibility, the mitigation of every three to five years.
4. The role of the
The prevention of major accidents as described in The review should involve a detailed examin-
this manual is basically a task that the ation of the written statements, in particular of the
manufacturer operating a major hazard installation hazard assessment. Furthermore, it must include an
has to cope with. Within the framework of a major on-site inspection of those components or
hazard control system, this task must be supported processes identified in the safety report as being
and reviewed by the authorities. In order to meet " safety-relevant " .
these responsibilities, the authorities will need to
perform the following activities. As part of the safety report should describe the
on-site emergency plan, the authorities must
review this to make sure that it is consistent with
4.1. Establishment of an inventory the off-site emergency plan. Details about on-site
of major hazard installations and off-site emergency plans are given in Chapter 6
This manual deals with a number of potentially of this manual.
hazardous industrial activities and substances. The
competent authorities will need to identify these
major hazard installations in order to draw up an 4.3. Mitigation of consequences
inventory. The procedures for identification are
described in Chapter 2. Depending on the number The off-site emergency plans are likely to be
of identified installations in relation to the resources prepared by the local authorities. They should be
that are available, it will be necessary to set drawn up in consultation with the manufacturer
priorities for the review of safety reports and the and organisations such as the fire brigade, police,
implementation of off-site emergency plans. This ambulance service, hospitals, water authorities,
must be carried out on the basis of the following public transport, and so on.
criteria :
The off-site emergency plan must be main-
-
type and quantities of hazardous substances tained in a state of readiness ; provision must be
handled ; and made for training and exercises, the details of
-
location of the installations in relation to which appear in section 6.3.
populated areas.
In addition to helping manufacturers deal with
Furthermore, it may be of help to consider how the immediate effects of accidents on site, the
many accidents have occurred in the past with emergency services should be prepared to cope
these substances. Literature on accident statistics with possible consequential effects in the
is available (Lees, 1980). International data bases surrounding area. Off-site effects usually take
(e.g. MHIDAS in the United Kingdom) also enable longer to develop and therefore allow some time for
this information to be rapidly obtained. contingency action to be taken. Equally they may
continue for a period of several hours or possibly
4.2. Receipt and review of the longer and require considerable mobilisation of
safety reports resources to cope with possible evacuation,
restriction of access, movement of foodstuffs and
According to the priorities deduced from the control of water supplies.
inventory of major hazard installations, the
authorities will need to set a deadline for the
preparation of safety reports. They should allow 4.4. Other roles
sufficient time (i.e. one or two years) for the
preparation of these reports by existing works. 4.4.1. Siting
When the reports are reviewed, the authorities will
need to check : The authorities need to decide whether certain
major hazard installations should be separated from
-
whether the requirements listed in Chapter 3 of the population living and working outside the
the manual have been fulfilled ; and installation. This is described in detail in
-
whether the information given is correct Appendix 8.
Major hazard control
Much of the earlier part of this manual has 6.1.4. Identification and assessment of
been concerned with preventing accidents through hazards
good design, operation, maintenance and
This stage is crucial to both on-site and off-site
inspection. Achieving all this will reduce the risk of
emergency planning and requires works
an accident, but it will not eliminate it altogether -
managements systematically to identify what
absolute safety is not achievable, and an essential emergencies could arise in their plants. These
part of major hazard control is concerned with
should range from small events which can be dealt
mitigating the effects of a major accident.
with by works personnel without outside help to
An important element of mitigation is emerg- the largest event for which it is practical to have a
ency planning, i.e. recognising that accidents plan. Experience has shown that for every occasion
are possible, assessing the consequences of such that the full potential of an accident is realised,
accidents and deciding on the emergency there are many occasions when some lesser event
procedures, both on site and off site, that would occurs or when a developing incident is made safe
need to be implemented in the event of an before reaching full potential.
emergency. Most major hazard accidents come within the
Emergency planning is just one aspect of safety following categories :
and cannot be considered in isolation. In particular, (1) Events involving flammable materials
it is not a substitute for maintaining good
standards inside the works. Before starting to (a) major fires with no danger of explosion ;
prepare the plan, works managements should hazards from prolonged high levels of
ensure that the necessary standards, appropriate to thermal radiation and smoke ;
their safety legislation, are in place. (b) fire threatening items of plant containing
hazardous substances ; hazards from spread
Emergency plans are likely to be separate for
of fire, explosion or release of toxic
on-site and off-site matters, but they must be
substances ;
consistent with each other, i.e. they must be
related to the same assessed emergency (c) explosion with little or no warning ; hazards
conditions. While an on-site plan will always be the from blast wave, flying debris and high
responsibility of the works management, different levels of thermal radiation.
legislations may place the responsibility for the off-
(2) Events involving toxic materials
site plan elsewhere : for example, the EC Seveso
Directive requires the local authority to prepare the (a) slow or intermittent release of toxic
off-site plan. substances, e.g. from a leaking valve ;
Major hazard control
(b) items of plant threatened by fire (Chemical This overall assessment of the major hazard
Industries Association, 1976); hazards from provides the framework for both emergency plans
potential loss of containment ; to be drawn up.
(c) rapid release of limited duration, due to Techniques for the more formal identification
plant failure, e.g. fracture of pipe ; hazards and assessment of hazards have been developed
from toxic cloud, limited in size, which may and are used routinely in many countries,
quickly disperse ;
Table 8. Effects of blast over-pressure on structures
(d) massive release of toxic substance, due to --
Table 10. Effects of chlorine gas concentrations formulation of the plan and liaison with outside
(pprn) on people (1 ppm = 3 mglrn3) authorities, including the emergency services ;
Concentration (ppm) T ~ m e Effect
procedures :
3-6 - Causes stinging or burnmg
(i) raising the alarm ;
sensation but tolerated without
undue ill effect for up to 1 hour (ii) communications both within and outside
10 1 min Coughing the works ;
10-20 30 mins Dangerous - immediate
irritation of nose, throat appointment of key personnel and their duties
and eyes with cough and and responsibilities :
lachrymation
100-150 5-10 mins More vulnerable people might (i) works incident controller ;
suffer fatahty
(ii) works main controller ;
300-400 30 mins Predicted average lethal
concentration for 50 % of active emergency control centre ;
healthy people
1 000 Brief (a few Likely to be fatal action on site ;
breaths)
action off site.
such a release is identified, the remedial action person in charge of the plant at the time of the
must be appropriately quick if it is to be worth incident and should provide 24-hour cover when
taking. shift operation applies. The site incident controller
may have to take decisions involving neighbouring
The plan needs to take account of absences
plant liable, perhaps, to be involved in an
due to sickness and holidays, and of shut-down
escalating emergency if it is not shut down.
periods, for example when only security personnel
may be present: in other words, it must be The responsibilities of the site incident
applicable to all the variations in manning, and so controller include the following :
on, that could occur while the hazard exists.
to assess the scale of the incident (both for
6.2.2. Alarm and communication internal and external emergency services) ;
mechanism to initiate the emergency procedures to secure
Communication is a crucial factor in handling the safety of employees, minimise damage to
an emergency. It is the practice at many works that plant and property and minimise loss of
any employee can raise an emergency alarm, so material ;
allowing the earliest possible action to be taken to to direct rescue and fire-fighting operations
control the situation. until (if necessary) the fire brigade arrives ;
Alarm systems vary and will depend on the size to search for casualties ;
of the works. There should be an adequate number
to arrange evacuation of non-essential workers
of points from which the alarm can be raised either
to assembly areas ;
directly, by activating an audible warning, or
indirectly, via a signal or message to a permanently to set up a communications point with the
manned location. The alarm should alert the emergency control centre (subsection 6.2.4);
incident controller (subsection 6.2.3),who should to assume the responsibilities of the site main
assess the situation and implement appropriate controller pending his or her arrival ;
emergency procedures. In areas where there is a to provide advice and information as requested
high level of noise, it may be necessary to install to the emergency services.
more than one audible alarm transmitter or flashing
lights. Automatic alarms may be appropriate on It is important that the site incident controller
some sites. is readily recognisable at the scene of the incident.
This is usually achieved by the wearing of a
There should be a reliable system for informing
distinctive safety helmet and jacket, which is
the emergency services as soon as the alarm is
known to all concerned. It should contrast with
raised on site. The details of the communication
equipment worn by the emergency services.
arrangements should be agreed locally ; in some
cases it may be advisable to have a direct line to The site main controller is often chosen from
the fire brigade. Predetermined code words to the senior management of the works and has the
indicate the scale and type of the emergency may general responsibility of directing operations from
be valuable. the emergency control centre after relieving the site
incident controller of the responsibility for overall
6.2.3. Appointment of personnel and
control.
definition of duties
Effective emergency plans require that, in the The specific responsibilities of the site main
event of an accident, nominated individuals are controller include :
given specific responsibilities, often separate from (a) to decide (if not decided already) whether a
their day-to-day activities. The two principal people major emergency exists or is likely, requiring
are the site incident controller and the site main the emergency services and the off-site
controller. emergency plan (section 6.3);
The site incident controller will take control of (b) to exercise direct operational control of the
handling the incident. He or she will often be the works outside the affected area;
Emergency planning
continually to review and assess possible (b) an adequate number of internal telephones ;
developments to determine the most probable (c) radio equipment ;
course of events ;
(d) a plan of the works, to show :
to direct the shutting down of plants and their
evacuation, in consultation with the site (i) areas where there are large inventories of
incident controller and key personnel ; hazardous materials ;
to ensure that casualties are receiving (ii) sources of safety equipment ;
adequate attention ; (iii) the fire-fighting system and additional
to liaise with chief officers of the fire and police sources of water ;
services and with the factory inspectorate ; (iv) site entrances and roadways, including up-
to control traffic movement within the works ; to-date information on roadworks ;
to arrange for a log of the emergency to be (v) assembly points ;
maintained ; (vi) the location of the works in relation to the
to issue authorised statements to the news surrounding community ;
media ;
(vii)lorry parks and rail sidings ;
to control rehabilitation of affected areas after
(additional works plans should be available
the emergency.
to show affected areas, etc., during an
Apart from the two site controllers, other works emergency ;)
personnel will have key roles to play in the (e) notepads, pens and pencils ;
implementation of the emergency plan. These will
include senior managers of plants not directly (0 a nominal roll of employees ;
involved in the emergency, first aiders, atmospheric (g) a list of key personnel, with addresses,
monitoring staff, casualty reception staff and public telephone numbers, etc.
relations staff to liaise with the media. All need to
The emergency control centre should be sited
be aware at the emergency pre-planning stage of
in an area of minimum risk. For large sites, or
the precise nature of their roles.
where toxic releases might be anticipated,
6.2.4. Emergency control centres consideration should be given to setting up two
control centres to ensure, as far as possible, that
The emergency control centre is the place from
which the operations to handle the emergency are one will always be available for use should the other
be put out of action.
directed and co-ordinated. It will be attended by
the site main controller, key personnel and the
senior officers of the fire and police services. 6.2.5. Action on site
The primary purpose of the on-site emergency
For a small works it may be a designated office
plan is to control and contain the incident and so to
which converts to a control centre in the event of
prevent it from spreading to nearby plant. It is not
an emergency. For large works, a purpose-built
possible to cover every eventuality in the plan and
facility is advisable. In all cases, however, the
the successful handling of the emergency will
centre should be equipped to receive and transmit
depend on appropriate action and decisions being
information and directions from and to the incident
taken on the spot. Other important aspects needing
controller and other areas of the works, as well as
to be considered include the following:
outside.
(a) Evacuation. Non-essential personnel will usually
Emergency control centres should therefore be evacuated from the incident area and also
contain the following (as applicable) : from adjacent areas. Evacuation should be to a
(a) an adequate number of external telephones ; if predetermined assembly point in a safe part of
possible, one should accept outgoing calls only, the works. In some cases, particularly where
in order to bypass jammed switchboards during toxic releases are being considered, alternative
an emergency ; assembly points need to be arranged to allow
Major hazard control
for the effects of wind direction. Assembly (e) Rehabilitation. The emergency will continue
points need to be clearly marked. The plan until all fires have been extinguished with no
should designate someone to record all risk of reignition or, for a gas release, when the
personnel arriving at the assembly point so that escape has been stopped and the gas cloud
the information can be passed to the safely dispersed. Even then, care is required
emergency control centre. when re-entering the incident area. The local
(b) Accounting for personnel. It is important to be factory inspectorate may wish to initiate an
able to account for personnel during an inquiry and should be consulted regarding the
emergency, but it can be particularly difficult. collection of evidence before it is disturbed.
Because of visitors, contractors, shift changes, 6.2.6. Planning shut-down procedures
holidays and sickness absence, it is normally
not practical to maintain a detailed roll of For single plant sites, shut-down procedures
personnel on site at any one time. Nominal may be comparatively simple, with no knock-on
rolls, which can be updated during the early effects elsewhere on site. With complex sites, such
stage of an emergency, are usually kept. as large petrochemical works or refineries, plant
Detailed lists of contractors on site should be operations are often interlinked and the shut-down
maintained, with a similar list for visitors. of any key plant on site (e.g. a power station) may
have significant implications for other plant.
At the emergency control centre, a nominated Emergency plans will need to take account of this
person should collate the lists of personnel so that ordered and phased shut-downs can take
arriving at the assembly points with those place when necessary, depending on the type of
involved in the incident. These should then be incident occurring.
checked against the nominal roll of those
believed to be on site, updated with known 6.2.7. Rehearsing emergency procedures
changes for that day. Where it is possible that Once the emergency plan is finalised, it should
missing people might have been in the area of be made known to all personnel so that each knows
the emergency, the incident controller should his or her role in the event of an emergency. It is
be informed and arrangements made to essential that the plan is regularly tested because it
organise a further search. is only through such rehearsals that defects become
(c) Access to records. This will be necessary in apparent. The plan can be tested in a number of
order that relatives of any casualties can be different ways. Communication is a key component
quickly informed. It is suggested that lists of of handling an emergency and a rehearsal of the
names and addresses of works personnel communications system, including contingency
should be kept in the emergency control centre. action if part of the system (e.g. telephones)
These will need to be regularly updated to take becomes inoperative, should be undertaken.
account of changes in personnel, address, next Evacuation rehearsals should be regularly carried
of kin, and so on. out and should cause minimum disruption to the
normal activities. More elaborate exercises,
(d) Public relations. Any incident will attract the
involving the emergency services where they are
interest of the media, and a major accident is
part of the emergency plan, will also need to take
likely to involve widespread radio and television
place.
coverage. Unless appropriate arrangements are
made, this can divert personnel from the task of Many organisations use table-top exercises to
handling the emergency. It is essential to make test their emergency plans. These are very cost-
arrangements for the authoritative release of effective because they do not interrupt the day-to-
information during any emergency of day running of the plant and because the organiser
significant length, and a senior manager or of the exercise can "arrange" for a variety of
member of the staff should be appointed as the difficulties to arise which will need on-the-spot
sole source of this information. Inquiries made decisions to be taken. Full-scale exercises,
to other employees should be directed to this providing a realistic rehearsal setting, will still be
appointed person. needed to complement the table-top exercises.
Emergency planning
6.2.8. Plan appraisal and updating of the off-site activities. As with the on-site plan,
an emergency control centre will be required within
Emergency planning rehearsals and exercises
which the emergency co-ordinating officer can
should be monitored by observers not involved in
operate.
the exercise, and preferably independent of the
site, e.g. senior officers from the emergency An early decision will be required in many
services or factory inspectorate. After each cases on the advice to be given to people living
exercise, the plan should be thoroughly reviewed to "within range " of the accident - in particular
take account of omissions or shortcomings. whether they should be evacuated or told to go
Emergency plans, particularly for complex sites, are indoors. In the latter case, the decision can
the subject of continual refinement and updating, regularly be reviewed in the event of an escalation
but it is important that any changes of substance of the incident. Consideration of evacuation may
are made known to those likely to be involved in include the following factors :
that part of the plan when used for a real in the case of a major fire but without explosion
emergency. risk (e.g. an oil storage tank), only houses close
to the fire are likely to need evacuation,
6.3. Off-site emergency planning although a severe smoke hazard may require
6.3.1. Introduction this to be reviewed periodically ;
The off-site emergency plan is an integral part if a fire is escalating and in turn threatening a
of any major hazard control system. It should be store of hazardous material, it might be
based on those accidents identified by the works necessary to evacuate people nearby, but only
management which could affect people and the if there is time ; if insufficient time exists,
environment outside the works. Thus, the off-site people should be advised to stay indoors and
plan follows logically from the analysis that took shield themselves from the fire. This latter case
place to provide the basis for the on-site plan and particularly applies if the installation at risk
the two plans should therefore complement each could produce a fireball with very severe
other. The off-site plan in detail should be based on thermal radiation effects (e.g. LPG storage) ;
those events which are most likely to occur, but for releases or potential releases of toxic
other less likely events which would have severe materials, limited evacuation may be
consequences should also be considered. Incidents appropriate down wind if there is time. The
which would have very severe consequences yet decision would depend partly on the type of
have a small probability of occurrence will be in housing " at risk " . Conventional housing of solid
this category, although there will be certain events construction with windows closed offers
which are so improbable that it would not be substantial protection from the effects of a toxic
sensible to consider them in detail in the plan. cloud, while shanty houses which can exist
These events might include aircraft crashes on to close to factories, particularly in developing
the installation. However, the key feature of a good countries, offer little or no protection.
off-site emergency plan is flexibility in its
application to emergencies other than those The major difference between releases of toxic
specifically included in the formation of the plan. and flammable materials is that toxic clouds are
generally hazardous down to much lower
The roles of the various parties who may be concentrations, and therefore hazardous over
involved in the implementation of an off-site plan
greater distances. Also, a toxic cloud drifting at,
are described below. Depending on local
say, 300 metres per minute covers a large area of
arrangements in different countries, the
land very quickly. Any consideration of evacuation
responsibility for the off-site plan will be likely to
must take this into account.
rest either with the works management or, as is the
case under European Community legislation, with Although a plan should have sufficient
the local authority. Either way, the plan must flexibility built in to cover the consequences of the
identify an emergency co-ordinating officer range of accidents identified for the on-site plan, it
(subsection 6.3.3) who would take overall command is suggested that it should cover in some detail the
Major hazard control
have appointed an emergency planning officer to play following a major accident, and they should
(EPO) to carry out this duty as part of the EPO's form an integral part of any emergency plan.
role in preparing for a whole range of different For major fires, injuries will be the result of the
emergencies within the local authority area. The effects of thermal radiation to a varying degree, and
EPO will need to liaise with the works to obtain the the knowledge and experience to handle this in all
information to provide the basis for the plan. This but extreme cases may be generally available in
liaison will need to be maintained to ensure that most hospitals. For major toxic releases, the effects
the plan is continually kept up to date. vary according to the chemical in question, and it
It will be the responsibility of the EPO to ensure is important for health authorities who might be
that all those organisations which will be involved involved in dealing with the aftermath of a toxic
off site in handling the emergency know of their release to be familiar with the treatment
role and are able to accept it by having, for appropriate to such casualties.
example, sufficient staff and appropriate equipment Major off-site incidents are likely to require
to cover their particular responsibilities. medical equipment and facilities additional to those
Rehearsals for off-site plans are important for available locally, and a medical "mutual aid "
the same reasons as on-site plans (section 6.2) and scheme should exist to enable the assistance of
will need to be organised by the EPO. neighbouring authorities to be obtained in the
event of an emergency.
6.3.6. Role of the police
6.3.9. Role of the government safety
The overall control of an emergency is normally
authority
assumed by the police, with a senior officer
designated as emergency co-ordinating officer This will be the factory inspectorate in most
(subsection 6.3.3). countries. Inspectors are likely to want to satisfy
themselves that the organisation responsible for
Formal duties of the police during an producing the off-site plan has made adequate
emergency include protecting life and property and arrangements for handling emergencies of all types,
controlling traffic movements. including major emergencies. They may wish to
Their functions include controlling bystanders, see well-documented procedures and evidence of
evacuating the public, identifying the dead and exercises undertaken to test the plan.
dealing with casualties, and informing relatives of In the event of an accident, local arrangements
death or injury. regarding the role of the factory inspector will
6.3.7. Role of the fire authorities apply. These may vary from keeping a watching
The control of a fire is normally the responsi- brief to a close involvement in advising on
bility of the senior fire brigade officer who would operations. In cases where toxic gases may have
take over the handling of the fire from the site been released, the factory inspectorate may be the
incident controller on arrival at the site. The senior only external agency with equipment and resources
fire brigade officer may also have a similar to carry out tests.
responsibility for other events, such as explosions In the aftermath, factory inspectors may wish
and toxic releases. Fire authorities having major to ensure that the affected areas are rehabilitated
hazard works in their area should have familiarised safely. In addition, they may require items of plant
themselves with the location on site of all stores of and equipment essential for any subsequent
flammable materials, water and foam supply points, investigation to be impounded for expert analysis,
and fire-fighting equipment. They may well have and may also want to interview witnesses as soon
been involved in on-site emergency rehearsals both as practicable.
as participants and, on occasion, as observers of
exercises involving only site personnel. 6.4. Rehearsals and exercises in
6.3.8. Role of the health authorities off-site emergency planning
Health authorities, including doctors, surgeons, Extensive experience in the chemical industry
hospitals, ambulances, and so on, have a vital part with on-site emergency planning has proved the
Major hazard control
need and value of rehearsals of emergency necessary to gather the information needed for
procedures. overall co-ordination, e.g. between works and
emergency services, and between the works
The organisation responsible for producing the
emergency control centre and the incident.
off-site plan should test its arrangements in
conjunction with on-site exercises. Table-top Managements of major hazard works are well
rehearsals have proved extremely useful in such placed to advise on the setting up of rehearsals,
cases, although needing close control to maintain a and particularly to advise on the scope for an
sufficient element of realism in the exercises. escalation in the degree of emergency.
An essential component of any trial is that of
testing fully the various communication links
7. Implementation of major
hazard control systems
7.1. Introduction Any definition for identifying major hazards is
"
sophisticated inspection and enforcement regimes, Once the definition has been finalised, the next
on the one hand, requiring the co-ordinated stage is to identify where the major hazard works
attention of many different authorities at local and exist for any particular region or country. If the
national level, to very limited inspection definition has been established in legislation, works
programmes, on the other, often concentrating on coming within its scope may have been required to
the structural integrity of buildings and excluding notify their activity to the control authority.
the major hazard aspects of the operations. Where, however, a country wishes to identify
This wide variability of control means that the major hazard works before the necessary legislation
speed of implementation of a major hazard control is in place, considerable progress can be achieved
system will depend on the facilities already existing informally, particularly where the co-operation of
in each country, particularly with regard to trained industry is available. Existing sources such as
and experienced factory inspectors, together with factory inspectorate records, information from
the resources available locally and nationally for the industrial bodies, and so on, may enable a
different components of the control system provisional list to be obtained which, apart from
described in this manual. allowing early inspection priorities to be allocated,
will enable an assessment to be made of the
For all countries, however, implementation will
resources required for different parts of the control
require the setting of priorities for a stage-by-stage
system. These provisional arrangements would
programme. It is most important that, where
need to be confirmed legally a s soon as practicable.
existing control arrangements are few, the planned
programme should not attempt too much too soon.
Experience has shown that this leads easily to a 7.3. Setting priorities
slippage in the planned time for meeting targets, 7.3.1. Establishment of a group of
with a subsequent general loss of morale. experts
For countries considering establishing a major
7.2. Identification of major hazard control system for the first time, an
hazards important first stage is likely to be setting up a
This is the essential starting-point for any major group of experts as a special unit at government
hazard control system - the definition of what level. The unit should consist mainly of trained
actually constitutes a major hazard. Any list needs engineers (particularly chemical engineers),
to be clear and unambiguous in order that all the chemists and physicists, and should have the task
organisations involved in implementing the various of advising government, industry management,
components of a system can establish quickly trade unions, local authorities, factory
which works come within the definition and which inspectorates, and so on, on all aspects of
do not. establishing a control system. Where the expertise
is not readily available, it may be necessary to
Although definitions exist in some countries
consider seconding experts from industry,
and particularly in the EC, a particular country's
universities or consultancies, possibly part time, to
definition of a major hazard should reflect local
assist in this important work.
priorities and practices and, in particular, the
industrial pattern in that country. It would be Where resources available for new major hazard
particularly unhelpful, for example, to bring within work are very limited, it is important not to dilute
scope far more works than the control authority this effort by moving experts away from a central
could allocate resources for. base to work in areas on their own. The resources
Major hazard control
are generally better kept together as an expert unit Once the plan has been drawn up, early
in which members can develop as a team and pool rehearsals are essential to identify its weaknesses
their individual experiences. (particularly in the chain of communication) and to
rectify them.
The group will have to set priorities in deciding
on its early work programme. Where definitions of 7.3.3. Emergency planning off site
major hazards have already been decided and the
works identified, these can be collated for the A fuller description of off-site emergency
whole country, with early priorities being directed planning is given in section 6.3. This is an area
at the most commonly occurring major hazards which has received less attention than on-site
(likely to be chlorine ammonia and LPG). emergency planning, and many countries will be
faced with considering this for the first time.
The group may be required to train factory
inspectors in the techniques of major hazard Advice can be obtained from the countries of
inspection, including operational standards for such the EC, which has a requirement for off-site
works. They will need to be familiar with the planning for all the largest major hazard works.
methods for major hazard assessment (e.g. hazard Here, the duty is placed on the local authority to
and operability studies) and to be able to advise draw up the plan based on information about
government, industry and local authorities when assessed accidents and their consequences
they are considering new or modified projects and obtained from the works.
drawing up emergency plans.
It may well be the case in some countries that
They should also be able to provide advice this duty is more appropriate for the works than for
about the siting of new major hazards and the use the local authority, for it is at works management
of land nearby, e.g. for residential development. level that the technical expertise lies, often with the
support of a multinational organisation.
They will need to establish contacts in other
countries in order to keep up to date with major The off-site emergency plan will have to link
hazard developments, including new technologies the possible accidents identified by the works, their
and legislative changes. expected likelihood of occurrence and the proximity
of people living and working nearby. It must have
7.3.2. Emergency planning on site addressed the need for evacuation and how it
A fuller description of on-site emergency might be achieved - bearing in mind that
planning is given in section 6.2. On-site emergency conventional housing of solid construction offers
planning should not be confined to major hazard substantial protection from toxic gas clouds
works but is fully appropriate to a whole range of whereas a shanty-type house is vulnerable to such
activities storing hazardous materials in smaller accidents, and also remembering that sufficient
time is often unavailable to allow widespread
quantities. It is likely to have been recognised
evacuation.
already by the managements of major hazards as
requiring priority attention. Existing legislation may
Finally, the emergency plan must identify
well have required emergency plans to have been organisations whose help will be required in the
drawn up as part of the general duty of safe event of an emergency and must ensure that they
operation. Where this is not the case, it should be know what role is expected of them : hospitals and
remedied urgently. medical staff should, for example, have decided
Emergency plans require that the works be how they would handle large numbers of casualties
assessed for the range of accidents that could take and in particular what treatment they would give to
place, together with how they would be tackled in them. This is particularly important for accidents
practice. The handling of these potential accidents involving the lesser-known toxic gases.
will require both staff and equipment, and a check
should be made to ensure that both are available in The off-site emergency plan will need to be
sufficient numbers. rehearsed ; fuller details are given in section 6.3.
Implementation of control systems
Detailed references are available for a range of the time carefully. It is likely that at each visit a
check-lists, including management systems, plant different sample will be selected for inspection,
siting, plant layout, physical and chemical leading over time to a full coverage of the site. With
properties, process design, fire precautions, this in mind, and with inspectors changing over
training and incident investigations (Lees, 1980). the years, it is important to keep accurate records
of what was inspected and the actions which arose
7.3.7. Inspection of works by factory
from that inspection. If the inspector then moves
inspectors
job, his or her successor can look at the file and
This section describes aspects to be considered maintain continuity with the overall strategy for
by inspectors at major hazard works. Necessarily, it that works.
concentrates on the techniques of identifying and
inspecting items of plant which, in the event of a A key part of the inspection will be to check
failure, would give rise to a serious risk to the that operators are familiar with the safety aspects
safety of personnel both on and off site. of the plant, both hardware and software, and have
clear operating instructions covering, for example,
The work of a generalist factory inspector will their required action in the event of process
depend on whether he or she has specialist deviation. Works inspection, testing and
inspectors (subsection 7.3.8)in support. Here it is maintenance schedules will need to be examined
assumed that this is the case. Where it is not, this for the sample of plant selected. The inspector
section and the next dealing with the work of would also need to check the emergency
specialist inspectors should be read together. procedures for that plant and their integration into
The majority of serious incidents arise from the the overall on-site emergency plan.
loss of containment of a hazardous substance. 7.3.8. Inspection of works by
Therefore, it is necessary in the first instance to specialists
identify those items of plant which contain
Specialist inspectors will include electrical,
hazardous materials in sufficient quantity to cause
mechanical, civil and chemical engineers. Their
a serious incident.
role is likely to be to provide specialist support to
The responsibilities arising from major hazard the generalist factory inspectors, including advice
works fall on the works managements, and it is on the selection of samples for inspection, and then
they who should provide the expertise and to apply their specialist skills in the subsequent
resources to evaluate the risk of their own inspection.
operations - and to take precautions accordingly.
Their work will include such procedures as :
The role of the factory inspector as the enforcing
authority is to make sufficient checks on what (a) inspecting pressure vessels for design,
management has done to be satisfied of its operation and maintenance to approved
competence to operate the plant safely and to standards ;
maintain control in the event of an incident. (b) checking computer-controlled chemical plant
for software integrity ;
Factory inspectorates normally do not have the
resources fully to inspect every item of plant and (c) checking the layout of liquefied gas
every operational procedure at a major hazard installations together with the associated fire
works. These need to be sampled, and the setting precautions ;
of priorities will be necessary, particularly at the (d) checking the procedures for plant modifications
largest plants, in order that the appropriate sample to maintain the initial integrity of the plant after
selection is made. Sampling here means the modification ;
selection of a plant component (e.g. a pressure
(e) checking the design and maintenance
vessel) as representing a number of similar
procedures for pipelines carrying hazardous
components, and then inspecting this sample in
materials.
depth. A factory inspector faced with the
inspection of a large site must estimate the Specialist inspectors should be aware of the
resources available to achieve this and then plan world-wide experience of accidents involving their
Implementation of control systems
particular discipline and be able to advise factory site populations, which may determine whether the
inspectors and works management on that basis. process or plant can be put into operation.
Above all, specialist inspectors, particularly Evaluation, then, involves examining the plant
those chemically based, would be likely to have and asking such questions as "What if . . . ? ",
first-hand experience of some of the major hazard " How likely . . . ? " and " Could it happen? ", and
substances. Their advice may be crucial when deciding on actions leading from that assessment.
factory inspectors are faced with licence 7.3.10. Actions arising from evaluation
applications to start a new major hazard works,
particularly in relation to conditions which may Evaluation in conjunction with the factory
need to be applied, and to a consideration of the safety report provides a basis for :
potential off-site impact. (a) deciding if a new process can be licensed ;
7.3.9. Evaluation of major hazards (b) deciding on the layout of a new plant or
process ;
This should be carried out by specialists, if
possible, according to guide-lines drawn up, for
(c) deciding on hardware and software control
requirements, e.g. automatic shut-off valves ;
example, by the group of experts (subsection 7.3.1)
or by specialist inspectors or general factory (d) formulating an on-site emergency plan and
inspectors, possibly with assistance from the works providing information for an off-site emergency
management. Evaluation involves a systematic plan ;
study for major accident hazard potential, including (e) deciding on the separation required between
knock-on effects, missiles, and so on. It will be a the works and the neighbourhood ;
similar exercise, although in much less detail, to
(f) deciding the extent to which the public in the
that carried out by the works management in
neighbourhood should be informed about the
producing its safety report for the factory
major hazard (subsection 7.3.11).
inspectorate and in establishing an on-site
emergency plan. 7.3.11. Information to the public
Evaluation will include a study of all handling Experience of major accidents, particularly
operations of hazardous materials, including those involving toxic gas releases, has shown the
transport, because it is in this general category that importance of the public nearby having prior
major hazard accidents are most frequent. warning of: (a) how to recognise that an
emergency is occurring ; (b)what action they
An examination of the consequences of process should take ; (c)what remedial medical treatment
instability or major changes in the process variables would be appropriate for anyone being affected by
will be included. The works management should the gas. EC legislation now requires those living
have looked at this in detail during the hazard and near to the largest major hazard sites to be given
operability study at the design stage, but an information, particularly covering their action in the
independent examination, albeit again in much less event of an emergency. For inhabitants of
detail, is well worth while. conventional housing of solid construction, the
The evaluation should also look at the advice in the event of an emergency usually is to
positioning of one hazardous material in relation to go indoors and close all doors and windows, switch
another, e.g. are potentially explosive substances off all ventilation or air conditioning, and switch on
too close to pressurised toxic gases? the local radio for further instructions.
The consequences of common mode failure will Where large numbers of shanty-dwellers live
also need to be assessed, e.g. what would be the close to a works, this advice would be
consequences of a total and sudden loss of power inappropriate because, for example, of the low
feeding both plant and safety features? protection from gas clouds that such housing offers,
and large-scale evacuation might be necessary. The
The evaluation will consider the consequences difficulties of this are discussed in section 6.3. In
of the identified major accidents in relation to off- these cases, film shows are considered a useful
Major hazard control
List of dangerous
substances and threshold
quantities
(derived from Annex I11 t o EC Directive
(82/501/EEC))
4-Aminodiphenyl
Benzidine
Benzidine salts
Dimethylni trosamine
2-Napthylamine
Beryllium (powders, compounds)
Bis(ch1oromethyl)ether
1,)-Propanesultone
2,3,7,8-Tetrachlorodibenzo-p-dioxin (TCOD)
Arsenic pentoxide, Arsenic ( V ) acid and salts
Arsenic trioxide, Arsenious (111) acids and salts
Arsenic hydride (Arsine)
Dimethylcarbamoyl chloride
4-(Chloroformyl ) morphol ine
Carbonyl chloride (Phosgene)
Chlorine
Hydrogen sulphide
Acryloni trile
Hydrogen cyanide
Carbon disulphide
Bromine
Amnon i a
Acetylene (Ethyne)
Hydrogen
Ethylene oxide
Propylene oxide
2-Cyanopropan-2-01 (Acetone cyanohydrin)
2-Propenal (Acrolein)
2-Propen-1-01 (Ally1 alcohol )
Allylamine
Antimony hydride (Stibine)
Ethyleneimine
Formaldehyde (concentration 2 90%)
Hydrogen phosphide (Phosphine)
Bromomethane (Methyl bromide)
Methyl isocyanate
Nitrogen oxides
Sodium selenite
Bis(2-chloroethyl )sulphide
Phosacetim
Tetraethyl lead
Tetramethyl lead
Promurit (I-(3.4-Dichloropheny1)-3-triazenethio-
carboxami de
Chlorfenvinphos
Crimidine
Chloromethyl methyl ether
Dimethyl phosphoramidocyanidic acid
Carbophenothion
Dialifos
Cyanthoate
Ami ton
52. Oxydisulfoton
53. 00-Diethyl S-ethylsulphinylmethyl phosphorothioate
54. 00-Diethyl S-ethylsulphonylmethyl phosphorothioate
55. Disulfoton
56. Demeton
57. Phorate
58. 00-Diethyl S-ethylthiomethyl phosphorothioate
59. 00-Diethyl S-isopropylthianethyl phosphorodithioate
60. Pyrazoxon
61. Pensulfothion
62. Paraoxon (Diethyl 4-nitrophenyl phosphate)
63. Parathion
64. Azinphos-ethyl
65. 00-Diethyl S-propylthiomethyl phosphorodithioate
66. Thionazin
67. Carbofuran
68. Phosphamidon
69. Tirpate'2.4-Dimethyl-1,3-dithiolane-2-carboxaldehyde
0-methylcarbanmyloxime
70. Mevinphos
Cycloheximide
Diphacinone
Tetramethylenedisulphotetramine
EPN
4-Fluorobutyric acid
4-Fluorobutyric acid, salts
4-Fluorobutyric acid, esters
4-Fluorobutyric acid, amides
4-Fluorocrotonic acid
4-Fluorocrotonic acid, salts
4-Fluorocrotonic acid, esters
4-Fluorocrotoni c acid, amides
Fluoroacetic acid
Fluoroacetic acid, salts
Fluoroacetic acid. esters
Fluoroacetic acid, amides
Flueneti 1
4-Fluoro-2-hydroxybutyric acid
4-Fluoro-2-hydroxybutyric acid, salts
4-Fluoro-2-hydroxybutyric acid, esters
4-Fluoro-2-hydroxybutyric acid, amides
Major hazard control
139. Chlorotrinitrobenzene
140. N-Methyl-N,2,4,6-N-tetranitroaniline
141. 2.4,6-Trinitrophenol (Picric acid)
142. Trini trocresol
143. 2,4,6-Trinitrophenetole
144. 2.4,6-Trinitroresorcinol (Styphnic acid)
145. 2,4,6-Trinitrotoluene
146. (a) Annmnim nitrates'
(b) Annmniwn nitrates in the form of fertilisers2
147. Cellulose nitrate (containing > 12.6% nitrogen)
148. Sulphur dioxide
149. Hydrogen chloride (liquefied gas)
150. Flamnable substances as defined in Annex IV(c)(iii)
151. Sodium chlorate
152. tert-Butyl peroxyacetate (concentration 2 70%)
153. tert-Butvl ~eroxvisobutvrate (concentration > 80%)
154. tert-6ut;l beroxhaleate (conientration 2 BOX)
155. tert-Butyl peroxy isopropyl carbonate (concentration
2 80%)
156. Dibenzyl peroxydicarbonate (concentration 2 90%)
157. 2.2-~is(tert-buty1peroxy)butane (concentration 2 7 0 % )
158. 1.1-Bis(tert-butylperoxy)cyclohexane (concentration
2 80%)
159. Oi-sec-butyl peroxydicarbonate (concentration 2 80%)
160. 2 . 2 - D i h y d r o ~ e r 0 ~ y ~ r 0 ~ a(concentration
ne L 30%)
161. Di-n-propyl peroxydicarbonate (concentration 80%)
162. 3.3.6.6.9.9-Hexmthyl-1.2,4.5-tetroxacyclononane
(concentration 2 75%)
163. Methyl ethyl ketone peroxide (concentration 2 60%)
164. Methyl isobutyl ketone peroxide (concentration 2 6 0 % )
165. Peracetic acid (concentration 2 6 0 % )
166. Lead azide
167. Lead 2,4,6-trinitroresorcinoxide (Lead styphnate)
168. Mercury fulminate
169. Cyclotetramethylenetetranitramine
170. 2,2',4,4'.6,6'-Hexanitrostilbene
171. 1,3,5-Triamino-2.4,6-trinitrobenzene
172. Ethylene glycol dinitrate
173. Ethyl nitrate
174. S o d i m picramate
175. Barium azide
176. Di-isobutyryl peroxide (concentration 2 50%)
177. Diethyl peroxydicarbonate (concentration 2 30%)
178. tert-Butyl peroxypivalate (concentration 2 77%)
179. Liquid oxygen
180. Sulphur trioxide
List of dangerous substances
Example of a rapid
ranking method for
the classification
of unitdplant elements
(reproduced from the section on "Description of
foreseeable hazards and of preventive provisions to
control such hazards " , in Operational safety report :
Guideline for the compilation, Draft manual,
Netherlands, Directorate-General of Labour, Labour
Inspectorate.)
Example of a rapid ranking method
This shows how a rapid ranking system can be In the case of storage of dangerous substances
used in order to classify separate elements of plant in packaging units (bags, bottles, drums, etc.), the
within an industrial complex. It is a simplified total of packaging units stored in one location is
version of the method established by the Dow regarded as one plant element.
