Vous êtes sur la page 1sur 8

G.R. No.

146717 November 22, 2004 In the course of the construction of the project, petitioner sought various EOT
to complete the Project. The extensions were requested allegedly due to several
TRANSFIELD PHILIPPINES, INC., petitioner, factors which prevented the completion of the Project on target date, such as
vs. LUZON HYDRO CORPORATION, AUSTRALIA and NEW ZEALAND force majeure occasioned by typhoon Zeb, barricades and demonstrations. LHC
BANKING GROUP LIMITED and SECURITY BANK denied the requests, however. This gave rise to a series of legal actions between
CORPORATION, respondents. the parties which culminated in the instant petition.

TINGA, J.: The first of the actions was a Request for Arbitration which LHC filed before the
Construction Industry Arbitration Commission (CIAC) on 1 June 1999.10 This
Subject of this case is the letter of credit which has evolved as the ubiquitous was followed by another Request for Arbitration, this time filed by petitioner
and most important device in international trade. A creation of commerce and before the International Chamber of Commerce (ICC)11 on 3 November 2000. In
businessmen, the letter of credit is also unique in the number of parties involved both arbitration proceedings, the common issues presented were: [1) whether
and its supranational character. typhoon Zeb and any of its associated events constituted force majeure to justify
the extension of time sought by petitioner; and [2) whether LHC had the right
to terminate the Turnkey Contract for failure of petitioner to complete the
Petitioner has appealed from the Decision1 of the Court of Appeals in CA-G.R. SP Project on target date.
No. 61901 entitled "Transfield Philippines, Inc. v. Hon. Oscar Pimentel, et al.,"
promulgated on 31 January 2001.2
Meanwhile, foreseeing that LHC would call on the Securities pursuant to the
pertinent provisions of the Turnkey Contract,12 petitionerin two separate
On 26 March 1997, petitioner and respondent Luzon Hydro Corporation letters13 both dated 10 August 2000advised respondent banks of the
(hereinafter, LHC) entered into a Turnkey Contract3 whereby petitioner, as arbitration proceedings already pending before the CIAC and ICC in connection
Turnkey Contractor, undertook to construct, on a turnkey basis, a seventy (70)- with its alleged default in the performance of its obligations. Asserting that LHC
Megawatt hydro-electric power station at the Bakun River in the provinces of had no right to call on the Securities until the resolution of disputes before the
Benguet and Ilocos Sur (hereinafter, the Project). Petitioner was given the sole arbitral tribunals, petitioner warned respondent banks that any transfer,
responsibility for the design, construction, commissioning, testing and release, or disposition of the Securities in favor of LHC or any person claiming
completion of the Project.4 under LHC would constrain it to hold respondent banks liable for liquidated
damages.
The Turnkey Contract provides that: (1) the target completion date of the
Project shall be on 1 June 2000, or such later date as may be agreed upon As petitioner had anticipated, on 27 June 2000, LHC sent notice to petitioner
between petitioner and respondent LHC or otherwise determined in that pursuant to Clause 8.214 of the Turnkey Contract, it failed to comply with
accordance with the Turnkey Contract; and (2) petitioner is entitled to claim its obligation to complete the Project. Despite the letters of petitioner, however,
extensions of time (EOT) for reasons enumerated in the Turnkey Contract, both banks informed petitioner that they would pay on the Securities if and
among which are variations, force majeure, and delays caused by LHC when LHC calls on them.15
itself.5 Further, in case of dispute, the parties are bound to settle their
differences through mediation, conciliation and such other means enumerated
under Clause 20.3 of the Turnkey Contract.6 LHC asserted that additional extension of time would not be warranted;
accordingly it declared petitioner in default/delay in the performance of its
obligations under the Turnkey Contract and demanded from petitioner the
To secure performance of petitioner's obligation on or before the target payment of US$75,000.00 for each day of delay beginning 28 June 2000 until
completion date, or such time for completion as may be determined by the actual completion of the Project pursuant to Clause 8.7.1 of the Turnkey
parties' agreement, petitioner opened in favor of LHC two (2) standby letters of Contract. At the same time, LHC served notice that it would call on the securities
credit both dated 20 March 2000 (hereinafter referred to as "the Securities"), to for the payment of liquidated damages for the delay.16
wit: Standby Letter of Credit No. E001126/8400 with the local branch of
respondent Australia and New Zealand Banking Group Limited (ANZ Bank)7and
Standby Letter of Credit No. IBDIDSB-00/4 with respondent Security Bank On 5 November 2000, petitioner as plaintiff filed a Complaint for Injunction,
Corporation (SBC)8 each in the amount of US$8,988,907.00.9 with prayer for temporary restraining order and writ of preliminary injunction,
against herein respondents as defendants before the Regional Trial Court (RTC)
of Makati.17 Petitioner sought to restrain respondent LHC from calling on the However, the appellate court failed to act on the application for preliminary
Securities and respondent banks from transferring, paying on, or in any manner injunction until the temporary restraining order expired on 27 January 2001.
