Académique Documents
Professionnel Documents
Culture Documents
TABLE OF CONTENTS
1.0 SCOPE
2.0 GENERAL
2.1 Requirements
2.2 Geotechnical Information
2.3 Plan and Profile Drawings
6.0 BIBLIOGRAPHY
1.0 SCOPE
This Standard establishes the specific parameters and procedures for the design of unpaved
access road, structure pad and slope protection from erosion/encroachment of transmission
line Right-of-Way (ROW), for use in overhead transmission line system of National Grid
Saudi Arabia.
2.0 GENERAL
2.1 Requirements
Access to the transmission line ROW and along the transmission line requires
various operations including construction of road approaches, filling of ditches,
dozing trails, and other works depending on the type of terrain. Suitable road
approaches are required for safe access of equipment and vehicles. Proper surface
drainage shall be provided. For easier accessibility during construction and later for
inspection, operation and maintenance of the transmission lines, unpaved access
road shall be located as near as possible to transmission lines.
All access roads, finger roads and structure pads shall be permanent for operation
and maintenance purpose by National Grid Saudi Arabia.
2.2.4 California Bearing Ratio (CBR) Test plots including CBR vs Dry Density
2.2.5 Recommendations
The design of unpaved access road and structure pad shall make use of the
transmission line plan and profile drawings, which show the left and right profile at
15 m away from the transmission centerline.
The unpaved transmission line access road shall be designed for adequate traffic volume to
assure the safe movement of construction and maintenance equipment along the ROW.
Design of access road shall take into account the grade and topographical conditions of the
terrain to be traversed and shall be in accordance with the following requirements:
The maximum grades for different types of terrain based on the specified
design speed shall be the following:
a. Flat 10.5%
b. Rolling 13.5%
c. Mountainous 15.0%
3.1.7 Path Required for Vehicle (10-meter long truck for line wash)
The typical cross-section of access road shall consist of subgrade, subbase, and
surface/base course. The requirements are given below:
3.2.1 Subgrade
e. In areas where the existing subgrade material has a CBR value of less
than 15, subgrade modification shall be done to improve the CBR to
a minimum of 15 after four days of soaking.
3.2.2 Subbase
a. Material
c. Finish
d. Tolerances
The top of the completed surface course shall not show any deviation
in excess of 20 mm when tested with a 3 m straightedge. The
completed thickness of the surface course shall be within 20 mm of
the design thickness of 300 mm.
3.2.4 Fill materials, including water used during compaction, shall have chloride
and sulfate contents equal to or less than the existing soil. Seawater shall
not be used for compaction.
3.2.5 In continuous/uninterrupted hilly areas where hard & solid bed rock is
encountered, access road shall be prepared by rough grading at the existing
levels followed by compaction in order to suit four wheel drive (4WD)
vehicles. Such roads shall serve the purpose to access the structure
locations during the construction stage and later on, same roads shall be
utilized by National Grid Saudi Arabia for operation & maintenance. These
roads shall be subject to approval and acceptance of National Grid Saudi
Arabia.
Road intersection and access road crossing are locations where roads cross each
other at a common elevation. The typical plan layout of intersection shall be as per
Figure TE-2211-0700-00. Adequate advanced warning of the intersection, traffic
directional arrows and signs shall be provided as per following:
Crash barriers are required to protect any fence, boundary wall, culvert, or
any other utilities, which are close to the transmission line structures. Crash
barrier shall be in compliance with TES-P-119.19.
3.4 Routes
Access road shall be routed within the ROW of the proposed transmission lines.
3.4.2 The existing access road shall be upgraded as per requirements of this
standard. Precautionary measures to be taken in order to avoid any damage
to the existing access road. Any damage during construction shall be
repaired/rectified without any extra cost to National Grid Saudi Arabia.
3.5.1 The minimum basic wheel load for the pipeline crossings shall be seven (7)
metric tons.
3.5.3 The pipeline shall be protected against damage from vehicle collision by
means of at least 1 m high stabilized earth berm over the pipe and
extending 30 m beyond both edges of the road (measured perpendicular to
the road).
3.5.4 Backfill material shall be the same material as that of access road (as
specified in section 3.2) and shall be free of material that may damage
coatings of steel pipe. Backfill shall be placed in layers of 300 mm or less
and the degree of compaction shall be same as for the access road.
3.5.5 Unless otherwise specified, the minimum cover over steel pipes shall be
1.5 m for unpaved road crossing.
3.5.6 The minimum width of the crossing shall be 5 m, excluding the side slopes.
4.1.1 The edge of the pad shall have a minimum distance of 15 m from any point
of the structure foundations or guy anchors.