Chemical Company. Besides this rapid ranking
method, other methods are available. Generally, the
more laborious the method, the more reliable are
the results as an indication of the hazards.
2. Determination of fire and
explosion index F and toxicity
index T
1. Subdivision of the installation
For each separate plant element which
Before hazard indexing can be applied, the contains flammable or toxic substances, a fire and
installation in question should be subdivided into explosion index F andlor a toxicity index T may be
logical, independent elements or units. In general, a determined in a manner derived from the method
unit can logically be characterised by the nature of for determining a fire and explosion index
the process that takes place in it. In some cases, developed by the Dow Chemical Company (United
the unit may consist of a plant element separated States).l
from the other elements by space or by protective
walls. The fire and explosion index F is calculated
from :
A plant element may also be an apparatus,
instrument, section or system that can cause a
F = MF x (1 + GPH,,) x (1 + SPH,,,),
specific hazard. in which :
MF = material factor = a measure for the
Examples of logical, independent units are
potential energy of the dangerous
given below :
substances present (according to
- feed section ; National Fire Protection Association
(NFPA) data : see section 3) ;
- heating sectionlcooling section ;
- reaction section ; GPH,,, = general process hazards = a measure for
the hazards inherent in the process (from
- compression section ; the nature and characteristics of the
- distillation section ; process : see section 4) ;
- wash section ; SPH,,, = special process hazards = a measure for
the hazards originating from the specific
- collection system ;
installation (process conditions, nature
- filtration section ; and size of the installation : see section
- buffer tanks ; 5).
- prill tower ;
The toxicity index T is calculated from
- destruction section ;
- flare system ;
- blow-down system ;
- recovery section ;
in which :
- quench section, etc
T, = toxicity factor (obtained from NFPA data (see
In the case of storage installations, each tank, section 6) ;
bunker and silo is regarded a s a separate unit. T, = supplement for MAC-value (see section 6)
Major hazard control
For GPH,,, and SPH,,, the same values apply as for and solids, volume percentage for gases) need not
the determination of the fire be considered here.
and explosion index.
For the determination of F and T, a form may 3. Determination of the material
be used which is inserted in table 2.1. factor MF
Where more than one dangerous substance The starting-point for the calculation of the fire
occurs in one plant element, a fire and explosion and explosion index is the material factor. This
index F and/or a toxicity index T must be factor is a measure of the energy potential of the
determined - when desired with the help of the most hazardous material, or mixture of materials,
form - for each substance. present. The material factor is denoted by a
When determining the hazard category of the number from 0 to 40, with the higher numbers
plant element, the highest values found for F or T indicating greater energy available.
respectively are applied. The material factor is determined using only
Substances which occur in a concentration of two properties - flammability 2 and reactivity -
less than 5 per cent (weight percentage for liquids characterised by instability and water reactivity of
Table 2.1 Determination of the fire and explosion index F and of the toxicity index T
used".
Exothermic r e a c t i o n s 4.1
Endothermic r e a c t i o n s 4.2 0.20
M a t e r i a l h a n d l i n q and t r a n s f e r 4.3
Process u n i t s w i t h i n a b u i l d i n a
Add: GPHtot
4.4
-
(1 + GPHtot) x m a t e r i a l f a c t o r MF = sub-factor
- I n storaae I
C o r r o s i o n and e r o s i o n 5.7 1
Leakaqe i o i n t s and o a c k i n q 5.8 1
*
-
-
Add: SPH
( 1 + SPHtot) x s u b - f a c t o r f i r e and e x p l o s i o n i n d e x F
TOXICITY INDEX T ( s e e 6)
Th + T
100
( 1 + GPH
tot
+ SPH
tot)
- T o x i c i t y index T c
I * The t e r m "process" i n c l u d e s h a n d l i n g as w e l l as s t o r a g e .
I
C o n s u l t 4 and 5 f o r t h e p e n a l t y t o be used. For a number o f process hazards t h e p e n a l t y t o
be used i s f i x e d and can be taken f r o m t h e p r e c e d i n g column " p e n a l t y " .
Example of a rapid ranking method
a chemical. The material factors for many materials For a flashpoint below -20' C the hazard value
are listed in Appendix 2 (a). The material factor for flammability is 4. This may be checked by
should be determined for every dangerous calculating H,, :
substance occurring in the plant element. H,, = 1780.78 x 0.745 = ca. 1326 kJ.bar/mol.
The material factor may be derived from table An H,, of 1326 gives a hazard value of 4 for
2.2, using the numerical value for both flammability flammability.
and reactivity as contained in NFPA l i t e r a t ~ r e . ~
The adiabatic decomposition temperature is :
For example, ethylene oxide with a
flammability of 4 and a reactivity of 3 leads to a
T, = 675 + 273 = 948 K.
material factor of 29 from table 2.2. Acrylic acid, This gives a hazard value of 2 for reactivity. On
with a flammability of 2 and a reactivity of 2, leads the basis of table 2.2, a material factor of 24 will be
to a material factor of 24 from table 2.2. applicable to propylene oxide.
Flashpoint or Hcv can be used for flammability
N,. The value of H,, is calculated by multiplying the 4. Determination of general
heat of combustion, kJImol, by the vapour pressure
at 300K (27" C) in bar. For materials boiling below
process hazards
300K use 1.00 for vapour pressure. For N,use the 4.1. Exothermic reactions
adiabatic decomposition temperature T,. 4.1.1.
A 0.20 penalty is required for :
For example, propylene oxide has the following - combustion = the combustion of solid, liquid or
basic properties : gaseous fuel with air as in a furnace.
- flashpoint below -20" C ; 4.1.2. The following reactions require a 0.30
- heat of combustion 30.703 kJ/g ; penalty :
- mol. weight 58 ; (a) hydrogenation = the addition of hydrogen
- heat of combustion is thus 30.703 x 58 = 1780.78 atoms to both sides of a double or triple bond ;
kJ/mol ; hazards are the use of hydrogen under
pressure and at a relatively high temperature ;
- vapour pressure 0.745 bar (27" C);
hydrolysis = the reaction of a compound with
- decomposition temperature 675" C . water, such as the manufacture of sulphuric or
phosphoric acids from oxides ;
Table 2.2. Determination of material factor
alkylation = addition of an alkyl group to a
compound to form various organic
-
Adiabatic 830- 935- 1010-
decomposition< 830 ,1080
temp.Td K 935 1010 1080 compounds ;
I reactivity
I isomerisation = rearrangement of the atoms
Flash Hcv
in an organic molecule, such as a change from
PO; n t kJ.baymo, a straight chain to a branched molecule, or
displacement of a double bond ; hazards are
None <4.10-~ 0 dependent on the stability and the reactivity
-
of the chemicals involved and may in some
> 100 ~.10-~-2.5 1
LO-100 2.5-LO
->r
.-
-
2
cases require a penalty of 0.50 ;
sulfonation = introduction of an S03H radical
. z - into an organic molecule through reaction
-20-+LO LO- 600 3 with H2S04;
"- -
neutralisation = reaction between an acid and
<-20 >600 C
I a base, to produce a salt and water.
1 Material Factor MF I
4.1.3. The following require a 0.50 penalty :
59
Major hazard control
(b) Apply penalty of 0.60when process or Figure 2.1. Penalty for operating pressure
handling conditions are above atmospheric
boiling point.
(c) Materials such as hexane and carbon
disulphide have low auto-ignition
temperatures and can be ignited on hot steam
lines : penalty 0.75.
5.2. Low pressure
No penalty is required for processes that
operate at atmospheric or sub-atmospheric
pressure, provided air leakage into the system will
not create a hazard. Example : vacuum distillation
of glycols.
(a) When air leakage into the system could create
a hazard, apply a 0.50penalty. Example :
handling pyrophoric materials, diolefins with
hazard of peroxide formation and catalysed
polymerisation.
(b) Hydrogen collection systems require a 0.50 Operating pressure : bar (absolute) +
penalty.
The penalty Y may also be calculated with the
(c) Any vacuum distillation at less than 0.67 bar formula Y = 0.435 log P, in which P is the absolute
absolute should be penalised at 0.75if air or
contaminants leaking into the system could pressure at which the relief valve is set, expressed
create a hazard. in bars.
The penalty curve in figure 2.1 is for flammable
5.3. Operation in or near flammable range
and combustible liquids and must be corrected for
(a) Storage of flammable materials requires a other materials as follows
penalty of 0.50for outdoor tanks, if the gas-air
(a) for highly viscous materials such as tars,
mixture in the vapour space is generally in or
bitumen, heavy lubricating oil and asphalts,
near the flammable range.
multiply the penalty b y 0.7;
(b) For processes that operate close to the
flammable limits or where it is necessary to (b) for compressed gases, multiply the penalty b y
,I o.
1.L,
use instrumentation and/or nitrogen or air
purging to stay outside the explosion limits, (c) for pressurised liquefied flammable gases,
use a 0.75penalty. Examples : oxidation of multiply the penalty b y 1.3;
toluene to benzoic acid, dissolving of rubber, (d) penalties are not applicable to extrusion or
direct oxidation in ethylene oxide process. moulding operations.
(c) For processes that normally operate in the 5.5. Low temperature
flammable range, use a 1.00penalty.
Examples : ethylene oxide distillation and (a) For processes that operate between 0" C and
storage. -30" C, add 0.30.
5.4. Operating pressures (b) For processes that operate below -30" C, add
0.50.
Operating pressures above atmospheric
pressure require a penalty which will increase as The purpose is to make allowance for presumed
brittleness. Moreover, in case of leakage, cold liquid
the operating pressure increases.
will come into contact with the relatively hot
The penalty to be applied is given in figure environment, which can cause considerable
2.1. evaporation.
Major hazard control
5.6.2. In storage
1 ;:::
For flammable substances in storage, the
penalty to be used with respect to the quantity
A
-;,,,
U
0.60
-
liquids (curve B). 0.1 0
.2 L .6 .8 1.0 2 L 6 8 10 20 LO 60
The penalty Y may also be calculated with : Energy in kJ X lo9
b
- resistant linings (plastics, brick, etc.) liable to Curve A : pressurised liquefied gas
damage at seams, joints or pinholes. Curve B : flammable liquids.
Example of a rapid ranking method
5.8. Leakage of joints and packing Table 2.4. Penalty T, for MAC-value
gasket^,^ sealing of joints or shafts and packing Mac-ppm Penalty T.
can be sources of leaks, particularly where thermal
or pressure cycling occurs. A penalty factor should
be selected according to the design and materials
chosen for these items, as follows :
pump and gland seals likely to give some The toxicity index (T) is now calculated as
leakage of a minor nature : 0.10 ; follows :
processes known to give regular leakage
problems on pumps and flange joints : 0.20;
T= Th + Ts (1 + GPH,, + SPHtot).
100
process fluids penetrating in nature, abrasive
In this the material which gives the highest
slurries which cause continuous sealing
problems : 0.40 ;
+
value of T, Ts is determining.
GPH,, = the total of General Process Hazard
sight glasses, bellows assemblies and
penalties (see section 4) ;
expansion joints : 1.50.
SPHtOt= the total of Special Process Hazard
penalties (see section 5).
Acetaldehyde 1-Chlorobutane
Acetic acid Chloroform
Acetic anhydride Chloromethylethyl ether
Acetone o-Chloro phenol
Acetonitrile Chloropicrin
Acetyl chloride 1-Chloropropane
Acetyl peroxide Chlorostyrene
Acetyl salcyl acid Coumarin
Acetylene o-Cresol
Acrolein Cumene
Acrylic acid Cumene hydroperoxide
Acrylamide Cyanuric acid
Acrylonitrile Cyclobutane
Allyl alcohol Cyclohexane
Allylamine Cyclohexanol
Allyl chloride Cyclopropane
Allyl ether
Ammonia Diesel fuel
tert-Amylacetate Dibutyl ether
Aniline o-Dichlorobenzene
p-Dichlorobenzene
Barium stearate 1,2-Dichloroethylene
Benzaldehyde 1,2-Dichloropropene
Benzene
Benzoic acid 3,5-Dichlorosalicylicacld
Benzoyl chloride Dicumyl peroxide
Benzoyl peroxide Dicyclopentadiene
Bisphenol A Diethyl amine
Bromobenzene
Diethyl benzene
Butane
Diethyl carbonate
1,3-Butadiene
Diethyl peroxlde
Butanol
Diethanolamine
1-Butene
Diethylene glycol
n-Butyl acetate
Diethylamine triamine
Butyl alcohol
Dlethyl ether
n-Butylamine
Butyl bromide Diisobutylene
n-Butyl ether Diisopropylbenzene
tert-Butyl hydroperoxide Dimethyl amine (anhy.)
Butyl nitrate 23Dimethyl propanol
tert-Butyl peroxide n-Dinitrobenzene
Butylene 2,4-Dinitro phenol
Butylene oxide m-Dioxane
Dioxolane
Calcium carbide Diphenyl oxide
Calcium stearate Dipropylene glycol
Carbon disulphide Di-tert-Butyl peroxide
Carbon monoxide Divinyl benzene
Chlorine dioxide Divinyl ether
Major hazard control
A guide to
hazard and
operability studies
(Originally published as Chemical Industry Safety
and Health Council of the Chemical Industries
Association : A guide to hazard and operability
studies (London, 1977) : reproduced by permission
of the United Kingdom Chemical Industries
Association Ltd., by whom copyright of the
material is held.)
Foreword
The Chemical lndustry is an industry concerned with innovation. It produces a
continual stream of new processes and products which sometimes involve working
at extremes of temperature, pressure, scale of operation or of toxicity. Major
changes lead in turn to a series of minor changes as knowledge increases and
processes are optimised.
There'is within the lndustry great and growing awareness of the necessity to
apply more systematic approaches to safety-particularly in plant design. In
addition, there is increasing pressure from society at large for improved standards
of safety.
Whenever something new is carried out there is the danger that some part of the
process will not behave in the expected manner and that such a deviation could
have serious effects on other parts of the process.
This guide introduces the technique and has been written to give an appreciation
of the method itself, its scope and its value.
Major hazard control
Note on presentation
The sequence of chapters has been arranged firstly to convey the basic principles
of the technique and then to place it in context.
Some preparative work is necessary before the examination and naturally there
is follow-up work to deal with and document the hazards exposed. Chapter 3
deals with the practical procedures for carrying out a Hazard and Operability Study.
Hazard and Operability Studies are not an end in themselves but are part of an
overall procedure for the initiation, design, construction, commissioning and
operation of facilities. Studies can be undertaken at various stages, the timing of
which is discussed in chapter 4.
Further aspects are discussed in Appendices. The first three deal with practical
applications including worked examples for various types of plant. Practical advice
is given subsequently on how to make a start with Hazard and Operability Studies,
how to train people to carry them out and how to provide a continuing support
for those engaged in them.
Hazard and operability studies
Contents
1 INTRODUCTION
2 PRINCIPLES OF EXAMINATION
2.1 The basic concept
2.2 A simple example
2.3 Meanings of guide words
2.4 Further advice on the use of guide words
3 THE PROCEDURE FOR A STUDY
3.1 Definition of objectives
3.2 Team composition
3.3 Preparative work
3.4 Examination in practice
3.5 Follow-up work
3.6 Recording
4 THE PROGRAMMING OF STUDIES
4.1 Early checking for major hazards
4.2 Studies at 'design freeze' stage
4.3 Studies pre start-up
4.4 Studies on existing plants
5 GLOSSARY OF TERMS
6 ACKNOWLEDGEMENTS
7 REFERENCES
APPENDICES
1 Application to a continuous plant
2 Application to a batch plant
3 Application to a proprietary item of equipment
4 How to start Hazard and Operability Studies
5 Training
6 The formalisation of Hazard and Operability Studies
Hazard and operability studies
I INTRODUCTION
Primarily, safety in the design of chemical plants relies on the application of
various codes of practice or design codes which are based on the wide experience
and knowledge of professional experts and specialists in the industry. Such
application is backed up by the experience of local plant managers and engineers
who have been involved in similar plants and who have had direct experience in
their operation.
All new projects embody some element of change but in the chemical industry
the degree of change from one plant to the next is often considerable. It is
important to recognise that the body of established experience expressed in codes,
etc is limited by the extent of existing knowledge and can only be relevant to the
extent to which it is possible to apply it to new products, new plant and new
methods of operation involved in the new design. It has become increasingly clear
in recent years that although codes of practice are extremely valuable, it is par-
ticularly important to supplement them with an imaginative anticipation of hazards
when new projects involve new technology.
The need to check designs for errors and omissions has been recognised for a
long time, but this has traditionally been done on an individual basis. Experts have
usually applied their special skills or experience to check particular aspects of
design. For example the instrument engineer would check the control systems
and having satisfied himself that the systems were satisfactory would put his mark
of approval on the design and pass it to the next 'expert'. This kind of individual
checking, provided it is carried out conscientiously, will obviously improve the
design but clearly it has little chance of detecting hazards concerned with the
interaction of a number of functions or specialisms. These hazards are likely to
result from the unexpected interaction of seemingly safe components or methods
of operation under exceptional conditions. If it is wished to study such interactions
in new designs, the combined skills of a group of experts is required. Their total
knowledge and informed imaginations can be used to anticipate whether the
plant will operate as intended under all possible circumstances.
This report provides a method of working for such a group so that they can carry
out their task systematically and thoroughly.
Material A
Material B \
Overflow
Reaction : A + B = C
Component B must not exceed Component A to avoid an explosion
The part of the plant examined i s outlined thus------------
The intention is partly described by the flowsheet and partly by the process control
requirements to transfer A at some specified rate. The first deviation is that
obtained by applying the guide word NOT, DON'T or NO to the intention. This is
combined with the intention to give
DON'T TRANSFER A
The flowsheet is then examined to establish the causes which might produce a
complete cessation of flow of A. These causes could be
i Supply tank is empty
ii Pump fails to turn-mechanical failure
-electrical failure
-pump is switched off, etc
iii Pipeline is fractured
iv Isolation valve is closed
Clearly some at least of these are conceivable causes and so we can say that this
is a meaningful deviation.
Major hazard control
We now apply the next guide word which is MORE. The deviation is
MORE A IS PASSED INTO THE REACTION VESSEL
The cause would be that the characteristics of the pump may, under some circum-
stances, produce excessive flow rate. If this cause is accepted as realistic, we
then consider the consequences
i The reaction produces C contaminated with an excess of A which goes on into
the next stage of the process
ii The excess flow into the reaction vessel means that some will leave the vessel
by the overflow
Four further guide words are in turn applied to the design intention of this part,
to ensure that all conceivable deviations are explored.
When the pipeline which introduces raw material A has been examined, it is
marked on the flowsheet as having been checked. The next part of the design is
then chosen for study and this could be the pipeline which introduces raw material
B into the reaction vessel. This sequence is repeated for every part of the design,
each line, the vessel auxiliaries such as stirrers, any services to the vessel such as
the provision of heating and cooling and the vessel itself. A chart of the sequence
is given in Figure 2. This particular approach is sometimes called the 'line by line'
method.
The proposed action is also noted if it can be agreed straight away. If there is
some doubt about the action or if further information is required, the matter must
be brought forward to a subsequent meeting.
Hazard and operability studies
Select a line
Examine consequences
Detect hazards
Repeat 6-10 for all meaningful deviations derived from first guide words
Repeat 5-1 2
End
8 Repeat 1-22 for all vessels o n flowsheet
The other related deviation is that which occurs when the design intention is
incompletely achieved. The guide words are PART OF and the deviation PART
OF TRANSFER A. This could mean
i A component of A is missing. Here a knowledge of the composition of A is
required so the effects of the missing component can be assessed
ii The omission of one or more reactors if the pump delivers A to more than one
reactor.
The final two deviations are again qualitative but none of the original design
intention is retained. The first of these is the opposite of the design intention. The
guide word is REVERSE and the deviation REVERSE TRANSFER OF A. This
means flow from the reactor back through the pump. The flowsheet is examined
to see if this is possible and the consequences are assessed.
Lastly, there is the complete substitution of the design intention by something else.
The guide words are OTHER THAN and the deviation is OTHER THAN TRANSFER
A. This could mean
i The transfer of a different material. The flowsheet is examined to see if this is
possible. Substitution could arise in a number of ways. For example, the wrong
material could be delivered or another material admitted via the T piece on the
suction side of the pump. Information would be gathered on possible materials
and their effects
ii A change in the implied destination, ie transfer of A somewhere other than the
reactor. lnspection of the flowsheet shows that this can happen via the T piece
iii A change in the nature of the activity. For example, can A solidify instead of
being transferred 7
When they are used on broadly-expressed intentions they are all applicable. They
may also be applied at the detailed level of descriptive words or phrases. However,
when they are applied to intentions expressed in fine detail, some restrictions and
even some modifications may be found necessary.
When they are applied to an activity such as REACT or TRANSFER it is usual to
find that all the guide words will generate intelligible notional deviations. Some-
times more than one deviation will be generated by one guide word. Similarly
when they are applied to substances, all guide words, with the possible exception
of REVERSE, will be intelligible. Again, more than one deviation may be developed.
For example, MORE STEAM can mean a greater quantity or rate of steam (a
capacity increase) or steam at higher pressure (an intensity increase).
When dealing at a more detailed level of design intention, some restriction will be
found because the possible modes of deviation are reduced. For example, suppose
the design intention for a temperature of 100C was being considered. The only
possible modes of deviation (if we forget about the absolute zero) are MORE, ie
above 100Cand LESS, ie below 100C.
When the guide words are applied to time aspects, MORE and LESS may mean
longer and shorter duration or higher and lower frequencies. However, when
dealing with sequence or absolute time, the extra guide words SOONER or
LATER give more insight than OTHER THAN. Similarly when dealing with
position, sources or destination, WHERE ELSE is more useful than OTHER
THAN. Again HIGHER and LOWER will give more meaning than MORE and
LESS for deviations in elevation.
When dealing with a design intention involving a complex specification of
temperatures, rates, composition, pressures, etc, it may be better to apply the
whole sequence of guide words to each element individually rather than apply
each guide word across the whole range of the specification. Also, when applying
AS WELL AS I A qualitative increase All the design and operating intentions are
achieved together with some additional
activity
REVERSE The logical opposite of the This is mostly applicable to activities, for
intention example reverse flow or chemical reaction.
It can also be applied to substances, eg,
'POISON' instead of 'ANTIDOTE' or 'D'
instead of 'L' optical isomers
guide words to a sentence it may be more useful to apply the sequence of guide
words to each word or phrase separately, starting with the key part which
described the activity.
essential that the team contains enough people with sufficient knowledge and
experience to answer the majority of those questions without recourse to further
expertise.
As an example, a typical small chemical plant would be examined by a team
consisting of each of the following
Mechanical engineer
Chemical engineer
R & D chemist
Production manager
Project manager responsible for the project as a whole
This group should contain sufficient expertise to provide the necessary technical
input. Additionally if some members of the team are drawn from those who also
have some responsibility for the design of a plant, they will be particularly
motivated to produce a successful design and a safe operating procedure. Norm-
ally these members of the team will have the necessary authority to make changes.
The blend of disciplines will vary with the type of project. Some projects will
require the inclusion of different disciplines for example
Instrument and electrical engineers
Civil engineers
Pharmacists, etc
The team should not be too large, ideally between three and five technical mem-
bers. If a study seems to require a large number of people it is worthwhile trying
to break it down into several disparate parts with some variation of team compo-
sition for each part.
The training of team members is discussed in Appendix 5 (p. 117).
Supporting team members
Because examination sessions are highly structured and very systematic, it is
necessary to have someone to control the discussion. We will call this person the
'study leader'.
The study leader has a role to play throughout a study. He should help whoever
has commissioned the study to define its scope. He may help with the selection
and training of the team. He will advise on the assembly of the necessary data
and may help convert this into a suitable form. However, his most obvious role
emerges during the examination sessions where he guides the systematic question-
ing and he must be thoroughly trained for this job. It is not desirable that he
should be responsible for making a major technical contribution. If possible, he
should not have been closely associated with the subject of the study as there is
a danger of developing blind spots and failing to use the technique objectively.
But he should have sufficient technical knowledge to be able to understand and
control the team discussions. The characteristics and training required are discussed
in Appendix 5 (P. 117).
In addition to the study leader it is sometimes desirable to have a further supporting
member of the team to make a note of the hazards as they are detected. This
person is known as the study 'secretary' or 'scribe'. It may appear extravagant to
employ two people in a supporting role. However, experience indicates that this
arrangement greatly increases the rate of working of the team as a whole. It is
better to employ seven people for two days rather than six people for four days
on a given study. The training of secretaries is also discussed in Appendix 5.
The attitude of team members
It is imperative that the team as a whole should have a positive and constructive
Major hazard control
attitude to a study as its success ultimately depends upon the imaginative thinking
of the members.
This positive attitude must be built up from the definition stage onwards. Suitable
training is a great help and should create a climate in which the team members
are anxious to start the study. At times during the examination sessions, some
team members feel the approach is tedious but a well-led team ultimately derives
considerable satisfaction from its design work receiving such a thorough analysis.
Sometimes it will not be possible to start at the beginning of a flowsheet and work
downstream. Instead the team will start with the first operating instruction and
apply the guide words to it (or to part of it) and refer to the line diagram, flow
process charts, etc. The study leader will usually prepare a plan for the sequence
Hazard and operability studies
of study before the study starts. A list of typical plants of this type together with
a simplified example is given in Appendix 2 (P.101).
The study leader will often have to prepare a suitable model tailored to suit the
application of the technique to the equipment. This may include a display of its
relationships with operators and with other plant. This preparative work will often
involve a lengthy dialogue between the project engineer and the study leader and
sometimes involves the manufacturers as well. The study leader will prepare a plan
for the study and discuss both the model and the plan with the team prior to
starting the study. A list of typical equipment which might be treated in this way
and an example are given in Appendix 3 (P. 107).
Once the data has been assembled and the model made (if necessary) the sti~dy
leader is in a position to start to arrange meetings. The first requirement is to
estimate the team-hours needed for the study. This can be built up in a number
of ways. As a general rule each individual part to be studied, eg each main pipeline
into a vessel, will take an average of fifteen minutes team time. The simple
example shown in Figure 1 should take one and a half hours made up of fifteen
minutes each for the two inlets, two exits, the vent and the vessel itself.
Thus an estimate can be made by considering the number of pipelines and vessels.
Another way to make a rough estimate is to allow two and a half hours for each
vessel. Fifteen minutes should also be allowed for each simple verbal statement
such as 'switch on conveyor', 'motor starts', 'conveyor starts'.
Having arrived at an estimate of the team hours required, the study leader (or
secretary) can consider arranging meetings. Ideally the duration of examination
sessions should be restricted to three hours (preferably in the morning). Longer
periods of examination are undesirable because it is usually found that effectiveness
begins to fall off. Under extreme time-pressures, examination sessions have been
held for two consecutive days but such a programme should be attempted only
in very exceptional circumstances.
ideally there should be not more than two sessions per week to allow for the
follow-up work described in Section 3.5. This might give rise to difficulties when
individual members of the team have to travel to the meeting place.
Examination sessions should be arranged to be carried out in rooms which are
free from distractions and with plenty of table space for flowsheets, charts, etc.
With large capital projects, it is often found that one team cannot carry out all
the studies within the time constraints imposed. It may therefore be necessary to
use a multiplicity of teams and team leaders. One of the team leaders should then
act as a co-ordinator and allocate sections of the design to different teams and
prepare time schedules for the study as a whole.
Examination sessions are highly structured with the study leader controlling the
discussion by following his predetermined plan. If the approach is based on the
flowsheet he selects the first vessel and asks the team to explain its broad function.
He selects the pipeline or other element of the design and asks the team to make
its purpose explicit. This is not always straightforward but until every member of
the team knows exactly what something is supposed to do, deviations cannot be
generated. A similar approach is used if the study sequence is based on operating
instructions.
The study leader then applies the first guide word and the team discussion starts.
It is sometimes necessary, particularly with an inexperienced team, for the study
leader to stimulate the team discussion by asking further questions such as 'Can
the flow stop?' or 'Does it matter if it stops?' As far as possible only probing
questions should be asked by the study leader. The team should not only provide
the technical answers but be encouraged to be creative and think of all the
deviations and hazards themselves.
As hazards are detected the study leader should make sure everyone understands
them. As mentioned earlier, the degree of problem-solving during the examination
sessions can vary. There are two extreme positions
i A solution is found for each hazard as it is detected before looking for the
next hazard
ii No search for solutions is started until all hazards have been detected
If a question is noted for future evaluation, a note is also made of the person
nominated to follow it up.
The study leader should sum up at the end of the team discussion before starting
with the next guide word. However, he must maintain sufficient pace to avoid the
team becoming bored and also he must keep as far as possible to an agreed
timetable. To this end it may be necessary to terminate an erudite discussion
between two experts by suggesting the point of disagreement be noted and
resolved outside the meeting.
Although the study leader will have prepared for the study, the technique is very
penetrating and may expose gaps in the model or in the knowledge of the team
members. It may sometimes be necessary to elaborate on some aspects during
the meeting or even postpone certain parts of the study in order to obtain more
information.
It has already been mentioned that sometimes a study secretary is used as well
as a study leader. Secretaries are frequently employed in either of the following
circumstances
i When the examination must be carried out very quickly because of time
pressures on members of the team
ii The study is complex and the leader must guide the team using a number of
sources of information simultaneously, eg a combination of flowsheets, opera-
ting instructions, sequence control charts and bar-charts. The use of a secretary
enables the leader to concentrate on directing the study
Finally it must be emphasised that follow-up work is not complete until all the
acknowledged hazards have been dealt with by implementation of all the agreed
actions.
3.6 Recording
An important activity of the study team is to record the results of the study. One
useful form of record is a 'Hazard file'. This contains
i A copy of the data (flowsheets, running instructions, bar charts, models, etc)
used by the team during the examination sessions and marked by the study
leader to the effect that they have been examined
ii A copy of all the working papers, questions, recommendations, redesigns, etc
produced by the team and others as a result of the study
The file should be retained on the plant so that it is a .source of information if
changes are subsequently contemplated by the operating personnel.
In addition, the results of a study may also be the subject of a specially prepared
report. This is usual if the study includes a quantification of particular risks.
Reports can also be written for the guidance of managers or other practitioners if
a study has some interesting or unique features.
The formal recording of the study may in future have further implications. For
example, insurance premiums may be affected or planning permission may be
assisted by evidence of a well-conducted study.
Finally, the information generated by studies can be used to improve future designs.
5 GLOSSARY OF TERMS
HAZARD AND OPERABILITY The application of a formal systematic critical
STUDIES examination to the process and engineering
intentions of new or existing facilities to assess
the hazard potential of mal-operation or mal-
function of individual items of equipment and
their consequential effects on the facility as a
whole.
6 ACKNOWLEDGEMENTS
This guide is based on a report by Mr R. E. Knowlton and Dr D. K. Shipley of ICI
Pharmaceuticals Division. Helpful comment from practitioners of Hazard and
Operability Studies in other parts of ICI were also taken into account and permission
to use Dr H. G. Lawley's example fromchem. Eng. Prog., April 1974,in Appendix 1
is gratefully acknowledged.
The guide was edited for general industry use by representatives of
BP Chemicals Ltd
The Chemical lndustries Association Ltd
ICI Central Safety Department
Shell Chemicals (UK) Ltd
7 REFERENCES
Lawley, H. G., Operability Studies and Hazard Analysis, Chem. Eng. Prog.,
April 1 974.
Farmer, F. R., I. Chem. E. Symposium Series No. 34, Major Loss Prevention
in the Process lndustries, 1971,p. 82.
Stewart, R. M., I. Chem. E. Symposium Series No. 34,Major Loss Prevention
in the Process lndustries, 1971,p. 99.
Houston, D. E. L., I. Chem. E. Symposium Series No. 34,Major Loss Prevention
in the Process lndustries, 1971,p. 21 0.
Bullock, B. C., The development and application of quantitative risk criteria
for chemical processes, Fifth Chemical Process Hazard Symposium, I. Chem.
E., Manchester, April 1974.
Kletz, T. A., Hazard Analysi-A Quantitative Approach to Safety, I. Chem. E.
Symposium Series No. 34,1971.
Melinek, S. J., Methods of determining the optimum level of safety expendi-
ture, Building Research Establishment Current Paper, CP88174.
Raybould, E. B.,and Minter, A. L., Problem Solving for Management. London,
Management Publications, 1971,pp. 86-90.
Nadler, G., Work Design. Homewood (Illinois), Irwin, 1963.
Whitmore, D. A., Work Study and Related Management Services. London,
Heinemann, 1968,p. 183.
Hazard and operability studies
APPENDIX 1
Application to a continuous plant
The original development of the method based on plant flowsheets occurred
when the technique was applied to large, continuous, single-stream plants and
the technique has been widely used in this application.
The following are typical of continuous plants which have been studied
Methanol plants
Ammonia plants
Petrochemical plants
Chlorine plants
Soda-Ash plants
As an example of the use of the technique for identifying inadequacies in design
and for drawing attention to important operating requirements in the case of a
continuous process, a synopsis of part of a paper by H. G. Lawley (Reference 1)
is given below.
The system considered is the feed section of a proposed olefin dimerisation unit,
the preliminary design being as shown in Figure 3 and the process description is
as follows
'An alkenelalkane fraction containing small amounts of suspended water is
continuously pumped from bulk intermediate storage via a half-mile pipeline
section into a bufferlsettling tank. Residual water is settled out prior to
passing via a feedlproduct heat exchanger and preheater to the reactor
section. The water, which has an adverse effect on the dimerisation reaction,
is run off manually from the settling tank at intervals. Residence time in the
reaction section must be held within closely defined limits to ensure adequate
conversion of the alkene and to avoid excessive formation of polymer.'
Tsble 2 summarises the results for the first line section from intermediate storage
up to the buffer tank and also indicates the manner in which the need for action
was recogniged.
It is imperative to ensure that before starting an examination, the design intention
is clearly defined. In the particular case given in this example the intention is
Not. N o NO FLOW (1) No hydrocarbon avail- Loss of feed to reaction sec- (a) Ensure good communications
able at intermediate tion and reduced output. with intermediate storage
Storage Polymer formed i n heat operator
exchanger under no flow (b) Install low level alarm on
conditions settling tank LIC
(2) JI pump fails (motor As for (1 ) Covered by (b)
fault, loss of drive, im-
peller corroded away,
etc)
(3) Line blockage, isolation As for (1 ) Covered by (b)
valve closed in error, or JI pump overheats (c) Install kickback on JI pumps.
LCV fails shut (d) Check design of JI pump
strainers
(4) Line fracture As for (1) Covered by (b)
Hydrocarbon discharged in (e) lnstitute regular patrolling and
area adjacent to PL~ b l i chig inspection of transfer line
CO
way
CD
More MORE FLOW (5) LCV fails open or Settling tank overfills ( f ) Install high level alarm on LIC
LCV bypass open in and check sizing of relief oppo-
error site liquid over-filling
(g) lnstitute locking off procedure
for LCV bypass when not in use
Incomplete separation of (h) Extend J2 pump suction line to
water phase in tank leading 1 2 i n above tank base
to problems on reaction
section
-
(6) Isolation valve closed Transfer line subjected t o ( j ) Covered by (c) except when
i n error or LCV closes, full pump delivery or surge kickback blocked or isolated.
with JI pump running pressure Check line, FQ and flange
ratings, and reduce stroking
speed of LCV if necessary.
Install a PG upstream of LCV
and an independent PG on
settling tank
Guide Word Deviation Possible Causes Consequences Action Required
More (contd.) (7) Thermal expansion in an Line fracture or flange leak (k) lnstall thermal expansion relief
isolated valved section on valved section (relief dis-
due to fire or strong charge route to be decided later
sunlight in study)
MORE TEMPERATURE (8) High intermediate stor- Higher pressure in transfer (I) Check whether there is ade-
age temperature line and settling tank quate warning of high temper-
ature at intermediate storage. If
not, install
Less LESS FLOW (9) Leaking flange or valve Material loss adjacent to Covered by (e) and the checks
stub not blanked and public highway in (1)
leaking
LESS TEMPERATURE (10) Winter conditions Water sump and drain line (m) Lag water sump down to drain
freeze up valve, and steam trace drain
valve and drain line downstream
As well as ORGANIC ACIDS (1 1) Disturbance on distilla- lncreased rate of corrosion of (n) Check suitability of materials of
PRESENT tion columns upstream tank base, sump and drain construction
of intermediate storage line
+
0 -
0
Part of HlGH WATER (12) High water level in in- Water sump fills up more (p) Arrange for frequent draining off
CONCENTRATION termediate storage tanks quickly. lncreased chance of water from intermediate
I N STREAM water phase passing to re- storage tank. lnstall high inter-
action section face level alarm on sump
HlGH CONCENTRATION (13) Disturbance on distilla- Higher system pressure (q) Check that the design of settling
OF LOWER ALKANES OR tion columns upstream tank and associated pipework,
ALKENES I N STREAM of intermediate storage including relief valve sizing, will
cope with sudden ingress of
more volatile hydrocarbons
Other than MAINTENANCE (14) Equipment failure flange Line cannot be completely (r) lnstall low-point drain and N,
leak etc drained or purged purge point downstream of LCV.
Also N, vent on settling tank
APPENDIX 2
Application to a batch plant
Many of the more specialised materials produced by the chemical industry are
made in plants which are partially or completely batch operations.
The following list gives typical products made by batch processes
General organic intermediates
Dyestuffs
Speciality chemicals such as antioxidants
Bulk drugs
Fermentation products
Some polymers
A number of 'formulated products' are made by batch processes including
Pharmaceuticals
Paints
Catalysts
Photographic emulsions
Cosmetics
Specialised formulations
The general characteristics of batch plants as compared with continuous plants
are as follows
i By definition, the status of the various parts of the plant are changing cyclically
with respect to time and therefore a line diagram alone gives a very incomplete
picture
ii The processes are usually multistage, the individual units multipurpose and the
plant as a whole multiproduct. Therefore there is a large number of possible
interconnections between units
iii The operators may take part physically in some of the process activities such as
removing product from filters
As an example of the application of the technique to a batch process, consider
the hypothetical plant shown in Figure 4. This shows a plant consisting of two
measure vessels, four reaction vessels, a condenser, an absorption tower with its
circulation system and a nutsche filter with its filtrate receiver. This plant is typic al,
although it has been simplified with the omission of most of the connections to
vessels, vents, inert gas inlets, bursting discs, stirrers, heating and cooling sup plies
to jackets, etc.
In addition to the flowsheet, operating instructions will have been prepared.
Typically these consist of tables containing the operation number, a description
of the operation, the precautions to be taken and finally a column for the operator
to initial once the operation has been completed. A typical layout of operating
instructions concerning this hypothetical example is shown in Table 3.
It may be desirable to prepare a bar-chart which shows the status of each piece
of equipment throughout a complete batch cycle. For instance, in this example,
while batch 1 is being filtered, batch 2 could be reacting in vessel 3, with batch 3
being transferred from vessel 1 to vessel 2 and the measure vessels being filled
in preparation for batch 4. These bar-charts are usually produced by the plant
management.
Finally, it may be necessary to flow-chart the operators' movements. This aspect
will be dealt with in detail in Appendix 3.
As part of the preparative work the study leader should prepare (at least mentally)
and plan a programme for the study. His first decision must be whether to study
Major hazard control
the plant in a sequence derived from the flowsheet or the sequence of the
operating instructions.
Let us suppose he has decided to use the sequence of operating instructions. The
early instructions will be concerned with a number of preparative activities, starting
stirrers and turning cooling water on, checking vessels and starting the absorption
tower circulation efc, so let us start this example with lnstruction 23 (Table 3)
which states 'Charge 100 1 of material C from the drum to the general purpose
measure vessel using the air ejector'.