disposing of the Securities or any renewals or substitutes thereof. The RTC Immediately thereafter, representatives of LHC trooped to ANZ Bank and
issued a seventy-two (72)-hour temporary restraining order on the same day. withdrew the total amount of US$4,950,000.00, thereby reducing the balance in
The case was docketed as Civil Case No. 00-1312 and raffled to Branch 148 of ANZ Bank to US$1,852,814.00.
the RTC of Makati.
On 2 February 2001, the appellate court dismissed the petition for certiorari.
After appropriate proceedings, the trial court issued an Order on 9 November The appellate court expressed conformity with the trial court's decision that
2000, extending the temporary restraining order for a period of seventeen (17) LHC could call on the Securities pursuant to the first principle in credit law that
days or until 26 November 2000.18 the credit itself is independent of the underlying transaction and that as long as
the beneficiary complied with the credit, it was of no moment that he had not
The RTC, in its Order19 dated 24 November 2000, denied petitioner's complied with the underlying contract. Further, the appellate court held that
application for a writ of preliminary injunction. It ruled that petitioner had no even assuming that the trial court's denial of petitioner's application for a writ
legal right and suffered no irreparable injury to justify the issuance of the writ. of preliminary injunction was erroneous, it constituted only an error of
Employing the principle of "independent contract" in letters of credit, the trial judgment which is not correctible by certiorari, unlike error of jurisdiction.
court ruled that LHC should be allowed to draw on the Securities for liquidated
damages. It debunked petitioner's contention that the principle of "independent Undaunted, petitioner filed the instant Petition for Review raising the following
contract" could be invoked only by respondent banks since according to it issues for resolution:
respondent LHC is the ultimate beneficiary of the Securities. The trial court
further ruled that the banks were mere custodians of the funds and as such they WHETHER THE "INDEPENDENCE PRINCIPLE" ON LETTERS OF
were obligated to transfer the same to the beneficiary for as long as the latter CREDIT MAY BE INVOKED BY A BENEFICIARY THEREOF WHERE THE
could submit the required certification of its claims. BENEFICIARY'S CALL THEREON IS WRONGFUL OR FRAUDULENT.

Dissatisfied with the trial court's denial of its application for a writ of WHETHER LHC HAS THE RIGHT TO CALL AND DRAW ON THE
preliminary injunction, petitioner elevated the case to the Court of Appeals via SECURITIES BEFORE THE RESOLUTION OF PETITIONER'S AND LHC'S
a Petition for Certiorari under Rule 65, with prayer for the issuance of a DISPUTES BY THE APPROPRIATE TRIBUNAL.
temporary restraining order and writ of preliminary injunction.20 Petitioner
submitted to the appellate court that LHC's call on the Securities was premature WHETHER ANZ BANK AND SECURITY BANK ARE JUSTIFIED IN
considering that the issue of its default had not yet been resolved with finality RELEASING THE AMOUNTS DUE UNDER THE SECURITIES DESPITE
by the CIAC and/or the ICC. It asserted that until the fact of delay could be BEING NOTIFIED THAT LHC'S CALL THEREON IS WRONGFUL.
established, LHC had no right to draw on the Securities for liquidated damages.
WHETHER OR NOT PETITIONER WILL SUFFER GRAVE AND
Refuting petitioner's contentions, LHC claimed that petitioner had no right to IRREPARABLE DAMAGE IN THE EVENT THAT:
restrain its call on and use of the Securities as payment for liquidated damages.
It averred that the Securities are independent of the main contract between
them as shown on the face of the two Standby Letters of Credit which both A. LHC IS ALLOWED TO CALL AND DRAW ON, AND ANZ BANK
provide that the banks have no responsibility to investigate the authenticity or AND SECURITY BANK ARE ALLOWED TO RELEASE, THE
accuracy of the certificates or the declarant's capacity or entitlement to so REMAINING BALANCE OF THE SECURITIES PRIOR TO THE
certify. RESOLUTION OF THE DISPUTES BETWEEN PETITIONER AND
LHC.