4.1.2 The maximum side slope shall be 4 horizontal to 1 vertical. Side slopes
shall be as flat as possible, to increase safety by providing additional
maneuver area in emergencies and maintenance work.
4.1.3 Structure pads shall be graded to drain water away from structure
foundations with slope of 1.5 to 2 percent.
4.1.5 Wherever the transmission line is passing through Sabkha, water logged,
water course, flooded and swamp areas; the filling shall be done to get
structure pad at minimum elevation of 1.5 m above the surrounding area.
4.1.6 The typical design drawings of structure pad for different transmission line
towers shall be as shown in Figure TE-2211-0100-00 to TE-2211-0600-00.
4.1.7 The top of the subbase material for structure pad shall be elevated
minimum 750 mm from the existing grade level in desert area affected by
sand shifting & sand dunes.
4.1.8 In continuous/uninterrupted hilly area where hard & solid bed rock
encountered, the structure pad shall be prepared by rough grading at
existing levels followed by compaction with suitable equipments in order
to access the structure locations.
4.1.9 The top of structure pad located in wadi or water channel/streams shall be
higher than the highest expected wadi flood level by 350 mm. The sides of
structure pad shall be stabilized and protected. All approvals shall be
obtained from National Grid Saudi Arabia prior to start of construction
works.
The typical details of finger road and structure pad are shown in Figure
TE-2211-0900-00. Finger road shall not be taken from the existing roads of Saudi
Aramco, SWCC, MOT and Municipality. Finger road shall be developed as shown
in Figure TE-2211-1000-00.
Protection of slopes adjacent to structure pads shall be carried out, where such slopes are
liable to be washed away or eroded by wind. Erosion control is required when slope or
excavation is steeper than 1 horizontal to 1 vertical. Slopes shall have contour trenches for
each 2 meters change in elevation. These shall be 0.4 meters deep and of rough construction.
The following are the recommended methods of slope protection and sand control.
Sand encroachment/erosion on the structure pads and access roads shall be prevented
by spraying the specified areas along the right-of-ways with crude oil or other
approved compound such as slow setting asphalt emulsion meeting the requirements
of ASTM D 2397 for CSS-Ih, to stabilize the surface. Spray area shall not be less
than 20 m radial distance from the edge of access road/structure pad and finger
roads.
In wadi areas where ground water level is high, or in areas submerged with water,
rip-rap or concrete barrier/lining shall be constructed within ROW to protect access
road and structure pad from erosion.
5.2.1 Rip-rap shall be placed on the slopes of structure pads and in places along
the slopes of access road where erosion control is required, and shall be of
durable stones or hard rocks. The geotextile (min. mass 200 gm/m2 Tensile
& Elongation in compliance with ASTM D 4632) shall be placed beneath
the rip-rap in order to maintain the separation between rip-rap and
underlying soil. Proper size of stones to be pitched in sequence to protect
geotextile membrane. Rip-rap shall be uniformly distributed to produce a
compact rip-rap with a minimum thickness of 300 mm. The minimum
specific gravity of stone shall be 2.5 and the maximum absorption shall be
six (6) percent. The loss by abrasion shall not be greater than 45% when
subjected to 500 revolutions in a Los Angeles Abrasion Machine in
accordance with ASTM C131.
5.2.2 Concrete barriers shall be designed to protect the slopes of structure pads
from erosion.
5.2.3 Small stretches of access roads which are lower than the normal level, and
where there is difference of levels on two sides of access road, box or pipe
culverts with wing walls shall be used. The concrete shall be severe
exposure type per 70-TMSS-03. The design shall be carried out based on
site conditions, approved by National Grid Saudi Arabia.
6.0 BIBLIOGRAPHY
6.3 ASTM C 131 Standard Test Method for Resistance to Degradation of small-size
Coarse Aggregate by Abrasion and Impact in the Los Angeles Machine
6.4 ASTM D 1241 Standard Specification for Materials for Soil Aggregate Sub-base,
Base and Surface Courses
6.5 ASTM D 1557 Standard Test method for Laboratory Compaction Characteristics of
Soil
6.6 ASTM D 1883 Standard Test Method for CBR (California Bearing Ratio) of
Laboratory Compacted Soils
6.8 ASTM D 4632 Standard Test method for Grab Breaking Load and Elongation of
Geotextiles.
6.9 SAES-L-460 Saudi Aramco Engineering Standard for Pipeline Crossings under
roads and rail roads.
FIGURE TE-2211-0500-00 ACCESS ROAD AND PAD FOR GUYED H-FRAME STRUCTURES
FIGURE TE-2211-0600-00: ACCESS ROAD AND PAD FOR GUYED MONOPOLE STRUCTURES