While this instruction is perfectly adequate for operational pilrposes with a trained
operator it is too complex to be used to generate deviations. The study leader
should decide how to tackle each instruction either as part of his preparation or
during the actual examination sessions. In this instance, the instruction can be
split into a part dealing with the air ejector and the rest dealing with the liquid
transfer.
The study leader will ask a member of the team to describe the purpose of the
air ejector. The purpose could be stated as 'Remove some air from the measure
vessel'. The guide words are applied to this statement and the attention of the
team is directed to the measure vessel and its attachments with the results shown
in Table 4.
The second part of lnstruction 23 will then be 'Charge 100 1 of material C to
measure vessel' and this instruction can be used as it stands. The guide words
are applied to it with the results shown in Table 5.
The team may carry out some quick problem-solving. For example, a number of
the identified hazards can be removed by substituting in lnstruction 23 the final
phrase 'using residual vacuum' and this alteration could be agreed by the team a t
this point. The instruction is marked as having been examined.
The team would then proceed to lnstruction 24 which reads 'Transfer 100 1 of
material C from the general purpose measure vessel to vessel 1 via the orifice
plate'. While this instruction is sufficiently simple for it to be examined without
breaking it up into parts, it is not entirely explicit. The study leader would ask a
member of the team to make the exact intention clear. The aim could be to supply
C at a restricted rate to avoid an excessive reaction. The examination then starts
with the results shown in Table 6.
Again the team may carry out some problem-solving. For example, it could decide
to install another dedicated measure vessel complete with orifice plate for material
C and thus avoid some of the hazards. Provided this could be carried out simply,
the drawing and the instructions would be modified and checked on the spot. If
however there were any complications-for example, coupling two measure
No
---
Operation I Precautions 1 initials
23
24
I Charge 100 1 of material C from the
drum to the general purpose measure
vessel using the air ejector
Drum
Absorption
-
Tower t To
J
Vessel 1
Vessel 4
Vessel 2
Vessel 3
I
T o vacuum
.1 I ,
Filtrate
Receiver
T o Effluent 4
Disposal
Major hazard control
Table 4 DEVIATIONS FROM 'REMOVE SOME AIR FROM THE MEASURE VESSEL'
REMOVE MORE AIR Completely evacuate measure Can vessel stand full vacuum?
vessel
REMOVE LESS AIR Insufficient suck to transfer con- Process inconvenience but no
tents of drum hazard
- -
OTHER THAN Put air ejector on when measure Spray contents along line and out
REMOVE AIR vessel full through flame trap. Similar
hazards to AS WELL AS
Although one purpose of a Hazard and Operability Study is to check the equipment
for safety, it is also a check on procedures, particularly operating instructions. The
technique finds ambiguities or obscurities in instructions and it helps to produce
instructions at the correct level of detail.
Hazard and operability studies
CHARGE MORE C Charge a quantity greater than If vessel is over-filled with ejector
100 1 running, C is pulled into air
ejector with hazards already
raised in Table 4.
If excess were put into the
measure vessel, how could i t be
removed safely 7
CHARGE LESS C Charge a quantity less than 100 1 No hazard at this stage
REVERSE CHARGE Flow from measure vessel to Spillage of material. Possible spray
OF C drum hazard
CHARGE OTHER Mix-up with drums. List the Possible reactions in measure
THAN C other materials vessel or corrosion of measure
vessel
Major hazard control
DON'T TRANSFER C. Blocked line. Shut valves. Pres- Process inconvenience but no
sure too high in vessel 1 hazards
APPENDIX 3
Application to a proprietary item of equipment
Studies have been carried out on unit operations such as mixing, separation,
reacting, drying, distillation, milling, tabletting, sterilisation packing, polymerisation,
cracking and blending. Often such operations are conducted in proprietary items
of equipment such as centrifuges and spray driers which may need to be studied
in depth both in terms of the principles of their operation and in their interaction
with materials, facilities and other equipment. The technique can also be applied
to service facilities such as boilers, incinerators and storage vessels.
As an example, let us consider the proprietary sterilisation autoclave shown in
Figure 5.
Sterilisation of stillage-loaded materials is achieved by treatment with steam
humidified sterilising gas in a jacketted autoclave chamber under specified condi-
tions. Two entries are provided to the chamber-from the sterile and from the
non-sterile working areas of the facility.
Steam is admitted to the chamber via a let-down system and sterilising gas via a
vaporiser. The chamber may be evacuated via a cooler either directly to drain
or via a luted sealed catchpot to a vent stack. Filtered atmospheric air may be
admitted via a non-return valve. A relief valve is fitted to the chamber which
exhausts to the vent stack and may be by-passed by opening a vent valve if it is
required to dump the contents to stack. Water is circulated through the jacket and
heated indirectly by means of steam.
Once the autoclave is charged and the doors closed, automatic sequence control
takes over and programmes the process as shown in Figure 6. The machine itself
checks the progress of the process cycle, monitoring the status of the chamber
and auxiliaries. Certain checks (see Figure 6 : Autochecks) control progress in
association with timers.
In modelling this type of equipment, it must be borne in mind that both the
operator and the machine control the overall process between them and that the
operator is physically involved in moving process materials. The latter activity is
expressed in the form of a flow process chart (Figure 7) using method study
charting symbols. A complete list of such symbols is shown in Figure 8.
For this type of study a stage by stage plan for the examination would be appro-
priate as shown in Table 7. The equivalent of Stages 1, 3 and 5 have already been
considered earlier in the guide. The purpose of this Appendix is to demonstrate
the method of handling Stages 2 and 4.
Mains Water
To Vent Stack
f Gas
-/A-
A
Sterile
Side
Door
+
To Drain
Hazard and operability studies
Major hazard control
3
1Line-by-line approach Complete process and service lines and
auxiliaries and manually operated systems, to
defined battery limits, as shown in Figure 5
Charts of this kind may be drawn for any process using the standard symbols
shown in Figure 8, and assistance with this technique can be obtained from a
number of sources. (See References 8 to 10).
Guide words are applied to each element of the chart as exemplified in Table 9
which considers possible deviations on the element STILLAGE ENTERED,
FORKS EXTEND.
1r
Loaded Stillages
Await Charging
Stillage Raised
Stillage Located
o n Forks
Forks Retract
(Prep. t o Transport)
Stillage t o
Chamber Door
Stillage Elevated
t o Chamber Level
Stillage Entered,
Forks Extend
Stillage Released
Forks Lowered
Stillages
Located
Manually
Major hazard control
The above examples are those approved by the ASME (American Society of
Mechanical Engineers)
Hazard and operability studies
LESS Too little steam, too low steam Iscondensationon product deleterious 7
HUMIDIFY pressureltemp
PART OF Steam in but loss of vac. pump Chamber will be partly pressurised.
HUMIDIFY (or valve D closes) Load very wet, temperature too high.
Chamber partly filled with water. Cycle
will continue and sterilising gas may
not enter due back pressure
Vacuum, but no steam in Cycle will continue; if lack of humidity
is not detected and action taken, load
will n o t be sterile
OTHER THAN Sterilise by omission of humidi- Cycle will continue-load will not be
HUMIDIFY fying step sterile (as above)
Major hazard control
APPENDIX 4
How to start Hazard and Operability Studies
Hazard and Operability Studies may be started in an organisation because there
is a desire to improve safety, even though the current performance may be good,
or because some members of the organisation have read or heard about the
technique and its benefits and want to try it.
The way in which a study is started will of course depend on the organisation but
it usually follows one of four approaches
A Do-it- Yourself approach
The Evolutionary approach
The Educational approach
A Crash programme.
A Do-it-yourself approach
Although expert help is desirable and will reduce costs by speeding up the process
of gaining competence, it is not essential. The early pioneers had no expert advice
and a t least five organisations have started to carry out Hazard and Operability
studies from a foundation much less firm than that now possessed by the reader.
The first step is to agree a trial should be carried out and appoillt a person to act
as a study leader for this trial. The person selected should preferably have a technical
background with production experience together with some knowledge of method
study in general and critical examination in particular.
This person should make himself very familiar with this booklet. It is suggested
that he then carries out a small exercise on his own in applying the technique to
something very simple such as a solvent storage vessel which is supplied by a
tanker.
Armed with this experience he should, in discussion with management, select the
first real subject for a trial. The subject could be a project around 'design freeze'
or an existing unit. He will then select the team in the usual way.
At this stage he will be in a position to arrange an appreciation training course
for the team members together with others who may be involved in later studies.
The training could be built up from the following
i A general introduction including course objectives
ii The principles of examination with the tutor basing his talk on 2.1 then working
through 2.2, followed by 2.3
iii He can then explain the detailed sequence as in Figure 2
iv He could use his personal experience with the storage tank example (or other
simple example) to provide an exercise which the course members would work
on in (say) groups of 4 aided by Table 1
The study leader will then have a team sufficiently trained to start a study on the
selected topic. Progress is likely to be slow for the first few examination sessions
until both the leader and the team start to feel at home with the technique.
The rest of the study follows the basic procedure mentioned earlier. If the chosen
project is a small one lasting say two or three team days, the study leader may
remain in charge throughout, and this is the ideal. If the study is lengthy, then it
may be worthwhile training an in-house study leader to take over.
After the first (hopefully successful) demonstration, the technique is gradually
extended to cover the relevant parts of the organisation and become one of its
standard procedures.
The Educationalapproach
This is usually initiated by senior management and since the approach requires a
significant commitment, particularly of management and training resources, it will
have resulted from a policy decision to use the technique. Adopting this approach,
it is advisable to carry out the following steps
i Obtain the necessary training and experience to produce one or if necessary
.II. more study leaders
Develop and present appreciation courses for senior and middle management
so that they can give their managerial support to the teams
iii Develop and present suitable appreciation and team-membership training
courses for those who will actually carry out the studies
More details of the training courses are given in Appendix 5.
The approach is straightforward. Teams are set up and study leaders are obtained
to train and lead the teams and to train other study leaders from within the
organisation.
The requirements for such a programme are
i Recognition by all levels of management of the need
ii Availability of the technique in a form appropriate to the problem
iii Availability of experienced study leaders at short notice
iv Availability of resources to ensure that follow-up actions are implemented
Hazard and operability studies
APPENDIX 5
Training
There are four main kinds of training concerned with Hazard and Operability
Studies
Senior management appreciation course
Course for team members
Study Leader training
Secretary training
Hazard and Operability Studies can also be included in a general management
training course.
Secretary training
The secretary must have an appreciation of the technique. In addition, he must
be given some guidance on how to record succinctly, but in a way which imme-
diately identifies the section of plant referred to, the nature of the hazard and the
circumstances in which it can occur.
Major hazard control
APPENDIX 6
The formalisation of Hazard and Operability Studies
Appendices 4 and 5 have indicated how to start Hazard and Operability Studies
in an organisation and the kinds of training which should be provided, but these
steps are only preliminaries. To obtain full benefit the ultimate aim should be to
make the approach part of the 'way of life' within the organisation.
It is difficult to lay down rules for the formalisation of the technique because
organisations differ greatly in structure; the manner in which studies are introduced
could also influence the situation. Nevertheless, the following guidelines have
emerged as a result of experience.
In parts of the chemical industry where Hazard and Operability Studies are most
fully established, there are specialist groups providing overall leadership in the
technique. They contain skilled study leaders and provide training, advice and
assistance in the application of the technique. They do some, but not necessarily
all, of the study leading. In addition, they develop the technique for new, wider
or more specialised applications. This group can be part of a management services
department, a safety department or that part of an engineering department which
handles the capital programme.
In addition to the specialist group, there will be trained study leaders who can
assist on a part-time basis. All appropriate people concerned with plant design
and operation should in time have some training and experience as team members.
Although the technique may initially be introduced on an experimental or optional
basis, it will tend to be deployed in an increasing number of projects. Ideally its
growth should increase to the extent that it becomes a natural part of the design
process. Formalisation at this stage will then be seen as evidence of commitment
at, say, board level, and should ensure that the appropriate resources will be made
available to carry out the studies and to implement the actions which are produced.
The formalisation usually takes the form of company instructions which cover the
following points
i The time in the development of a project at which a study should be carried out
ii The criteria by which it is decided to study existing facilities
iii The responsibility for initiating the studies
iv The methods of reporting and recording of the information generated during a
study.
Appendix 4
Consequence calculation
methods
Consequence calculation methods
1.3. Maximum liquid release rates for distance and prevailing weather conditions.
commercial LPGs Concentrations and durations can be estimated
using computer models which combine a physical
This can be determined from figure 4.2.
description of the gas cloud behaviour with
experimental data. Box-type computer models are
1.4. Maximum gas release rates for frequently used to predict the dispersion behaviour
commercial LPGs of gases like chlorine which are denser than air. A
This can be determined from figure 4.3. model known as DENZ can be used for
instantaneous releases (e.g. failure of a storage
1.5. Maximum two-phase release rates for vessel) and gives information shown in figure 4.5.
commercial LPGs
For continuous releases (e.g. from a leaking
This can be determined from figure 4.4 pipe), a model known as CRUNCH will give
information shown in figure 4.6.
CHLORINE
This information can be used in conjunction
The consequences of releases of toxic gases with table 10 in section 6.1.4 of the manual to
like chlorine are time-dependent and will vary with estimate the effects of a release on people.
Consequence calculation methods
1 = PROPANE @ 30C
2 = PROPANE @ 15"C
3 = PROPANE @ 0C
4=BUTANE @ 30C
5=BUTANE @ 15C
6 = BUTANE @ 0"C
10 100 1,000
Hole dlameter (mm)
Consequence calculation methods
Release rate 1
1 = PROPANE @ 30C
2 = PROPANE @ 15C
3 = PROPANE @ 0C
4=BUTANE @ 30C
5=BUTANE @ 15C
6 = BUTANE @ OC
10 100 1.000
1 = PROPANE @ 30C
2 = PROPANE @ 15"C
3 = PROPANE @ 0C
4=BUTANE @ 30C
Contents
Glossary
Introduction
Scope
Legal requirements
Properties and hazards of LPG
Location, separation and grouping
Mechanical integrity
Fittings
Piping
Vaporisers
Security
Marking and identification of
the installation and its contents
Hazardous area classification
for electrical equipment
Fire precautions
Loading and unloading facilities
Commissioning and decommissioning
Maintenance and examination
Operational procedures
Training
Bibliography
people storing LPG and those enforcing safety the general duties of the HSW Act. It may also
requirements. This guide may b e used where b e subject to additional legal requirements:
people have duties under the HSW Act and may
also b e used as good practice in other (a) at the premises subject to the Factories Act
circumstances such as storage vessels at 1961, the Highly Flammable Liquids and
domestic premises. The recommendations are Liquefied Petroleum Gases Regulations 1972
intended to minirnise the risks of fire and (HFL Regulations) will apply;
explosion from escaping LPG and from a fire at (b) the Notification of Installations Handling
or near a store. Hazardous Substances Regulations 1982
(NIHHS) require that all premises at which 25
2 The information in this guidance gives one
tonnes or more of LPG are kept should b e
way of achieving an acceptable standard of
notified to the Health and Safety Executive
safety. Each case must b e considered on its
(HSE). Guidance on these regulations can b e
merits, and special circumstances may
found in HSE booklet HS(R)l6;
necessitate variations from the recommendations.
It is not intended to preclude the use of (c) the general requirements of the Control of
alternative designs, materials and methods where Industrial Major Accident Hazards
these provide equivalent safety standards. Regulations 1984 (CIMAH) apply to all
Neither is it the intention that the premises where LPG in any quantity is
recommendations should b e applied rigidly to produced or processed or where 50 tonnes
existing premises, where for a variety of reasons or more are stored. Guidance on the CIMAH
it may not be practicable to comply with them, Regulations can b e found in HSE booklet
although such alterations as are considered to b e HS(R)21 and on the emergency plans
reasonable or essential for safety should b e required by the regulations in HSE booklet
made. New installations should comply with the HS(G)25;
advice in this guidance from the date of (d) at premises subject to the Fire Certificates
publication. (Special Premises) Regulations 1976, enforced
by HSE, and the Fire Precautions Act 1971,
Scope enforced by the Fire Authority, the presence
3 This guidance deals solely with installations of LPG may b e taken into account when
where LPG is stored under pressure at ambient considering the general fire precautions;
temperatures in fixed vessels larger than 150 (e) the operation of loading and unloading road
litres. It applies to all such installations whether tankers and tank containers with a capacity
or not the material is stored for use on site or greater than 3m3 when they are loaded or
transhipment and subsequent use off site and unloaded while still on a vehicle, is subject
includes guidance on the design, construction to the requirements of the Dangerous
and examination of LPG storage vessels. Substances (Conveyance by Road in Road
Information is also presented on the precautions Tankers and Tank Containers) Regulations
to b e taken during loading and offloading of road 1981;
tankers and rail tankers. if LPG is supplied through a pipeline, the
(f)
4 Guidance is not given on the storage of Pipeline Act 1962 may apply. However the
cylinders or cartridges containing LPG. Advice Act does not apply to certain specified
on these matters can b e found in Guidance Note pipelines including those wholly within
CS4 and Guidance Note CS8. Advice on the factory premises, mines, quarries and
storage of refrigerated LPG, previously contained petroleum depots. This Act is enforced by
in Guidance Note CS5 should b e obtained from the Pipelines Inspectorate of the Department
your local HSE office. of Energy to whom enquiries should b e
made;
Legal requirements (g) where LPG is supplied as a gas through
5 The storage of LPG will usually b e subject to pipes to premises, the supply must b e
The storage of LPG at fmed installations
at 50C bar 7
authorised by or under the Gas Act 1986, Properties and hazards of LPG
subject to certain exceptions. It is an offence
for any person to supply gas through pipes 6 The two liquefied petroleum gases in general
without authorisation in circumstances where use are commercial butane and commercial
authorisation is required. Further particulars propane. Their main physical properties are
may b e obtained from the Office of Gas given in Table 1. These hydrocarbons exist a s
Supply, Southside, 105 Victoria Street, gases at normal temperatures and pressures but
London SWlE 6QT. can b e liquefied under moderate pressure. If the
pressure is subsequently released, the
hydrocarbons again become gaseous.
Note: although LPG itself is not subject to the 7 LPG is colourless and its density as a liquid is
Petroleum (Consolidation) Act 1928 the Petroleum approximately half that of water. If LPG is spilt on
Licensing Authority may take its presence into water, it will float on the surface before
account in determining the condition of any vapourising. The liquid has approximately 1/250th
licence that may b e issued under the Act. of the gas volume.
Major hazard control
The storage of LPG at fixed installations
8 The gas or vapour is at least 1% times as form and b e potentially dangerous. In this state
dense as air and does not disperse easily. It will the internal pressure is approximately
tend to sink to the lowest possible level a d may atmospheric and, if a valve is leaking or left
accumulate in cellars, pits, drains or other open, air can diffuse into the vessel forming a
depressions. flammable mixture and creating a risk of
explosion. LPG will also b e displaced to the
9 LPG forms flammable mixtures with air in atmosphere.
concentrations of between approximately 2% and
10%. It can, therefore, b e a fire and explosion Location, separation and grouping
hazard if stored or used incorrectly. There have
been incidents in which escapes of LPG have 15 LPG vessels sited above ground should b e
been ignited, resulting in serious fires. If LPG located in the open air in a well ventilated
escapes into a confined space and is ignited, an position in accordance with the separation
explosion could result. If an LPG vessel is distances given in Table 2, column (a).
involved in a fire, it may overheat and rupture Underground or mounded vessels should b e
violently giving an intensely hot fireball and may located so that the manhole and pressure relief
project pieces of the vessel over considerable valves are in a well ventilated position in
distances. accordance with the separation distances given
10 Vapour/air mixtures arising from leakage or in Table 2, column (d). Advice should be
other causes may b e ignited some distance from obtained from the enforcing authority before
the point of escape, and the flame travel back to using separation distances less than those in
the source. Table 2. The siting of installations involving
vessels greater than 337 500 litres (150 te) should
11 At very high concentrations, when mixed be discussed with HSE.
with air, LPG vapour is anaesthetic and
subsequently an asphyxiant by diluting or 16 LPG vessels should not b e located one
decreasing the available oxygen. above the other. The ground beneath or adj'acent
to connections into vessels or ancillary
12 LPG can cause severe cold bums to the skin equipment containing LPG should b e concreted
owing to its rapid vaporisation and the or compacted and free from pits, depressions,
consequent lowering of temperature. drains and culverts. When all the vessel
Vaporisation of LPG can also cool equipment to connections are grouped at one end, the
the extent that it may b e cold enough to cause concrete or compacting may only b e necessary
cold bums. Protective clothing such as gloves beneath the connections. The ground within the
and goggles should b e worn if this cooling is separation distance given in Table 2, column (a)
likely to occur. should, as far as possible, b e flat and level, other
13 LPG is normally odorised before distribution than beneath the vessel and where it is sloped to
so that is has a characteristic smell which can an evaporation area or catchment pit.
easily b e recognised. This enables detection by 17 Weeds, long grass, deciduous shrubs and
smell of the gas at concentrations down to one trees and any combustible material should b e
fifth of the lower limit of flammability removed from an area within the separation
(approximately 0.4% of the gas in air). Significant distance in Table 2 column (a) of any LPG vessel
leaks may also be detected by a hissing sound of up to 2500 litres capacity (1.1 te) and within 6m
or by icing in the area of the leak. Small leaks of larger vessels. Sodium chlorate should not b e
may b e detected by brushing the suspect areas used to clear weeds near LPG vessels.
with a detergent/water mixture where bubbles
will form at the leak. On no account should a 18 Shrubs or trees provided to screen LPG
naked flame or other source of ignition be used vessels from view should not interfere with
to detect a leak. ventilation and therefore should only b e located
on one side of the installation. Evergreen shrubs
14 A vessel which has held LPG and is or trees may b e located lm from vessels up to
nominally empty may still contain LPG in vapour
Major hazard control
Height to top of -
P.R.V.
Vessel
1 tonne
The storage of LPG a t fixed installations
Of any single vessel in a group I Of all vessels I Above ground vessels Buried or mounded vessels
I in a group I -
Nominal LPG From buildings, From buildings etc to
Litres Gallons Capacity Litres Gallons boundary, With Between Between
(tomes) propem line or fire vessels Valve Vessel vessels
fixed source of wall Assembly
ignition
(a) @) (c) (d) (e) (0
-
m m
0.3* 1
1.5 1
4 1
7.5 1.5
11 Y4 of sur
of the
dia of 2
adjacent
vessels
11
15
-
*For vessels up to 500 litres capacity, the fire wall need be no higher than the top of the vessel and may form part of the site
boundary. The fire wall for a vessel up to 2500 litres water capacity may form part of a building wall in accordance with Figure
2. Where part of the building is used for residential accommodation the wall, including any overhanging but excluding the
eaves, against which the LPG is stored should be of 60 minutes he-resisting construction and imperforate.
$The spacing between adjacent vessels should be determined by the site conditions and the needs for safe installation, testing,
maintenance and removal of vessels.
5000 litres capacity for this purpose. For larger any large spillage of LPG to an evaporation area
vessels the separation distances in paragraph 17 or catchment pit. These should be sited in a safe
apply. place away from occupied buildings, boundaries
19 For all vessels with connections below the or sources of ignition. Escaping LPG should be
liquid level the ground beneath the vessel or diverted to the evaporation area or catchment pit
connections should be sloped to prevent the by sloping the ground in the required direction
accumulation of liquid beneath them and ensure and where necessary by installing low walls,
a flow away from the vessel, adjacent vessels or usually no more than 500mm high, to direct the
ancillary equipment towards a safe area. It is not flow in the right direction. Catchment pits will
necessary to compact or concrete the ground normally only be appropriate at large
beneath connections that are plugged or blanked installations.
off.
2 1 Catchment pits should have sufficient
20 Propane vessels with a capacity of 56 250 capacity to contain the largest credible leak and
litres (25 te) or more and butane vessels with a should be sufficiently well ventilated to permit
capacity of 11 250 litres (5 te) or more, and in the safe dispersion of small leaks. Gas detectors
each case with connections below the liquid should be installed in the pit to provide warning
level should have provision made for directing of the presence of LPG vapour.
Major hazard control
The storage of LPG at fixed installations
22 Any catchment pit should be far enough 29 LPG cylinders in excess of 50kg total quantity
away from LPG vessels, buildings, boundaries etc with pressure relief valves which vent horizontally
so that if filled with LPG which ignites, the should not be stored within 1.5m of vessels of
thermal radiation would not exceed the following more than 5000 litres capacity or 3m of vessels
levels: below this size. Up to 300kg of LPG in cylinders
fitted with vertically venting pressure relief valves
(a) 7.8 Kw/m2 at work areas, process facilities eg most fork truck cylinders, may be stored
and unprotected LPG vessels; within the vessel security compound at least lm
(b) 12.6 Kw/m2 at boundaries; from the vessel. See Table 3.
(c) 31.5 Kw/m2 at LPG vessels protected by 30 Up to 300kg of propane in cylinders may b e
water sprays or thermal insulation. kept within 7.5m or 3m of a vessel (see
paragraph 29) for the purposes of pressure
23 Evaporation areas should b e at least 3m from
augmentation of a butane vessel in cold weather
LPG vessels. The area should be surfaced with
or to provide an emergency supply of propane
stone chippings or similar materials to increase
in the event of a failure of the bulk supplies. The
the surface area and promote evaporation and
cylinders should b e positioned at least Im from
dispersion of the gas.
the vessel. The Dressure relief valves should b e
24 Vessels should not b e sited in places that are directed away from the vessel or a fire wall
known to b e susceptible to flooding. should b e built between the cylinders and
25 LPG storage vessels should be installed at vessel.
least 6m from the bund wall of any tank 31 Buildings or structures in which cylinders are
containing a flammable liquid with a flash point filled with LPG or other flammable gases should
below 32C and from any tank containing a b e sited 10m from bulk LPG vessels up to
flammable liquid with a flash point in the range 135 000 litres capacity (60 te) and 15m from larger
32 to 65OC. The minimum separation distance vessels. This separation distance is not necessary
between an LPG storage vessel and the top of where only a small number of cylinders are filled
the bund of any tank containing a flammable e g for fork lift trucks. See Table 3. For
liquid should b e 3m. See Table 3. underground vessels this distance may b e
26 Vessels containing liquid oxygen should b e reduced to 5m or the separation distance in
sited not less than the separation distance given Table 2 column (d), whichever is the greater.
in Table 4 from vessels containing LPG. Vessels 32 So far as is reasonably practicable, horizontal
containing toxic or other hazardous materials storage vessels should b e sited so that their long
stored under pressure eg chlorine should b e at axes do not point towards nearby occupied
least 15m from LPG storage vessels or at the buildings, important items of equipment or
separation distances given in Table 2, column (a), storage tanks containing hazardous materials.
whichever is the greater.
27 LPG storage vessels should not be located Fire walls
within the bunded enclosure of a vessel 33 The purpose of a fire wall is to protect the
containing a flammable liquid, any heated storage vessel or vessels from thermal radiation from a
vessel eg heavy fuel oil vessel, liquid oxygen or fire nearby and to ensure an adequate dispersion
any other hazardous substance. distance to boundaries, buildings and sources of
28 The number of above ground LPG storage ignition for LPG leaking from the vessel or its
vessels in one group should not exceed six fittings.
subject to the maximum total capacity of a group 34 A fire wall should b e imperforate and of
given in Table 2. Any vessel in one group should solid masonry, concrete or similar construction.
b e 7.5m or the separation distance given in Table Except for vessels up to 500 litres (0.25 te) a fire
2, column (c) whichever is the greater, from the wall should be at least 2m high or as high as the
nearest vessel in another group unless a fire wall top of the vessel whichever is the greater and
is erected between the two groups. should b e sited between lm and 3m from the
Major hazard control
The storage of LPG a t fixed installations
Flammable liquids
f.pt. <32"C 6m to bund wall
tpt. 32-45C 6m to tank and 3m
to a bund wall
Tank containing toxic or 15m or the separation
hazardous substance distance in Table 2 column
(a) whichever is the greater
LPG cylinders total quantity 3m for LPG vessels < 5000
of LPG >50kg litres capacity
nearest point of the vessel. With the provision of 40 All vessels should b e marked with the
a fire wall, the separation distances may b e minimum safe operating pressure. Where this is
reduced to the values given in Table 2 column not known and cannot b e determined it should
(b). For vessels up to 500 litres see footnote to b e assumed to b e 1 bar absolute (zero bar
Table 2. gauge) and the vessel marked accordingly.
35 The distance between the vessel and any Underground and mounded vessels
specified feature measured around the ends of 41 Underground vessels should b e located in
the fire wall should b e equal to or greater than ground which is well drained. The vessel should
the separation distance given in Table 2 preferably b e located within a concrete or brick
column (a). lined pit which will allow sound installation and
36 Normally a fire wall should only b e provided backfill and provide easy access for inspection.
on one side of a vessel or group of vessels. Vessels may b e installed in open ground
excavations where these criteria can b e met.
Mechanical integrity 42 Underground and mounded vessels should
37 The mechanical integrity of LPG vessels will be placed on a firm foundation and installed so
not initially b e assured unless the correct design as to prevent movement or flotation. The surface
criteria are adopted. These should reflect of vessels should b e suitably prepared and
process needs and environmental conditions and treated to protect them from corrosion. Methods
particular attention should b e paid to vacuum of protection may include surface coatings and
and low temperature use. The design of cathodic protection.
underground and mounded vessels will require
an appreciation of the more arduous conditions 43 The excavation should b e large enough to
introduced. allow for easy installation and should permit a
clear gap of at least lm between the shell of the
38 LPG vessels should b e designed, vessel and the walls before backfilling. When
constructed, tested and certified to an lowering the vessel into place, care should b e
appropriate standard e g BS 5500 for new vessels. taken to avoid damage to the coating. When the
They should b e constructed from steel which is vessel is in place, the coating should b e checked
suitable for use at the minimum safe operating by suitable fault detection apparatus and any
temperature. Their design requirements should damage repaired.
meet or exceed the following criteria.
44 The backfill material should b e inert, non-
Propane Butane
corrosive, free from abrasive materials or
Maximum safe operating pressure 14.5bar gauge 4.83 bar gauge
(2 10 PSKJ) (70 ~ s i g )
particles likely to damage the vessel coating and
M I N ~ safe
u ~ operating pressure 0 bar gauge 480 millibar carefully consolidated to give a minimum cover
absolute of 500mm.
(7 psi absolute)
Minimum safe operating temperature-40C -18C 45 Mounded vessels should b e covered by a
The design requirements for vessels to b e used suitable material which is inert, non-corrosive,
interchangeably for propane and butane storage free from particles or abrasive materials likely to
should be: damage the vessel coating and carefully
Maximum safe operating pressure 14.5 bar gauge (210 psig)
consolidated to give a minimum cover of 500mm.
Minimum safe operating pressure 480 mbar absolute (7 psi absolute) The mound should protect the vessel from the
Minimum safe operating temperature -40C effects of thermal radiation and should b e
39 Existing butane installations should b e sufficiently robust to remain in place in the event
checked by a competent person to determine of jet flame impingement.
whether they meet the design criteria in 46 Underground and mounded vessels should
paragraph 38. If not the vessel or installation normally b e fitted with a manhole of not less than
should b e modified to meet the criteria or a 560mm internal diameter to allow access for
vacuum prevention system installed. See inspection. Where a manhole is not provided,
Appendix. inspection ports may b e needed and it may be
Major hazard control
The storage of LPG at fixed installations
necessary to excavate the vessel to thoroughly addition to an effective parking brake, wheel
inspect it. Vessel fittings and connections may b e chocks should b e provided.
mounted on the manhole cover or attached
54 Because of the temporary nature of skid
directly to the vessel. If this latter method is
mounted vessels it is particularly important that
used, excavation may b e necessary for
the piping is to a high standard and thoroughly
inspection.
checked for leakage before use, each time the
Skid mounted vessels vessel is moved.
positioned so as not to spread the LPG or flange and the vessel and the intervening piping
resultant flame over the vessel shell. is designed, constructed, and tested in
accordance with the vessel's design code, the
Drain connections shut-off valve may be located at the downstream
66 Drain connections should be less than 50mm end of that length of piping. All connections in a
in diameter and fitted with two shut-off valves in vessel greater than 3mm diameter for liquids, and
series. The length of piping between the valves 8mm diameter for vapour should have an
should be at least 0.5m to minimise the risk of emergency shut-off valve eg an excess flow
sumultaneous obstruction of both valves by the valve, a non-return valve or a remotely operated
freezing of any water present in the LPG. The emergency valve.
piping down stream of the second valve should 71 Remotely operated emergency valves
not discharge beneath the vessel. The second capable of local manual operation should b e
valve and piping should be adequately fitted to all piping greater than 19mm internal
supported and secured to prevent mechanical diameter which carries liquid if:
damage or breakage by vibration or jet forces.
Both valves on the drain systems should have a (a) the supply of LPG is to an activity requiring
means of actuation which cannot be readily frequent making and breaking of
removed or moved from the closed position connections e g tanker fdling, cylinder filling;
except by intentional operation. (See paragraph or
195). (b) the activity occurs where the general public
67 Alternatively, a satisfactory arrangement for has access or where a significant number of
drain lines could be a single valve and a plug or people not familiar with the specific
blanking plate fitted on the discharge side of the emergency procedures are likely to b e
valve. Additional pipework and a second valve nearby and whose number and location
should b e fitted, when required, in accordance would make it difficult for them to evacuate
with paragraph 66. quickly eg automotive fuel dispensing; or
68 No drain line should discharge within 6m of (c) the vessel is of 225 000 litres (100 te) water
any drainage system where this would b e liable capacity or greater.
to create a hazard.
Contents gauges 72 Pumps should not be sited beneath an LPG
69 Any gauging device that relies on bleeding vessel. Pumps should be securely installed and
LPG to atmosphere should b e fitted with an located in accordance with Table 5. Positive
opening no greater than 1.4mm diameter. displacement pumps should have a bypass or
Gauging devices should clearly indicate when other suitable protection against over-pressure.
the vessel is full to its maximum normal capacity. Compressors
Sight glasses should not be used for measuring
the liquid level in LPG storage vessels except in 73 Vapour compressors should preferably be
special applications e g LPG meter provers. installed in the open air in a well ventilated
position at least 4.5m from an LPG vessel,
Valves buildings and boundaries. If installed in a
building, then the building should b e made of
70 All liquid and vapour connections on vessels
should b e fitted with a shut-off valve which noncombustible material with a lightweight roof
preferably is fire safe, except for relief valves and should have good natural ventilation,
and where the connection through the tank shell particularly at low level. The building should not
b e used for any purpose other than compression
is not greater than 1.4mm diameter. The valve
should be located as close to the vessel as and distribution of LPG and other gases.
practicable. However, where there are no Compressors should have at least one:
mechanical joints between the shut-off valve (a) high pressure cut-off switch, or similar
Major hazard control
Storage vessels (a) Within 1.5m in all directions from the discharge orifice of Zone 1
fixed liquid level gauges, rotary or dip gauges, filler openings
@) Up to 1.5m above ground level and within the distances set Zone 2
out for a fixed source of ignition in Table 2 column (a)
Relief valve discharge (a) Within direct path of discharge Fixed electrical equipment
should not b e installed.
@) Within 1.5m in all other directions from point of discharge Zone 1
(c) Beyond 1.5m but within 4.5m, or the separation distance in Zone 2
Table 2 column (a) in the case of vessels with a capacity not
exceeding 2500 litres, in all directions from point of discharge
Tanker loading and (a) Within 1.5m in all directions from a point where connections Zone 1
unloading are regularly made or disconnected for a product transfer
@) Beyond 1.5m but within 4.5m or the separation distance in
Table 2 column (a) in the case of vessels with a capacity not Zone 2
exceeding 2500 litres, from point of connection or
disconnection
Notes
1 Where any area is classified under more than one factor the higher classification should prevail
2 Any pit, trench or depression falling within a Zone 1 or Zone 2 area should be treated as a Zone 1 area throughout.
3 The term 'outdoors in open air' includes pumps, compressors and vaporisers which are covered by a canopy.
The storage of LPG at fixed installations
device, on the discharge side of the made to BS 5958: Part 1:1980 for further
compressor; information.
means to prevent liquid LPG entering the 78 Piping should be sized and routed so as to
compressor; eg a catchpot with a liquid level restrict the contents of the pipe to the minimum
sensor. and thus reduce the potential hazard. The route
selected should minimise the possibility of
Piping physical damage particularly from vehicles but
where such damage may be foreseen, protective
74 Piping should be properly designed and barriers, bollards etc should be provided. Piping
constructed with due regard to low temperature should preferably be run above ground and
service. The materials used should be suitable routed away or protected from excessive heat or
for use with LPG. In general steel piping should cold. The routing of piping containing liquid LPG
be used but for vapour lines solid drawn copper or vapour at pressure above 31 rnbar gauge in
tubing may b e used. When using copper pipe buildings should be avoided. Where this is not
the potential hazards from work hardening of the reasonably practicable any such piping within a
material should be recognised. Cast iron pipe building should be in a well ventilated position
should not be used. Pipes conveying propane protected from physical damage. The length of
vapour should be constructed from materials pipe within the building should be kept to a
suitable for use at temperature down to -20C. minimum.
Where these pipes may be subject to two-phase
flow eg on flare and blowdown systems, lower Underground pipes
design temperatures may be appropriate. 79 Where piping carrying liquid is installed
75 Detailed advice on piping for use with LPG underground:
can be found in LPGITA COP No 22. All metal
piping with a nominal bore greater than 50mm, (a) the piping design should make due
all piping at full vessel pressure and all pipes allowance for any additional loading or
carrying liquid should be designed and constraint imposed by backfill or
constructed to an acceptable standard such as underground location;
BS 3351 or ANSI B31.3. (b) corrosion protection should be provided
76 Joints in piping should be kept to a where necessary eg proprietary wax-
minimum. Piping more than 50mm outside impregnated tape, tar/bitumen overwraps, or
diameter should have welded or welded flanged cathodic protection. Specialist advice should
joints except when connecting to equipment be sought;
fitted with screwed connections. Piping 50mm (c) piping should be run,adequately supported
diameter and less may have screwed joints. and laid, in a shallow open concrete or
Where piping has screwed joints which may be masonry-lined trench with open grid covers,
subject to vibration, consideration should be where necessary, to allow safe movement of
given to tack welding them to prevent them from pedestrians;
coming loose. Jointing compounds for screwed
connections and joint rings should be suitable for (d) the trench may b e backfilled with an inert,
use with LPG. non-conosive material free from abrasive
particles likely to damage the corrosion
77 To prevent the accumulation of static protection. See paragraph 188 for advice on
electricity metal piping should be electrically maintenance requirements;
continuous so that the resistances to earth of the
(e) protection should be provided in the form of
installation does not exceed lo6 ohms. In
load bearing slabs or covers for those
practice a value of less than 100 ohms is readily
attainable and is unlikely to deteriorate with time sections over which traffic passes or where
superimposed loads will occur;
to a level above 106 ohms unless the plant is
subject to serious corrosion. Reference should be (0 all pipe joints underground should be welded;
Major hazard control
as an alternative to running a liquid filled devices should not be sited beneath the vessel.
pipe in a concrete or masonry trench, the Hydrostatic relief valves located under vessels
pipe may be run inside an outer pipe. The should be positioned so that escaping LPG is not
outer pipe should be sealed to the inner pipe directed towards the vessel surface or adjacent
at both ends and the space between the two access ways. At oil refineries and similar large
should be monitored to detect leakage, installations alternative arrangements may be
normally by registering a pressure change. provided to prevent overpressurisation of piping.