In its Resolution dated 28 November 2000, the Court of Appeals issued a
temporary restraining order, enjoining LHC from calling on the Securities or any B. LHC DOES NOT RETURN THE AMOUNTS IT HAD
renewals or substitutes thereof and ordering respondent banks to cease and WRONGFULLY DRAWN FROM THE SECURITIES.21
desist from transferring, paying or in any manner disposing of the Securities.
Petitioner contends that the courts below improperly relied on the "Transfield Philippines, Inc. v. Luzon Hydro Corporation" before Branch 56 of
"independence principle" on letters of credit when this case falls squarely the RTC of Makati, which is an action to enforce and obtain execution of the ICC's
within the "fraud exception rule." Respondent LHC deliberately misrepresented partial award mentioned in petitioner's Manifestation of 12 April 2004.
the supposed existence of delay despite its knowledge that the issue was still
pending arbitration, petitioner continues. In its Comment to petitioner's Motion for Leave to File Addendum to
Petitioner's Memorandum, LHC stresses that the question of whether the funds
Petitioner asserts that LHC should be ordered to return the proceeds of the it drew on the subject letters of credit should be returned is outside the issue in
Securities pursuant to the principle against unjust enrichment and that, under this appeal. At any rate, LHC adds that the action to enforce the ICC's partial
the premises, injunction was the appropriate remedy obtainable from the award is now fully within the Makati RTC's jurisdiction in Civil Case No. 04-332.
competent local courts. LHC asserts that petitioner is engaged in forum-shopping by keeping this appeal
and at the same time seeking the suit for enforcement of the arbitral award
On 25 August 2003, petitioner filed a Supplement to the Petition 22 and before the Makati court.
Supplemental Memorandum,23 alleging that in the course of the proceedings in
the ICC Arbitration, a number of documentary and testimonial evidence came Respondent SBC in its Memorandum, dated 10 March 200327 contends that the
out through the use of different modes of discovery available in the ICC Court of Appeals correctly dismissed the petition for certiorari. Invoking the
Arbitration. It contends that after the filing of the petition facts and admissions independence principle, SBC argues that it was under no obligation to look into
were discovered which demonstrate that LHC knowingly misrepresented that the validity or accuracy of the certification submitted by respondent LHC or into
petitioner had incurred delays notwithstanding its knowledge and admission the latter's capacity or entitlement to so certify. It adds that the act sought to be
that delays were excused under the Turnkey Contractto be able to draw enjoined by petitioner was already fait accompli and the present petition would
against the Securities. Reiterating that fraud constitutes an exception to the no longer serve any remedial purpose.
independence principle, petitioner urges that this warrants a ruling from this
Court that the call on the Securities was wrongful, as well as contrary to law and In a similar fashion, respondent ANZ Bank in its Memorandum dated 13 March
basic principles of equity. It avers that it would suffer grave irreparable damage 200328 posits that its actions could not be regarded as unjustified in view of the
if LHC would be allowed to use the proceeds of the Securities and not ordered prevailing independence principle under which it had no obligation to ascertain
to return the amounts it had wrongfully drawn thereon. the truth of LHC's allegations that petitioner defaulted in its obligations.
Moreover, it points out that since the Standby Letter of Credit No.
In its Manifestation dated 8 September 2003,24 LHC contends that the E001126/8400 had been fully drawn, petitioner's prayer for preliminary
supplemental pleadings filed by petitioner present erroneous and misleading injunction had been rendered moot and academic.
information which would change petitioner's theory on appeal.
At the core of the present controversy is the applicability of the "independence
In yet another Manifestation dated 12 April 2004,25 petitioner alleges that on 18 principle" and "fraud exception rule" in letters of credit. Thus, a discussion of
February 2004, the ICC handed down its Third Partial Award, declaring that the nature and use of letters of credit, also referred to simply as "credits," would
LHC wrongfully drew upon the Securities and that petitioner was entitled to the provide a better perspective of the case.
return of the sums wrongfully taken by LHC for liquidated damages.
