Daily Report

Project Name: KBK Project


Project Code: 03 YG 00400 Report Date : 24-Jun-2017 Saturday No. of Day 694 Report No. DPR-388

Project Start Date 2015-8-1 Contract Period 458 Calendar Day AM PM Fine
Weather
Estimate Completion Date 2016-10-31 Remain Period (236) Calendar Day 6~8 8~10 10 ~12 13~15 15~17 17~19 Rain

Work Force
M&E Site Office General Crane Crane Steel
Trades PM PE SAE Site Engr QA/QC QS Admin Safety Security Surveyor Geotech Welder
engineer Store Staff Workers Operator Helper Worker
Today 1 1 1 1 1 1 1 2 3 7
Operator Helper Manson Steel
Trades M&E Manson Carpenter Total
(ACP) (ACP) worker Supervisior
Today 1 2 2 24

Machine & Equipments onsite

Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks

25 Ton Crane 0 0 0 1.5 Hp Submer; pump 4 4 4 19KW Welding Box 6 6 6

Sheet pile machine 0 0 0 1 Hp Motor pump 1 1 1 60 KVA generator 1 1 1

3"x3" Air Compressor 1 1 1 1.5 Hp Motor pump 1 1 1

165 KVA Generator 1 1 1 2Hp Pressure pump 0 0 0

Material Delivery On Site

Quantity Quantity Quantity


Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total

FO-OP-01 REV-00 Page:1/2


Daily Report

Project Name: KBK Project


QC - Test Sampling

Item Remarks
Test
Sample
Taken

LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT
HSE Conducted By
Safety Officer

Works Carried out Details

Trades Of Work Location Remark

1 Main beam installation work at 1st and 2nd floor At grid (A)
2 Deck sheet installation and welding work at 1st flloor At grid (B-D)
3 Tighteining bolt & nuts at 1st to 3rd floor At grid (A-B)
4 Pump water at passenger lift and car lift pit area At basement floor
5 Removed earth beside external wall At grid E
6 Housekeeping work

Special Event

Visitors Site
Purpose To discus M& E work
on site Instruction

Project Manager Project Engineer Prepare By: Site Engineer

Name U Khin Maung Myint Name Name Aye Wit Yee Soe

Signature Signature Signature

FO-OP-01 REV-00 Page:2/2


KBK Project
Site Progress Photo
Date: 24.6.2017

Deck sheet installation work at 1st floor (grid B-C)

Removed earth beside exterior wall


Steel Structure Installation work at 1st floor , grid A