The outer sleeve should terminate above
ground or in a suitable inspection pit; Flexible connections
isolation valves should be provided at both 83 Hoses for conveying LPG should comply with
ends of the underground section; BS 4089. They should only be used where
necessary, and should be as short as reasonably
the route of the pipe-run should be recorded practicable. Where flexible connections are used
and, where practical permanently marked; for conveying liquid LPG, a hydrostatic relief
piping conveying inert or flammable liquids, valve should be installed to limit the internal
may be laid in the same trench but that pressure to not more than the design pressure of
containing corrosive or toxic materials and the hose or the operating pressure of the fixed
steam should not be; piping whichever is the lower. See paragraph 152
for guidance on hoses used for loading and
it is recommended that electric cables are unloading.
not laid in the same trench as LPG piping.
Electric cables may be laid in the same 84 Emergency isolation devices eg non-return
trench if protected by an outer pipe or valves, excess flow valves or remotely operated
sleeve. emergency valves should b e installed in piping
convevina liauid LPG to which hoses are
Suitable polyethylene (PE) pipe may be used connected, to prevent the prolonged discharge
to convey LPG vapour and LPG/air mixtures. PE of LPG in the event of failme of the hose.
pipe should be buried but where at the terminals
it is brought above ground it should be as short Supports for vessels and piping
as possible and not longer than 2m. It should Vessel supports
also be protected against ultra-violet light and
mechanical damage e g by sleeving. Alternatively, 85 The design of supports should follow the
the transition to metal pipework may be made recommendations in the code to which the
with a suitable fitting below ground. vessel is constructed. Supports should permit
81 Piping conveying LPG vapour may be buried movement of the vessel due to changes in
in an open excavation backfilled with a material temperature and should be designed to prevent
which is non-corrosive. Metal piping should be or drain any accumulation of water. Supports for
protected from corrosion e g using proprietary horizontal vessels should be located to give
wax impregnated tape, tadbiturnen overwraps, minimum moments and deflections to the vessel
cathodic protection. The backfill for metal piping shell. Additional supports may be required to
should be free from abrasive particles likely to meet special circumstances.
damage the protective coating. 86 Vessels should be properly installed on firm
Hydrostatic relief valves foundations and supported on concrete, masonry
or structural steel supports. These supports
82 Piping in which liquid LPG may be trapped, (excluding supporting feet 460mm or less in
for example, between shut-off valves, should be height, vessel saddles, or skirts of vertical
protected against excessive pressure by fitting vessels) should be so constructed or protected as
hydrostatic relief valves. If these devices to be at least 2hr fire resisting.
discharge to atmosphere, the discharge should
be to the open air and should not endanger 87 Where piers are used as part of the vessel
people or equipment. Where possible the support for horizontal vessels with a capacity
The storage of LPG a t fixed installations
exceeding 5000 litres (2.2 te), provision should b e tracing of the vapour discharge line with the
made for securing the vessel at one end, the provision of condensate pockets capable of
other being free to move. The end secured containing the quantity likely to b e condensed
should b e that to which the principal liquid and during a plant shut-down. With hot water heated
the vapour pipes are attached. Saddles should vaporisers, anti-freeze may b e added to the water
normally be welded to the vessel shell. Where to prevent freezing.
saddles are not welded to the vessel, their
91 Vaporisers should b e designed, fabricated
support should b e shaped to conform with the
and tested in accordance with an appropriate
vessel shell and wear pads provided to prevent
pressure vessel code e g BS 5500.
damage or weakening of the vessel shell.
92 Heating coils should not b e installed inside a
88 Vertical vessels should b e supported by an
storage vessel to act as a vaporiser.
open structure which will allow good natural
ventilation under the vessel and provide 93 If not already included in the requirements of
adequate explosion relief. If a cylindrical skirt is the manufacturing standard the following
used to support the vessel, pipes from the additional information should b e plated on the
vessel, within the skirt, should have welded or vaporiser or included in documentation which is
welded flanged joints. readily available:
(a) the manufacturer's name and vaporiser serial
Pipe supports number;
89 Supports should b e adequately designed, (b) the code to which it was made;
spaced and secured to suit the pipe
configuration and to withstand anchorage and (c) the maximum safe operating pressure;
guide friction forces. (d) the maximum and minimum safe operating
temperature;
Vaporisers (e) the year of manufacture.
General
94 Vaporisers should b e installed in a well
90 Vaporisers can b e low pressure steam- ventilated position, preferably in the open air and
heated, hot water heated, electrically heated, or not in or near a pit or depression. They should
direct gas fired. They should b e of sufficient b e separated from important buildings,
capacity to vaporise LPG at the maximum vapour boundaries or adjoining property lines as in
offtake required from the installation. For butane, Table 6. The ground beneath vaporisers should
precautions against the accumulation of b e concreted and sloped so that any leak of LPG
condensate in the vapour discharge line should flows towards a safe place away from the
b e taken. This may require insulation and heat vaporiser and any LPG vessel.
Up to 36 Up to 80 3
> 36-227 > 80-500 7.5
Over 227 Over 500 15
Major hazard control
The storage of LPG at fixed installations
surveillance of the installation, the site perimeter Marking and identification of the
fence may suffice for security. However, where installation and its contents
the installation is remotely located on the site,
subject to infrequent surveillance, and 112 The purpose of any marking and
particularly where trespass on to the site is identification is to:
known, the installation should b e enclosed by its
own security fence to supplement that at the (a) draw attention to the hazardous nature of the
perimeter. contents;
108 The requirement for a security fence may (b) avoid confusion, whether during normal
b e relaxed for vessels of less than 9000 litre (4 te) operations or in an emergency, which might
capacity provided that access to the valves and lead to incorrect actions likely to cause an
fittings is denied, eg, by a substantial lockable incident or make it worse.
cover, an open mesh wire fence between the Such marking is in addition to that in paragraphs
support piers. Where a lockable cover is 51 and 93.
provided it should b e kept locked at all times
other than during vessel filling. The key to the 113 All markings and identifications should b e
cover should b e readily available in an both clear and durable. The information should
emergency. This relaxation should not be applied either b e on plates or tags etc securely attached
where the public have uncontrolled access. to the part to which it relates, or directly marked
onto it. Paper labels are not satisfactory.
Protection against vehicular damage
114 The direct stamping of information onto any
109 The location of vessels and their part should only b e carried out if this does not
attachments, e g piping, in areas used by motor impair the integrity of that part and is capable of
traffic should b e avoided. Where protection is withstanding wear and possible over-painting
required, substantial crash barriers or bollards without becoming illegible.
should b e provided. The security fence is 115 The vessel should b e clearly marked with
unlikely to provide adequate protection on its the words 'Liquefied Petroleum Gas' or the name
own, nor is the restriction of traffic by marking of of the material stored where confusion could
the ground, warning notices, etc. arise. The words 'Highly Flammable' should b e
added or a pictorial sign conforming to the Safety
1 10 Underground vessels should b e protected
Signs Regulations 1980.
from the effects of ground loading by traffic
either by fencing off the area above the vessels 116 Piping should b e marked or colour-coded,
or by the provision of load-bearing covers. or both, to indicate the contents conveyed, and
Underground pipework should b e similarly whether the contents are liquid or vapour. Colour
protected where necessary. coding, where appropriate, should b e in
accordance with BS 1710.
111 Petrol driven cars and other vehicles which
are under the control of the site occupier should Valves and connections
b e parked at least 6m, or the separation distance 111 The operation of all manual isolation valves
given in Table 2, column (a) whichever is the should b e clear. The operating points for
smaller, from LPG vessels. Diesel powered remotely operated isolation valves and manually
vekicles under the control of the occupier may operated fixed water-drench systems should b e
b e parked to within 3m of the vessels providing clearly identified and the mode of operation
they do not hinder ventilation. Vehicles not marked.
under site control eg those belonging to
members of the public, should be parked no 118 Where butane and propane
closer than the separation distances given in loading/unloading connections are adjacent they
Table 2 column (a). should b e clearly identified.
The storage of LPG a t fmed installations
Hazardous area classification for responsibility of the local fire authority to make
electrical equipment provision for fire fighting purposes, and to equip
and maintain a fire brigade accordingly to meet
119 Electrical equipment should only b e all normal requirements. The local fire authority
installed in a safe area away from LPG vessels may make arrangements with works fire teams to
and equipment. Where this is not reasonably provide assistance but the local authority brigade
practicable the area around an LPG vessel and will assume control of fire fighting operations
equipment can b e subdivided according to the upon arrival at a fire. The fire brigade should b e
degree of probability that flammable called out whenever a fire occurs which may
concentrations of vapour may arise and the threaten the LPG storage.
electrical equipment suitably protected
depending on its location. Those subdivision are 124 The fire service will wish to b e consulted at
an early stage where LPG storage is planned.
defined as:
The enforcing authority (see glossary) should b e
Zone 0 An area in which a flammable gadair consulted where additional guidance on fire
mixture is continuously present, or fighting and protection facilities is required
present for long periods. which is not to b e found in this document.
Zone 1 An area in which a flammable gadair
mixture is likely to occur in normal Fire protection
operation. 125 LPG storage vessels threatened by fire
Zone 2 An area in which a flammable gadair should b e kept sufficiently cool to prevent vessel
mixture can only occur in abnormal failure. This protection can b e achieved by the
conditions and not in normal operation. discharge of water onto the vessels at a rate
sufficient to maintain an adequate film of water
A more complete explanation of the method of over the surface of the vessels and supports.
classification can b e found in BS 5345 and
guidance in choosing suitable electrical 126 Vessels may also b e protected from radiant
equipment for those zones in Health and Safety heat by burial, mounding or other methods, such
booklet HS(G)22. as insulating coatings, provided an equivalent
standard of protection to adequate water drench
120 If electrical equipment has to b e installed systems (ie monitors or fixed sprays) can b e
near LPG vessels etc, it should meet the achieved. Where these methods are used, water
standards and separation distances in Table 5. for fire protection need not b e provided except
121 LPG vessels d o not normally require for unprotected manholes on underground or
lightning protection. mounded vessels. Water protection for the tanker
offloading bay and any process plant containing
Fire precautions LPG may still b e required.
General Water supplies
122 The possiblity of a major fire outbreak can 121 At all installations there should b e an
b e minimised by good plant design and layout, adequate supply of water for fire protection for
sound engineering, good operating practice and use in an emergency. To provide adequate
proper instruction and training of personnel in protection for a vessel threatened by fire an
routine operations and action to b e taken in an application rate of 9.8 litres/m2/min over the
emergency. Good plant design and layout should whole surface of the vessel for at least 60
include consideration of water supplies, fire minutes is required*. The capacity of the supply
protection equipment, fire fighting, means of may need to b e increased where there are no
access for fire brigade appliances, protection of
fire brigade personnel and arrangements to
ensure an early call out to the fire brigade in the *The use of water sprays to protect fire engulfed LPG storage
event of fire. tanks. Billinge, Moodie and Beckett. 5th International
symposium. Loss Prevention and Safety Promotion in the
123 Under the Fire Services Act 1941 it is the Process Industries. 1986.
Major hazard control
Litres Tonnes
150 - 2500 < 1.1 Water supply for fire brigade use lOOm away
Domestic
150 - 2500 < 1.1 Water supply for fire brigade use lOOm away
Commercial and 19mm hose reel or 2 x 9 litre water extinguishers
industrial 2 x 9kg dry powder extinguishers (not commercial sites)
Water supply
Fixed and/or portable monitors
19mm hose reel
2, x 9kg dry powder extinguishers
Water supply
Automatic fixed sprays
19mm hose reel
c
2 x 9kg dry powder extinguishers
additional water supplies available near the and usually no further than lOOm from the
premises. If water is supplied via a recirculating vessels.
system the storage reservoir should hold 30 mins 132 At remote installations where the population
supply without recirculation. Special near the vessels is low, making it easy to
consideration should be given to the possibility evacuate the area, it may b e acceptable for the
that there could be a loss of power on the site water supply to be more than lOOm from the
and the consequences this would have for the vessels. In these cases the fire brigade should be
fire protection arrangements provided. consulted. A comprehensive evacuation plan
128 On-site hydrants and fixed drench systems should be available which the residents in the
should be designed so that the water flow can vicinity of the installation are familiar with.
be controlled from a safe position beyond the Installations with a total inventory in vessels
separation distances set out in Table 2 greater than 2500 litres (1.1 te) but less than
column (a). Connections for fire brigade use 56 250 litres (25 te)
should be provided on the water supply to fixed
drench systems. The connections should be 133 For installations in this inventory range fire
located in a safe place agreed with the fire protection may consist solely of an adequate
brigade. water supply for fire brigade use except for
vessels exceeding 15 750 litres capacity (7 te)
129 There should be adequate drainage to deal with liquid outlets. The level of fire protection
with water used for fire protection and would depend on the installation meeting the
firefighting purposes. Water sealed interceptors other provisions of this guidance note. When
should be fitted, where necessary, to prevent deciding on the level of protection consideration
LPG entering the storm drains and sewers. should also be given to the ease of evacuation of
Fire protection equipment the surrounding area and the attendance time of
the fire brigade.
130 The provision for fire protection at fixed
installations depends on a number of 134 For vessels with liquid outlets, where the
considerations. These include the maximum vessel size exceeds 15 150 litres ( I te) and
storage capacity of the installation, individual remotely operated emergency valves are not
vessel sizes, the number of tanker deliveries and fitted to the liquid outlets, consideration should
whether there is an increased risk of fire on site be given to providing a means for applying
which may affect the vessels e g at LPG cylinder cooling water to the vessels. This may be fixed
filling plants. Paragraphs 131 to 141 provide or portable monitors or other suitable means.
guidance on the standards for fire protection Installations with a total inventory in vessels of
which will be required by the enforcing 56 250 litres (25 te) but less than 112 500 litres
authority. This guidance is summarised in Table 7. (50 te)
Higher standards of fire protection may be 135 At bulk installations with inventories from
required by the enforcing authority where other 56 250 litres (25 te) but less than 112 500 litres
factors prevail such as increased off-site risks and (50 te) means should be provided to apply
hazards, location of the nearest water supply and cooling water to the vessels. Portable or fixed
the time for the fire brigade to reach the site. monitors or other suitable means may be used
Domestic and small installations for this purpose.
131 Domestic installations and those small Installations with a total inventory in vessels of
commercial or industrial installations with vessels, 112 500 litres (50 te) and greater
where the capacity of each vessel does not 136 At bulk installations with inventories of
exceed 2500 litres (1.1 te), should be provided 112 500 litres (50 te) and greater, the vessels
with an adequate water supply for fire brigade should be provided with fixed fully automatic
use. For these premises an adequate water water spray systems capable of detecting a fire
supply may consist of hydrants, ponds, canals or threatening the vessels and operating the sprays
rivers. The supply should b e readily accessible without manual intervention. A fire detection
Major hazard control
system dependent solely on the sensing of This equipment should b e selected and located
excess vessel pressure is not adequate for this to enable fires adjacent to the vessels to b e
purpose. At refineries and similar large extinguished and so prevent fire spreading to or
installations where continuous supervision is jeopardising the LPG installation. Fire
available, manually operated water sprays may extinguishers or hose reels or an equivalent
b e sufficient. At these installations it may not b e combination of the two types of equipment may
necessary to simultaneously drench all storage b e provided. Fire extinguishers should be
vessels and means may b e provided to allow selected, sized, located and maintained in
drenching of individual vessels or groups of accordance with BS 5306: Part 3: 1980, and hose
vessels. A remote manual operating point should reels should b e selected and installed in
b e provided in a safe place (see paragraph 128). accordance with BS 5306: Part 1: 1976.
Other installations where fire protection is 143 All fixed LPG installations should b e
required provided with at least one 19mm hose reel. At
small installations with vessels up to 2500 litres
131 Fixed water spray systems should b e fitted (1.1 te), two 9 litre water extinguishers may b e
to bulk vessels at cylinder filling installations. A provided as an alternative. Hose reels and
similar level of protection may b e necessary at extinguishers need not b e provided at domestic
some aerosol filling plants where the vessels premises because of the lack of trained people
could b e threatened by a fire involving the filling to operate them.
installation or the aerosol store. Fixed spray
systems are not necessary where automotive LPG 144 In addition to the requirements in
is dispensed and paragraph 71 applies or where paragraphs 142 and 143, at least two fire
only a small number of cylinders are filled e g for extinguishers suitable for extinguishing an LPG
fork lift trucks. fire should b e provided (see paragraph 146).
Powder extinguishers rated at least 22318 (eg a
138 At installations with a total inventory in capacity of 9kg) would normally b e suitable.
vessels of 56 250 litre (25 te) or greater, the road Powder extinguishers need not be provided at
tanker bay should b e provided with the same domestic and small commercial installations
level of fire protection as the fixed vessels. where it is unlikely that anyone will b e available
139 At installations where an average of more who has been trained to fight LPG fires.
than two road tanker deliveries a week take Access
place, or where more than two road tankers a
week are filled with LPG, based on the 145 Access to and around the installation should
consumption over six months including the b e provided for fire fighting and should b e kept
winter period, consideration should b e given to free at all times.
the provision of additional fire protection at the Fire instruction and training
tanker bay.
146 People on premises where LPG is stored
140 Rail loading and unloading gantries should should receive adequate instructions with training
b e provided with fixed water sprays or an as appropriate to enable them to understand the
equivalent form of fire protection. fire precautions and action to b e taken in the
141 For the purposes of the paragraphs 131 to event of fire or leakage of LPG. They should
138 individual vessels may b e considered in receive instruction and training appropriate to
isolation where they are the sum of the their responsibilities in the event of an
separation distances given in Table 2, column (a) emergency. Those trained to fight LPG fires
apart. should b e aware that these fires should not
normally be extinguished unless the source of
Portable fire fighting equipment LPG can b e isolated. At commercial and
industrial sites notices setting out the emergency
142 There should b e sufficient and suitable procedures should b e prominently displayed
portable fire fighting equipment on the premises. near the LPG storage area. At domestic
The storage of LPG at fixed installations
installations the user should b e provided with full (d) b e hydraulically tested every year;
instructions which include the action to b e taken be periodically checked for electrical
in an emergency. continuity;
(f) have written records of the tests in (d) and (e);
Loading and unloading facilities
(g) b e kept so that the hose will not b e
General physidally damaged or adversely affected by
141 Written instructions should b e given which the weather when not in use or when being
clearly define responsibilities for all personnel conveyed;
involved in loading/unloading operations. (h) have means for protecting their end fittings
against damage or ingress of foreign material;
148 Manning levels for LPG transfer operations
will b e dictated by the size and complexity of a (i) where appropriate, b e protected by a roc oil
particular installation. As a general safety rule the or similar device to protect against external
number should not b e less than two. For many damage;
installations, this would normally b e the road Cj) b e replaced or repaired when damaged or
tanker dnver and an employee from the site. In worn.
some cases, particularly at domestic and small 153 Loading arms or flexible hoses in which
installations, this may b e impractical, as only the liquid could be trapped bemeen shut-off valves
driver will b e present.
should b e protected against excess pressure
149 Except in those cases mentioned in caused by t h e thermal expansion of the contents,
paragraph 148, a responsible person on site e g by hydrostatic relief valves or by their design.
should check that the quantity and type of LPG
being transferred is suitable for the receiving Loading/unloading of road tankers
vessel. Vessels should b e checked to see how 154 In order to minimise the risk of accidental
full they are before filling, and also during filling movement, the tanker should stand on an
using the contents gauge where fitted. The essentially level site during loading or unloading.
maximum level device should b e used to ensure Chocks should b e placed against the vehicle's
overfilling does not occur. Road and rail tankers wheels or other means provided to prevent
should preferably b e check weighed prior to vehicle movement prior to loading/unloading.
leaving the depot to ensure they have not been These should only b e removed when transfer is
overfilled. Specifications for filling ratios for LPG complete. The ground beneath the tanker should
can b e found in BS 5355: 1976. b e drained, cambered or have a shallow gradient
150 Overfilling can have extremely serious to a safe place to prevent any spillage from
consequences and any overfilled tanker or remaining under the vehicle or from flowing
vessel should have the excess LPG removed under any vessels or piping in the fixed
immediately in a safe manner. installation.
155 The loadinghnloading operation should
151 The point of transfer, where connections
and disconnections are made should b e sited in only b e carried out when it is safe to d o so and
a well ventilated position. where practical b e separated from other traffic
movement. Where vehicles or pedestrians are
152 Flexible hoses used for conveying LPG to likely to pass by, physical barriers may b e
and from road and rail tankers into fixed piping needed to deter them approaching the transfer
or vessels should: operation.
(a) b e designed and constructed to an 156 Consideration should b e given to the
appropriate standard e g BS 4089; provision of a driveway protection device on all
(b) have a means of identification; installations with vessels of 9000 litres capacity
(c) b e examined for kinks and wear on every (4 te) or above. Examples of such devices are:
occasion prior to use. Hose fittings should b e (a) a self-sealing breakaway coupling connected
similarly examined; to the flexible hose;
Major hazard control
means to shut emergency isolation valves on tanker should b e discharged to earth. The tank
both the fixed plant and the tanker of the road tanker should b e electrically bonded
automatically to the fixed installation before any LPG transfer
an interlocked physical barrier or similar operation is carried out. The electrical bonding
system on either the vehicle or static connection should b e broken only after the
installation; liquid and, where used, the vapour balance
connection have been disconnected.
a means to automatically actuate the vehicle
braking system to lock immediately the Loading/unloading rail tankers
delivery hose is taken from its normal transit
stowage position until it is restored to that 162 The rail loading/off-loading operation should
position; b e separated from other rail traffic, e g on a
a brake flap arrangement which must b e siding. The transfer point should b e sited in a
moved aside to gain access to the filling well ventilated position at least 15m from
branch, the action of which actuates the buildings, boundaries, sources of ignition and
braking system. any storage vessel forming part of the fixed
installation.
157 When a vehicle's engine is used during
loading/unloading, usually to drive a pump, an 163 In order to minimise the risk of accidental
emergency engine cut-off device should b e movement, the track should b e laid essentially
installed so that the engine can b e switched off level. A slight downward gradient of less than
from outside the cab. 1:250 is acceptable, provided that this is away
from the main line track, or in the case of a
158 The road tanker should stand off the siding ending at buffers, towards the buffers.
highway while unloading and b e positioned so
164 Rail tankers containing LPG should not b e
that it can b e readily driven away in the event of
loose shunted.
an emergency, if it is safe to d o so. The location
of the tanker should permit the driver to see the 165 Physical barriers should b e provided where
tanker when standing at the storage vessel. there is a possibility that a tanker could b e
While the driver is at the vessel he should b e damaged by road vehicles, e g where a road and
able to stop filling immediately the vessel is full. a rail siding are sited beside each other.
159 At some installations, e g at domestic 166 A barrier gate and other means of positive
premises it may not be possible to park the isolation should b e provided to prevent a train
tanker off the road during unloading. Where this from be in^ accidentally pulled away while the
is so the tanker should not cause an obstruction tankers are connected to the fixed installation.
to others and the Highway Code should b e Suitable means include:
observed. (a) removal of the locomotive;
160 Hoses should not b e run across a public (b) removal of the towing cable or isolation of
footpath or pavement during unloading unless the capstan motor;
there is no alternative and where consideration of (c) locked points;
the safety of the public indicates that it will not (d) application of wagon handbrakes.
constitute a significant hazard. In such cases,
before and during unloading, warning notices, Interlocks may b e provided with product transfer
readable from 6m, should b e set up on both pumps, isolation valves, etc to ensure that the
sides of the hose stating: train has been correctly positioned before
transfer begins. Signals may b e provided for
(a) Warning - LP Gas Transfer Taking Place; additional security.
and
167 A system of work should be provided to
(b) No Smoking or Naked Flames,
ensure the tankers are not moved without the
or words to that effect. knowledge and approval of the plant personnel
161 Any accumulated static electricity on a road in charge of the LPG transfer operations. Traffic
The storage of LPG at fixed installations
179 Evacuation is only suitable for vessels maintenance schemes are properly monitored.
designed to full vacuum conditions. All significant repairs or replacements should b e
recorded.
De-commissioning
185 A scheme for examining the installation
180 The installation to b e de-commissioned and should b e drawn up by or b e endorsed by a
purged free of LPG should b e isolated from any competent person and reviewed after each
process, plant or vessels containing LPG. examination. Vessels should b e examined at
Normally, this is achieved by removing pieces of intervals as required by a competent person.
piping or by fitting blanks or spades in the Direct heated vaporisers should b e thoroughly
pipes. The closure of shut-off valves is not a examined at intervals not exceeding one year.
suitable means of isolation.
186 The scope of any particular examination and
Before opening, an LPG vessel should be: the inspection techniques to b e used should b e
emptied of liquid LPG as far as possible, by decided by the competent person. Examination
normal use or transfer to another suitable of pressure vessels should include support
vessel, flaring or venting. Where a drainline structure, holding down arrangements and
is used for emptying the vessel it should foundations.
comply with paragraph 66. If it is necessary
to vent LPG to atmosphere, only the minimum 187 Examination of underground or mounded
vessels should include tests for corrosion eg
quantity of material should be vented;
detailed ultrasonic thickness checks. If internal
purged with an inert gas until it contains less access is not possible the external surface of the
than 4% LPG and remains at or near that vessel will need to b e exposed to enable
concentration of LPG, ie there are not heavy examination to take place.
ends still gassing off flammable vapours;
188 Underground piping carrying liquid which
purged by displacement with water or
is laid in a backfilled trench should b e examined
another suitable method. Care should b e
for corrosion, or tested in such a way as to
taken to ensure no heavy ends remain which
establish continuing integrity, at least once every
could lead to the formation of a flammable
ten years.
atmosphere when air is introduced into the
vessel 189 Any significant deterioration or defects
found and any remedial work undertaken, should
Maintenance and examination b e recorded on the examination report with
182 The installation should b e properly particulars of the inspection techniques used.
maintained to acceptable standards determined The effect of such deterioration, defect or repair
and overseen by a competent engineer of should b e assessed by the competent person
appropriate discipline with the objective of and the safe working limits endorsed or modified
maintaining the established safe operating limits. accordingly.
Emphasis should b e placed on features affecting 190 The examination report should specify:
the integrity of the installation or the ability to
take emergency action. For installations rented (a) the maximum safe operating pressure;
from the gas suppliers this work may b e carried (b) the minimum safe operating pressure;
out by the company owning the vessel.
(c) the minimum safe operating temperature;
183 A maintenance scheme should b e prepared
(d) the maximum permissible load (on supports);
which includes protective devices and
instruments, the form and detail of which should (e) the date of next examination.
reflect the needs of the particular installation.
Servicing and maintenance handbooks may b e 191 Any repair or modifications undertaken
adequate for simple installations. should b e to a standard which is at least equal to
the original design and construction code.
184 Suitable records should b e kept so that all Where such work may affect the integrity of the
The storage of LPG at fixed installations
installation it should b e overseen and certified by 194 Particular care should b e taken when
a competent person who should endorse or draining storage vessels in service in order to
modify the safe operation limits accordingly. minimise the escape of LPG. Of the two drain
valves, that nearer to the vessel should b e fully
opened first and draining then controlled by
Operational procedures gradually opening the second valve. If, on
opening the second valve, no flow occurs, both
192 Written operating procedures should b e valves should b e closed immediately to allow
prepared which clearly define the actions or subsequent investigation. On completion of the
functions required of people involved. These draining operation, the valve furthest from the
should cover both normal and emergency storage vessel should b e closed first, then the
operations and b e regularly reviewed to ensure other valve.
that they are appropriate at all times. They
should b e amended to take into account any
alterations or modifications to the installation. The Training
procedures should b e readily available and 196 Employers should ensure that employees
preferably clearly displayed. Where appropriate, concerned with LPG are familiar with its
copies or relevant abstracts should b e issued to properties and hazards. Employees should b e
people on site., including contractors entering or instructed on normal operations, including
working at the site. loading and off-loading procedures and
193 Procedures should include: emergency operations, fire-fighting and
emergency shut-down. This instruction should b e
the transfer of LPG to or from the installation followed by appropriate practical training
(for which check lists may prove a useful
sessions designed to ensure that each employee
supplement);
is competent to carry out their duties and also to
the transfer of LPG at other sites when ensure that they are familiar with the installation
delivery tankers operate from the site; and its operating procedures. Training should b e
a continuous commitment and include refresher
permit-to-work systems; courses, where appropriate. The emergency
plant maintenance and modification including procedures should b e practiced at least once a
the maintenance of protected electrical year, except at domestic installations.
equipment; 197 All operations at LPG installations should b e
performed by properly trained personnel. A
emergency procedures. sufficient number of people should b e appointed
194 Employees and self employed people and trained to supervise procedures and
should only act within their sphere of operations at the installation.
responsibility. Any deviation from the written 198 The operator should b e made aware of any
procedures should only b e undertaken with the plant alterations, and any change in operating
written authority of the appropriate responsible procedures and should receive additional
person on site. training to ensure safe operation of the installation.
Major hazard control
The Classification, Packaging and Labelling of Part 4: 1970 Non combustibility test for materials.
Dangerous Substances Regulations 1984 (SI 1984 Part 8: 1972 Test methods and criteria for the fire
No 1244) ISBN 0 11 047244 6 HMSO. resistance of elements of building construction
Gas Act 1986 ISBN 0 10 544486 3 HMSO. BS 1710:1984. Specification for identification of
pipelines and services.
Pipelines Act 1962, ISBN 0 10 850098 5 HMSO.
BS 335 1:1971. Piping systems for petroleum
Petroleum (Consolidation Act) 1928 refineries and petrochemical plants.
ISBN 0 10 8502 12 0 HMSO.
BS 4089:1966. Rubber hose and hose assemblies
LPGITA Codes for liquefied petroleum gas lines.
LPGITA (UK) Code of Practice No 1 March 1978. BS 4250: 1975. Specification for Commercial Butane
Installation and maintenance of bulk LPG storage and Propane.
at consumers' premises. ISBN 0 900323 9. BS 5146: Inspection and test of valves. Part 1:1974:
LPGITA (UK) Code of Practice No 22 LPG Piping Steel valves for petroleum, petrochemical and
- System design and installation. allied industries.
The storage of LPG at fixed installations
BS 5306 Code of Practice for fire extinguishing BS 6651: 1985 Code of Practice for protection of
installations and equipment on premises. structures against lightning.
Part 1: 1976 Hydrant systems, hose reels and BS 6759: Part 3: 1984 Specification for safety
foam inlets. valves for process fluids.
Note: British Standards are obtainable from the
Part 3: 1985 Code of Practice for the selection, British Standards Institution, Sales
installation and maintenance of portable fire
Department, Linford Wood, Milton
extinguishers. Keynes, MK14 6LE.
BS 5345: Code of Practice for the selection, Tel (0908) 32006 (call queuing system
installation and maintenance of electrical operates)
apparatus for use in potentially explosive American Petroleum Institute Standards
atmospheres (other than mining applications or
explosive processing and manufacture). API 520 Recommended Practice for the Design
and Installation of Pressure. Relieving Systems in
Part 1: 1976 Basic requirements for all parts of the Refineries.
Code. Part 1: Design
Part 2: Installation
BS 5355: 1976 Specification for filling ratios and
developed pressures for liquefiable and API 607 Fire tests for soft seated quarter turn
permanent gases. valves.
API 6FA Specification for fire tests for valves.
BS 5423: 1980 Specification for portable fire
extinguishers. API 2000 Venting atmospheric and low pressure
storage tanks (non-refrigerated and refrigerated).
BS 5499: Fire safety signs, notices and graphic
symbols. Part 1: 1984: Specification for fire safety American National Standards
signs. ANSI B3 1.3 Chemical Plant and Petroleum
BS 5500: 1985 Unfired fusion welded pressure Refinery Piping.
vessels.
1: 1981 addenda to ANSVASME B3 1. 3 - 1980
BS 5958: Code of Practice for the control of edition (ANSVASME B3 1.3a-1980).
undesirable static electricity. Part 1: 1980: General
2: 1982 addenda to ANSI/ASME B3l.3 - 1980
considerations.
edition (ANSVASME B31.3b - 1982).
Major hazard control
(d) Vacuum breakers Vacuum breakers will pressure in the vessel. Pressure sensors in the
prevent a vacuum from occurring but can pipework between the vaporiser or propane
introduce many operating and safety problems vapour source and the vessel may not give a true
and should normally only b e used in an indication of the pressure in the vessel.
emergency. Specialist advice should b e obtained
from the LPG supplier. (a) High pressure alarm This should b e set
below the vessel relief valve setting and should
(e) Inert gas pressurisation An inert gas can
warn of an abnormally high vessel pressure.
b e fed into the vessel vapour space but may
Water sprays fitted to the vessel which are
introduce operating problems because of the
operated automatically by high vessel pressure
non-condensible nature of the gas. Specialist
and which sound an alarm are suitable.
advice should be obtained from the LPG
supplier.
(b) Low pressure alann This should warn of an
abnormally low pressure indicating a fault in the
High and low pressure alarms
pressure control equipment. It should b e set
4 The pressure sensors for the high and low above the minimum safe operating pressure of
pressure alarms should monitor the vapour the vessel.
Appendix 5 (b)
Contents
Foreword
Introduction
Siting of installations
Unloading area
Design and location
Potential incidents
Deliveries of liquid chlorine by road tanker
Deliveries of liquid chlorine by rail tanker
Interlocks
Design considerations for the access structure at
the unloading point
Valves
Types of valve
Vertical globe valves
Conical plug valves (PTFE sleeved)
Ball valves
Remotely controlled valves
Major hazard control
Storage vessels
Design criteria
Connecting pipework and means for isolation of
storage tanks
Liquid chlorine inlet
Liquid chlorine outlet
Vent and compressed dry gas lines
Relief system
Instrumentation
Chlorine vaporisers
Methods of heating
m e s
Regulation of throughput
General installation
Safety
Hazards
Routine and emergency isolation
Pressure control valve
Corrosion
Chlorine absorption system
Vent collection system
Absorption equipment
Instrumentation
Disposal of effluent rom the chlorine absorption
plant
Protective and emergency equipment
Respiratory protective equipment for routine
use
Respiratory protective equipment for
emergencies
Protective clothing for emergencies
Emergency tool kits
Containment of chlorine leakage
Operator selection and training and operating
Mctions
Operator selection and training
Operating instructions
Maintenance
Clearance procedures
Modifications of the chlorine systems
Emergency procedures
Chlorine detector alarms
Local alarm stations
Works emergency plan
Emergency control centres
Site emergency team
Emergency assembly areas
Attention to casualties
Appendices
1 Properties of chlorine
2 Outside installations and inside
installations
3 Publications and standards
4 Procedures for discharging road tanks of
chlorine
5 Summary : Types of vaporiser
Major hazard control
Foreword
This advice was prepared by a Working Party which met under the auspices of HSE's Chemical
National Industry Group and is based on the Guidelines for Bulk Handling of Chlorine at Customers
Installations published by the Chemical Industxies Association Ltd in 1980. As knowledge develops,
the advice may need to be updated again in the future.
Membership of the Working Party consisted of representatives from the four UK producers of
chlorine, a representative of the Transport and General Workers Union, and staff from HSE working
under an HSE chairman.
The guidelines may be applied to any bulk chlorine installation but they are not intended to be a
detailed design code. Some existing installations may not at present meet all the recommendations
and, in some cases, not all the recommendations may be appropriate. It is for the occupier, usually in
consultation with the chlorine supplier and/or specialist advisers, to judge the need in any particular
case. If modifications are shown to be needed, a responsible decision is required on the nature and
timing of changes to be made. The final responsibility remains with the company operating the plant
to do so safely.
A CIA publication Inter-Company Collaboration for Chlorine Emergencies published in 1978 is
relevant. It gives advice to chlorine users faced with emergencies and gives details of the immediate
assistance which is available under the Chlor-Aid scheme.
The HSE is grateful to representatives of the chlorine industry for their assistance and co-operation in
preparing this advice, and to the Chemical Industxies Association Ltd for permission to reproduce
substantial portions of the 1980 Guidelines.
Safety advice for bulk chlorine installations
10 For existing installations, control of present 16 The unloading area should be on reasonably
population density is not posible. However, level ground with adequate surrounding space
developments nearby which would increase the providing good access from different directions.
number of people are controllable and would be Adequate lighting covering all escape routes
permitted by the local Planning Authority only should be provided and the provision of
after detailed consideration, which will normally emergency lighting may be advisable.
include the use of advice received on request
from the HSE. 17 Sufficient manually operated alarm stations
need to be provided to enable warning to be
11 The location of new chlorine installations given in the everit of a chlorine escape. Further
within a site has to be such as to take into details on emergency procedures will be found
account possible damage from flooding or in paras 247 to 263.
subsidence, and the possible damage they might
receive should neighbowing plant or factories 18 The unloading point should preferably be
suffer a catastrophe by fire or explosion. reasonably close to, but not less than 5m from,
Installations should be sited at a sufficient distance the storage installation. However, if there is a
(25m minimum) from public roads or main railway physical impact barrier between the tanker and
lines to reduce the risk of damage to the chlorine the storage installation, this distance can be
reduced. The unloading point should also be
installation in the event of an accident. Protective
sited at a safe distance from any plant or
barriers should be installed where necessary.
equipment which might give rise to fire or
12 In all cases, suitable fences, together with explosion.
adequate security supervision, should be
19 It may be desirable to install a remotely
provided to minirnise the possibility of
controlled valve on the discharge line to the
unauthorised access.
storage tanks.
13 Hazards arising from aircraft may normally be
20 The possible effect on the locality of the
regarded as minimal with probabilities below the escape of chlorine should be considered, taking
level of significance required for any special note of the prevailing wind direction, ventilation
consideration. However, attention may be intake, the location of control rooms and
necessary in exceptional circumstances, for presence of the general public.
example if the installation is at the end of an
airport runway or close to an airfield which is Potential incidents
used for training.
21 The following potential incidents which could
14 The installation is preferably located in the result in chlorine escape need to be considered.
open air; under some circumstances installation
in a building may, however, be appropriate. In (a) Damage to chlorine lines by the tanker while
formulating a decision on this matter, it is it is moving to or from the unloading point;
important that a full review be made, taking into allowance has to be made for adequate
account the factors listed in Appendix 2. clearance from the valve dome when it is
open.
(b) Movement of the tanker durkg the transfer
Unloading area operation, eg. the n o d upward movement
of the tank on its suspension, can cause
Design and location damage if there is inadequate flexibility in the
connection.
15 To rninimise the possibility of chlorine
escape during transfer of the liquid chlorine from (c) Damage to the liquid chlorine tanker, storage
the transport vehicles to the storage installation, tank or connecting pipework caused by
detailed attention to the siting, design and layout impact from other vehicles, by movement
of the unloading equipment and operating caused by inadequate braking or chocking or
procedure is essential. careless operation by the driver.
Safety advice for bulk chlorine installations
(d) Errors in operating procedures. (b) Control by suitable means of the volume and
speed of adjacent traffic.
(e) Equipment failure due to corrosion.
(f) Damage caused by fire or explosion. (c) The closure of warning barriers and/or the
placing of warning notices when the chlorine
Deliveries of liquid chlorine by road tanker tankers are in position.
22 It is strongly recommended that the following (d) Provision of an interlock (see para 25) system
means of minimising potential risks are adopted to prevent coupling or uncoupling of the
wherever -possible. liquid chlorine lines unless barriers or
warning notices are in position. It is
Provision of a separate unloading area for the recommended that the interlock system
sole use of chlorine tankers. This could be a extends to ensuring that appropriate points
lay-by with adequate side protection (such as on the rail sidings are locked and wheel
a motorway-type crash barrier) or a stops raised before transfer of liquid chlorine
cul-de-sac. can start.