The letter of credit evolved as a mercantile specialty, and the only way to
LHC filed a Counter-Manifestation dated 29 June 2004,26 stating that understand all its facets is to recognize that it is an entity unto itself. The
petitioner's Manifestation dated 12 April 2004 enlarges the scope of its Petition relationship between the beneficiary and the issuer of a letter of credit is not
for Review of the 31 January 2001 Decision of the Court of Appeals. LHC notes strictly contractual, because both privity and a meeting of the minds are lacking,
that the Petition for Review essentially dealt only with the issue of whether yet strict compliance with its terms is an enforceable right. Nor is it a third-party
injunction could issue to restrain the beneficiary of an irrevocable letter of beneficiary contract, because the issuer must honor drafts drawn against a
credit from drawing thereon. It adds that petitioner has filed two other letter regardless of problems subsequently arising in the underlying contract.
proceedings, to wit: (1) ICC Case No. 11264/TE/MW, entitled "Transfield Since the bank's customer cannot draw on the letter, it does not function as an
Philippines Inc. v. Luzon Hydro Corporation," in which the parties made claims assignment by the customer to the beneficiary. Nor, if properly used, is it a
and counterclaims arising from petitioner's performance/misperformance of contract of suretyship or guarantee, because it entails a primary liability
its obligations as contractor for LHC; and (2) Civil Case No. 04-332, entitled following a default. Finally, it is not in itself a negotiable instrument, because it
is not payable to order or bearer and is generally conditional, yet the draft which govern the legal complexities arising from transactions involving letters
presented under it is often negotiable.29 of credit, not only between or among banks themselves but also between banks
and the seller or the buyer, as the case may be, the applicability of the UCP is
In commercial transactions, a letter of credit is a financial device developed by undeniable.
merchants as a convenient and relatively safe mode of dealing with sales of
goods to satisfy the seemingly irreconcilable interests of a seller, who refuses to Article 3 of the UCP provides that credits, by their nature, are separate
part with his goods before he is paid, and a buyer, who wants to have control of transactions from the sales or other contract(s) on which they may be based
the goods before paying.30 The use of credits in commercial transactions serves and banks are in no way concerned with or bound by such contract(s), even if
to reduce the risk of nonpayment of the purchase price under the contract for any reference whatsoever to such contract(s) is included in the credit.
the sale of goods. However, credits are also used in non-sale settings where they Consequently, the undertaking of a bank to pay, accept and pay draft(s) or
serve to reduce the risk of nonperformance. Generally, credits in the non-sale negotiate and/or fulfill any other obligation under the credit is not subject to
settings have come to be known as standby credits.31 claims or defenses by the applicant resulting from his relationships with the
issuing bank or the beneficiary. A beneficiary can in no case avail himself of the
There are three significant differences between commercial and standby contractual relationships existing between the banks or between the applicant
credits. First, commercial credits involve the payment of money under a and the issuing bank.
contract of sale. Such credits become payable upon the presentation by the
seller-beneficiary of documents that show he has taken affirmative steps to Thus, the engagement of the issuing bank is to pay the seller or beneficiary of
comply with the sales agreement. In the standby type, the credit is payable upon the credit once the draft and the required documents are presented to it. The
certification of a party's nonperformance of the agreement. The documents that so-called "independence principle" assures the seller or the beneficiary of
accompany the beneficiary's draft tend to show that the applicant has not prompt payment independent of any breach of the main contract and precludes
performed. The beneficiary of a commercial credit must demonstrate by the issuing bank from determining whether the main contract is actually
documents that he has performed his contract. The beneficiary of the standby accomplished or not. Under this principle, banks assume no liability or
credit must certify that his obligor has not performed the contract.32 responsibility for the form, sufficiency, accuracy, genuineness, falsification or
legal effect of any documents, or for the general and/or particular conditions
By definition, a letter of credit is a written instrument whereby the writer stipulated in the documents or superimposed thereon, nor do they assume any
requests or authorizes the addressee to pay money or deliver goods to a third liability or responsibility for the description, quantity, weight, quality,
person and assumes responsibility for payment of debt therefor to the condition, packing, delivery, value or existence of the goods represented by any
addressee.33 A letter of credit, however, changes its nature as different documents, or for the good faith or acts and/or omissions, solvency,
transactions occur and if carried through to completion ends up as a binding performance or standing of the consignor, the carriers, or the insurers of the
contract between the issuing and honoring banks without any regard or goods, or any other person whomsoever.39
relation to the underlying contract or disputes between the parties thereto. 34
The independent nature of the letter of credit may be: (a) independence in toto
Since letters of credit have gained general acceptability in international trade where the credit is independent from the justification aspect and is a separate
transactions, the ICC has published from time to time updates on the Uniform obligation from the underlying agreement like for instance a typical standby; or
Customs and Practice (UCP) for Documentary Credits to standardize practices (b) independence may be only as to the justification aspect like in a commercial
in the letter of credit area. The vast majority of letters of credit incorporate the letter of credit or repayment standby, which is identical with the same
UCP.35 First published in 1933, the UCP for Documentary Credits has undergone obligations under the underlying agreement. In both cases the payment may be
several revisions, the latest of which was in 1993.36 enjoined if in the light of the purpose of the credit the payment of the credit
would constitute fraudulent abuse of the credit.40
In Bank of the Philippine Islands v. De Reny Fabric Industries, Inc., 37 this Court
ruled that the observance of the UCP is justified by Article 2 of the Code of Can the beneficiary invoke the independence principle?
Commerce which provides that in the absence of any particular provision in the
Code of Commerce, commercial transactions shall be governed by usages and Petitioner insists that the independence principle does not apply to the instant
customs generally observed. More recently, in Bank of America, NT & SA v. case and assuming it is so, it is a defense available only to respondent banks.
Court of Appeals,38 this Court ruled that there being no specific provisions LHC, on the other hand, contends that it would be contrary to common sense to
deny the benefit of an independent contract to the very party for whom the Professor John F. Dolan, the noted authority on letters of credit, sheds more light
benefit is intended. As beneficiary of the letter of credit, LHC asserts it is entitled on the issue:
to invoke the principle.
The standby credit is an attractive commercial device for many of the
As discussed above, in a letter of credit transaction, such as in this case, where same reasons that commercial credits are attractive. Essentially, these
the credit is stipulated as irrevocable, there is a definite undertaking by the credits are inexpensive and efficient. Often they replace surety
issuing bank to pay the beneficiary provided that the stipulated documents are contracts, which tend to generate higher costs than credits do and are
presented and the conditions of the credit are complied with. 41 Precisely, the usually triggered by a factual determination rather than by the
independence principle liberates the issuing bank from the duty of ascertaining examination of documents.
compliance by the parties in the main contract. As the principle's nomenclature
clearly suggests, the obligation under the letter of credit is independent of the Because parties and courts should not confuse the different functions
related and originating contract. In brief, the letter of credit is separate and of the surety contract on the one hand and the standby credit on the
distinct from the underlying transaction. other, the distinction between surety contracts and credits merits some
reflection. The two commercial devices share a common purpose. Both
Given the nature of letters of credit, petitioner's argumentthat it is only the ensure against the obligor's nonperformance. They function, however,
issuing bank that may invoke the independence principle on letters of credit in distinctly different ways.
does not impress this Court. To say that the independence principle may only
be invoked by the issuing banks would render nugatory the purpose for which Traditionally, upon the obligor's default, the surety undertakes to
the letters of credit are used in commercial transactions. As it is, the complete the obligor's performance, usually by hiring someone to
independence doctrine works to the benefit of both the issuing bank and the complete that performance. Surety contracts, then, often involve costs
beneficiary. of determining whether the obligor defaulted (a matter over which the
surety and the beneficiary often litigate) plus the cost of performance.
Letters of credit are employed by the parties desiring to enter into commercial The benefit of the surety contract to the beneficiary is obvious. He
transactions, not for the benefit of the issuing bank but mainly for the benefit of knows that the surety, often an insurance company, is a strong financial
the parties to the original transactions. With the letter of credit from the issuing institution that will perform if the obligor does not. The beneficiary also
bank, the party who applied for and obtained it may confidently present the should understand that such performance must await the sometimes
letter of credit to the beneficiary as a security to convince the beneficiary to lengthy and costly determination that the obligor has defaulted. In
enter into the business transaction. On the other hand, the other party to the addition, the surety's performance takes time.
business transaction, i.e., the beneficiary of the letter of credit, can be rest
assured of being empowered to call on the letter of credit as a security in case The standby credit has different expectations. He reasonably expects
the commercial transaction does not push through, or the applicant fails to that he will receive cash in the event of nonperformance, that he will
perform his part of the transaction. It is for this reason that the party who is receive it promptly, and that he will receive it before any litigation with
entitled to the proceeds of the letter of credit is appropriately called the obligor (the applicant) over the nature of the applicant's
"beneficiary." performance takes place. The standby credit has this opposite effect of
the surety contract: it reverses the financial burden of parties during
Petitioner's argument that any dispute must first be resolved by the parties, litigation.
whether through negotiations or arbitration, before the beneficiary is entitled
to call on the letter of credit in essence would convert the letter of credit into a In the surety contract setting, there is no duty to indemnify the
mere guarantee. Jurisprudence has laid down a clear distinction between a beneficiary until the beneficiary establishes the fact of the obligor's
letter of credit and a guarantee in that the settlement of a dispute between the performance. The beneficiary may have to establish that fact in
parties is not a pre-requisite for the release of funds under a letter of credit. In litigation. During the litigation, the surety holds the money and the
other words, the argument is incompatible with the very nature of the letter of beneficiary bears most of the cost of delay in performance.
credit. If a letter of credit is drawable only after settlement of the dispute on the
contract entered into by the applicant and the beneficiary, there would be no
practical and beneficial use for letters of credit in commercial transactions.