Restriction by suitable means of the speed of
traffic on adjacent roads. (e) A system of work whereby one person is
responsible for the whole operation of
The placing of warning barriers, notices, unloading, and a second is within call during
moveable barriers or road cones, and the connection and disconnection. The second
closure of gates when the chlorine tankers man should b e in the area and available
are in position. throughout unloading.
provision of an interlock (see para 25) system
(f) Routing of chlorine pipelines in the area to
to prevent coupling of liquid chlorine lines to minimise the risk of damage from collision by
the tankers unless barriers are in position.
the tanker, other vehicles or mobile
A system of work whereby one person (the equipment.
driver) is present throughout the unloading,
and a second is present during connection Interlocks
and disconnection. The second man should
be in the vicinity and available throughout the 25 As indicated in paras 22 to 24, interlocks
unloading. A typical procedure is set out in have value in preventing approach by other
Appendix 4. tankers and may also be made part of a system
to prevent inadvertent movement of a tanker still
Routing of chlorine pipelines in the area to
minimise the risk of damage from collision by connected up. For example, interlocks can be
the tanker, other vehicles or mobile devised to ensure that the vehicle brakes are
equipment. fully applied before the unloading pipe is finally
connected up, or the pressure in the unloading
Where a separate unloading area cannot be pipe activates a flashing sign to remind the driver
provided and the unloading point is on a factory that he is connected (the latter system may be
through road, such roads should be closed to appropriate at a producer plant or a consumer
other vehicle traffic during the m s f e r of liquid plant with a large throughput). The manoeuvring
chlorine. necessary to locate a road tanker precisely in
relation to a solid pipe connector may make it
Deliveries of liquid chlorine by rail tanker more difficult to devise an interlock to the
24 It is strongly recommended that the following highest standard of security. In such cases, an
means of minimising potential risks are adopted. interlock to prevent access of other tankers is
strongly recommended, and special attention
(a) Closure of the sidings to other traffic during must b e paid to the system of work which
transfer of chlorine from tankers to storage, effectiveiy prevents accidental movement of the
by locking the points. tanker, and to driver training.
Major hazard control
Design considerations for the access structure at 31 For h-ansfer to storage, it is necessary to
the unloading point couple the liquid chlorine outlet line on the
26 Satisfactory access should be provided to the tanker to the inlet line to storage and also to
permanent pipework for discharge of the chlorine connect a supply of dry compressed air, nilrogen
tankers and to ensure that connections to the or chlorine vapour to the tanker.
tankers can be made with minimum risk. Where Design and maintenance
this involves w o r h g from a place above ground
level, a permanent structure should be provided, 32 Failure of the unloading connections can
designed so that, in case of emergency, escape is result from inadequate design, incorrect materials
possible with minimum risk. or construction, improper use or inadequate
inspection and maintenance. It is, therefore,
21 A substantial and non-flammable (e.g. steel) essential to ensure that the design standards are
structure should be provided and platforms adequate, that testing and inspection procedures
should be free of obstructions and have non-slip are regularly carried out and that the equipment
surfaces, adequate toe-boards and guard-rails. is satisfactorily maintained.
Alternative escape ways should be provided with
stairways of standard slope; vertical ladders or Types of connection
steep stairways should b e avoided. If vertical
ladders are unavoidable, ensure that safety 33 Three types of connection are available.
hoops, etc, do not impede access by people (a) Flexible couplings which give a solid
wearing breathing apparatus. The design of connection but with a degree of flexibility
moveable platforms giving access to the top of when coupled.
the tankers should be such as to minimise the
possibility of accidents due to collision with (b) Flexible hoses.
tankers. Interlock systems may be used for this (c) Articulated arms.
purpose.
Flexible couplings are normally used but flexible
28 It may be useful to provide protection against hoses or articulated arms may be used by
the weather on fixed gantries at unloading points, agreement with the chlorine supplier.
for example by windbreaks or overhead canopy.
Flexible couplings
29 Adequate storage space for emergency
equipment (e.g. gas masks, air sets, protective 34 Flexible couplings are normally constructed
clothing and spare equipment) should be from steel pipe. Flexibility is provided by
provided in a safe location to be readily available cranking of a free length of pipe (less usually by
in an emergency. a coil) to allow for vertical movement of the
tanker during discharge. Screwed connections
are used for the connections to the tanker;
Connections between the tanker screwed connections are commonly used at
either end of the flexible coupling.
and the fiied lines to the storage
35 Piping local to the tanker berth should not
installation be fixed for the first 5-lrn (15-20 ft) but it needs to
be supported. The system of support used
30 Operations of road loading and unloading are should ensure that the pipework is kept above
subject to the Dangerous Substances the headroom required by the tanker when it is
(Conveyance by Road in Road Tankers and Tank being put in position. The support should also
Containers) Regulations 1981. Connections for the allow the pipework the necessary vertical
transfer of liquid chlorine require very careful movement of 150mm (6 in). A minimum pipe
consideration, as they are the most likely source diameter of 20mm (Y4in) is recommended.
of problems which could lead to a release of
chlorine to the environment. Pipework should b e 36 The design criteria for flexible couplings
as simple as possible. constructed from pipework are similar to those
Safety advice for bulk chlorine installations
for fixed pipework (see paras 41 to 46). Where Refer to Appendix 4 for a typical procedure.
the connections are screwed connections, the (b) Maintenance
gasket should be a trapped joint ring.
(i) Engineering inspection to be carried out at
Flexible hoses least once per year, or per 1000 operations; a
record to be kept of these inspections.
37 Flexible hoses, the design of which should be
agreed with the chlorine supplier, require more (ii) Renewals to be carried out at regular
frequent testing than do the flexible couplings intervals, or as required as a consequence of
described in the previous section. The life of the engineering inspection.
flexible hoses is shorter than that of flexible steel (iii) Replacement flexible connections to be
pipes but positioning of tankers is easier. Flexible dried out, after testing, with dry air to dew
Monel braided hose connections are normally point - 40C.
constructed up to 50mrn (2 in) size for the liquid
chlorine discharge, and 25mm (1 in) size for the
compressed gas connection to the tanker. Pipework for liquid chlorine
38 The operating instructions covering
unloading should ensure that visual inspection Permanent pipework at the unloading point
and leak testing of the flexible hoses is carried 4 1 The permanent pipework at the unloading
out before the introduction of liquid chlorine. point consists of the following lines.
Articulated arms Pipework for pressurising the tanker with dry
air, nitrogen or chlorine.
39 Articulated arms, with swivelled joints, are
occasionally used on manufacturing installations Pipework for the transfer of liquid chlorine to
with high output which are outside the scope of storage.
the present guide. Pipework for compressed air supplies that
operate remotely controlled valves on the
Operating and maintenance procedures tanker if these are installed.
40 Operating procedures for unloading should Lines should be colour-coded and/or labelled;
specify requirements for inspection and testing of detailed design requirements for the pipelines
couplings before use; maintenance procedures and fittings are described below. The system for
should lay down requirements for engineering off-loading of liquid chlorine is described in paras
inspection and renewal. Details are summarised 134 to 156.
below:
Pipelines for liquid chlorine
(a) Operating
42 Routing of pipelines for liquid chlorine should
(i) Visual inspection, before use, with normally be above ground and should be such as
particular attention to threads. to maximise protection from mechanical damage,
(ii) Use of new gaskets (CAF) each time corrosion and fire. A minimum diameter of 20mm
connections are made to the tanker. The (Y4 in) is recommended to ensure adequate
discarded gaskets should be collected and mechanical strength and lines should be clearly
disposed of safely, bearing in mind that they labelled and painted yellow (e.g. to 08E51-BS 4800).
contain asbestos.
Design criteria for pipelines transferring liquid
(iii) Proving of connection tightness before chlorine to storage tanks or from storage to point
introduction of liquid chlorine. of use
(iv) Capping of pipes after use and protection 43 Pipework should be designed, fabricated,
of pipes to reduce the possibility of inspected and tested in accordance with a
accidental damage to threads and ingress of recognised Code, e g BS 3351 or ANSI B3 1.3 and
moisture. any additional requirements of this section.
Major hazard control
Design pressure Should be in accordance with Stress relief All fabricated items and butt welds
design codes but no less than 12 barg (174 psig), should be stress relieved before final inspection
corresponding to a design temperature of and testing.
+45OC. Any part of the system which may
operate at a higher temperature should be Inspection and pressure testing All butt welds
designed to withstand the corresponding vapour should be fully radiographed or ultrasonically
pressure. examined.
resistant to chlorine and able to cope with the Vertical globe valves
stresses to which they may b e subjected. The
60 This type of valve is preferably used for
valve body should preferably be fabricated of isolation of liquid chlorine stock tanks or for large
forged steel; cast iron is not acceptable. If the flows of chlorine, while the billetglobe valve is
valve design is such that liquid chlorine could particularly recommended for installation on the
trapped within the body when the valve is liquid chlorine outlet line from chlorine storage
closed, provision should be made to avoid tanks (see para 88). The gas seal around the valve
excess pressure which may develop with spindle in globe valves may be formed by a
temperature rise. packed gland (preferably using rings or chevrons
55 Owing to evaporation of liquid chlorine, of PTFE) or by a bellows seal. The bellows should
operating temperatures may fall to -35OC; the be backed up by a secondary seal. Globe valves
valves should be selected not to fail if this may, with advantage, be fitted with a back seating
occurs. Problems which are specific to cold or to arrangement which isolates the gland from line
liquid chlorine limit the application of certain pressure when the valve is fully open.
designs of valve.
Conical plug valves (PTFEsleeved)
56 The selection of the appropriate type of 6 1 Conical plug valves, PTFE sleeved, are
valve for each application should be reviewed satisfactory for isolation of liquid chlorine lines,
with the suppliers of the liquid chlorine who will particularly when quick isolation may be
be able to suggest manufacturers of valves required, but the primary valve on the storage
whose equipment has given satisfactory service tank is preferably a globe valve.
with liquid chlorine. This will reduce the
possibility of unsatisfactory valves being used 62 Conical plug valves for use with liquid
which will require replacement after a short chlorine require provision for the avoidance of
period and could be a potential source of hazard. problems arising from liquid chlorine trapped in
the bore when the valve is closed. If this makes
57 It is emphasised that, during maintenance the valves uni-directional, they need to be
operations, reliance on valves of whatever type marked with an indication of the required
for isolation is insufficient. The design of the direction of liquid flow to ensure correct
system should be such that complete isolation of installation. Gas-tightness is provided by a PTFE
the section concerned is possible. Suitable sleeve inserted into the body of the valve and by
methods for achieving this include the installation a supplementary seal along the length of the
of spool pieces in the lines which can be spindle between the valve body and head. Care
removed and substituted by blanks, or the should be taken to avoid the application of side
insertion of slip plates. thrust to the spindles of plug valves.
Types of valve Ball valves
58 Valves of the following types have been 63 This type of valve can be used for isolation
developed for use with liquid chlorine or dry in liquid chlorine lines and should incorporate
chlorine gas under pressure. the following.
(a) Vertical globe valves (a) spherical turning limited to a quarter-turn;
(b) Conical plug valves (b) straight-through flanging;
59 Valves have to be degreased before use and 64 Ball valves should be avoided when
should be completely dry. It is recommended operating conditions involve large and frequent
that after this treatment the valves should be temperature changes.
stored in individual gas-tight plastic bags ready 65 Ball valves for use with liquid chlorine should
for installation when required. make provision for the avoidance of problems
Major hazard control
arising from liquid chlorine trapped in the bore the tanks under all circumstances, including those
when the valve is closed. If this makes the valve in which bulky protective equipment (such as self-
uni-directional they need to be marked with an contained breathing apparatus) is being used.
indication of the required direction of liquid flow
to ensure correct installation. 72 All chlorine storage tanks should be installed
in a bund which is impervious to liquid chlorine.
Remotely controlled valves The bund should be capable of taking the
contents of the largest storage tank with adequate
66 The rate of closure of any actuated valve freeboard and a sump. If there is a subdivision to
should not be so rapid as to cause undue give' a separate section under each tank, each
pressure surges in the system. section should have a sloping floor leading to a
sump, which may serve more than one tank.
Sumps should not be connected to drain.
Storage vessels Provision should be included for removal of rain
water over the bund wall, not via drain or through
67 In this advice, storage of liquid chlorine valves in the bund.
under pressure only is considered. Storage of
liquid chlorine at low temperatures and low 73 As leaks of liquid chlorine are potentially
pressure is sometimes used on chlorine more dangerous than leaks of gaseous chlorine,
producing plants but is not appropriate for the system needs to be so designed that sources
consuming installations. of leakage of liquid are reduced to a minimum. A
major contribution to this will be the avoidance of
68 The capacity of a chlorine storage tank joints which are continuously exposed to liquid
should be significantly greater than the capacity chlorine (for example, bottom outlets should not
of a full load of liquid chlorine from a road or rail usually be fitted, see para 78); thus, any leakage
tanker. To minimise the danger of over-filling, an will be only as gas.
installation consisting of smaller tanics which
would require split loads is not recommended. 74 The severity of a leak is reduced by lowering
the pressure within the system and therefore it is
69 Installation of bulk storage facilities should be
important that facilities for transferring gaseous
considered only if the annual consumption of
chlorine to a consuming process or to a waste-
chlorine is sufficient to justify bulk supplies rather
chlorine absorption plant are available when
than purchase of liquid chlorine in drums.
chlorine is being transferred.
70 In considering the number of individual
storage tanks for a required total storage capacity, 75 Chlorine storage tanks should be erected
following points should be taken into account. above ground level. Installation in deep pits is not
recommended because it increases the difficulties
The minimum size of tank should be of treatment and dispersal of a chlorine escape
adequate to accommodate the maximum and of access for maintenance or repair.
foreseen unit delivery.
76 Layout for the area should be planned to
If continuity of supply is essential, at least two provide all facilities necessary for good
tanks will be required to allow time for housekeeping; ample storage space is needed for
necessary inspections and to facilitate maintenance and safety equipment, which has to
maintenance. This also provides greater be readily accessible in the event of an
flexibility of operation. emergency.
Increasing the number of storage tanks leads 77 Thermal insulation of the storage tanks is not
to an increase in the ancillary plant and normally required. However, if the vessel
equipment with a corresponding increase in operates at low temperature and lagging is
complexity of operation. required, the material should b e fire-resistant,
The distance between adjacent storage tanks chemically inert to liquid or gaseous chlorine and
should be adequate to provide good access to resistant to ingress of atmospheric moisture.
Safety advice for bulk chlorine installations
83 Whenever two valves are installed in series operated valve which is designed to give positive
for isolation, it is recommended that the system isolation and which is suitably positioned may also
of operation is planned so that each valve is used serve as one of the two isolation valves required
exclusively for a defined period during normal above.
operation. This ensures that both valves are kept
90 In addition, it is strongly recommended that
in operable condition at all times.
flow in the line to the consuming plant should be
84 An application of the principles in this limited to the maximum required by the process;
section is shown diagrammatically in Fig 3. Not this may be achieved by the incorporation in the
all installations will be to this pattern, and line of an excess flow valve or an orifice. The
variations (some of which are described in the object of this flow-restricting device is to reduce
text) may be appropriate. the size of a release ram a major failure to less
than the full-bore flow through the pipe. It is not
Liquid chlorine inlet necessarily set to control the flow to as little as
85 The liquid chlorine inlet should not normally the maximum process demand, where this
extend further into the tank than the maximum maximum would be so small as to lead to other
liquid level. The use of a dippipe on the inlet problems of maintenance, such as proneness of
h e could result in liquid chlorine flowing back if the orifice to blocking, etc. It is not
the filling line failed: this possibility is avoided by recommended that the excess flow valve or
use of a short inlet line at the top of the tank or, orifice be located within the tank in the dippipe
alternatively, by drilling holes in the top of the itself because of the problem of removing the
dippipe so that liquid will not siphon back. A full liquid chlorine from the tank in the event of the
dippipe may be provided as an inlet to a vessel ball sticking or blockage of the orifice. In some
for importation and exportation, but in such a case plants, the flow restrictor can be replaced by a
it should be fitted with the additional controls suitable flow or pressure sensor operating the
appropriate to a liquid chlorine outlet. remotely-operable shut off valves (see para 104).
Excess flow valves may be advisable for lines
86 The isolation valve on the chlorine inlet line, normally taking a flow of chlorine much less than
directly bolted to the flange on the storage tank, the flow which could pass through in fault
should preferably be a globe valve. conditions. They are not suitable for lines in
87 A back-up valve should be provided, which which the normal flow rate is high, and for which
may be remotely operated. Alternatively, both a other means of fault detection and flow isolation
remotely-operated valve and a back-up isolation should be used.
valve may be installed.
Vent and compressed d r y gas lines
Liquid chlorine outlet 91 Vent lines and compressed dry gas lines can
88 The removal of liquid chlorine rom the be connected to the storage tank either through
storage tank is by means of a dippipe, the separate inlets or through a combined single
arrangements for which should ensure that liquid inlet. In either case, the valve directly connected
chlorine cannot be released if the joint between to the storage tank should be backed up by a
the isolation valve and storage tank fails. This is second valve.
most satisfactorily achieved on new plant by use 92 To limit the liquid volume in the storage tank
of a billet-type globe valve, bolted to the flanged to that permitted by the filling ratio, an ullage
branch on the storage tank, the dippipe being pipe can be screwed into the bottom of the valve
screwed into the bottom of the valve. on the vent line. The length of this ullage pipe is
89 The main isolation valve should be backed up such that, if liquid chlorine rises above the
by an additional valve to enable isolation to be correct level, it will flow through the ullage pipe.
achieved if one valve fails to seat effectively. The ullage pipe should be checked when the
Depending on local piping arrangement, provision routine inspection of the storage installation is
of one or more remotely controlled valves is made. A low temperature or other alarm can be
recommended for emergency control. A remotely fitted on the vent line rom the storage tanks to
I f there is any risk
of liquor from thevent
orifice absorber being sucked
Dry air or back, this line should
include a preventive
dry N2 supply
system at
controlled pressure (para. 94)
(see para. 142)
Liquid CI, t o
I consuming plant
I I
give warning if liquid chlorine is entering the of a short ullage pipe on the vapour vent. If a
ullage pipe on the vent line. high contents alarm is ignored during fiUing of the
tank, the liquid reaches the bottom of the ullage
93 The procedure for tmnsfemng liquid chlorine pipe and evaporates in the vent-line above the
to the storage tanks should provide for the vent vent control valve, producing frosting of the pipe.
valve to be opened slightly at the end of
discharge to check that the tank has not been 100 Regular checking and inspection
over-filled (see typical procedure in Appendix 4). procedures need to be planned and appropriate
94 The prevention of suck-back of aqueous records need to be kept of the results.
liquor into the vent line requires similar 101 As an alternative to the measurement of the
precautions to those described for vaporisers (see quantity of liquid chlorine by weight,
paras 184 to 186). The prevention of back-diffusion measurement by liquid level in the tanks is also
of moisture is described in paras 205 to 207. acceptable. However, selection of suitable
equipment is difficult and should be discussed
Relief system with the chlorine supplier.
95 The special requirements for the isolation
102 The pressure in the chlorine storage tanks is
valves on the pressure relief system on the measured by gauges specially developed for use
storage tanks are covered in paras 111 to 115.
with liquid chlorine; these have silver or tantalum
diaphragms. The gauges need to be completely
degreased before use and subsequently tested
96 Control instrumentation on storage tanks and using only clean, dry, oil-free compressed air.
elsewhere in the installation should, wherever The pressure gauges may be fitted with switches
possible, be designed to fail safe. Electrical and to give an alarm if pressure exceeds, or falls
electronic equipment, unless specially protected below, a pre-set value. Alternatively, pressure
against corrosion, should not be placed in areas switches may be used to give an independent
where it could be affected by gas leaks. signal for the high and low pressure alarms.
91 The quantity of liquid chlorine in each 103 The air in a building housing chlorine
storage tank is preferably determined by storage tanks may be continuously monitored to
installing the tank on load cells or on a give warning of chlorine leakage, particularly for
weighbridge. The weight of liquid chlorine in plants which are normally unattended (see para
each tank should be indicated locally and may 251). Regular and efficient maintenance is
be repeated in the plant control room. Alarms essential to keep such monitoring equipment in
are required on the contents measuring device. effective operation especially in plants such as
A high-contents alarm in the control room (and certain water treatment plants which are routinely
on complex plants, possibly an extra-high unattended but monitored by telemetry. The
contents alarm) is required for safety reasons. detectors should be set at about the
recommended exposure limit of 1 ppm.
Note There is little safety value in the optional extra-high
alarm unless it is run independently of the system giving the 104 Where reference is made to flow or
highcontents alarm. pressure sensors 'operating' valves (para 90
98 A low contents alarm may be useful for above) the choice remains whether the operation
operational reasons and may have safety is automatic or via manual intervention. At the
implications if, for example, there could be extremes, operation should be automatic in an
process upsets on failure of chlorine supply or unmanned plant, and may b e indirect in a well-
passage of padding air into a downstream vessel. instrumented plant with a continuously manned
conixol room.
99 The independent contents indicators would
n o d y be instruments, but on a simple 105 Instrumentation associated with the
installation, with good manning and attendance at automatic pressure relief system is included in
the tanks, the extra high-level alarm may consist paras 108 and 116 to 122.
Safety advice for bulk chlorine installations
114 Procedures to b e followed in the event of with a pressure sensing device to give an alarm if
the failure of a bursting disc should b e clearly pressure builds up in the vessel. The alarm
defined and based on the principle that at no system needs to be capable of being tested
time should a vessel b e boxed up so that regularly to ensure that it is operable.
unacceptable pressure may b e developed. (See para 122).
Procedures may vary with plant design but they
should b e in written form and include safe 120 The compressed air or nitrogen connection
working practices for removing the vessel horn to the expansion vessel should be arranged to
normal service, stabilising the pressure, changing avoid the possibility of inadvertently pressurising
the bursting disc, venting the expanse tank, and the vessel. This may be achieved by physical
returning the vessel to normal use. disconnection, isolating blanking plates, or by
double block valves supported by safe systems of
System of maintenance work. If an expansion vessel serves more than
one storage vessel, arrangements should b e made
115 At any installation where a locked-open for prompt response to a pressure alarm signal
isolating valve precedes a bursting disc, a safe hom it.
system of work should be defined which will
ensure so far as is reasonably practicable that no 121 While the risk of the expansion vessel itself
unacceptable pressure from any source can being over-presswised with chlorine is minimal
occur in the vessel whilst the isolating valve is because of the precautions described above,
closed. Such safe systems will vary with plant procedural or mechanical means to ensure that
design but should: this cannot occur should b e agreed with the
chlorine supplier and the Health and Safety
be in a written form, unambiguous and Executive (Industrial Air Pollution Inspectorate and
readily available; Factory Inspectorate).
include a permit-to-work system;
Pressure alarms
b e included in plant personnel training
122 There should be a high-pressure alarm on
programmes;
every storage vessel, and an additional pressure
b e properly supervised with responsibilities indicator/alarm at each important safety location
clearly allocated; on the relief arrangement. This means that one
additional pressure alarm may suffice on an
b e regularly updated particularly when plant installation where each storage vessel has its own
design, operating procedures or management expansion vessel, and that alarm may be either in
systems are modified, and the relief line (if there is a single bursting disc) or
b e rigidly adhered to. on the expansion vessel. When one expansion
vessel serves several storage vessels, there should
Expansion vessels be an additional pressure alarm within each relief
116 The design requirements for the construction assembly and also one on the expansion vessel.
of the expansion vessel are similar to those for the
storage tanks; the capacity should be about 10%
of the largest storage vessel. Inspection and commissioning sf
!17 The expansion vessel should be capable of
chlorine tank installations
being vented manually to an absorption system. General
118 The storage installation needs to be emptied 123 Inspection, testing and commissioning is the
of liquid chlorine during inspection and chlorine consumer's responsibility and will be
maintenance of the expansion vessel unless organised and controlled by him. UK chlorine
provision has been made for alternative means of suppliers as a matter of policy give advice if
release of pressure. requested to do so and visit the plant before it is
119 The expansion vessel should be provided commissioned, since they deliver chlorine only if
Safety advice for bulk chlorine installations
they consider the installation to be satisfactory. chlorine duty should be made by a competent
The installer of the equipment also has inspecting authority within five years of
responsibilities under Section 6 of the Health and commissioning. Thereafter the frequency of
Safety at Work etc Act. further thorough examinations should b e
determined by the inspecting authority and noted
124 Initial inspection and testing should be on the thorough examination certificate. The
carried out in accordance with the design code interval should not normally exceed five years. A
(see para 18). The first thorough service competent person to carry out such examination
examination of a vessel specified for liquid should have the knowledge, experience and
Major hazard control
Pressure alarm
gauge
resources to search for, detect and assess 125 The scope of the thorough examination
particular defects associated with systems should be determined by the inspecting authority
containing chlorine. Resources should include who will include any non-destructive testing
access to appropriate non-destmctive testing and considered appropriate. The thorough
laboratory facilities, together with professional examination certificate should specify all
technical ability to relate inspection findings to inspection and testing techniques employed and
appraisal of vessel integrity, safe working contain specific details of any deterioration found
parameters and future use. in the vessel or vessel ancillaries.
Safety advice for bulk chlorine installations
Inspection procedure
Preparation for internal inspection
129 Prior to opening the storage vessel for
inspection, the vessel needs to be emptied of
liquid chlorine and purged to remove all traces of
chlorine. Procedures for this should be covered by
precise operating instructions and normally include:
(a) breaking of all pipework connections to the
vessel by removal of spools or by blanking 081;
-Bursting disc
Testing (See HSE Guidance Note GS 4 Safety in of back-diffusion of chlorine which could lead to
pressure testing) dangerous conditions in other airconsuming units,
132 On completion of re-assembly of the particularly instrumentation.
equipment and drymg out to the required level, 137 It is important to vent gas to an absorption
following procedure is employed; system (see paras 198-211) from a 'padded' tank
Pressure testing with dry compressed air or after the transfer operation is complete, in order
nitrogen at around 120 psig; to restore the pressure in the tank to about the
vapour pressure of chlorine at the temperature of
Introduction of a small quantity of chlorine to
the tank contents. If this is not done, the tank may
the storage vessel and pressurisation with
over-pressurise as it warms up, and cause the
compressed air or nitrogen to around 120 psig; relief system to operate.
Checkng of all joints for leakage using an
ammonia bottle. Compressed nitrogen
If there is no sign of leakage, the tank is left 138 Compressed nitrogen may be produced in a
under pressure for about 12 hours and the check liquid nitrogen evaporation unit.
is repeated.
Compressed air
133 All associated pipelines, which need to have
been dried out, are then gas tested before 139 The compressed air to be used needs to be
introducing liquid chlorine into the system. oil-free and have a dew point below -40C.
Normally, air should be compressed to around
150 psig using a truly oil-free compressor
(50 ft3/rnin bee air capacity); if an oil-lubricated
Unloading of liquid chlorine f?om compressor is used it should be fitted with an oil
tankers to storage filter which must be regularly maintained.
140 The compressed air is cooled to remove part
General
of the moisture content and finally dried, using a
134 Transfer of liquid chlorine from tankers to regenerative-type drying system, to a dew point
liquid chlorine storage may be effected either by below -40C. The dew point should preferably
use of dry compressed air or dry nitrogen or by be monitored continuously using a monitor
use of chlorine gas pressure. The methods provided with an alarm that gives waming if the
employing dry compressed air or nitrogen are dew point exceeds a pre-set figure. It is important
simpler and the use of chlorine gas pressure is to recharge or regenerate drymg agents
normally encountered only in special according to the advice of the suppliers of the
circumstances. equipment and o f a e chlorine.
Unloading using dry compressed air or dry 141 A guard tower, filled with anhydrous calcium
nitrogen chloride, may be installed after the regenerative
system as a further safeguard. For small
135 The recommended system for transfer of installations a drier using anhydrous calcium
liquid chlorine from chlorine tankers to the storage chloride only may be adequate. Proper checks on
vessels, by 'padding' with dry air or dry nitrogen, the condition of the drymg agent are essential.
is outlined in Fig 3. Detailed requirements, which
supplement information given in previous sections, Supply to the system
are reviewed below. However, for each installation 142 The compressed dry air or dry nitrogen
the system used must rninimise the risk of should be stored in a pressure receiver fitted with
excessive pressure and should be agreed between a relief valve set to operate at the chlorine storage
the supplier and customer. plant's safe w o r h g pressure or 150 psig,
136 A separate and independent d r y whichever is the less. From the receiver the gas
compressed air or nitrogen system should be should pass through a non-return valve, or
used for chlorine duty, to minimise the possibility pressure- actuated shut-off valve, followed by a
Safety advice for bulk chlorine installations
reducing valve to give a supply at the pressure operate satisfactorily on an intermittent basis.
required for unloading the tankers. This supply will Diaphragm compressors or dry carbon ring
also be suitable for other purposes on the chlorine reciprocating compressors are suitable for this
plant such as drying out or purging of pipelines duty provided that maintenance is cartied out on
and vessels provided precautions are taken to a regular basis.
prevent backflow of chlorine into the air system.
Pressure gauges should be installed upstream and 149 Diaphgm compressors for this purpose use
downstream of the pressure reducing valve so that stainless steel double diaphragms with inert fluid
checks can be made that the padding gas between them.
pressure is greater than the chlorine pressure. It is 150 Dry carbon ring compressors should
important to provide safeguards and alarms to preferably be purged with dry air after use, to
ensure that excessive gas pressures cannot be avoid problems resulting from residual chlorine
applied to the chlorine system. This may be in the compressor leaking from shaft glands.
particularly important if the padding gas is During operation of the compressor, the shaft
supplied from high pressure cylinders. glands should be pressurised with dry,
143 The liquid chlorine discharge line on the compressed, inert gas.
chlorine tanker should be connected to the 151 If cooling of the compressor body is
permanent pipework at the unloading point (see required, this should preferably be accomplished
paras 30 to 41). by air cooling. If jacket cooling is necessary, this
144 A pressure gauge, a vent line to the should be achieved by circulation through an
absorber and a connection for dry compressed external heat exchanger with provision to detect
gas should be installed close to the end of the leakage of chlorine into the heat exchange fluid.
permanent pipework at the unloading point, with Direct water cooling should be avoided.
the necessary isolation valves, as detailed in Fig 3.
152 The compressor needs to be fitted with a
145 The liquid chlorine line from the unloading by-pass so that the chlorine can be recycled until
point to the liquid chlorine storage vessels should its temperature is raised sufficiently to prevent
be reasonably short. If it is necessary to use a liquefaction in the delivery lines. The temperature
long liquid chlorine line to storage, the need to of the chlorine should be monitored using an
protect this line against over-pressure must be indicator which is fitted with an alarm set to
considered (see paras 47 to 53). sound if it exceeds 90C.
Unloading using chlorine gas pressure 153 A pressure relief system on the compressor
delivery line should also be provided to prevent
146 Liquid chlorine may be transferred from the
chlorine tankers to the storage vessels by padding the delivery pressure exceeding a pre-set figure.
with dry chlorine gas. The gas is normally taken Use of vaporised chlorine
from one of the stock tanks but this should
preferably not be the one into which the tanker is 154 As an alternative zo the use of a compressor,
being unloaded. The supply of dry chlorine gas at the pressurised chlorine vapour may be produced
the required pressure may be obtained by re- from a vaporiser as outlined below.
compressing chlorine vapour from a storage tank
or by vaporisation of liquid chlorine. 155 Liquid chlorine is transferred from the
chlorine storage tanks to a chlorine pumping tank.
147 A source of dry, compressed, oil-free air or The pumping tank need only be of relatively
nitrogen is still required, for drymg out and small capacity and should have a bottom run-off
purging the system (see above). which is connected to the suction of the chlorine
pump (see para 164). The liquid chlorine is then
Use of recompressed chlorine vapour pumped to a vaporiser operating at the required
148 Selection of the appropriate compressor for pressure from where it can be used to transfer
recompression of chlorine vapour requires careful liquid chlorine to the storage tanks by
consideration to ensure that the equipment can pressmising the chlorine road tankers.
Major hazard control
156 In case of an emergency resulting from may be stopped rapidly in the event of failure at
failure of the joint at the bottom of the pumping the chlorine consuming plant (see para 89). Long
tank, discharge of chlorine to the environment has liquid chlorine pipelines to consuming units may
to be minirnised. This can be done by installing need to be protected against over-pressure (see
an internal valve within the tank or alternatively by paras 47 to 53).
dumping the contents to an empty receiver.
161 The possibility of suck-back of aqueous
solutions from an absorption system, or of process
liquids, needs to be strictly rninimised. This
Transfer of chlorine to the requires detailed consideration at the design stage.
consuming units
Transfer of liquid chlorine 162 For many applications the vapour presure of
157 Transfer of liquid chlorine from the storage the liquid chlorine in the storage tank is adequate
tanks to the consumina- units mav be achieved bv to transfer the liquid chlorine to the consuming
unit although there may be problems in cold -
using the vapour pressure of the liquid weather with outdoor installations. When the
chlorine alone; liquid has been removed from the tank, it may
padding the chlorine storage tank with dry, also be acceptable for part of the remaining gas
compressed gas; to be used on process. However, a minimum
transfer of the liquid chlorine to a separate positive pressure should always be maintained in
tank from which it is pumped using a pump the storage vessels; this should be defined for
specially designed for use with liquid each system.
chlorine;
a submerged liquid chlorine pump installed Transfer of liquid chlorine by padding with dry
inside the liquid chlorine tank. co~pressedgas
Methods (a) and @) are normally the most 163 Transfer by padding the storage tanks with
satisfactory for customer installations. dry compressed gas is straightforward; the action
and precautions which will be required are
158 Under special circumstances and by similar to those detailed in paras 135-142.
agreement with the chlorine suppliers, liquid
chlorine from the tankers may be transferred Transfer of Liquid chlorine using a separate
direct to process or to a chlorine vaporiser; this is P-P~W
a special and unusual arrangement.
164 Completely enclosed pumps have been
Transfer of gaseous chlorine developed for transfer of liquid chlorine: these
are used when the chlorine is required at higher
159 Apart from venting, safety considerations do pressure (above say 100 psig) or when the use of
not permit the discharge of gaseous chlorine from dry inert compressed gas is not acceptable. The
tankers directly to process at customer premises. liquid chlorine is first transferred from storage to
Such a procedure could cause potential hazard by a separate pumping tank which usually consists
concentrating the small traces of explosive of a pressure vessel with a bottom connection.
nitrogen tcichloride present in the chlorine; there The liquid chlorine is withdrawn from the bottom
could in addition be a risk of suck-back of of the pumping tank to the suction of the pump.
moisture or other materials into the tanker under A remotely operated valve is preferably installed
abnormal circumstances, outside the control of the inside the tank or between the pumping tank
suppliers of the chlorine. and the pump for isolation in emergency. In
design of this system, care must be taken to
Precautions ensure that the nett positive suction head (NPSH)
160 Arrangements should be made so that the is adequate to meet the minimum requirements
flow of liquid chlorine from the storage vessel for the pump used.
Safety advice for bulk chlorine installations
Transfer of liquid chlorine using a submerged should not be used because of the risk of local
Pump overheating.
165 Submerged liquid chlorine pumps are also Heating with hot water
used for transfer of liquid chlorine from storage to
the consuming units. If this procedure is adopted, This is the most frequently used method; the
detailed discussion will be required with both the normal working temperature (60-70C)is well
chlorine supplier and the equipment supplier to below that at which any significant reaction of
check that the system is satisfactory. carbon steel occurs with dry chlorine.
Self-regulating vaporisers
171 In some types of vaporiser the Liquid 174 The quantity of chlorine in a chlorine
chlorine is fed in at the bottom and gas is drawn vaporiser system is relatively small compared with
off via a control valve at the top. When demand is that normally contained in the main chlorine
high, the liquid chlorine level rises in the storage tanks. Nevertheless, the system design
container, and a greater heat exchange surface should be such that failure of equipment can be
area is presented to the liquid. When demand is detected and rectified quickly and that any
low, the greater vapour pressure at the consequent release of chlorine to the environment
temperature of the heating medium drives the is rninimised.
liquid chlorine out of the vaporiser back into the
storage vessel and the evaporation rate falls. This Hazards
system is usually applicable to vaporisers with a 175 The potential hazards with chlorine
relatively small chlorine capacity, i.e. vertical tube vaporisers are related to the function of the
bundles, coil types and concenttic tube types. device i.e. to supply heat to a corrosive and toxic
liquefied gas under pressure. They include;
Constant level vaporisem
(a) the risk of pinhole leaks, which lead to rapid
172 Other types of vaporisers, usually found only corrosion and increased loss of chlorine;
in largecapacity plants, sacrifice certain
advantages of the self-regulating types noted (b) rapid corrosion, if any moisture is allowed into
above in order to achieve much larger the chlorine system;
vaporisation rates. These types require a separate (c) concentmtion of impurities in the chlorine,
instrumentation and control arrangement to such as explosive nitrogen ttichloride, as the
provide a constant level of liquid chlorine in the chlorine is evaporated;
kettle or shell with high and low level alarms. In
such types (where there can be parts of the liquid (d) reverse flow of reaction fluids, caused by a fall
chlorine pool which are not well-mixed), there is a in pressure in the vaporiser, or by excess
greater tendency to concentrate the less volatile pressure in the process, or by solution of
impurities than in a self-regulating vaporiser, and a chlorine gas in the fluid. The presence of the
separate purge and vaporiser circuit may be fluid (water, solvent or reagent) in the vaporiser
required to deal periodically with the residues. can cause corrosion or local violent reaction;
The design and operation of these larger-capacity (e) canyaver of liquid chlorine as bulk fluid or
vaporisers is a specialised topic, and requires droplets into the gas line or into the process
consultation between the user, the designer, and itself. This can (depending on the materials of
the chlorine supplier. construction and on the process) cause
damage or hazard;
General installation
(f) overheating a vaporiser, which can apply
173 The vaporiser should be installed in the excessive gas pressure to the system, since
storage area or in an adjacent space as close as the vapour pressure of chlorine rises very
possible to the chlorine storage tanks in order to steeply with temperature;
keep pipelines carrying liquid chlorine short.
Change over of liquid chlorine supply rom one (g) the expansion of liquid chlorine which when
storage tank to another can affect operating heated, applies great hydraulic forces if the
conditions in the vaporiser system and any such system is closed up and full of liquid.
Safety advice for bulk chlorine installations
176 These basic hazards are considered in more Accelerated corrosion and reaction (high
detail below, but grouped according to the temperature)
remedial measure provided. 181 If the temperature of the steel tubes
containing chlorine is too high, there is a risk of
Flooding and liquid canyover rapid chemical reaction between the chlorine
177 Flooding (filling) of the chlorine vaporiser and steel. The temperature should normally be
with liquid chlorine may result from operation of restricted to a maximum of 120C.A limit of
the equipment above its capacity, inadequate about 70Cis applicable if the vaporiser consists
heating, or fouling of the heat transfer surfaces. of galvanised steel in a water bath, in order to
An indicator of gas flow to process may be of avoid rapid corrosion of the water side of the
value to the operator for routine purposes, and heat exchange surface. If operation is required at
will also indicate excessive withdrawal rates. higher temperatures, vaporisers of nickel or
available nickel alloys (such as Monel 400 or
118 If the temperature of the heating medium Inconel) may be required. In such cases, the
falls too low in a self-regulating evaporator, it is downstream chlorine (gas) lines may also require
possible for the outgoing gas to be inadequately to be resistant at higher than usual temperatures.
superheated, or even for liquid chlorine to pass
182 Temperature control is usually achieved
through the vaporiser. The same may happen if
thermostatically. If the heating medium is steam,
the level of water in a water bath falls. In the
the temperature can be monitored by low
extreme, if chlorine is drawn off but no heat is
pressure and high pressure alarms on the steam
supplied to the vaporiser, it is possible for ice to
inlet. The pressure of steam should normally be
form on the heat exchanger surfaces and damage
limited to 15 psig (120Cequivalent) and the
them severely.
steam has to be saturated, not superheated.