In the standby credit case, however, the beneficiary avoids that payable by the Contractor shall in the aggregate not exceed 20% of the
litigation burden and receives his money promptly upon presentation Contract Price. The Contractor shall pay Liquidated Damages for Delay
of the required documents. It may be that the applicant has, in fact, for each day of the delay on the following day without need of demand
performed and that the beneficiary's presentation of those documents from the Employer.
is not rightful. In that case, the applicant may sue the beneficiary in tort,
in contract, or in breach of warranty; but, during the litigation to 8.7.2 The Employer may, without prejudice to any other method of
determine whether the applicant has in fact breached the obligation to recovery, deduct the amount of such damages from any monies due, or
perform, the beneficiary, not the applicant, holds the money. Parties to become due to the Contractor and/or by drawing on the Security."45
that use a standby credit and courts construing such a credit should
understand this allocation of burdens. There is a tendency in some A contract once perfected, binds the parties not only to the fulfillment of what
quarters to overlook this distinction between surety contracts and has been expressly stipulated but also to all the consequences which according
standby credits and to reallocate burdens by permitting the obligor or to their nature, may be in keeping with good faith, usage, and law. 46 A careful
the issuer to litigate the performance question before payment to the perusal of the Turnkey Contract reveals the intention of the parties to make the
beneficiary.42 Securities answerable for the liquidated damages occasioned by any delay on
the part of petitioner. The call upon the Securities, while not an exclusive
While it is the bank which is bound to honor the credit, it is the beneficiary who remedy on the part of LHC, is certainly an alternative recourse available to it
has the right to ask the bank to honor the credit by allowing him to draw upon the happening of the contingency for which the Securities have been
thereon. The situation itself emasculates petitioner's posture that LHC cannot proffered. Thus, even without the use of the "independence principle," the
invoke the independence principle and highlights its puerility, more so in this Turnkey Contract itself bestows upon LHC the right to call on the Securities in
case where the banks concerned were impleaded as parties by petitioner itself. the event of default.

Respondent banks had squarely raised the independence principle to justify Next, petitioner invokes the "fraud exception" principle. It avers that LHC's call
their releases of the amounts due under the Securities. Owing to the nature and on the Securities is wrongful because it fraudulently misrepresented to ANZ
purpose of the standby letters of credit, this Court rules that the respondent Bank and SBC that there is already a breach in the Turnkey Contract knowing
banks were left with little or no alternative but to honor the credit and both of fully well that this is yet to be determined by the arbitral tribunals. It asserts
them in fact submitted that it was "ministerial" for them to honor the call for that the "fraud exception" exists when the beneficiary, for the purpose of
payment.43 drawing on the credit, fraudulently presents to the confirming bank, documents
that contain, expressly or by implication, material representations of fact that
Furthermore, LHC has a right rooted in the Contract to call on the Securities. to his knowledge are untrue. In such a situation, petitioner insists, injunction is
The relevant provisions of the Contract read, thus: recognized as a remedy available to it.

4.2.1. In order to secure the performance of its obligations under this Citing Dolan's treatise on letters of credit, petitioner argues that the
Contract, the Contractor at its cost shall on the Commencement Date independence principle is not without limits and it is important to fashion those
provide security to the Employer in the form of two irrevocable and limits in light of the principle's purpose, which is to serve the commercial
confirmed standby letters of credit (the "Securities"), each in the function of the credit. If it does not serve those functions, application of the
amount of US$8,988,907, issued and confirmed by banks or financial principle is not warranted, and the commonlaw principles of contract should
institutions acceptable to the Employer. Each of the Securities must be apply.
in form and substance acceptable to the Employer and may be provided
on an annually renewable basis.44 It is worthy of note that the propriety of LHC's call on the Securities is largely
intertwined with the fact of default which is the self-same issue pending
8.7.1 If the Contractor fails to comply with Clause 8.2, the Contractor resolution before the arbitral tribunals. To be able to declare the call on the
shall pay to the Employer by way of liquidated damages ("Liquidated Securities wrongful or fraudulent, it is imperative to resolve, among others,
Damages for Delay") the amount of US$75,000 for each and every day whether petitioner was in fact guilty of delay in the performance of its
or part of a day that shall elapse between the Target Completion Date obligation. Unfortunately for petitioner, this Court is not called upon to rule
and the Completion Date, provided that Liquidated Damages for Delay upon the issue of defaultsuch issue having been submitted by the parties to
the jurisdiction of the arbitral tribunals pursuant to the terms embodied in their stipulations in the Turnkey Contract.55Indeed, the Turnkey Contract is plain and
agreement.47 unequivocal in that it conferred upon LHC the right to draw upon the Securities
in case of default, as provided in Clause 4.2.5, in relation to Clause 8.7.2, thus:
Would injunction then be the proper remedy to restrain the alleged wrongful
draws on the Securities? 4.2.5 The Employer shall give the Contractor seven days' notice of
calling upon any of the Securities, stating the nature of the default for
Most writers agree that fraud is an exception to the independence principle. which the claim on any of the Securities is to be made, provided that no
Professor Dolan opines that the untruthfulness of a certificate accompanying a notice will be required if the Employer calls upon any of the Securities
demand for payment under a standby credit may qualify as fraud sufficient to for the payment of Liquidated Damages for Delay or for failure by the
support an injunction against payment.48 The remedy for fraudulent abuse is an Contractor to renew or extend the Securities within 14 days of their
injunction. However, injunction should not be granted unless: (a) there is clear expiration in accordance with Clause 4.2.2.56
proof of fraud; (b) the fraud constitutes fraudulent abuse of the independent
purpose of the letter of credit and not only fraud under the main agreement; 8.7.2 The Employer may, without prejudice to any other method of
and (c) irreparable injury might follow if injunction is not granted or the recovery, deduct the amount of such damages from any monies due, or
recovery of damages would be seriously damaged.49 to become due, to the Contractor and/or by drawing on the Security.57

In its complaint for injunction before the trial court, petitioner alleged that it is The pendency of the arbitration proceedings would not per se make LHC's
entitled to a total extension of two hundred fifty-three (253) days which would draws on the Securities wrongful or fraudulent for there was nothing in the
move the target completion date. It argued that if its claims for extension would Contract which would indicate that the parties intended that all disputes
be found meritorious by the ICC, then LHC would not be entitled to any regarding delay should first be settled through arbitration before LHC would be
liquidated damages.50 allowed to call upon the Securities. It is therefore premature and absurd to
conclude that the draws on the Securities were outright fraudulent given the
Generally, injunction is a preservative remedy for the protection of one's fact that the ICC and CIAC have not ruled with finality on the existence of default.
substantive right or interest; it is not a cause of action in itself but merely a
provisional remedy, an adjunct to a main suit. The issuance of the writ of Nowhere in its complaint before the trial court or in its pleadings filed before
preliminary injunction as an ancillary or preventive remedy to secure the rights the appellate court, did petitioner invoke the fraud exception rule as a ground
of a party in a pending case is entirely within the discretion of the court taking to justify the issuance of an injunction.58 What petitioner did assert before the
cognizance of the case, the only limitation being that this discretion should be courts below was the fact that LHC's draws on the Securities would be
exercised based upon the grounds and in the manner provided by law.51 premature and without basis in view of the pending disputes between them.
Petitioner should not be allowed in this instance to bring into play the fraud
Before a writ of preliminary injunction may be issued, there must be a clear exception rule to sustain its claim for the issuance of an injunctive relief.
showing by the complaint that there exists a right to be protected and that the Matters, theories or arguments not brought out in the proceedings below will
acts against which the writ is to be directed are violative of the said right. 52It ordinarily not be considered by a reviewing court as they cannot be raised for
must be shown that the invasion of the right sought to be protected is material the first time on appeal.59 The lower courts could thus not be faulted for not
and substantial, that the right of complainant is clear and unmistakable and that applying the fraud exception rule not only because the existence of fraud was
there is an urgent and paramount necessity for the writ to prevent serious fundamentally interwoven with the issue of default still pending before the
damage.53 Moreover, an injunctive remedy may only be resorted to when there arbitral tribunals, but more so, because petitioner never raised it as an issue in
is a pressing necessity to avoid injurious consequences which cannot be its pleadings filed in the courts below. At any rate, petitioner utterly failed to
remedied under any standard compensation.54 show that it had a clear and unmistakable right to prevent LHC's call upon the
Securities.