179 The temperature of the heating medium is
usually controlled thermostatically. If flooding
High pressure
occurs it can result in potential hazard 183 High pressure is usually a serious safety
(depending on the process and plant materials) consideration. A high pressure alarm operated
due to carryover of liquid chlorine into the from the pressure gauge or by individual pressure
vapour lines. Adequate instrumentation and switch should be fitted. The high pressure alarm
alarms should always be provided to give has to be particularly carefully maintained and
immediate warning of this condition, unless a regularly tested. A common working temperature
thorough assessment of the plant and process for vaporisers is 70C.The vapour pressure of
has shown they are not necessary. Low chlorine at 70C is over 300 psi. It follows that
temperature alarms may be arranged to cut off
the liquid chlorine supply to the vaporiser or (in every effort should be made to enswe that
self-regulating types only) the gaseous chlorine the vaporiser is not isolated full of liquid
outlet may be closed, driving the liquid chlorine chlorine. Strict observance of written
back into the bulk storage. procedures for shutdown is vital;
every effort should be made to avoid
180 A knock out pot (or spray catcher) may be accidentally isolating the vaporiser on both
fitted to prevent droplets and spray from passing sides. Care should be taken to ensure that the
into gas pipelines where they might damage the closing arrangements for the emergency
material of the pipes. There is a safety advantage valves take this into account;
in the presence of a knock out pot if the process
would be unstable if supplied with some liquid the vaporiser shell and pipes should be
chlorine. In all cases where the possibility of designed for a safe working pressure which
liquid passing to process is unacceptable, it is operational controls ensure cannot be
strongly recommended on safety grounds that a exceeded.
low temperature detector alarm be fitted near the Chlorine vaporisers in the UK are usually not
knock out pot. provided with their own pressure relief, and
Major hazard control
consequently the procedures to ensure the from the storage vessel), so as to minimise the
conditions in (a) and @) are vital. release which could occur in the event of a
major plant failure. The feasibility of these
Reverse flow additional devices will depend on the detailed
184 A low pressure gas alarm can be fitted to design of the system.
the outlet gas line. This gives warning of loss of 189 The hazards of total isolation of the vaporiser
supply to the process, but the safety sigruficance are considerable (see above, para 183). If liquid
of low pressure is small, unless there is a risk of chlorine is locked in, the consequences will be
the process fluid (e.g. water from a chlorinator) most severe if the evaporator is filled (e.g. if the
s u c h g back into the valves, evaporator or valves close together in a condition of major gas
storage with the possible consequences of local line leak). If there is a gas space over the chlorine
reaction. The possibility of suck-back into the when the vaporiser is isolated and heated, the
vaporisers should so far as possible be eliminated. internal pressure will reach that of chlorine at the
This requirement should be given very careful heating medium temperature. Consideration should
consideration at the design stage. Water be given to ensuring that vaporiser, lines and
chlorinating package systems usually incorporate valves are designed to withstand such pressure, or
a set of valves in the control system to prevent incorporate arrangements to relieve it to a safe
suck-back or push-back. The arrangements vary, place. (Relief of the vaporiser is not found on non-
and care needs to be taken to ensure that the chemical consumer installations in the UK,but may
system provided does give protection in the event be found on certain high-throughput chemical
of, for example, a leak back at the ejector non- plants). Automatic valves should not be arranged to
retum valve. The system needs to be checked close together when an alarm is raised. One
and maintained frequently. approach is to arrange the gas control valve to
185 Similar precautions against suck-back and close on alarms related to improper w o r h g of the
push-back of liquors will be needed on chemical system (e.g. low gas pressure, downstream
plant. process alarms, low temperature) and the liquid
control valve at the bulk storage to close on alarms
186 Arrangements should be made for an alarm related to chlorine release (e.g. detectors local to
to operate if the gas pressure falls below a safe the vaporiser and storage, manual alarms). There is
level; if necessary, this could be used to initiate some safety advantage, if the plant is continually
purging of the system, using dry air or other manned, in providing for manual intervention in
suitable gas. the system rather than providing wholly automatic
operation of shut-down, but care should be taken
Routine and emergency isolation that this does not introduce sigruficant delays into
181 The vaporiser has to be capable of being the response to an alarm.
isolated for maintenance, etc; and also in 190 Isolation of the vaporiser is still conceivable,
emergencies such as a failure of the vaporiser but interlocks between the inlet and outlet valves
itself through leakage or a failure of the gas line to prevent isolation are not usually fitted because it
downstream. In addition to a manual valve on the is occasionally necessary to close both valves
liquid inlet and on the gas outlet, remotely during cleaning and overhaul. A safe system of
operable valves are recommended on both inlet work for maintenance and operation is thus a vital
and outlet. A pressure reducing or flow control part of the safety arrangements.
valve will usually be fitted on the outlet (see para
191) and it is sometimes possible for this valve to Pressure control valve
be the remotely-operable shut-off valve also. 191 All vaporiser designs incorporate an element
188 As a back-up safety device in the event that of superheating of the vapour, either in the
automatic valves fail to operate (or are not vaporiser itself or as a separate unit, so that the
activated) in an emergency, there is some chlorine gas emerging is not liable to reliquefy into
advantage in providing a flow restrictor or excess the control valves, where it could cause problems
flow valve in the liquid inlet (typically on the exit of irregular pressure in operation and local erosion.
Safety advice for bulk chlorine installations
These problems are avoided in the remaining run require replacing. If the anodes are found wholly
of the chlorine gas system by reducing the gas consumed at inspection, a thorough examination
pressure. A suitable automatic control system to of the vaporiser should be undertaken.
achieve this, e.g. a pressure control system, 196 Accumulation of solid deposits reduces the
should be provided. effectiveness of a vaporiser and can also enhance
corrosion. The vaporiser needs to be cleansed
Corrosion and dried again regularly. Close attention to the
192 Regular inspection has to be carried out in cleaning procedure will rninimise corrosion but
accordance with the requirements of the scheme typically, the chlorine evaporator cylinder in a
set by the engineering inspection body. The type lc system (see illustrations) should be
equipment should be thoroughly dried out renewed after five years. The old one may be
before recommissioning. Moisture left in the submitted to a competent inspection body for
system can lead to very rapid corrosion. The certification for further use if required.
procedure should be covered by a written 191 The water bath or condensate outlet should
Operating Procedure. be monitored for chlorine leaks by redox or
193 The frequency of inspection and maintenance conductivity measurements. This early warning of
of vaporisers will need to be greater than that of minor leaks is helpful in all cases, and is very
fixed storage tanks because of the higher strongly recommended if cathodic protection is
operating temperature, the conditions favouring not provided and maintained.
corrosion and the possible deposition of solids.
The consequence of a minor chlorine leak from
the chlorine side of a vaporiser heating bath could
be very serious since the mixture of chlorine and
Chlorine absorption system
moisture is extremely corrosive. The pressure of
198 Detailed consideration should be given to
the steam or hot water bath compared to the
ensuring that in all chlorine-using operations
chlorine supply should be designed so that it is
chlorine can, in an emergency, be vented to an
unlikely that water would actually enter the liquid
absorber without emission to the environment.
chlorine line to the vaporiser, but rapid corrosion
of the evaporator surfaces could occur, with a 199 Control of chlorine emissions from Scheduled
substantial release of chlorine. Corrosion of the Works should be the subject of consultations with
heat exchanger surfaces is not directly monitored. HM Industrial Air Pollution Inspectorate (or HM
Industrial Pollution Inspectorate for Scotland).
194 The inspection authority will specify
inspection frequencies for a particular installation. 200 In some installations, the nature of the
One manufacturer of water authority chlorine plant consuming process is such that absorption of the
recommends that the evaporator vessel itself chlorine is possible without a special absorption
should be visually examined internally and unit. However, in such circumstances operators
externally once a year or after 250 tomes chlorine need to ensure that during maintenance periods
has passed, whichever is the more frequent. This adequate absorption capacity is always kept
recommendation is a reasonable guide for small available to accommodate any chlorine emissions.
evaporators given reasonably light use. Coil-in- Examples of installations where a separate
bath evaporators are commonly given a rigorous absorption plant may not be essential include
inspection every two years, and the coils are cooling-water treatment plants and bleach liquor
discarded if seriously pitted. production plants.
195 The evaporator vessel or tubes are 201 For most bulk storage installations, however,
frequently protected against water corrosion by a separate chlorine absorption plant is required
cathodic protection. Typically the anodes should and it should always be maintained in a state of
be checked visually every 3-6 months. The readiness. The quantity of reagents available in
frequency should be established by experience of the absorption system needs to be adequate to
the rate at which the anodes are consumed and deal with any foreseeable emergency.
Ma.jor hazard control
206 Vent systems from relief systems, which are 213 Consideration should be given to the
likely to operate only infrequently, may be provision of a pressure indicator fitted with an
protected from backdiffusion of moisture by the alarm to show if there is excessive venting or a
use of protective membranes. In some cases it blockage in the absorption system.
may help to provide a controlled dry gas purge 214 A monitor to detect chlorine may be installed
through the vent lines. on the outlet from the absorber.
207 If there is any risk of moisture Disposal of effluent h m the chlorine absorption
contamination, the pipework has to be fabricated
of rubber-lined or plastic-lined carbon steel, or plant
plastic resistant to wet chlorine (e.g. PVC, Hetron 215 The disposal of the liquor from the chlorine
or Atlac 382), or glass. absorption plant requires careful consideration, as
the presence of hypochlorite may create problems.
208 If there is any possibility of liquid chlorine If the waste liquor is discharged without treatment,
carry-over, liquid gas separators should be the possibility of interaction with other effluents
installed on the lines to avoid excess pressure or should be investigated (for example, a mixture with
overloading of the absorption system; these acid effluent can lead to evolution of chlorine in
separators are fitted with a temperature alarm to the effluent mains, and with amrnoniacal effluent
indicate the presence of liquid chlorine in the can lead to formation of nitrogen hichloride).
separator. Furthermore, if it is possible for liquid
chlorine carry-over to take place, plastic pipework 216 Under some circumstances, it may be
should not be used. Pipework should be sized to necessary to treat the effluent to reduce hypo-
take into account the maximum possible flows chlorite content to an acceptable level; this may
under the most unfavourable conditions. be achieved by treatment with sodium sulphite.
Safety advice for bulk chlorine installations
since the use of foam and water may in certain toxicological properties of chlorine, as well as
circumstances aggravate the problem. If the spill is detailed descriptions of the process operations
indoors and contained, it wiU'rapidly cover itself required of the operators. Operators should be
with a cold vapour layer and a coating of slushy provided with personal protection, clothing, eye
chlorine hydrate. Application of foam would cause protection etc, as appropriate, and be trained in
renewed evolution of vapour because of the heat its use. On-the-job training should be carried out
supplied. Covering a stabilised spill with plastic under the guidance of an experienced operator
sheets may often be the best action. The Fire who is familiar with the process and management
Brigade may carry stocks of suitable foam, but the and supervisory staff should also be involved in
decision to use it should be taken in conjunction training. Emphasis must be given to safety
with the senior technical manager on site. precautions and methods of dealing with
emergencies.
Operator selection and training 233 The training programme should include
coverage of procedures for special operations
and operating instructions which arise only at infrequent intenmls; for
example plant shut-down, isolation and preparation
227 The main risk of chlorine escape to the
of equipment for maintenance and inspection and
environment arises from incorrect operation of
plant recommissioning. Training and practice with
the plant. Selection and training of process
breathing apparatus should also be carried out.
operators is thus extremely important for efficient
and safe operation. 234 Re-training should be carried out regularly at
defined intenmls.
228 Detailed operating instructions are required
for all process work and procedures involved in operating instnlctions
the unloading of liquid chlorine tankers,
operation of the storage installation and utilisation 235 Written operating instructions are required
of the chlorine. for all foreseeable routine and emergency
operations ranging from guide cards for simple
229 Procedures need to be defined in detail for operations to complete manuals.
plant commissioning and shut-down, for periodic
plant testing and inspections, and for emergency 236 The operating instruction should cover each
action to deal with chlorine spillages and gas process operation in detail and should be fonnally
escapes. issued by the manager responsible for the
operation of the plant section concerned. He is
Operator selection and training also responsible for authorising any subsequent
230 Careful selection of operators for bulk amendments.
chlorine handling installations is necessary. It is 237 Copies of the instructions, which should
essential that the personnel selected are of include a flowsheet and indicate valves to be
adequate physical fitness and they should pass a closed in an emergency, should be available in
medical examination before engagement. The the working area for operators and in the control
objectives of preemployment and routine centre for supervisors.
medical examination are discussed in Guidance
Notes MS 18 and 20. Operators need to b e 238 Supervisors should check regularly that
capable of effective communication and be operations are carried out precisely according to
the written instructions.
reliable under stress conditions. Previous
experience in the chemical or similar industry is
very desirable.
Maintenance
23 1 Operator training should comprise both off-
the-job and on-the-job training instruction. 239 Satisfactory maintenance of plant, equipment
232 Off-the-jobtraining should include basic and instrumentation is essential to minirnise
information on the physical, chemical and hazards.
Safety advice for bulk chlorine installations
240 Schedules need to be prepared defining the 246 Written schemes of examination and
required frequency for servicing, testing and maintenance, and arrangements for proper control
inspection; these schedules should be strictly of repairs and modifications, are provided for in
adhered to and be adequately recorded. the proposed Pressure Systems and Transportable
Gas Containers Regulations (Consultative
241 Detailed written instructions covering all
Document 1984). Any modifications or repairs
routine maintenance operations should be
which could affect the integrity of the system
available. These should be f o d y approved and would have to be defined and overseen by a
issued by the responsible maintenance engineer. competent person.
Supervisors should check regularly that work is
carried out according to these instructions.
242 Close liaison is necessary between the
Emergency procedures
maintenance engineer and the process manager,
to ensure that maintenance work is started only Note Further guidance is contained in CIMAH Regulations
after the equipment concerned has been 1984 and associated publications. The CIMAH
adequately prepared by process personnel and is Regulations make specific requirements for emergency
free from chlorine. procedures at some chloke sites.
(c) Adequate emergency equipment (compressed affected by the chlorine escape; they will need
air sets, supplies of suitable foam as agreed to be advised of the size and expected duration
with the emergency services, protective of the release together with the areas which
clothing, etc) should be available in the could be affected, to allow the police and the
centres (see paras 222-226); site main controller to agree whether the public
should remain indoors or be evacuated.
(d) Emergency First Aid facilities, including
equipment for administration of oxygen, need Emergency assembly areas
to be provided;
261 Emergency assembly areas should be
(e) A large scale map (1:25,000 or 1:10,000) of the designated for use in a chlorine emergency by
surrounding area should be available to assist personnel not involved in the emergency team.
in determining which parts of the factory and The assembly areas allow for counting of
the local neighbourhood are likely to be personnel and for controlled evacuation if the
affected; need should arise. Preferably the assembly area
(f) Wind direction indicators have to be visible should be at the periphery of the works site with
from or indicated in each control centre; good exit for evacuation. A building with upper
storeys at a location upwind of the chlorine
(g) Equipment and information are needed to release may offer sufficient protection while the
assess the likely extent of the gas cloud for release is brought under control. Evacuation of
various sizes of release and various weather personnel to the assembly areas should be
conditions. directed by a senior member of the emergency
258 The Emergency Plan has to specify in team who would take wind direction into
advance the individuals and deputies responsible account. There will be occasions when
for the action necessary to deal with the evacuating off-site is not the best action, for
emergency. example, when the release is sudden and of
limited duration.
Site emergency team
Attention to casualties
259 There should be a trained emergency team
with the following key personnel 262 Persons who have inhaled chlorine gas
should be kept at rest with the head and chest
(a) Site Incident Controller He is the senior raised. They have to be kept w m . It is essential
man on-site responsible for the initiation of that qualified medical attention is obtained
the emergency plan and the direction of on- quickly, as serious symptoms may develop up to
site operations; 48 hours later. All persons who have been
(b) Site Main Controller He is normally the affected by chlorine gas should be examined
Works Manager or deputy and has overall locally by a medically competent person or sent
responsibility for the operation of the to hospital by ambulance.
emergency plan. He will maintain close 263 First Aid attendants should be aware of the
liaison with the police and fire services and dangers arising from gassing by chlorine. The
will advise them on the risk; following basic rules should be observed
(c) Other key personnel These include: (a) if chlorine has affected the eyes, they should
(i) the team responsible for the control of the be irrigated immediately with plenty of clean
chlorine release; water (preferably tap water);
(ii) the team responsible for the search for (b) contaminated clothing should be removed and
casualties, for first aid and for the control affected skin washed with plenty of water;
of evacuation.
(c) artificial respiration should not be applied if the
260 The police will b e responsible for dealing patient is breathing. (Oxygen may however be
with members of the public who might b e administered by suitably qyaUied personnel).
Major hazard control
(a) a medium or major leak will result in a high Notification of Installations Handling Hazardous
local concenlration of gas and therefore Substances Regulations 1982.
emergency access has to be made to a Reporting of Injuries, Diseases and Dangerous
confined toxic atmosphere; Occurrences Regulations 1985.
(b) the point of leakage may be difficult to Control of Industrial Major Accident Hazards
idenQfy owing to lack of dispersion and mist Regulations (CIMAH Regulations) 1984.
formation;
(c) if the building is heated, there will be greater Proposed legislation (Publication of consultative
ground evaporation and flash from a liquid document)
leak; Control of Substances Hazardous to Health
(d) access for maintenance is likely to be more Regulations.
difficult. Pressure Systems and Transportable Gas
9 It follows that indoor installations require:
Containers Regulations (1984).
(Conveyance by Road in Road Tankers and Tank BS 3351: 1971 Piping Systems for Petroleum
Containers) Regulations 1981 Refineries and Petrochemical
Guidance Note GS 5 Entry into confined spaces Plants.
Guidance Note MS 18 Health surveillance by BS 1560: Steel Pipe Flanges and Flanged
routine procedures Fittings (Nominal Size '/a in to 24
Guidance Note MS 20 Preemployment health in) for the Petroleum Industry.
screening.
Booklet HS(G)25 F'utther guidance on emergency
BS 1560: Part 2: 1970 Metric Dimensions.
plans BS 4882: 1973 Bolting for Flanges and Pressure
Notes on Best Practicable Means, BPM 18, Containing Purposes
Chlorine works. BS 2815: 1973 Compressed Asbestos F%re
Jointing.
Chemical Industries Association
BS 2915: Bursting Discs and Bursting Disc
Codes of Practice for Chemicals with Major Assemblies.
Hazards - Chlorine. BS 1501: Steels for Fired and U n i i d
Major Hazards-Memorandum of Guidance on Pressure Vessels. Plates.
Extensions to Existing Chemical Plant Introducing
a Major Hazard. BS1501:Partl: 1980CarbonandCarbon
Inter-Company Collaboration for Chlorine Manganese Steels. Imperial Units.
Emergencies. BS 1501: Part 2: 1970 Alloy Steels. Imperial Units.
Safety Audits - A Guide for the Chemical Addendum No. 1 (1973) to BS 1501: Part 2: 1970.
Industry.
Is it Toxic? Addendum No. 2 (1975) to BS 1501: Part 2: 1970.
A Guide to Hazard and Operability Studies. BS 1501: Part 3: 1973 Corrosion and Heat
Recommended Procedures for Handling Major Resisting Steel. Imperial Units.
Emergencies. BS 1501-1: 1958 Steels for use in the
Chlorine Institute, Inc.
Chemical Petrochemical and
10 W40 Street, New York, NY 10018, USA. Allied Industries.
Chlorine Manual (4th Edition, 1969).
Chlorine - Its Manufacture, Properties and Uses
ACS Monograph Series J S Sconce (1962).
National Institute for Occupational Safety and Le Chlore, Institut National d e Recherche et d e
Health (NIOSH) Securite, Paris 1978.
US Department of Health, Education and Welfare
Public Health Service Bureau Intenrational Technique du Chlore,
Centre for Disease Control Avenue Louise 250, Bte 12, 1050 Brussels
NIOSH Belgium.
Cincinnati Reports covering recommendations by the
OHIO 45226 USA. Chloprine Storage and Transport Sub-Committee
Criteria for a Recommended Standard: Addresses of chlorine producers
Occupational Exposure to Chlorine Hays Chemicals Ltd, Murgatroyd Division,
Sandbach, Cheshire CW 11 9PZ, United Kingdom.
British Standards Specifications
Imperial Chemical Industries PLC, Mond Division,
BS 3947: 1976 Specification for Liquid Chlorine P 0 Box No 13, The Heath, Runcorn, Cheshire
BS 5355: 1976 Specification for Filling Ratios WA7 4QF, United Kingdom.
and Developed Pressures for Staveley Chemicals Ltd, Staveley Works,
Liqueiiable and Pennanent Chesterfield S43 2PB, United Kingdom.
Gases.
The Associated Octel Company Ltd, P 0 Box 17,
BS 5500: 1982 U d i W o n Welded Pressure Ellesmere Port, Wirral, Cheshire L65 4HF, United
Vessels. Kingdom.
Safety advice for bulk chlorine installations
Appendix 4 Procedures for Customer 7 Will ensure that any warning notices
discharging road tanks of chlorine are displayed and barriers are erected,
and will operate any safety interlocks
(see para 40). associated with the road vehicle berth.
NOTE This typical procedure assumes that the Customer 8 Where there are two or more tanks
storage tanks and associated items of the customer will determine which tank
equipment have a safe w o r h g pressure is to receive and check that the storage
of at least 175 psig. If this is not the case tank cannot be overfilled. The pressure
then the air system pressure, relief on the tank before commencing
devices etc will have to be altered to suit discharge should not normally be
and delivery systems arranged so as to be greater than 85 psig but in very hot
capable of w o r h g within the limits of all weather it may be higher.
the components. Customer 9 Will ensure before discharge that the
Action 1 Safety. The procedures are vent valve on the stock tank fiUing pipe
designed to rninimise potential leaks by is CLOSED.
ensuring that all newly made joints are Driver 10 Will (weaxing a gas mask) remove
tested by gas pressure with at most both caps from the road tank valves
only a small amount of liquid. During and the customers filling arms and test
these test operations a gas mask must for leaks. Using new CAF joint rings
be worn. Similarly a gas mask must be connect both air supply and liquid
worn during the disconnecting discharge arms to the appropriate
operation when there is a possibility of valves on the tanker.
the escape of a small quantity of Joint 11 Wearing a gas mask, apply
residual vapour. During the rest of the pressure to the discharge connection,
operations it should be kept readily preferably by briefly opening the valve
available. to the stock tank. An alternative, less
Customer 2 Will operate all valves on the bulk desirable, method is to open the tanker
storage irkahtion including the filling discharge valve momen&Zy.The driver
pipe. (wearing a gas mask) test joints on the
Driver 3 On arrival at the works will weigh discharge pipe using ammonia water. If
off on the site weighbridge and satisfactory, the driver can remove his
proceed to the discharge berth. gas mask and then request the plant
operator to open the valve on the stock
Driver 4 Will position the tanker at the filling line after the drop arm.The liquid
discharge berth and place the chocks valve on the tanker can be slowly
in position to prevent movement. opened to fill the delivery line: the
Driver 5 Will present his notes to a pressure observed will be the pressure
responsible official. on the road tanker.
In signing these notes the customer Joint 12 Start the air compressor and when
accepts the responsibility that there is the line pressure is 120 psig open to
suflicient space available in the storage the road tanker. When the road tanker
tank to receive the full load from the pressure (as indicated on the filling pipe
road tank and that the instalation is fit to the stock tank) is 25 psig above that
and ready for the discharge to proceed. of the stock tank request the plant
Driver 6 Will tell the plant operator the operator to open the valve to the
weight of chlorine in the tanker so that appropriate stock tank and commence
he can determine where the final discharge of the road tank.
reading will be on the weighing Joint 13 Observe the discharge of the road
machine dial or load cell indicator. tanker is proceeding satisfactorily by
Major hazard control
reference to the weighing machine dial Driver 20 Before leaving the storage plant
or load cell indicator. ask the designated responsible person
Joint 14 Observe the stock tank pressure as to sign the advice note and
the discharge is proceeding. Should consignment note after the words "all
this rise to 90 psi request the customer operations connected with the
to crack open the vent valve on the discharge of the road tank have been
tank to reduce the pressure. completed satisfactorily". Hand one
copy to the responsible person. On
Joint 15 Indication that the road tanker has leaving the works weigh again on the
been completely discharged is: site weighbridge.
(a) fluctuation of pressure gauge on
the liquid chlorine delivery line;
(b) equalisation of tanker and line
Appendix 5 Summary: Types of
pressuke readings. vaporiser (See paras 110 to 112)
Joint 16 Close the liquid valve and the air Chlorine vaporisers may be divided into four
valve on the road tanker. Shut down basic types:
the air compressor. Ask the plant
operator to close the storage tank 1 Vertical tube bundle
valve and vent valve on the stock tank 2 Coiled tube immersed in a heating bath
if this has been opened. Ask the 3 Concentric tube
operator to crack open the vent valve 4 Kettle-type evaporator
on the stock tank filling pipe. When Vertical tube bundle (Type 1)
the hoar-kost begins to disappear and
the pressure gauge indicates zero ask Advantages of this type of system are
the operator to close the valve at the (a) small overall size for relatively large heat
end of the liquid discharge pipe. Close transfer surfaces;
filling line vent valve. (b) easy maintenance;
Customer 17 Crack open the vent valve on the (c) for the mode of operation in which the
stock tank for about one minute in chlorine is in tubes, the liquid chlorine is
order to check that the level of liquid automatically displaced by over-pressure when
chlorine in the tank is below the the vapour supply to the consuming plant is
bottom of the vent dip pipe. This shut off.
operation also vents noncondensable
gases. Check that the pressure in the .Disadvantages of this type of system are
tank is reasonable for the temperature
of the chlorine. (a) for the mode of operation in which the
chlorine is in the tubes, there is a risk of
Driver 18 Wearing a gas mask, disconnect instability at high throughput owing to
the liquid discharge pipe fiom the variation of liquid levels and a possibility of
tanker, replace the sealing plug and corrosion in the region of the liquid surface;
swivel back to the staging. Tell the (b) for the mode of operation in which the
plant operator that the vent can be chlorine is in the shell, it is difficult to dry out
closed. The short connecting pipes the shell.
kom the liquid and air valves can be
disconnected, both valves sealed and Coiled tube immersed in a heating bath (Type 2)
the tanker dome securely fastened.
Advantages of this type of vaporiser are
Customer 19 Under no circumstances allow any
section of the pipeline to be left (a) it is simple to maintain and operate;
unvented with liquid chlorine trapped (b) the long coil generally ensures adequate
betwen closed valves. superheating;
Safety advice for bulk chlorine installations
(c) there are no problems with differential thermal Disadvantages of this type of system are
expansion; (a) potential instability of operation at high and low
(d) plug flow operation avoids concentration of throughput;
high boiling impurities; (b) limitation of unit capacity owing to relatively
(e) drying out of equipment before use is small heat transfer surface area;
relatively easy; (c) greater difficulty in obtaining adequate
superheating of the chlorine.
(0 liquid chlorine is automatically displaced when
the vapour supply to the consuming plant is Kettle-type evaporator (Type 4)
shut off. Advantages of this type of system are
Disadvantages of this type of vaporiser are (a) It can be designed for large throughput;
(a) low throughput; (b) allowance for thermal expansion can easily be
made;
(b) external corrosion of the tube can easily occur,
especially near the liquid surface; (c) operation is stable provided that either the
level of chlorine in the kettle is controlled or
(c) irregular internal erosion of the coil may occur; the pressure of chlorine fed to the vaporiser is
(d) internal inspection and cleaning of the coil is controlled.
difficult. Disadvantages of this type of system are
Concentric tube units (Type 3) (a) since the vessel contains a relatively large
amount of liquid chlorine, the occurrence of
Advantages of this type of system are leakage or the development of excess pressure
(a) simple construction with minimum welding in the vessel poses a greater potential hazard;
requirements; (b) a relief system with a large capacity is
(b) ease of maintenance and operation; required unless the vaporiser is designed for
high pressure;
(c) easy provision of adequate corrosion
allowance; (c) operation can result in concentration of
nitrogen trichloride; the purging process
(d) automatic displacement of liquid chlorine when required to reduce this hazard may be difficult
the vapour supply to the consuming plant is to cany out on consumer premises;
shut off; (d) drying of the equipment on the chlorine side
(e) plug-flow operation above a certain minimum is difficult;
flow avoids concentration of high boiling (e) dismantling of the tubes is difficult and
impurities. requires a large space.
M a j o r hazard control
Chlorine gas
0
Liquid chlorine
218
Safety advice for bulk chlorine installations
Chlorine gas
Hot water
I .-
~ u t l e t
Steam
Condensate
Liquid chlorine
Control
Heating medium
Heating coil
Heating medium
return
Type 4 Kettle type evaporator
Appendix 5 (c)
Storage of anhydrous
ammonia under pressure
in the United Kingdom
(Reproduced from Health and Safety Executive :
Storage of anhydrous ammonia under pressure
in the United Kingdom, Health and Safety series
booklet HS(G) 30 (London, HMSO, 1986).)
Storage of anhydrous ammonia
Contents
Foreword
General information
Scope
Security
Health hazards
Spherical vessels
Siting
Sphere design
Foundations
Bunding
Ancillary equipment
Insulation
Site safety facilities
Employee training and safety
Commissioning operation and decommissioning
Inspection and maintenance
Emergency plan
Cylindrical vessels
Introduction
Physical properties and health hazards
of ammonia
Siting
Vessel design
Foundations
Bunding
Ancillary equipment
Insulation
Site safety facilities
Employee training and safety
'Commissioning and decommissioning
Inspection and maintenance
Bibliography
References
Storage of anhydrous ammonia
Foreword
A code of practice for the storage of anhydrous ammonia under pressure in the United Kingdom was
issued by the Chemical Industries Association (CIA) in 1980. The code covered storage in spherical
and cylindrical vessels. Since that time there has been continuing development of the knowledge
within the industry, particularly with respect to the measures required to avoid stress corrosion
cracking in spherical vessels. It has therefore been decided to update Part 1 of the 1980 CIA code to
incorporate this improved knowledge. The opportunity has also been taken to update Part 2.
This guidance was prepared jointly by the HSE,the Ammonia Product Group of the Chemical
Industries Association and ICI PLC. It is based on development of the 1980 CIA code which it now
supersedes. It is not intended to constitute a design code.
Grateful acknowledgement is made to those who contributed.
of the ammonia adjusts itself to the diminished suitable for ammonia service may b e used for
pressure. Since this adiabatic flash evaporation fittings and ancillary or adjacent equipment. The
takes place almost instantaneously throughout the use of copper and alloy containing copper in any
bulk of the liquid most of the contents of a equipment in other plant located in the vicinity of
ruptured pressure vessel will enter the the ammonia storage installation should be
atmosphere either as a vapour or as a fine liquid carefully considered.
aerosol. For this reason the design of the primary
(d) Ammonia combines with mercury to form
container should b e of a standard which virtually explosive compounds, so instruments containing
eliminates the possibility of a major failure; this mercury must not b e used if ammonia can come
guidance has been written on that premise. The into contact with the mercury.
design of equipment for storing and handling
substances such as ammonia under pressure is (e) The flammable limits of ammonia are from 16
well understood and the chance of a major to 25% by volume in air with an ignition
escape is very remote. However, when ammonia temperature of 65 1"C.Ignition of such mixtures is
is in association with certain other materials the difficult, but if it occurs in a confined space an
possibility of stress corrosion cracking presents explosion may result. The risk of this happening
particular problems. is low, therefore ammonia installations are not
regarded as significant fire hazards.
6 As ammonia is a hazardous chemical in both
liquid and gaseous forms, even in small 8 Ammonia is extremely soluble in water and
quantities safety is a prime consideration in any some organic solvents, heat being liberated
storage installation. during solution. The main physical constants are
as follows:
7 Everyone concerned with the storage of Atmospheric boiling point - 33.35OC
ammonia should be familiar with the following:
Freezing point - 77.70C
(a) At ordinary temperatures and atmospheric Critical temperature 132.40C
pressure anhydrous ammonia is a gas, but it may Critical pressure 114.25 bar absolute
be stored in liquid form under pressure. the
Latent heat (1 atm, minus 33C) 1370.76 kJ/kg
pressure will depend on the storage temperature.
For example, at an ambient temperature of 20C Liquid density See Nomograph
the pressure will be approximately 7.5 bar Vapour pressure See Nomograph
gauge; at a typical semi-rehigerated storage Vapour density See Nomograph
temperature of 0Cthe pressure will b e
Flammable limits (% by volume in
approximately 3 bar gauge. It may also be stored
at atmospheric pressure in liquid form by
air>
Auto ignition temperature 651C
reducing the temperature to its atmospheric
boiling point of 33C. Health hazards
@) Ammonia gas is pungent and colourless, and
serves as its own warning agent. Normally it is 9 At low concentrations in air, ammonia vapour
lighter than air and in the open will disperse by initates the eyes, nose and throat. Inhalation of
virtue of its own buoyancy. Gas produced from high concentrations produces a sensation of
liquid may mix with air, however, to produce suffocation, quickly causes burning of the
heavier-than-air mixtures which will stay close to respiratory tract and may be fatal. Liquid
the ground. ammonia causes severe bums on contact with
the skin. Severe damage can b e caused by
(c) Ammonia will not readily attack carbon exposure to high gas concentrations or direct
steels, but reacts strongly with copper and alloys contact with the liquid. A summary of symptoms
containing copper. The reaction is accelerated if and exposure periods associated with specific
water is present, even in minute quantities. Only ammonia vapour concentrations is given in
those steel and non-ferrous alloys proved to be Table 1.
Major hazard control
10 Attention is drawn to the requirements of the roads, railways and airports, taking due account
Health and Safety at Work etc Act 1974 of the direction of the prevailing wind.
(HSW Act), and associated regulations particularly
with reference to paras 89 to 97 of this 13 The choice of site should take into account
guidance*. existing plans for future development in the area.
11 It is recommended that this guidance should 14 In many cases the siting of spheres will
apply to all new installations designed after 1 require planning permission, so local authorities
January 1987 and to all other installations as far as should consult The Health and Safety Executive
is reasonably practicable, although it is (HSE) about the safety aspects of the siting in
recognised that existing installations may hot relation to people in neighbouring land uses. The
meet all the recommendations. Any required HSE advice will take account of the details of the
modifications will depend on individual installation and the size of the neighbouring
circumstances and a responsible decision will be population. It is unlikely that HSE would advise
favourably for a proposal which places a sphere
needed on the nature and timing of the changes within a few hundred metres of land uses where
to be made to equipment or procedures. there are likely to be substantial concentrations
Consideration should be given to further of housing. It is therefore recommended that
developments which may have taken place since manufacturers consult the HSE at the earliest
the preparation of this guidance. opportunity.
Spherical vessels 15 The proximity of roads and railways carrying
fast traffic should be taken into account. Suitable
Siting crash barriers should be erected, where
12 Spheres should be sited as far away as necessary, to avoid the risk of damage in the
possible from residential areas, public buildings, event of vehicle collision. In any case, spheres
should not be less than 25 metres from busy site
*Health and Safety at Work Act, 1974. HMSO. roads or through railways.
Storage of anhydrous ammonia
16 It is not practicable to guard against the risk spheres which have previously not been used for
of crashing aircraft but it should be noted that ammonia. This procedure should take due
most major crashes occur during landing or take- recognition of the present state of knowledge
off. Spheres should therefore not be sited near and should ensure that any doubts concerning
airports. the stress relief of complete very large spheres
have been resolved.
17 Recognition should be given to the presence
of, or proposals for, plant or processes involving
flammable and explosive materials. The ammonia Materials of construction
sphere should be located so that radiation from a
fire, or debris from an explosion, involving such 23 To minimise the risk of stress corrosion
plant or processes, should not cause damage to cracking the welding consumables should
the sphere. overmatch the tensile properties of the plates by
the smallest practicable amount. Furthermore, the
18 The storage area should be located so that it tensile strength of the plates should not be
is possible for road vehicles to reach it from two allowed to exceed the maximum detailed in the
directions. plate specifications. The minimum specified yield
strength of the steel from which the vessel is
Sphere design
made should not exceed 350 N/mm2. The
Design code individual plates for use in the sphere
construction should be identified during the
19 The sphere should, as a minimum manufacture and testing and marked accordingly.
requirement, be designed, fabricajed, erected,
inspected and tested in accordance with at least 24 Hard stamping of the plate material should
the equivalent standard to BS 5500*, for a not be allowed.
Category 1 vessel, with due regard to
Appendix D of that standard, including 100% 25 Copper and copper-bearing alloys should not
magnetic particle inspection of all internal welds be used. (See para 7(c)).
and any additional requirements of this part of
this booklet.
Sphere supports
Design conditions
20 The sphere should be designed to sustain 26 Most existing spheres are supported on legs
stresses imposed when it is filled to the but other methods are possible including
maximum permitted level and a pressure circumferential ring supports or part of a
superimposed equal to the vapour pressure of spherical concrete dish or 'egg cup'. The
the ammonia at the maximum design temperature supports should be designed to withstand the
together with any additional pressures which may weight of the vessel when filled with water.
result from the presence of inert gases, and Hollow tubular supports should be completely
external loads etc generally as defined in sealed against water and air which would lead to
Appendix A of BS 5500". progressive internal corrosion. Particular care
should be taken to ensure that water is not
21 The minimum design temperature should be trapped in the supports during construction. The
the lowest temperature the sphere can achieve in height above ground chosen for the sphere will
service. Preferably this should b e taken as -33OC depend partly on the ease of access required to
but in no case should it be taken as warmer than the bottom fittings and partly on the type of
-10C. pump to be used for discharging the ammonia.
22 Full thermal stress relief should be applied to The sphere will need to be high enough to
all new spheres after construction and to existing provide adequate nett positive suction head
(NPSH) for satisfactory operation of the pump,
* BS 5500 Specificationsfor unfired fusion welded pressure although the height may b e reduced by putting
vessels. the pump in a pit.
Major hazard control
close on failure of operating power or any other should be provided on the top of the sphere, big
fault in the operating system. Alternatively, enough to give convenient access to all the top
external remote operated valves may be used mountings. This platform should be carried on
provided they are made of austenitic stainless brackets which are welded to the crown plate
steel and bolted directly to the outlet nozzle. before it is stress-relieved; attachments should
have full penetration welds.
39 If there is a single bottom outlet fitted with
an internal valve, consideration should be given 46 Access stairs should not be welded to the
to the provision of a manually operated means of sphere.
releasing a seized valve to restore normal
47 Access stairs A stairway should be provided
operation.
to give access to the top of the sphere and it is
Constructional requirements preferable that this is independent of the sphere.
Alternatively, the stairs may be fixed to the
40 Preparation and protection of plates Before sphere support legs, but no part of them should
being despatched to site, all materials should be be welded to the pressurecontaining shell.
appropriately prepared and protected against Where appropriate, allowance should be made
corrosion. for possible differential settlement between the
sphere and the stairs.
4 1 Welding procedures - procedure and welder
qualification These should be the subject of 48 The stairway should have intermediate
agreement between the purchaser and supplier landings every 16 treads and should be at least
but should, as a minimum, meet the requirements 750 mm wide, complete with handrails and
of BS 5500, Appendix E. toeboards.