In the instant case, petitioner failed to show that it has a clear and unmistakable
right to restrain LHC's call on the Securities which would justify the issuance of Of course, prudence should have impelled LHC to await resolution of the
preliminary injunction. By petitioner's own admission, the right of LHC to call pending issues before the arbitral tribunals prior to taking action to enforce the
on the Securities was contractually rooted and subject to the express Securities. But, as earlier stated, the Turnkey Contract did not require LHC to do
so and, therefore, it was merely enforcing its rights in accordance with the tenor
thereof. Obligations arising from contracts have the force of law between the One final point. LHC has charged petitioner of forum-shopping. It raised the
contracting parties and should be complied with in good faith. 60 More charge on two occasions. First, in its Counter-Manifestation dated 29 June
importantly, pursuant to the principle of autonomy of contracts embodied in 200466 LHC alleges that petitioner presented before this Court the same claim
Article 1306 of the Civil Code,61petitioner could have incorporated in its for money which it has filed in two other proceedings, to wit: ICC Case No.
Contract with LHC, a proviso that only the final determination by the arbitral 11264/TE/MW and Civil Case No. 04-332 before the RTC of Makati. LHC argues
tribunals that default had occurred would justify the enforcement of the that petitioner's acts constitutes forum-shopping which should be punished by
Securities. However, the fact is petitioner did not do so; hence, it would have to the dismissal of the claim in both forums. Second, in its Comment to Petitioner's
live with its inaction. Motion for Leave to File Addendum to Petitioner's Memorandum dated 8
October 2004, LHC alleges that by maintaining the present appeal and at the
With respect to the issue of whether the respondent banks were justified in same time pursuing Civil Case No. 04-332wherein petitioner pressed for
releasing the amounts due under the Securities, this Court reiterates that judgment on the issue of whether the funds LHC drew on the Securities should
pursuant to the independence principle the banks were under no obligation to be returnedpetitioner resorted to forum-shopping. In both instances,
determine the veracity of LHC's certification that default has occurred. Neither however, petitioner has apparently opted not to respond to the charge.
were they bound by petitioner's declaration that LHC's call thereon was
wrongful. To repeat, respondent banks' undertaking was simply to pay once the Forum-shopping is a very serious charge. It exists when a party repetitively
required documents are presented by the beneficiary. avails of several judicial remedies in different courts, simultaneously or
successively, all substantially founded on the same transactions and the same
At any rate, should petitioner finally prove in the pending arbitration essential facts and circumstances, and all raising substantially the same issues
proceedings that LHC's draws upon the Securities were wrongful due to the either pending in, or already resolved adversely, by some other court. 67 It may
non-existence of the fact of default, its right to seek indemnification for damages also consist in the act of a party against whom an adverse judgment has been
it suffered would not normally be foreclosed pursuant to general principles of rendered in one forum, of seeking another and possibly favorable opinion in
law. another forum other than by appeal or special civil action of certiorari, or the
institution of two or more actions or proceedings grounded on the same cause
Moreover, in a Manifestation,62 dated 30 March 2001, LHC informed this Court on the supposition that one or the other court might look with favor upon the
that the subject letters of credit had been fully drawn. This fact alone would other party.68 To determine whether a party violated the rule against forum-
have been sufficient reason to dismiss the instant petition. shopping, the test applied is whether the elements of litis pendentia are present
or whether a final judgment in one case will amount to res judicata in
another.69 Forum-shopping constitutes improper conduct and may be punished
Settled is the rule that injunction would not lie where the acts sought to be with summary dismissal of the multiple petitions and direct contempt of
enjoined have already become fait accompli or an accomplished or court.70
consummated act.63 In Ticzon v. Video Post Manila, Inc.64 this Court ruled that
where the period within which the former employees were prohibited from
engaging in or working for an enterprise that competed with their former Considering the seriousness of the charge of forum-shopping and the severity
employerthe very purpose of the preliminary injunction has expired, any of the sanctions for its violation, the Court will refrain from making any
declaration upholding the propriety of the writ would be entirely useless as definitive ruling on this issue until after petitioner has been given ample
there would be no actual case or controversy between the parties insofar as the opportunity to respond to the charge.
preliminary injunction is concerned.
WHEREFORE, the instant petition is DENIED, with costs against petitioner.
In the instant case, the consummation of the act sought to be restrained had
rendered the instant petition mootfor any declaration by this Court as to Petitioner is hereby required to answer the charge of forum-shopping within
propriety or impropriety of the non-issuance of injunctive relief could have no fifteen (15) days from notice.
practical effect on the existing controversy.65 The other issues raised by
petitioner particularly with respect to its right to recover the amounts SO ORDERED.
wrongfully drawn on the Securities, according to it, could properly be threshed
out in a separate proceeding.

Vous aimerez peut-être aussi