42 Stress relief of plates with welded Sphere testing and examination
mountings The top and bottom crown plates
shall be stress-relieved after completion of all 49 The testing of the sphere should include
nozzle and attachment welds, before despatch to filling with water and testing in accordance with
site. Plates having leg connections or other Clause 5.8.3 of BS 5500. All spheres should be
support brackets and any other plate with a thoroughly inspected during construction in
welded connection, must be similarly stress- accordance with the fabrication code
relieved. In the case of leg connections the part requirements. In addition:
heat treated shall include, as a minimum, a
length of leg outside any lagging equal to its (a) 100% magnetic particle crack detection
examination should be carried out on all internal
diameter.
welds and at the location of removed toggle
43 Nozzle welding details All shell nozzle cleats, temporary attachments and scars before
welds should be full penetration welds to commissioning (see footnote to para 125 for
BS 5500. Figures E.2(3)a and b, (10)b and c, (1 l), preferred method). This will provide base data
(121, (201b, (W, (221, (23h (We, f and g, (25h b for subsequent examinations;
and c, should not be used. Welding neck (b) full visual inspection and magnetic particle
flanges, Figure E.2 (21)a,are preferred to the slip crack detection examination along at least 10% of
on types. each butt weld should be made on the external
44 Temporary attachments All temporary surface of the sphere.
attachments should be carefully removed after (c) ultrasonic testing: The wall thickness of the
use, ie not knocked-off, and scars made good shell and nozzles shall be measured ultrasonically
and ground smooth. Such scars should be tested and the nozzle-to-shell attachment welds flaw
by magnetic particle crack detection methods detected.
after grinding. This work should be done before
stress relieving. (d) if it is intended to use acoustic emission
testing at a later stage, a reference base should
45 Permanent attachments A central platform be taken during hydrotesting of new spheres.
Major hazard control
should be stress relieved*. Items in contact with 66 The liquid outlet line from the sphere to the
ammonia gas should be stress relieved if pump should slope uniformly, b e well insulated
required by the notes to Table 3 para 2. and kept as short as possible consistent with
sphere foundation movements, and movements
63 Compressors may be of the reciprocating or caused by thermal cycling, not causing excessive
rotary type, and both may b e lubricated or oil- stresses in the
freet. Oil lubricated compressors will result in
some contamination of the ammonia, and the 67 A bypass line should b e arranged to return
level which can be tolerated will influence the part of the pump's output to the sphere to cool
choice of compressor. the pump, should the delivery valve be closed
while the pump is still running. The orifice plate
Pumps or valve which controls the return flow should be
64 The most frequently used type is the as close to the sphere as possible and the return
centrifugal horizontal multi-stage pump fitted with line should discharge into the sphere vapour
a mechanical seal followed by a conventional space*.
gland with soft packing. 68 A device should be fitted to indicate loss of
65 A glandless canned motor pump is equally flow through the pump, due to vapour locking or
acceptable$ any other cause. This may be a differential
pressure or a low flow trip.
' Some steels, but not austenitics, are prone to stress corrosion 69 Materials of construction should be suitable
cracking in the presence of liquid ammonia contaminated with for subzero temperatures. (see para 80). Exposed
oxygen. As ammonia gas is drawn o f fthe sphere and re- copper or copper-bearing alloys should not be
liquefied, non-Condensibles (including oxygen) are inevitably used anywhere on the pump (see p a r - 7 ~ ) .
concentrated in the liquid in the pipework and vessels of the
refrigerated plant. Since thermal stress relief inhibits the
process of stress corrosion cracking, stress relief is applied to
Piping: Design
these items. 70 (a) Pipework should be designed in
t Rotary compressors normally use oil for sealing and cooling, accordance with BS 335 1t or ANSI B3 1.3$,
and not primarily for lubrication. and any additional requirements of this
section of this guidance.
$ Pumps will only work satisfactody, particularly when the
sphere liquid level is low, if adequate Net Positive Suction (b) Piping, valves and other fittings should
Head is available. The NPSH requirements of the pump be designed for the most arduous
selected should be ascertained at the design stage and the foreseeable combination of pressure and
sphere raised sufficiently above the ground to provide the
necessary head to enable the sphere to be completely
temperature conditions.
emptied. It should be noted that long suction lines effectively (c) Any increase in metal strength which
reduce NPSH. Inadequate insulation and/or poor means of
venting the suction lines leads to vapour formation and may occurs at temperatures below 0Cshould be
result in vapour locking of the pump. If, for some reason, ignored when determining design stress
insufficient head can be provided for a pump mounted at values.
ground level, additional effective head can be achieved by
either putting the pump in a pit or by using a vertical canned
pump in a borehole. In the latter case the pump must be * When an orifice is used to reduce flow, flashing will take
protected against possible damage from frost heave. place downskeam of the orifice. This will result in two-phase
(Frost Heaves and Storage Vessel Foundation. CEP Technical flow, which may cause vibrations in the pipework, leading to
Manual - Safety in ammonia plants and related facilities, subsequent fatigue failure. It is, therefore, preferable to place
Volume 12.) the orifice close the the sphere, thus ensuring that the liquid
The advantage of a glandless canned motor pump is that it is phase is maintained in the pipework.
a completely sealed unit and therefore never gives rise to
unpleasant working conditions due to minor gland leaks, t BS 3351: 1971 Piping systems for petroleum refeineries and
which frequently occur with conventionally glanded pumps. petro-chernical plants. British Standard Institution.
This type of pump, is therefore, particularly appropriate when
men are working continuously in the area, ie, road and rail $ ANSI B3 1.3 Code for pressure piping - Chemical plant a d
loading stations. petroleum refinery piping. American National Standard 1976.
Major hazard control
(d) Piping should be correctly aligned to accordance with the latest edition of the
avoid the imposition of stresses on bolting up design code.
but this is not intended to prevent the (n) All piping should be thermal stress
application of the correct initial preset relieved. (see footnote to para 62).
designed to reduce stresses due to thermal
contraction. The design code allowance for Piping: materials of construction
short-term variations from normal operating 71 (a) Materials used for pipelines and fittings
conditions should not be claimed. should be resistant to brittle b c t u r e at the
(e) The 'allowable stress range', defined in sub-zero temperatures encountered. (see
the design code and used for thermal para 80).
analysis, should be taken as half that (b) Valves should normally be flanged and
permitted by the code. made of carbon steel which has been
normalised as part of the manufacturing
(0 The number of joints should be kept to a process. If welded-in valves are used, they
minimum. Welded joints are preferred. should be made of impact-tested carbon
Flanged joints should only be used when steel.
connecting to flanged equipment (eg, valves,
pumps, etc). (c) No copper or copper alloys should be
used in valves or piping systems. (see para 7
(g) Spiral wound gaskets are recommended; (~1).
gaskets of compressed asbestos fibre (CAF)
(d) Welding electrodes should be selected
or aluminium may be used, but only with for low temperature duty. In order to
tongue and groove type joints. minimise the risk of stress corrosion cracking
(h) Liquid ammonia has a high thermal the welding, consumables should overmatch
coefficient of expansion and, therefore, some the tensile properties of the piping systems
means of safe venting should be provided on by the smallest practicable amount.
pipelines in which liquid can be trapped Piping: fabrication and erection
between valves, etc.
72 (a) In general, forged butt welding fittings
(jj Since liquid ammonia in a pipeline may should be used for bends, tees, reducers
be near or at its boiling point, the possibility and end caps.
and effect of two phase flow occurring
(b) Socket-weld fittings and connections
should be taken into account at the design
should be limited to 40 NS.
stage.
(c) Screwed fittings should be used only
Q Over-design resulting in an increase of when no alternative is available and limited
thickness should be avoided, because the to small bore proprietary connections, e g
risk of brittle facture increases with pressure gauges.
thickness. (d) If the line is to be 'pigged', long radius
(1) Welds should have complete root wrought bends are preferred.
penetration throughout the joint and be (e) Mitred elbows, lobster back bends and
subject to the fault limitations of BS 2633: set-in branches should not be used at sub-
1973". zero temperatures.
(m) Weld procedure and welder (f) Set-on branches should have full
qualification tests should include impact penetration welds.
testing of both weld and heat affected zone (g) Wrought bends and any fabricated
in their requirements and these should b e in fittings should be thermally stress relieved.
Q All butt welds should b e 100%
* BS 2633: 1923 Class 1 Arc welding of fem'tic steel pipework radiographed and all fillet welds crack
for canying fluids. British Standards Institution. detected.
Storage of anhydrous ammonia
81 Insulation at legs When a sphere is (g) Suitable crash barriers should be provided to
supported on legs, the legs should b e insulated protect vulnerable sections of pipeline and other
for a sufficient distance to reduce heat gain in equipment containing ammonia from vehicle
those areas. collisions etc. (see also para 15).
(a) The area of the sphere and its associated Q Key instrument readings on which plant
equipment should be clearly marked to indicate safety depends should be under constant
potential hazard and to warn against unauthorised surveillance, if necessary by remote reading. As
entry. Demarcation will vary from site to site; a minimum, these should include the pressure in
simple notices may suffice in some plant areas, the vapour space of the sphere and the level of
while fencing may be necessary at an isolated the liquid*.
location. (k) Personnel water drench facilities should be
provided so that any one who may be sprayed
(b) Where access is limited, by fencing for with liquid ammonia will have immediate access
example, two diagonally opposite gates should to an adequate water supply. These facilities
be provided so that in an emergency vehicles should preferably be located in at least two
can get in whatever the direction of the wind. positions and, if possible, close to points where
Emergency exits should b e provided at each connections and disconnections are frequent.
comer of the com~ound.For securitv reasons.
these exits should be designed to restrict (l) There should be an adequate supply of fire
unauthorised access. extinguishers of the COz or BCF vapour type at
strategic points in the area.
(c) Fire hydrants should be located around the
area, about 25 metres from the sphere itself, so (m) The following safety equipment should be
that access to a supply of water would always be readily available:
available irrespective of the wind direction. (i) Suitable respiratory protective equipment foi
Water curtains are effective in reducing the escape purposes for all personnel entering the
spread of an ammonia cloud. Care should be storage area.
taken when setting up such a curtain to ensure
that water does not come into contact with a
pool of liquid ammonia because this would cause
a large increase in the evolution of gaseous * Pressure Under normal operating conditions the pressure in
the sphere will automatically start and stop the refrigeration
ammonia. In addition water should be available compressors. If the start/stop mechanism fails to operate, the
throughout the site for dealing with small spills pressure in the sphere may become excessively high or low.
and leaks. The ultimate safeguards are the pressure relief valves, but,
before these valves operate, the attendant should be given
(d) The storage area should be well lit at night. sufficient warning of the malfunction to take corrective action.
hessure values should be transmitted to a recorder sited in a
(e) One or more wind socks should be provided manned control room and the recorder be fitted with low and
in a prominent position so that they can be easily high pressure audible alarms.
seen by personnel in the area.
Liquid level Readings of sphere liquid levels should be
(f) An emergency power supply or a flare stack
transmitted to a manned control room. Since levels change
should be provided where a power failure to the slowly, level indication only is required. In addition, the
refrigerating compressors (resulting in a sphere should be fitted with an independent high level device
discharge of ammonia from the relief valves) which will give an audible alarm in the control room, when it
could not be tolerated. is activated (see also para 34)
Storage of anhydrous ammonia
(ii) Two longer duration sets of breathing 94 Drench showers, eye-wash bottles and
apparatus for rescue purposes. protective equipment should be regularly
(i)bo~1 protective suits for rescue and inspected to ensure continued availability and
emergency purposes. good condition. Precautions should be taken to
prevent freezing.
(iv) Plastic or rubber gloves and boots.
(v) Goggles. 95 All employees or other personnel entering
(vi) First aid cabinets. the storage area should carry suitable respiratory
protection equipment at the ready.
(vii) A number of eye-wash bottles, situated at
several points in the area. 96 Smoking should be prohibited in the storage
area and notices to this effect should b e posted
Employee training and safety at several strategic points.
(d) The correct use of all types of protective 99 Although stress corrosion cracking may b e
equipment, fire extinguishers and breathing prevented by a well controlled thermal stress
apparatus. relief of the sphere before its first use with
ammonia, the maintenance of a low oxygen
Employee safety content is recommended both as an additional.
safeguard and to minimise the risk of stress
91 The management should regularly satisfy corrosion cracking elsewhere.
themselves that safe working practices are
100 Two methods of purging air frorn the
constantly adopted.
sphere are outlined, each of which is intended to
92 All employees should b e regularly involved reduce the average oxygen content of the gas in
in practice drills covering the action to be taken the sphere to less than 0.025% v/v prior to the
in the event of an emergency. introduction of liquid ammonia. This
concentration of oxygen in the gas in the sphere
93 There should be at least an annual refresher will ensure that the concentration of oxygen in
programme for employees in the correct use of the liquid ammonia during and after filling will
fire extinguishers, breathing apparatus and not exceed 2.5 ppm by weight which is
protective equipment. considered to b e the safe upper limit when
Major hazard control
the water content it about 100 ppm*. To combine possible purge procedures water and/or nitrogen
maximum oxygen removal with minimal ammonia displacement is preferred.
loss to atmosphere, the air should b e displaced
by water followed by nitrogen or by nitrogen (a) The water and nitrogen displacement
alone. method The sphere is filled with clean water as
101 All methods described for commissioning full as possible, provided the engineering and
and decommissioning involve venting gaseous civil design considerations permit this and
ammonia to atmosphere. If this procedure is provided the residual film of water and any
likely to give rise to environmental problems, the dissolved solids can be tolerated in the ammonia.
venting gas should b e absorbed in water by The water is then displaced with nitrogen gas
using a suitable scrubber, which will not permit which is introduced at the top of the sphere. This
water to be sucked back into the sphere, usually results in an oxygen level below 2%. If
especially during commissioning. this is not achieved, pressurising and
depressurising cycles can b e used to bring the
Commissioning oxygen content to an acceptable level. Checks
for leaks should b e made at this stage.
102 Precommissioning The following pre-
commissioning activities and checks should be A variant of this method is sometimes used
made that where air is likely to be trapped in branches and
(a) the sphere is clean and dry; manholes at the top. Water is filled to the top
and its level is then dropped by about 2 ft or so
@) all the refrigeration equipment is in working by displacing it with nitrogen gas. The gas in this
order; space is pressurised and depressurised until the
(c) the instrument system and alarms are oxygen content comes down to an acceptable
working; level. The remaining water is then displaced with
nitrogen gas. Any released nitrogen can be used
(d) the float gauges are free to move and are to purge ancillary equipment.
transmitting correctly;
(e) the relief valves are correctly installed and A positive pressure must be maintained at all
have been set to the required pressure; and times to prevent any ingress of air.
(f) manhole covers are fitted and all pipe (b) The nitrogen alone displacement method.*
connections have been made. The sphere is pressurised with nitrogen gas up
103 Leak testing and oxygen removal The to its working pressure and a check is made for
sphere is now ready for leak testing and for leaks. It is then slowly depressurised; it is good
purging to remove oxygen. Of the various practice to use the released nitrogen to purge
ancillary equipment. The nitrogen pressurising
and depressurising cycles are repeated until the
* To minirnise the possbhty of stress corrosion crackmg it is oxygen content of the gas is reduced to 2% or
desirable that all traces of oxygen are removed from the less.
system as quickly as possible after commissioning the sphere.
Although completely reliable data are not available on the
maximum levels of oxygen below which stress corrosion
104 Ammonia gas purge Once the oxygen
cracking will not occur, it is considered that the oxygen level concentration in the sphere is below 2% then
should not exceed 2.5 ppm by weight when the water content
is as low as 100 ppm. As a guide, every 1% oxygen left in the
sphere after nitrogen purgmg wdl result in about 1 ppm in the
liquid ammonia provided the subsequent ammonia purge is
* For very low pressure spheres the nitrogen method is not a
done carefully and as described in paras 104-107.The situation practicable means of purging. In such cases either the water
can be further improved by tillmg the sphere as quickly as and nitrogen displacement method outlined in para 103(a) or
possible after commissioning and paying particular attention the procedure used for atmospheric tanks is appropriate (See
to purging non-condensbles from the system. Thereafter Code of Practice for the Large Scale Storage of Fully
every effort should be made to ensure that the oxygen Refigerated Anhydrous Ammonia in the United Kingdom.
content is kept as low as possble. Chemical Industries Association, May 1985).
Storage of anhydrous ammonia
ammonia gas can b e admitted to complete the can clearly occur when it is being transferred
purge.* from manufacturer to user.
105 Ammonia gas is admitted at the top of the 110 The following guidelines should b e
sphere and the effluent gas taken from its base followed:
but piped to a high level. The gas is introduced
slowly initially, to achieve 'plug flow' condition in (a) Every effort should be made to keep the
the sphere. In this way a stable cloud of oxygen content of the ammonia as low as
ammonia vapour is established in the top few possible.
feet of the sphere with minimum mixing at the
ammonia/nitrogen interface. The ammonia gas (b) Serious consideration should b e given to
input rate can then be increased. Once the raising the water content of the ammonia to 0.2%
purge has started it should not be interrupted, W/W as the presence of water at or above this
otherwise undesirable mixing will take place. concentration appears to provide protection in
the liquid phase. When water is added, it should
106 After traces of ammonia are detected in the either be distilled water or plant condensate of
exit gas the concentration rises rapidly. The equivalent quality.
purging can b e stopped by shutting the exit
valve when an exit concentration of at least 90% (c) The oxygen content of the liquid ammonia
is achieved.? should b e checked at least once a month. With
carefully controlled operation the oxygen content
101 The ammonia can b e used to purge the should not exceed 2.5 ppm w/w. If a significantly
ancillary equipment. Gaseous ammonia is used to higher value is obtained additional measurements
build up pressure in the sphere before admitting will be necessary to determine whether it is due
liquid ammonia to avoid local chilling of the to the very real difficulty of excluding extraneous
sphere. oxygen from the analyser or to a departure from
Operation good operating practice which will need to be
identified and corrected. With careful exclusion
108 Although pure anhydrous ammonia is not in of extraneous oxygen from the sample and
itself thought to b e a medium liable to cause analyser, gas chromatography can be used to
stress corrosion cracking of carbon steel, determine these low levels of oxygen.
contamination of the ammonia with oxygen does
appear to promote stress corrosion cracking.
Decommissioning
109 A considerable degree of stress corrosion
cracking has been found in some ammonia 111 This section is concerned with safe
containers. High strength steels are more procedures for removing liquid and gaseous
susceptible to cracking than low strength steels ammonia from the storage sphere so that it can
and the impurity which promotes cracking has b e entered for examination.
been identified as oxygen. Ammonia as
produced contains no oxygen, but contamination 112 Remove as much liquid ammonia as
possible by using the normal product pumps.
There may b e some residual liquid left in the
sphere. Any remaining liquid will have to be
* A supply of gaseous ammonia is required to purge nitrogen removed by differential pressure transfer to an
bom the sphere during commissioning. The source of gas will adjacent vessel, or to a road or rail tanker. It is
depend on the installation. Provision should be made for
about 1 tonne of gas for each 1000 cubic metres of sphere important that all the liquid is drained from the
volume. sphere before the pressure is reduced to
atmospheric otherwise more vapour will b e
t High concentmtion of ammonia is necessary otherwise the evolved than necessary and, more important, the
compressors will overheat due to an excess of non- temperature in at least a part of the sphere will
condensable gases. A figure of not less that 90% ammonia is fall to minus 33C. Some spheres are not
desirable. designed for this temperature.
Major hazard control
123 The examination referred to in para 118 and Acoustic emission testing
122 should include the requirements in paras 124 129 Acoustic emission testing may be used to
to 139. assist in determining the integrity of the sphere.
Magnetic particle crack detection External
124 The examination should consist of visual 130 There should be a once-off assessment of
inspection and internal magnetic particle crack the external surface. In the case of an existing
detection of the welded seams in accordance uninsulated sphere the examination should
with British Standard 6072 as a minimum consist of full visual inspection and magnetic
requirement". Techniques and flux density particle crack detection examination along at
should be to the satisfaction of the competent least 10% of each butt weld. In the case of an
person. existing insulated sphere, ultrasonic flaw
detection testing from within the sphere of at
125 The induced magnetic field should be
least 10% of each external butt weld may be
applied by electro-magnetic coils (not open
used in place of the external examination. If any
circuit prods or probes) to produce a flux density
significant defect is found the extent of the
of sufficient strength to reveal the presence of
examination should be increased at the
significant cracks?.
competent person's discretion.
126 The extent of the magnetic particle crack 131 In addition, at each subsequent examination
detection examination should include 100% of all where significant internal defects are detected,
the internal welds and cleat areas. If significant ultrasonic testing should be used from within the
defects are found, the next inspection should be sphere to check the integrity of the external
within two years and should again include 100% surface opposite the internal defect prior to the
magnetic particle inspection of the welds and assessment called for in para 140.
cleat areas. Subject to no significant defects
being found, any subsequent inspection should 132 Shell nozzles whose wall thickness cannot
include at least: be measured ultrasonically from the nozzle bore
should be delagged locally and exposed for
(a) all the plate tee junctions in the lower half of examination.
the sphere.
133 The external support structure should be
(b) 25% of the bottom and second strake
circumferential seams, and inspected for deterioration of the protective
coating and resultant metal wastage. The
(c) the top crown plate, first and second strake attachment welds should be magnetic particle
tee welds plus 25% of the joining circumferential crack detected and breather holes (if any)
weld seams. checked.
Ultrasonic inspection 134 All lines from the sphere to their first
isolation should be inspected for support and
The wall t b d ~ ~ofs the
s shell and securement. The butt welds of these lines should
be measured and be delagged, 100% radiographed, and examined
flaw detection of shell to nozzle welds shall be for external co~osion.
applied (see para 49).
135 All in-line valves, such as isolation valves,
128 Where practicable this examination should excess flow and remote control valves should be
be made from the internal surface. removed and overhauled.
* BS 6072: Method for magnetic particle flow detection. British 136 All instrumentation and a l m s should be
Standards Institution. overhauled and re-calibrated.
t Care must be taken to use a technique that is sufficiently 137 Relief valves should be overhauled and
sensitive to reveal very fine cracks. The technique used
should have a sensitivity not less than that provided by the tested at least every two years and the
AC magnetic yoke. The use of nuorescent inks can improve interlocking isolation thoroughly checked as far
definition. as its construction permits.
Major hazard control
138 Extemal insulation should be examined for (f) maximum permitted weight of contents;
damage and breakdown of insulating properties.
The shell, where insulation is suspect, should be (g) date of next thorough examination.
exposed to facilitate inspection of the metal
surface prior to insulation repairs, particularly if
the sphere is situated in an aggressive Competent person
atmospheric environment.
141 A 'competent person' should have the
139 All closure and mounting studs or stud bolts knowledge, experience and resources to search
on the sphere should be renewed. All flange for, detect and assess particular defects
gaskets should be renewed. The flange gaskets associated with vessels containing ammonia, e g
and stud bolts should be renewed on the piping stress corrosion cracks. They should have access
between the sphere and first isolation. to appropriate NDT and laboratory facilities and
the professional technical ability to relate
Thorough examination report inspection findings to appraisals of vessel
integrity safe working parameters and future use.
140 Any significant deterioration found should
be recorded on the examination report with Routine inspection
particulars of the inspection techniques used.
The vessel should b e reassessed for continued
use with ammonia and the safe working limits 142 In addition to the periodic thorough
confirmed or revised. Any significant weld or examination the following discipline checks
material defects found should be critically should be carried out routinely.
examined with regard to effect on vessel (a) All automatic valves, a l m s and trip systems
integrity, origin and likelihood of recurrence. should be checked periodically to ensure their
Where defects are ground out or rewelded the satisfactory operation.
effect on safe working pressure should be
carefully analysed. Stress analysis should pay due (b) In the case of spheres surrounded by a wall
regard to residual and operational stresses with or bund, attention should be paid to surface
appropriate stress intensification factors where water drainage. The general good housekeeping
they apply. Where defects are left their in the area should include maintaining it free of
significance should be assessed by a h c t u r e debris and undergrowth.
mechanics analysis and be suitably monitored
when the vessel is returned to use. Where (c) Fire hydrants should b e regularly serviced
propagating defects are foreseeable a similar and maintained.
analysis should b e made in helping to determine
the date of the next examination. Where any (d) External insulation should be maintained in
metal has been removed or thinning has good order.
occurred, due consideration should be given to (e) Personnel safety equipment points should be
safe working pressure limits based on the checked daily and the items (eg, respirators,
remaining metal thichess. Certification should goggles, gloves, safety showers, etc) kept
be provided specifying: serviceable.
(a) maximum safe working pressure; (f) Instruction notices, sphere identity number
and valve nomenclature should be clearly
(b) minimum safe working pressure;
displayed and maintained legible by day and by
(c) maximum safe working temperature; night.
(d) minimum safe working temperature; (g) Site illumination should be regularly
maintained and serviced, (ie, kept clean and in
(e) maximum permissible ammonia fill; working order).
Storage of anhydrous ammonia
t A Guide to the Control of Industn'al Major Accident Hazards Guidelines for chemical sites on off-siteaspects of emergency
Regulations 1984, ISBN 01 1 883762. procedures Chemicals Industries Association 1985.
Major hazard control
* BS 474 1: 1971. Vertical cylindrical welded steel storage Site safety facilities
tanks for low temperature semce - single well tanks for
temperatures down to 50CBritish Standards Institution.
177 Reference should be made to para 88,
t BS 5500: Specifications for unified fusion welded pressure noting that the ~rovisionsof 88(f)and will not
vessels. British Standard Institution. apply.
Major hazard control
178 In addition it is considered that chemical and subsequent ones exceed twelve years.
absorption type respirators are adequate for
escape and lightweight protective suits are Internal
suitable for rescue and emergency purposes.
182 Following a full visual examination for any
Employee training and safety obvious signs of deterioration, a magnetic
particle examination should be carried out. The
See paras 89 to 97. extent of the first in-service examination should
include 100% of all the internal butt welds.
Commissioning and decommissioning
183 If significant defects are found, the next
119 The principles set out in paragraphs 98 to inspection should be within two years and should
117 should be taken as a general guide. With again include 100% magnetic particle inspection
these relatively small vessels it is common of the welds.
practice to purge air from the system directly
with ammonia gas. This is an acceptable practice 184 Subject to no significant defects being
because the risk of stress corrosion cracking has found, any subsequent inspection should include
been minimised by the selection of appropriate at least all the tee junctions and 10% of the total
steels and thermal stress-relief of the vessel. length of the butt welds selected at random (for
details of magnetic particle techniques see paras
180 Although it is still advisable to purge 124 to 126).
oxygen from the vessel as far as is practicable, a
185 A hydraulic test is not required under this
higher concentration of oxygen can be tolerated.
guidance but may be called for by the
Nevertheless it is considered desirable to
competent person. It will normally only be
continue the purge until a minimum
required if welding repairs have been found
concentration of 90% ammonia in air is measured
necessary (see para 119).
in the discharge.
186 The nozzle-to-shell attachment welds should
Inspection and maintenance be crack-detected by magnetic particle
inspection methods, and if defects are found, the
General inspection requirements imposed in para 126
181 The following only applies to fully stress- should apply.
relieved vessels. For any existing non-stress- 187 When corrosion is evident or suspected
relieved vessel being used for the storage of ultrasonic thickness measurements should be
ammonia under pressure the taken.
inspection/examination procedures given in
paras 118 to 142 to this guidance should apply. External examination
All vessels should be thoroughly inspected by a 188 If the internal examination exposes a
competent person during construction in significant defect there should be a one-off
accordance with the fabrication code assessment of the external surface. In the case of
requirement (see para 161) and again after not an existing uninsulated vessel the examination
more than three years senrice*. Subsequent should consist of full visual inspection and
periodic examination should take place at magnetic particle crack detection examination
intervals determined by the appropriate along at least 10/o of each butt weld and
inspection authority, depending on the results of opposite the defect. In the case of an existing
the first and each subsequent examination insulated vessel ultrasonic flaw detection testing
senrice examination. In no case should the from within the vessel of at least 10% of each
second examination interval exceed six years external butt weld and opposite defect may be
used in place of the external examination. If any
* The vessels covered by this part of the guidance are shop significant external defect is found the extent of
fabricated and thermally stress relieved, therefore the interval
between inspetions has been increased beyond the the examination should be increased at the
requirement for spheres. competent person's discretion.
Storage of anhydrous ammonia
'Safe handling of ammonia solutions' - H R Kruger BS 474 1: Vertical cylindrical welded steel storage
- Agricultural chemicals, November 1951, page 46 tanks for low temperature service - single wall
and following. tanks for temperatures down to minus 50C,
1971. British Standards Institution.
'Safe handling of compressed gases' -
Compressed Gas Association Inc, New York. CP 2004: Foundations, 1972. British Standard
Code of h c t i c e .
'Safety in the use and handling of ammonia' -
W L Nelson - Oil and Gas Journal, 16 September BS 3274: Tubular heat exchanges for general
1948, page 1053 and following. purposes, 1960. British Standards Institution.
'Safety recommendations for the construction of Frost Heaves and Storage Vessel Foundation.
tank cars for the transport of ammonia by road.' - CEP Technical Manual - Safety in ammonia plants
Association des Producteurs Europeens d'Azote and related facilities, Volume 12.
(APEA). BS 3351: Piping systems for petroleum refineries
'Storage and handling of anhydrous ammonia in and petrochemical plants, 1971. British Standards
tank car quantities' - L H Brandt, Chemical Institution.
Industries, August 1943. ANSI B31.3: American National Standard - Code
for pressure piping - Chemical plant and
General information petroleum refinerypiping, 1976.
'Anhydrous ammonia' - Chemical safety data BS 2633: Class 1 Arc Welding of Fem'tic Steel
sheet SE-8, revised - Manufacturing Chemists' Pipework for canylng fluids, 1973. British
Association Inc. Standards Institution.
'Anhydrous ammonia' - Pamphlet G 2 - BS 4434: Requirements for Refrigeration Safety
Compressed Gas Association Inc, New York. Part 1, 1969. British Standards Institution.
Corrosion, Volume 18, page 229 - Loginow and BS 4683: Electrical apparatus for explosive
Phelps, 1962. atmospheres, Part 3, 1972. British Standards
'Rules and recommendations relating to the Institution.
unloading of tank cars of ICC-1O5A and ICC-112A BS 5970 Code of Practice for thermal insulation
types containing anhydrous ammonia and the of pipework and equipment (in the temperature
leasing of tracks or railroad property adjacent range of -1 OOC to + 870C.
thereto for this purpose' - Bureau of Explosives
circular No 17-F, 5 January 1962, Bureau of Code of Practice for the Large Scale Storage of
Explosives, Association of American Railroads. Fully Refrigerated Anhydrous Ammonia in the
United Kingdom. Chemical Industries
Additional information Association, May 1975.
'Anydrous ammonia' - National Safety Council, Factories Act 1961, Section 30 and Chemical
Chicago, 1954. Works Regulations 1922, Regulation 7. See
Major hazard control
Redgrave's Health and Safety in Factories Control of Industrial Major Accident Hazards
Second Edition Butterworth Shaw & Sons 1982 for (CIMAH) Regulations 1984 SO 1984 No 1902
discussion of these requirements. HMSO.
Note ABCM Safety and Management: A guide HSE Booklet HS(R) - A Guide to the Control of
for the Chemical Industry, re-issued April Industtial Major Accident Hazard Regulations
1972 by the Chemical Indu&es 1984. HMSO.
Association. Chapter 7 interprets the
HSE Guidance Note on the Preparation of
Factories Act in detail and is helpful as a
Emergency Plans (to be published shortly).
supplementary reference work).
Recommended Procedures for Handling Major
Health and Safety Executive Guidance Note GS14
- Safety in Pressure Testing, HMSO. Emergencies, 2nd Edition, 1976 published by the
Chemical Industries Association.
BS 6072 - Method for magnetic particle flow
BS 6759: Part 3: 1984 Specification for Safety
detection. British Standards institution.
Valves for Process Fluids.
Appendix 6
Example of a safety
report
This is an example of a safety report which is
required for all major hazard works coming under
the EC " Seveso Directive ". It has been produced
for an existing plant in the Federal Republic of
Germany by the plant management, and is
reproduced by permission of Umweltbundesamt,
Fachgebiet " Aufklarung der ~ffentlichkeitin
Umweltfragen " , Bismarckplatz 1, 1000 Berlin
(West) 33.
This manual is intended for countries which
have well-developed major hazard control systems,
and others which are considering such a system for
the first time. A report of this complexity would
probably be more appropriate to the first category
of countries, but all countries which do not have a
reporting system should consider which elements
of a safety report would be appropriate to their own
needs and practices.
Safety report
pursuant to Article 7
of the Ordinance on
Major Hazard Control
of the Federal Republic
of Germany
(Storfallverordnung)for a
plant for the processing of
acrolein (Deka factory)
1. Description of the plant and the process 4.1.2.6. Fire and explosion protection
(Article 7 (1) 1) 4.1 3. Hazards from other operational units of the Deka
1.1. Description of the plant factory
1.1.1. Location 4.1.4. Environmentally incurred hazards
1.1.2. Protective zones 4.1.4.1. Adjacent plants
1.1.3. Accessibility 4.1.4.2. Traffic
1.2. Processes 4.1.4.3. Natural hazards
1.3 Reason for limiting the safety report to process No. 6 - 4.1.5. Sabotage
conversion with acrolein 4.2. Measures to limit accident ccnsequences
1.4. Construction design 4.2.1. Foundations and supporting structures
1.5. Description of the process 4.2.2. Protective measures and safety systems
1.5.1. Unloading and storage of acrolein 4.2.3. Emergency plans
1.5.2. Production 4.2.3.1. Emergencies initiated by events in the Deka
1.5.3. Energy supply factory
4.2.3.2. Emergencies initiated by events in neighbouring
2. Description of the safety-relatedsystems, the plants
hazards and the preconditions for the occurrence of
an accident (Article 7 (1) 2) 4.2.4. Responsibility
4.3. Supplementary measures
2.1. Safety-related systems
4.3.1. Monitoring, maintenance and repair activities
2 1.1. Acrolein unloading
4.3.2. Training of personnel, operating and safety
2.1.2. Acrolein storage instructions
2.1.3. Water separator B 71 and tank R 72 4.3.3. Documentation
2.1.4. Injection pump P 71 A/B
2.1.5. Flare for off-gas A 750 5. Accident consequences (Article 7 (1) 5)
2.1.6. Pipe-work and valves
2.2. Hazards and preconditions for an accident
3. Chemical identification of substances ; condition Figures
and quantity of substances in accordance with
Appendix I1 (Article 7 (1)3) 6.1. Plan of site and surrounding area
4. Description of fulfilment of the requirements 6.2. Site plan
imposed in Articles 3 to 6 (Article 7 (1)4) 6.3-
4.1. Measures for the prevention of accidents 6.7. Process diagrams
4.1.1. Special operational hazards 6.8. Basic diagram "Production of XXX using acrolein"
4.1.1.112. Acrolein unloading and storage 6.9. Equipment list with design data for process No. 6 :
Conversion with acrolein
4.1.1 3 Water separator B 71 and tank R 72
6.10. Acrolein unloading in front of building E405
4.1.1.4. Injection pump P 71 A/B
6.11. Plan of tank store, building G 404
4.1.1.5. Flare for off-gas A 750
6.12. Plan of building G 400, 4.5 m platform (extract from
4.1.1.6. Pipe-work, valves construction and component arrangement drawings)
4 1.2. General operational hazards 6 13. Acrolem unloading and storage, N,supply (flow chart)
4.1.2.1. Corrosion 6.14. Separator B 71 and liquid waste treatment R 72 (flow
4.1.2.2. Use of unsuitable material chart)
4.1.2.3. Sampling 6.15. Metering pumps P 71 A/B (flow chart)
4.1.2.4. Loss of energy 6.16. Flare (A 750) (flow chart)
4.1.2.5. Machine failure 6.17. Material and reaction data - acrolein
Example of a safety report
The Deka factory is an existing plant for the ignition temperatures >135" C (Ex T4) within its
production of organic intermediates. The individual protective zones according to TRbF 110 (see Ex-
processes for production of these intermediates are Notiz). 1
totally independent of one another and were also
introduced at different times in the Deka factory.
The Deka factory is one plant in accordance 1.1.3. Accessibility
with the Federal Law on Pollution Control The facilities of the Deka factory are accessible
(BImSchG). from several sides via passable roads (escape,
rescue, fire-fighting routes). The escape routes in
building G 400 meet the requirements of the
1. Description of the plant Regulations for the Prevention of Accidents. They
and the process are apparent from figure 6.12.
(Article 7 (1) 1)
1 NPA
H2 - Reactor
NH, --+
Propion-
aldehyde *
NPA = n-Propylamme
DNPA = Di-n-Propylamine
TNPA = Tri-n-Propylamme
TNPA
Figure 6.3. Conversion of aldehydes with ammonia
HIPA = Isopropylamine
DIPA = Di-i-Propylamine Less volatile substances
262
Example of a safety report
Butyrolakton
to tank store
Reactor
7-
L Butane diol-1.4
Figure 6.6.
Hydrogenation of unsaturates
t
Residue
Distillation
Acrolein
XXX
IC to tank
Reactor
263
Major hazard control
Example of a safety report
1.3. Reason for limiting the safety The design features of buildings G 400 and
report to process No. 6 - G 404 are apparent from the construction
conversion with acrolein drawings/component arrangement drawings.
The plant units in which processes 1-5 are Figure 6.12 is an extract from these drawings. The
employed are integrated in the Deka factory. safety of the buildings was verified within the
However, they are self-sufficient, independent plant scope of the licensing procedure.
units, which are not linked via the product chain. 1.5. Description of the process
Only process 6 uses a substance listed in The complete description of the process -
Appendix I1 of the Ordinance on Major Hazard conversion of acrolein to XXX with substance B - is
Control, namely acrolein (see basic diagram in given in the licence application dated 15 June 1979
figure 6.8). according to the Federal Law on Pollution Control of
the Federal Republic of Germany.
When discussing the hazards, the possible
hazards originating from plant units 1-5 are given 1.5.1. Unloading and storage of acrolein
special consideration (4.1.3). (figures 6.8-6.11)
1.4. Construction design Acrolein is delivered in railway tank-cars and
unloaded in front of E 405. N, pressure
Product-carrying equipment, pipe-work and
(approximately 1 bar overpressure) is used to empty
valves of the acrolein plant are manufactured from
the tank-cars into the acrolein tanks B 19, B 22 and
stainless steel (1.4541)and, in addition, in
B 23 in G 404.
compliance with the Project Media Code., The
design data and constructive details of the Special safety measures are taken for storage of
equipment are documented in the equipment list acrolein in tanks B 19, B 22 and B 23 because
(figure 6.9) and the technical data sheet^.^ acrolein tends towards exothermal polymerisation
Figure 6.9. Equipment list with design data (see figure 6.8.) for process No. 6:
Conversion with acrolein
Equipment Des~gndata
Intermediate tank
Pump
Separator
Metering pump
Tank with stirrer
Reactor
Column stripper
Distillation column
Collecting tank
Major hazard control
@ Emergency and
eye shower
- Hvdrant
a -
@ 4 rail dewatering
boxes 30 m in front
of and behind
filling point *
at higher temperatures and in the presence of pressurised column stripper K 710, in which highly
substances which cause an alkaline reaction (see volatile substances (primarily non-converted
figure 6.13). feedstock) are distilled off and transferred to R 72.
Each tank is vented with nitrogen (highly The water in R 72 contains approximately 1 per
purified) to keep substances causing an cent acrolein. This is decomposed in an exothermal
alkaline reaction away from acrolein. reaction by the continuous addition of caustic soda
Each tank can be sprinkled with water for to form higher molecular products. The water
cooling purposes. discharged into the liquid waste network for liquid
The acrolein is continuously circulated by waste requiring treatment is free of acrolein ; it
pumps. Methanol containing approximately 5 contains organic materials, which can be
per cent hydroquinone is automatically added biologically decomposed and contain neither metals
into this acrolein loop from tank B 19A using a nor halogens.
nitrogen overpressure of 2 bar if the
The XXX, from which most of the highly
temperature in one of the tanks exceeds 30" C.
volatile fractions have been removed in column
Temperature and tank level are measured and K 710, is transported to tank B 18 in the tank store
recorded. Both measured values are linked to G 404, where it is temporarily stored. The XXX is
an optical and acoustic alarm. then transferred from this store to column K 720 for
Each tank is equipped with two rupture discs further purification.
installed in series in a nozzle (set to 1.1and 1.9
In K 720, XXX is distilled at the top of the
bar overpressure). In the event of a pressure
column and is then collected as XXX (pure) in tanks
increase in the tank, e.g. as a result of
B 33 and B 57 of tank store G 404. The sump from
polymerisation of the acrolein, bursting of the
K 720 is collected in B 725 and discharged to the
first rupture disc automatically initiates the
residue incineration plant. The sump, which
water sprinkling system of scrubber K 709
contains neither metals nor halogens, can be
which is filled with Raschig rings. On bursting
incinerated without any problems.
of the second rupture disc, the acrolein vapour
produced in the tank is transferred to this The synthesis section of the plant is operated
scrubber and reacted there. The scrubber, and and monitored from the main control room of the
all other plant equipment from which acrolein Deka factory. Systems for further processing are
vapour can escape, are connected to a header operated locally.
leading to flare A 750.
All off-gas displaced from acrolein tanks B 19,
1.5.2. Production (figures 6.8, 6.9 and 6.12) B 22, B 23 and the production plant is burned in
The reaction component B is supplied via pipe- flare A 750 (figures 6.8 and 6.16).
work and input into the mixing tank B 71 via
intermediate tank B 70 and pump P 70. Acrolein is 1.5.3. Energy supply
also transferred from the tank store G 404 via pipe- For its energy supply, the Deka factory is
work. In the mixing tank B 71 (overpressure connected to the respective BASF network for
approximately 4 bar, ambient temperature), a small electricity, cooling water, steam, nitrogen,
quantity of the water present in the acrolein compressed air and natural gas. Emergency energy
separates out and is transferred to tank R 72. supplies are not required (see 4.1.2.4and 4.1.2.5).
The premixed feedstocks are transported via
Highly purified nitrogen : in order to assure the
the metering pump P 71 into the reactor C 70,
necessary purity, a separate nitrogen supply system
which is operated at temperatures of 100-200" C
which is independent of the nitrogen network is
and a pressure of 20-70 bar.
installed to provide nitrogen for operating systems
In the reactor C 70, acrolein reacts with containing acrolein (see figure 6.13). It consists of a
component B to form XXX. The reaction product is nitrogen cold evaporator and an emergency supply
transferred through a control valve to the non- from a battery of nitrogen steel cylinders.
8-019 8-022 P-021 A 1 8
[I-
E
+
C
Y
To P71 (AIB)
sheet 2
culvert
R72 . .
tank Intermediate Mixing Metering piston pump --I..-
tank tank BASF Akllengerellrchalt
Pm 72 A(B) '-"
,..O-F.".'C
Rm 72 Electric motor
Electric .-- . . , "*.
-..
motor
Rr 72
Propellor Stirrer
Figure 6.14. Separator B71 and liquid waste treatment R72 (flow chart)
Example of a safety report
The safety lighting for control room and escape PC 76-08 alb : 2 bar, protected by safety valve
routes is assured by lamps equipped with Y 762 alb. In addition, the operation is carried
individual batteries. out in compliance with the operating and
safety instructions.
2. Description of the safety- 2.1.2. Acrolein storage 3 x 20 t, building
related systems, the hazards G 404 (figure 6.13)
and the preconditions for the - Storage tanks B 19, B 22, B 23 with level,
occurrence of an accident pressure and temperature safety devices and
(Article 7 (1) 2) circuits :
LIA+S+ 76 - 10, 20, 30; LA+S+ 76-11, 21, 31;
2.1. Safety-related systems PICA+S+ 76 - 10, 20, 30; PIA+S+ 76-11, 21, 31;
The safety-related systems are established TIA+S+ 76 - 10111112, -20121122, -30131132 (in
through systematic consideration of the flow charts each case 2 out of 3).
of the overall plant. First of all, the overall plant is - Centrifugal pumps P 23 A/B for the transport
divided into technical units (systems) which either and circulation of acrolein (see 1.5.1(3)) with
(i) can be operated independently, or (ii) are of double rotating mechanical seal and sealing
great importance for the overall plant, or (iii) are liquid (methanol) at an N, overpressure of 9 bar.
necessary as auxiliary systems for plant operation - Protective and safety equipment:
(e.g. cooling system, off-gas system).
- hydroquinone tank B 19A (see 1.5.1(3)):
A system is safety related if this is at an N, overpressure of 2 bar and is
- substances listed in Appendix I1 are present or protected by safety valve Y 763 which is set
can form in quantities of significance for at 4 bar ; further alarms and switching by
safety ; PIA- 76-00 and LIA-S-76-00 respectively ;
-
the system is required for safe operation of the - scrubber K 709 (see 1.5.1(5)):
plant because it prevents accidents or limits liquid waste is collected in tank tub ;
consequences (protective systems and other - water sprinkling system for storage tanks
systems required for operating safety). (see 1.5.1(2));
The following safety-related systems are - collecting tank (tank tub) :
established on the basis of these considerations dimensioned in compliance with TRbF 110
(figures 6.8, 6.10-6.12; flow charts, figures 6.13- (can hold contents of largest tank) ; collected
6.16). liquid can only be pumped into the liquid
waste requiring treatment if the sump pump
2.1.1. Acrolein unloading in front of is started up ;
building E 405 (figures 6.10 and 6.13)
- - gas warning system at pumps P 23 A/B :
Railway tank-cars containing 20 t of acrolein,
normal tank-cars with riser pipe without floor - Sieger remote gas sensor at each pump,
drain, design in compliance with GGVE alarm threshold in ppm range.
(Ordinance on Rail Transportation of Hazardous Further inspection and safety measures are
Materials), Appendix XI (4 bar), unloading specified in the operating and safety instructions
equipment with hose connection, manual
valves, pipeline via pipe bridge to tank store, 2.1.3. Water separator B 71 and tank R 72
building G 404. with stirrer (liquid waste treatment)
- Unloading and transport of acrolein using (figure 6.14) description in 1.5.2
nitrogen at 1 bar overpressure (highly purified - B 71 is operated at an N2overpressure of 4 bar
N2from cold gasifier or compressed nitrogen (PIRC 70-01) and is protected by two safety
cylinder battery), controlled by PIC 76-01. valves set at 6 bar overpressure. The off-gas
Maximum overpressure from reducing station from the pressure control system and the safety
Major hazard control
valves is transferred to flare A 750 via a liquid 2.1.6. Pipe-work and valves
separator.
Materials and construction of piping, seals and
-
R 72 is operated unpressurised. In addition, the valves in compliance with Project Media Code.2
operating and safety instructions are observed.
The pipe from the acrolein unloading station
2.1.4. Injection pump P 71 Am, which from E 405 to G 404 is continuously welded and
feeds against overpressure in reactor C 70 insulated. Flanges are sealed with special seals,
(figure 6.15),see 1.5.2 type Spiroflex. All pipes carrying acrolein are
Check valves in the line to the reactor C 70 ; designed for a nominal pressure of at least 10 bar.
safety valves as overflow valves Y 3 A/B, response
overpressure 80 bar. The reactor C 70 and the downstream columns
are non-safety-related (see figure 6.8).
2.1.5. Flare for off-gas A 750 (figure 6.16)
Off-gas collection system ; safety system TIA- 75- The reactor C 70 and the downstream columns
00. contain a maximum total of 25 kg of acrolein with a
concentration of <1 per cent by volume
In addition, the flare is operated and regularly (established by means of analyses). The reaction in
inspected in compliance with the operating and the reactor C 70 is exothermal. The contents of the
safety instructions. reactor exhibit practically ideal mixing : the acrolein
concentration is therefore the same at all points of polymerisation of acrolein in the acrolein
the reactor. The reaction is controlled in such a way storage tanks because of impurities in the
that it takes place very quickly. For this reason, the acrolein or filling of the acrolein storage tanks
acrolein concentration is less than 1 per cent by with other products ;
volume. Although the reaction in C 70 is leakage from the centrifugal pumps P 23 A/B ;
exothermal, there are no conceivable events at
which temperatures and pressures could occur damage to/leakage from B 71 because of failure
which would be unacceptable from a safety-related of the pressure control system ;
viewpoint. exothermal reaction in R 72 because of failure
of the level safety system and operating errors
Even failure of reactor cooling (without when discharging water ;
simultaneous failure of the injection pump) does not
lead to a hazardous condition: at a peak of 250" C leakage from the diaphragm pumps P 71 AIB ;
the injection pump P 71 is shut down by the failure of flare A 750 because of operating errors
" temperature high " alarm and the subsequent or loss of natural gas supply.
reaction only causes a slight temperature and
Leakages from pipes (4.1.1.6),corrosion (4.1.2.1),
pressure rise. This shut-down, however, is not a use of unsuitable material (4.1.2.2),sampling
safety measure in the sense of accident prevention : (4.1.2.3),loss of energy (4.1.2.4),machine failure
if shut-down is not effected and P 71 continues
(4.1.2.5),hazards from other units of the Deka
feeding, (undesirable) high-molecular products form
factory (4.1.3),environmentally incurred hazards
with increasing temperature. However, their vapour
(4.1.4)and sabotage (4.1.5)can be ruled out as
pressure is so low that there is no further pressure
hazards leading to a major accident.
increase. The solids which have formed in the
reactor must then be removed mechanically. Shut-
down does not cause conditions which would 3. Chemical identification
endanger safety, but rather conditions which are of substances; condition and
operationally undesirable. quantity of substances in
Feedback from the reactor C 70 to upstream accordance with Appendix 11
systems as a result of a backflow of material is ruled (Article 7 (1)3)
out by the check valves between P 71 A/B and C 70
Quantity of acrolein handled :
and by the diaphragm pumps P 71 A/B themselves
(see figure 6.15). Similarly, the downstream (a) tank store : maximum 60 t ;
columns contain only very slight quantities of (b) B 71 : approximately 1 t ;
acrolein ; no reactions at all take place there either.
(c) acrolein tank-car : 20 t .
2.2. Hazards and preconditions Temperature : ambient temperature
for an accident
Material data : safety-related and toxicological
There is the possibility of an accident occurring data are apparent from figure 6.17. Safety-related
if large quantities of acrolein are released. In side reactions are not known.
principle, acrolein can be released as a result of:
-
overfilling of the storage tanks caused by 4. Description of fulfilment
operating errors when handling the unloading of the requirements imposed
equipment and failure of the level safety
systems ;
in Articles 3 to 6
-
damage to/leakage from the acrolein tank-car (Article 7 (1)4)
and the acrolein storage tanks because of
failure of the pressure safety systems ; 4.1. Measures for the prevention of
accidents
-
rupture of the hose connections of the
unloading system ; 4.1.1. Special operational hazards
Major hazard control
4.1.1.1/2. Acrolein unloading and storage 31) can cause overfilling of storage tanks B 19, 22
(figure 6.13) and 23.
Operating errors and failure of the level safety On the whole, operating errors are ruled out by
system (LIA*S+76-10,20, 30 and LA+S+ 76-11, 21, the operating instructions for unloading of the tank-
cars and for acrolein storage. If overfilling,
Figure 6.17. Material and reaction data- nevertheless, becomes a threat because of
acrolein (2-propenal,acrylaldehyde) operating errors or carelessness, the level safety
Acrolein is a colourless, very reactive, toxic liquid with a
penetrating smell. Irritation of skin, eyes and mucous system issues an alarm and closes supply valves
membranes. Inhalation causes burning of the respiratory tract HS 76-10, 20, 30 (shut-down).Both alarm and shut-
and lungs, oral intake leads to irritation, vomiting, diarrhoea. down have redundant back-up support (LIA*S*and
LAt S'). Consequently an alarm will always be
(a) General material data signalled and shut-down always effected even in
the case of failure of a process measuring and
Formula CH, = CH - CHO control safety system.
Molecular welght 56.06
Melting point -88C These measures practically rule out overfilling
Boiling point at 1013 mbar 53" C of the acrolein storage tanks.
Vapour pressure at 20" C 286 mbar
Denslty at 20" C 0.84 g/cm3 Damage to/leakage from the tank-ca~;as a
Rel, vapour density (air = 1) 1.94 result of too high internal pressure, can only be
Solubility in water at 20' C 26.7 g/100 cm3 caused by simultaneous failure of the nitrogen
Soluble in many organic solvents reducing station PC 76-08a/b, the related safety
valves and the pressure control system PIC 76-01.
(b) Safety-related material and reaction data
Damage to/leakage from the acrolein storage
Flash point -29" C tanks as a result of too high internal pressure, can
Danger class acc. to VbF A1 only be caused by simultaneous failure of the
Ignition temperature 280" C nitrogen reducing station PC 76-08a/b, the related
Ignition temperature (stabilised) 210" C safety valves and the "pressure high " safety system
Temperature class T3 PICAIS+ with simultaneous non-bursting of one of
Explosion limits in air 2.8 - 31 vol, per cent the rupture discs. PICAIS+ closes the ball valves in
Stabilised with hydroquinone (tendency to polymerlsation) the acrolein supply line HS 76-10, 20, 30 and the
Violent reaction with alkalis and oxidising substances
-
nitrogen supply valve at " pressure high" in the
(c) Health effects nitrogen line.
These safety measures practically rule out the
Acute toxicity : occurrence of a leakage from the acrolein storage
man : inhalation, LC,, = 153 ppm/lO min. ; tanks and the tank-car.
anlmal: rat, oral, LD,, = 46 mg/kg,
mouse, oral, LD,, = 40 mg/kg ; The following measures rule out rupture of the
odour level : = 0 2-0.4 ppm. hose connection of the unloading equipment and
release of acrolein :
(d) Maximum workplace conc. 0.1 ppm P 0.25 mg/m3
(a) there is no motor vehicle traffic at the
References : unloading station (see site plan, figure 1);
C. W. Smith: " Acrolein", Huthig Verlag, 1975. (b) the acrolein tank-cars cannot be moved
Hommel : " Handbuch der gefahrlichen Guter ", inadvertently because of the use of stop blocks ;
Merkblatt 218
Kuhn-Birett " Merkblatter gefahrliche Arbeitsstoffe " , (c) the only track to the unloading station is
No. A 09. blocked by a shunt which is locked in the
DEGUSSA : Merkblatt Acrolein. opposite direction and a double red lamp to
NIOSH : "Registry of toxic effects of chemical
prevent the approach of other railway cars
substances ", 1980.
during the unloading process ;
Example of a safety report
(d) the hose of the unloading equipment is always Starting polymerisation is initially detected by a
visually checked for defects before use ; temperature increase. The temperature is always
(e) during unloading, the operator supervises the kept below 20" C with the aid of the water
unloading process continuously. If leakages sprinkling system. Temperature safety systems
occur, the following measures are taken on the TIA+S+ 76-10/11/12, -20121122, -30/31/32 are
spot: acrolein is blown down into the flare via designed redundantly (two out of three) because of
the emergency blow-down system (HS 76-00 their importance. This practically rules out non-
open), and the acrolein line is closed (HC 76-01 detection of a temperature increase. If two of three
closed). measuring points detect a temperature in excess of
30" C, an alarm is signalled in the control room and
Filling of the acrolein tanks with a different the safety system automatically initiates the
product can lead to polymerisation of acrolein, following measures :
which in turn can cause bursting of the rupture
discs (see 1.5.1(5))and, finally, the ingress of (a) hydroquinone from the hydroquinone tank
acrolein into the collecting tank. The following B 19A is injected into the acrolein loop by
measures can almost certainly rule out this hazard : opening the respective valves HS 76-11, 21, 31 ;
(a) only acrolein tank-cars are unloaded at the (b) ball valve HS 76-03 is closed. This stops the
unloading station. As no other product is product flow from the tank store to the
unloaded there, the acrolein tanks cannot be production plant ;
filled with a different product even if operating (c) pump P 71 is shut down.
errors are made by the personnel (mixing up of
valves or unloading couplings) ; Polymerisation of acrolein is a reaction via
radicals. Hydroquinone captures radicals.
(b) before an acrolein tank-car is unloaded, an Hydroquinone radicals would react with the
analysis must be carried out to confirm that it radicals of the polymerisation reaction and therefore
contains acrolein of the specified purity ; stop the reaction.
(c) the acrolein storage tanks are only connected
by piping to the unloading station E 405 and The quantity of hydroquinone - dissolved in
the acrolein plant. There are absolutely no gas methanol - which is stored in tank B 19A amounts
or liquid-carrying pipe connections to other to approximately 40 kg. This is approximately 0.2
operating systems (except for the nitrogen per cent of the maximum quantity of acrolein
supply lines). stored in one tank (the quantity of hydroquinone
used for stabilisation of commercially available
Even slight impurities in the acrolein can lead monomers is in the order of 100 ppm).
to polymerisation. This hazard is ruled out by the
fact that highly purified nitrogen is used to expel As a first approximation, this quantity of
the acrolein from the tank-car and to cover the tank hydroquinone amounting to approximately 40 kg
contents. This nitrogen is not withdrawn from the could react with the same quantity of a radical
nitrogen network, but rather is highly purified starter (with the same molecular weight). It is not
nitrogen supplied by a cold gasifier. conceivable that such a quantity could enter an
acrolein tank as an impurity. This therefore ensures
In the event of loss of the nitrogen supply from that even the starting of polymerisation can be
the cold gasifier, an emergency supply of highly prevented.
purified nitrogen is available from steel cylinder
batteries. Declining nitrogen stocks are signalled by Nevertheless, additional protective systems are
PIA- 76-03 and 76-04 in the control room. provided : the collecting tank for acrolein, the water
jets which can also cool the ouside of the storage
Polymerisation of the acrolein in the storage
tanks and the scrubber K 709.
tanks is not to be expected in view of the existing
organisational and technical measures. If, contrary The pressure between the two series-
to expections, polymerisation nevertheless occurs, connected bursting discs of the storage tank is
the following measures are provided for this measured, PIAtS+ 76-11, 21, 31. On bursting of the
extremely unlikely case. first disc, the water valve HS 76-02 for scrubber
Major hazard control
K 709 is opened automatically. On bursting of the This effectively prevents a hazardous reaction
second disc, acrolein enters the scrubber. The between acrolein and caustic soda.
scrubber is loaded with approximately 2.5 mVh of
4.1.1.4. Injection pump P 71 A/B (figure 6.15)
water. A rough estimate shows that if acrolein
enters the scrubber in gaseous form, the scrubber A hazard as a result of leakages at this pump is
can condense up to 1 tlh, while if acrolein enters not to be expected. This is a diaphragm pump
the scrubber in liquid form, it can remove up to which does not present any problems to the outside
3 tlmin. arising from the sealing of rotating or moving parts.
An evaluation of the planned measures leads to Hazardous overpressure, which could form on
the conclusion that a hazard resulting from any closure of the pressure side of the pump, is
polymerisation of acrolein can be ruled out under prevented by an overflow valve between pressure
realistic assumptions. side and suction side (see 2.1.4).
4.1.1.5. Flare for off-gas A 750 (figure 6.16)
A leakage of acrolein from the centrifugal
pumps P 23 A/B is prevented by equipping both Failure of the flare can be caused by operating
pumps with double rotating mechanical seals (see errors or by loss of natural gas supply. Failure is
2.1.2).As additional protection, a gas warning detected by a decrease in temperature at the tip of
device is installed with two remote gas sensors the flare and is signalled in the control room by
directly at the two pumps (see 2.1.2)(primary TIA- 75-00. On failure, the entire acrolein plant is
explosion protection measure in compliance with shut down in compliance with the operating and
E 1.4.1EX-RL). safety instructions.
4.1.1.3. Water separator B 71 and tank R 72 Until the plant has come to a complete
(figure 6.14) standstill there is an emission of non-burned
acrolein via the failed flare. The quantity emitted is
Failure of the pressure control PIRC 70-01 in low : assuming 50 per cent saturation (the
water separator B 71 can lead to dangerous thermodynamically possible saturation) of acrolein,
overpressure. The tank is therefore equipped with one obtains a value of approximately 0.3 kglh of
two safety valves (shuttle valves), thus ruling out acrolein for approximately 1 mVh of off-gas from the
this hazard. pressure and level control systems. The gas leaves
Exothermal reaction acrolein - caustic soda in the flare at a height of about 28 m.
R 72. The water settling as the lower phase in B 71 Therefore failure of the flare does not present
is locally discharged by hand into mixing tank R 72 any hazard.
to prevent an unnecessary release of acrolein. At
the same time, this discharge is monitored in the 4.1.1.6. Pipe-work, valves
control room via LIRCAk70-02 and LIRS*A*70-03. Leakages at pipes and valves are unlikely as
The level process measuring and control system the pipes are continuously welded wherever
LIRS*Art70-03,which measures the level of the posslble and the flanges are equipped with special
acrolein-water interface and closes valve 70-03 at seals (type Spiroflex). Possible leakages are at most
level " low", is used only for additional safety. slight inconveniences which can be quickly
eliminated. The detection and localisation of
In the event of failure of LIRS*A*70-03 and leakages is considerably simplified by the typical
simultaneous operating errors during discharge, smell of acrolein and the very low odour level.
large quantities of acrolein can enter tank R 72 and Inspection tours of the plant are made every hour
cause a significant temperature increase as a result (4.3.1).
of the exothermal reaction with the caustic soda
present in the tank. If this occurs, the contents of Mechanical rupture of a pipe carrying acrolein
the tank can be directly cooled and diluted with is not classified as a hazard. The pipes are laid with
water via an additional water inlet. A pressure maximum protection. Furthermore, the fact that the
increase is not possible as R 72 is freely vented to pipes are designed for a nominal pressure of at
the atmosphere.. least 10 bar (which is not necessitated by the
Example of a safety report
process) ensures that they can withstand possible would result over a period of several days during
external mechanical loading. hot weather.
In order to avoid any error, e.g. during repairs, Such a slow temperature increase would,
the pipes are marked at intervals of approximately however, also indicate the absence of impurities in
5 m. the acrolein, i.e. that there is no danger of
polymerisation. Simultaneous occurrence of
4.1.2. General operational hazards polymerisation of acrolein as a result of impurities
and loss of cooling water is considered to be so
4.1.2.1. Corrosion
unlikely that this possibility is ruled out. Note :
All plant equipment and pipe-work coming into acrolein without any impurities is transported in
contact with the product is manufactured from railway tank-cars without cooling. The redundant
stainless steel (1.4541).According to the state of the temperature safety systems of the acrolein tanks
art (e.g. Ullmann), stainless steel is completely (and the related safety measures) are provided to
resistant to acrolein. This is confirmed by the prevent any polymerisation from starting with rapid
existing plant, in which no corrosion has been temperature increase.
detected in the course of a 15-year period.
In the event of loss of compressed air or
4.1.2.2. Use of unsuitable material electricity, the process measuring and control
The plant is designed and erected in systems, the electrical circuits fail-safe and the
compliance with the Project Media Code, which is plant can be shut down without any danger.
also adhered to for repairs and alterations. Since If the natural gas supply is cut off, there is a
commissioning of the plant, there has been no
slight emission of acrolein (see 4.1.1.5).The highly
indication of the fact that a material other than that purified nitrogen supply for coverage of all systems
specified has been used at any point as a result of containing acrolein is assured (see 2.1.1, 4.1.1.112).
error.
Loss of energy therefore does not cause a
4.1.2.3. Sampling
hazardous operational condition. For this reason,
Prior to unloading of the acrolein tank-car, a the plant is not equipped with independent energy
small vessel installed in the pipe between the tank- inputs nor with an emergency supply (except for
car and the storage tank is first filled. The operator highly purified nitrogen). The safety lighting is
then takes a sample by hand from this vessel which described in 1.5.3.
is isolated by valves. He only starts the unloading
operation after analysis. This basically rules out any 4.1.2.5. Machine failure
danger in connection with the sampling process. If the energy supply is cut off, all machines
4.1.2.4. Loss of energy stop. No further product is transported (P 23 AIB,
P 71 AIB). Failure of pumps P 23 and P 71 is not of
In the event of loss of steam, cooling water,
relevance for safety; it is only of importance for
compressed air, natural gas or electricity, the plant
product quality and plant reliability.
is shut down in compliance with the operating and
safety instructions. As none of the safety-related On shut-down of P 23 A/B, acrolein is no longer
systems has to be heated or cooled, loss of steam or circulated in the tank store. Hydroquinone cannot
cooling water cannot cause a hazard. be mixed in. Simultaneous occurrence of loss of
energy with a demand for hydroquinone to the
The heating (TIC 70-58) at R 72 is used only for
hydroquinone tank B 19A because of a temperature
heating at very low outside temperatures and to
increase in an acrolein tank is considered as being
protect the plant from freezing during shut-down.
so unlikely that an additional safety measure is not
The reaction in R 72 takes place at ambient
taken. (Long-term experience has shown that the
temperature.
energy supply fails for one-half to two hours every
However, sprinkling of the acrolein tanks would few years ; it has not been necessary to mix in
also fail in the event of loss of cooling water. A very hydroquinone since acrolein storage commenced in
slow temperature increase in the acrolein tanks 1969.)
Major hazard control
If the stirrer in R 72 fails, the reaction between 4.1.3. Hazards from other operational
acrolein and caustic soda does not take place units of the Deka factory
completely. There is an unpleasant odour because The adjacent operational units of the Deka
of traces of acrolein. factory contain flammable and toxic substances. In
4.1.2.6. Fire and explosion protection principle, hazards for the acrolein plant are,
All installations in the Deka factory are in therefore, (i) toxic emission, (ii) fire, and (iii)
compliance with the primary explosion protection explosion. Emission without ignition does not
measures as stated in E 1.3.1,E 1.3.2 and endanger the acrolein plant. The operating
E 1.3.3EX-RL. personnel is provided with the necessary personal
protective equipment and can shut down the
In hazardous locations (see 1.1.2),ignition acrolein plant at any time and without any
sources such as hot surfaces, flames and hot gases, problems to the control room. In order to prevent
mechanically generated sparks, electrical fire or explosion, all equipment in the Deka factory
installations, electrical compensating currents, is in compliance with explosion protection guide-
static electricity and lightning stroke are prevented lines (see 1.1.2).The acrolein plant has the same
or rendered ineffective by protective measures in safety standard a s the other operational units. All
compliance with E 2 EX-RL (secondary explosion operational units can be shut down at any time.
protection measures).
Fires in the direct proximity of the acrolein
An explosion cannot occur inside the storage tanks and the acrolein plant can be fought
equipment and pipe-work because all systems effectively (see 4.2.2).
containing flammable liquids and vapours are
covered with nitrogen (primary explosion protection A further hazard is the release of pressurised
measures in accordance with E 1.2.2EX-RL). All hydrogen with self-ignition from pieces of
flammable off-gases are conveyed to the flare equipment located at a distance of about 30 m. The
A 750, the ignition and combustion flame of which distance is too great for a hydrogen flame to come
is outside hazardous locations. into direct contact with components containing
acrolein (according to a flame length estimate
All work with an open flame must be approved based on the jet theory assuming unfavourable
in writing in advance. conditions). The indirect effect of a hydrogen flame
It is clearly shown that the plant can also as a result of radiation is low since no soot particles
withstand the loadings in the case of malfunction, can form. Furthermore, the plant can be shut down
and that it is adequately equipped with warning, at any time without any risk. Therefore this hazard
alarm and safety systems as well as with sufficient can be disregarded.
redundant process measuring and control systems
with proven equipment design. The plant is 4.1.4. Environmentally incurred hazards
designed in compliance with state-of-the-art safety 4.1.4.1. Adjacent plants (see site plan,
engineering ; in particular it complies with the figure 6.1 and section 1.1.1)
Regulations for the Prevention of Accidents, the
Pressure Vessel Code, the AD specfications, the The Deka factory is surrounded on two sides -
TRbF specifications, DINIVDE standards and the to the south and the west - by workshops, a pool,
EX-RL of the Union of Industrial Mutual Indemnity the canteen and office buildings, as well as storage
Associations. and packing plants. These do not represent any
hazard for the Deka factory.
The reliability of each individual installed
process measuring and control system is assured Production plants are located to the north and
by pertinent operating experience and special tests. the east. Only minor hazards are to be expected
Abnormal operating conditions are signalled from these plants : the distances are too great. The
optically and acoustically in the control room. All statement given in 4.1.3 is valid for the emission of
safety-related process measuring and control toxic substances. Fire and explosion are prevented
functions, e.g. level, pressure and temperature in in the surrounding plants, as in the Deka factory
the storage tanks, are designed redundantly. (see 4.1.2.6),by stringent explosion protection
Example of a safety report
measures in compliance with EX-RL. The Deka checked by guards who make hourly inspection
factory and the surrounding plants all exhibit the tours. Any persons not employed in the plant must
same standard of safety. register before entering the plant (registration card
system). This satisfactorily rules out sabotage.
The X factory presents a specific risk, namely
the emission of flammable gases. The X factory is 4.2. Measures to limit accident
subject to the Ordinance on Major Hazard Control consequences
of the Federal Republic of Germany. The most
important measure in this case is fast elimination of 4.2.1. Foundations and supporting
all ignition sources (extinguishing of the flare, structures
cancellation of any permits which have been issued Foundations and supporting structures were
for work with open flame, see 4.1.2.6). designed and constructed in compliance with the
If the Deka factory is endangered by adjacent building regulations. Their stability, which was
plants, the Deka factory is alerted via the block examined within the scope of the construction
alarm. The block alarm and measures to be taken permit and the permit issued in compliance with
are discussed in 4.2.3. the Federal Law on Pollution Control of the Federal
Republic of Germany, is suitable for the anticipated
4.1.4.2. Traffic loadings.
The distance to the Rhine is approximately 4.2.2. Protective measures and safety
800 m ; the distance to a public road approximately systems
250 m. The situation on the factory site is apparent
from the site plan (figure 6.1) and section 1.1.1.The The collecting tank for the acrolein storage
only factory road (east-west road) in the vicinity of tanks was planned and constructed in compliance
the Deka factory which is open to traffic is provided with TRbF 110 (see 2.1.2).
with a 10 m broad safety zone. In addition, the The water sprinkling system for the storage
Deka factory building containing offices and control tanks primarily serves to cool the tank contents.
room separates the acrolein plant from the road.
The distance from the road to the acrolein plant is Although the four stationary water jets are also
approximately 30 m. Traffic regulations on factory used for cooling, they are primarily for fighting fires
roads are as follows : 30 km/h. The plant is not in and for precipitating gases and vapours. They are
the vicinity of an airport or airfield. positioned in such a way (see site plan, figure 6.1)
that the acrolein tank store in particular can be
Traffic-incurred hazards can therefore be ruled easily reached with the water jet from all sides. In
out. the event of a fire in the direct vicinity of the
4.1.4.3. Natural hazards acrolein tanks, they could be cooled effectively. The
water jets and related booster pump are
The plant is situated in an area with low
dimensioned on the basis of pertinent experience
seismic activity (DIN 4149 seismic zone 1).In
collected by the plant fire brigade.
compliance with the building regulations, stability
is assured by the corresponding construction of the The two gas warning devices at pumps
foundations and the design. P 23 AIB enable fast detection of leakages (see 2.1.2
and 4.1.1.1/2).
Danger as a result of flooding is not to be
expected as the plant is located above the The number of fire extinguishers specified by
maximum high-water mark which has been the plant fire brigade is available.
established on the basis of many years'
When working under difficult conditions,
observation.
walkie-talkies are used to ensure communication
4.1.5. Sabotage between the plant and the control room.
The plant is situated on a fenced-in site and In compliance with the operating and safety
access to the plant is only granted to authorised instructions, an adequate quantity of the necessary
persons. The plant is illuminated at night and is protective gear is available for the operating
Major hazard control
Even the release of acrolein into the tank tub, site emergency measures and round-the-clock
which should not be realistically assumed, does not readiness of the plant fire brigade would limit the
affect a larger area than rupture of the filling hose. disturbance to the plant itself, thus ruling out any
This is because the escaping acrolein is diluted effect on the surrounding area.
within seconds with water from the water jets
The Deka factory is situated within a large
which are directed on to the tub and are always
plant complex. An off-site emergency plan exists for
ready for operation, thus drastically lowering the
all hazards which could in principle originate from
vapour pressure. When compared with rupture of
this plant. This plan was drawn up by the
the filling hose, the larger evaporation surface of
competent authorities with the co-operation of
the tub is compensated by the low effective vapour
plant management and is interlinked with the on-
pressure, thus resulting in approximately the same
site emergency plans of the plant. If there is any
evaporation rates and affected areas.
danger from a dispersing pollutant cloud, all
Precautions have been taken against all of emergency plans for the municipal area and all
these events : the fire brigade is alerted as measures to be taken by off-site emergency forces
scheduled, any plants which may be affected are have been specified in advance. Precautions which
warned in compliance with the emergency plan. should be taken by the population in the case of an
The fire brigade implements on-site emergency alarm, and with which the population is
measures after five minutes at most (confirmed by familiarised by means of addressed circulars and
numerous drills). The point of leakage is flushed newspaper articles, are always the same
with water andlor covered with foam. This independent of the specific pollutant. No other
drastically lowers the quantities discharged to the measures are necessary. In principle, the municipal
atmosphere (by at least a factor of 10). Water off-site emergency plan covers any hazards
screens are used if necessary. originating from the Deka factory.
The affected areas have been established on a
purely theoretical basis and are maximum
estimates : in each leakage case, the pollutant
concentration builds up slowly over minutes and is
reduced within minutes by the measures
implemented. The worst dispersion condition is
Notes
1 Record of explosion classification, i.e. establishing of
seldom encountered and, as has been shown by our hazardous locations.
experience, cannot occur at all in the factory The Project Media Code contains specifications for the
because of the specific atmospheric (wind materials and the construction of piping, seals and valves for all
media (substances) in the project, i.e. present in the plant, as a
direction, wind velocity, thermal lift at sources) and function of pressure, temperature and nominal diameter.
topographical conditions. Technical data sheets are used for technical descriptions
in inquiries and orders for equipment, tanks, pumps, etc. They
One can therefore assume that even if a large contain the design data as well as necessary data on materials,
quantity of acrolein was unexpectedly released, on- dimensions and type.
Appendix 7
Example of
accidents reporting form
(derived from Annex VI
to EC Directive (821501lEEC))
Example of accidents reporting form
Known :
(to be specified)
Not known :
poisoned
- material damage
...... injured
.................... poisoned
- material damage
7 . Medium- and long-term measures, particularly those aimed at preventing the recurrence of similar major accidents (to be
submitted as the information becomes available).
Appendix 8
Land-use near to
major hazard works
Land-use near to major hazard works
1. It is generally considered prudent to try to a range of major hazard works. These distances
separate works storing and using significant should be regarded as tentative and would need
qualities of hazardous materials from nearby to be considered under local circumstances to
centres of population including housing, decide on their applicability. Where these
shopping centres, schools, hospitals, etc. distances are considered to be unacceptably
large, more detailed assessment work (paragraph
2. Different countries pursue this objective using 4) may be necessary.
arrangements appropriate to their particular
legislation. In the United Kingdom, for example, 7. Categorisation of development
the use of land is controlled through land-use 7.1. In deciding on the separation required from
planning legislation where development normally a works, it can be helpful to categorise the
requires specific planning permission from the proposed development. This will enable
local authority, which can take account of any individual development decisions to be made
adjacent major hazard works. within the framework of a consistent approach.
3. An important consideration is the degree of 7.2. Categories of development can take
separation which is necessary. Ideally, one could account of a number of relevant factors in
calculate the worst-case accident occurring at deciding on whether to permit development, e.g.
the works and permit development only outside amount of time individuals spend in the
its hazard range. For most countries, and development, ease of implementing an
particularly for toxic hazards where the emergency plan, vulnerability of occupants of
consequences could, at worst, extend for several the development (old people more vulnerable to
kilometres, such a policy would blight large thermal radiation).
areas of land at considerable cost both to the One broad categorisation which has been widely
area and the country. used is based on three general categories :
4. An alternative approach is to use the techniques Category A : Residential, including houses,
of quantified risk assessment (QRA) to predict hotels, flats ;
the risk (or likelihood of harm) to an occupant of Category B : Industrial, including factories
the proposed development, and then to decide (unless they have high-density employment),
whether such a risk is tolerable. This approach warehouses ;
requires considerable sophistication in analysis
and computation techniques and would be Category C : Special, including schools,
unlikely to be appropriate except where hospitals, old peoples' homes.
comprehensive major hazard control measures Other types of developments can then be added
are already in operation. to the most appropriate of these categories, e.g.
theatreslcinemas and shopping centres could be
5. A middle approach, which has been endorsed included as Category A.
by the United Kingdom Advisory Committee on
Major Hazards, is to try to arrange a separation 7.3. In table 8.l.,and as a first approximation,
of developments from major hazard works. This the separation distances given should be
will achieve almost complete protection from the considered as follows :
more common but relatively minor accidents (a) within the separation distance - no
and, in addition, worth-while but not complete Category C development ;
protection from the severe but very rare major (b) within about two-thirds of the distance -
events. no Category A development ;
6. Based on this approach, table 8.1. gives (c) no restriction of Category B
suggested approximate separation distances for development.
Major hazard control
Table 8.1. Suggested approximate separation distances for major hazard works
Substance Largest tank slze Separation
(t) distance
(para. 7.3.)
(m)
Liquefied petroleum gas, such as propane and butane, held at 25- 40 300
a pressure greater than 1.4 bar absolute 41- 80 400
81-120 500
121-300 600
More than 300 1000
25 or more, only in cylinders or 100
small bulk tanks of up to 5 te
capacity
Liquefied petroleum gas, such as propane and butane, held 50 or more 1 000
under refrigeration at a pressure of 1.4 bar absolute or less
Phosgene 2 or more 1 000
Chlorine 10-100 1 000
More than 100 1 500
Hydrogen fluoride r 10 or more 1 000
Sulphur trioxide 15 or more 1000
Acrylonitrile 20 or more 250
Hydrogen cyanide 20 or more 1 000
Carbon disulphide 20 or more 250
Ammonium nitrate and mixtures of ammonium nitrate where 500 or more See note 1
the nitrogen content derived from the ammonium nitrate
exceeds 28 % of the mixture by weight
Liquid oxygen 500 or more
Sulphur dioxide 20 or more
Bromine 40 or more
Ammonia (anhydrous or as solution containing more than More than 100
50% by weight of ammonia)
Hydrogen 2 or more
Ethylene oxide 5-25
More than 25
Propylene oxide (atmospheric pressure storage) 5 or more
(stored under pressure) 5-25
More than 25
Methyl isocyanate 1
Classes of substances not specifically named
1. Gas or any mixture of gases which is flammable in air and 15 or more
is held in the installation as a gas (except low-pressure
gasholders)
2. A substance or any mixture of substances which is 25- 40
flammable in air and is normally held in the installation 41- 80
above its boiling point (measured at 1 bar absolute) as a 81-120
liquid or as a mixture of liquid and gas at a pressure of 121-300
more than 1.4 bar absolute More than 300
25 or more only in cylinder or small
bulk tanks of up to 5 te capacity
3. A liquefied gas or any mixture of liquefied gases which is 50 or more
flammable in air, has a boiling point of less than 0C
(measured at 1 bar absolute) and is normally held in the
installation under refrigeration or cooling at a pressure of
1.4 bar absolute or less
4. A liquid or any mixture of liquids not included in items 1-3 10 000 or more 250
above which has a flashpoint of less than 21C
1For b a ~ a e dammonlum nitrate stored m stacks of 300 t (maximum)a separation &stance of 600 m IS appropriate. For loose ammonium nitrate, the separation
d~stance w e n by-
600 p a c k size (t)( 113
300 1