Académique Documents
Professionnel Documents
Culture Documents
Report No. 7
By
PANEL OF EXPERTS
To
September 2007
CONTENTS
1. Introduction 1
2. Engineers response to report No. 6 5
3. Project Status 6
4. ECRD 8
4.1 Status 8
4.2 Materials 8
4.3 Quality Control 10
4.4 Design and Construction Details 10
5. Dykes 11
5.1 Status 11
5.2 Design Modifications 11
6. Plastic Concrete Cut-Off Wall 12
6.1 Status 12
6.2 Quality Control 12
6.3 Filter Cake and Joints 13
6.4 Cushion Material 14
7. CFRD 18
7.1 Status 18
7.2 Quality Control 19
7.3 Construction Issues 20
7.4 Leakage 22
7.5 Parapet Wall 23
7.6 Performance 24
i
8. Concrete Structure 25
8.1 Status 26
8.2 Construction Schedule 28
8.3 Powerhouse Uplift 28
8.4 Blasting 29
8.5 Concrete Materials 30
9. Instrumentation 31
9.1 Status 31
9.2 Review of Data 32
9.3 Analysis of Data 32
9.4 Impoundment Monitoring Plan 33
9.5 Long-term Monitoring and Systems 35
10. Health, Safety and Environment 36
11. Diversion and Spillway Closure 37
11.1 Sequence 37
11.2 Design Issues 38
11.3 Construction Issues 39
12. Risk Management Plan 40
12.1 Risk Analysis 40
12.2 Risk Management Strategy 42
Appendices A
Appendices B
Appendices C
ii
1.0 INTRODUCTION
The 7th Panel of Experts (the Panel) meeting for the Merowe Dam Project
Dr. Ahmed El-Tayeb Ahmed, Convener and Resident Engineer (the RE)
Lahmeyer International (the Engineer) are consultants for final design and
construction. The construction contract for the civil works has been
Since the last visit of the Panel, the plastic concrete Cut-Off Wall has been
completed allowing the further raising of the ECRD. The spiral case
installation for Units 1 to 4 were finished and further installations for the
1
The bridge deck is progressing. The spillway weir body in Bay 8 was
finished and concreting to final shape will start shortly. At the time of the
last meeting it was evident that first power production would be delayed by
about one year. The current plan now anticipates first power from Units 1
The purpose of this 7th meeting of the Panel was to inspect the progress of
related to the dams. However the closure of the spillway bays will continue
through 2008 and it involves control of the 2008 flood by means of the
spillway which will be partially completed at the time. This raises a number
of technical and schedule-related issues that bear on the risk associated with
the Contractor's proposed diversion plan which departs from the contractual
river diversion concept. The assessment of this risk and its management
part.
2
Panelists Materon and Morgenstern arrived in Khartoum on the evening of
September 1 and the Panel traveled to the site the next morning. The
inspection. The delay in several parts of the project was apparent. On the
following three days, presentations were made to the Panel and discussions
three days the Panel returned to the field to inspect fill placement procedures
and to assess the trimming of downstream slopes in the rockfill of the CFRD
structures.
and submitted a draft copy for review on the morning of September 7. the
report was finalized that day and the Panel departed for Khartoum. The
particularly the Resident Engineer, and to the staff of the Engineer. All have
3
It has been agreed that the next meeting of the Panel will be convened on
this would be an optimal time to make the final assessment with respect to
the risk associated with the spillway closure scheme, as presently conceived.
4
2.0 ENGINEER'S RESPONSE TO REPORT NO. 6
The Panel had recommended that the Engineer develop an action plan in
pleased to receive the action plan arising from Panel Report No. 6. The
manner.
wells.
5/PI5/ECRD.
The Panel wishes to state that it does not agree with the position of the
5
3.0 PROJECT STATUS:
Engineer. Key events noted since the last visit of the panel are:
work for both concrete and embankment construction, indicating that the
capacity to meet his required production rates. This will have to change in a
demonstrable manner if the planned spillway closure and river diversion are
6
to proceed in a reliable manner. This is discussed in more detail in Section
12 below. There is, for all practical purposes, no float time planned in a
As before, the Engineer has identified severe limitations associated with the
Time is running out to effect change. The requirements of the project need to
in Section 12.
7
4.0 ECRD
4.1 Status
Limited portions of Zone 1 material could be placed since the last meeting of
the Panel in March, 2007 due to construction of the plastic concrete COW,
which was completed at the end of July, 2007. late construction of RW6 was
However, rockfill was placed in the ECRD during this last period and is now
on average at Elv. 267 (higher on the left side). About 73% of ECRD filling
is complete.
During this visit, the Panel observed the resumption of placement of core
4.2 Materials
The Panel was advised that sufficient Marwa sand has been stockpiled to
meet the needs of the ECRD and Dykes and that the dredging operation has
been terminated.
8
The Panel received a summary of material characterization data for Zone 1B
(Formerly Zone 13L) supporting the conclusion that the material is suitable
Area L had been initiated by the Engineer to ensure that sufficient volume of
material for Zones 1, 1.1, and 1B will be available in a timely manner. At the
time of the last Panel meeting preliminary projections were promising in that
established and with a careful assessment of fill volume bulking from in-situ
adequate to satisfy the material needs of the project. Vertical face mixing in
to the quality of the construction. This must continue. Stockpiles have been
established as required to meet future needs and the Engineer will continue
9
the careful monitoring of borrow area L activities in the manner conducted
to date.
The studies conducted in Borrow Area L provide highly positive results and
the Panel commends the study team for the quality of this undertaking.
the filter layout were presented. The Panel agrees with the proposal of the
Engineer.
Discussion was held on procedures adopted for contact zone compaction and
for managing temporary, access roads. The Panel supports the design and
future gypsum at contact zones can be restricted to only the outer 2m thick
zones.
10
5.0 DYKES
5.1 Status
Fill placement on the left bank dyke is about 25% complete. Some
foundation preparation remains to be done. No fill has been placed for the
right bank structure although the foundation area has been prepared. The
right bank is not critical and the ability to complete the left bank in a timely
placing Zone 1B have been proposed and the Panel agrees with them.
as shown in the current IFC drawing, a number of design changes have been
made to the sections for both left and right banks to improve
11
6.0 PLASTIC CONCRETE CUT-OFF WALL
6.1 Status
The excavation of the trial panel began on April 4, 2007. The COW
Panel congratulates all involved. The project was fortunate to have secured a
During excavation some weak zones were encountered in the rock and its
depth was extended in the event that these weak zones might be
the cutter verticality and the trench walls after excavations were monitored.
12
program. It was generally shown to behave as expected, in conformance
with the specifications and the design requirements. Detailed reports on wall
The Panel is satisfied that construction has been to a high standard and that
this is supported by the results from the extensive quality control program.
Prior to the construction of the COW a section of trial panels upstream of the
COW was constructed. Subsequent inspection of the top portion of the joints
in the trial panels discovered filter cakes of slurry between the primary and
secondary panels. The thickness was about 1cm. Similar joint filling was
also present in the top portion of the main COW where it had already been
installed.
minimize its occurrence and assessment whether the filter cake can
13
The depth of significant joint filling is limited to about 6m.
It likely arises due to delays in replacing slurry and due to higher than
cake.
In any case the filter cake material cannot pipe into any adjacent
material.
joint infilling. The infilled joints that have already been created are encased
in the core. The Engineer has concluded that the remnant infilled joints left
A cushion material (Zone 22) is introduced on top of the COW to protect the
core of the dam from cracking as it settles over the plastic concrete wall.
14
The Engineer has approved a mixture consisting of Nile silt and 20%
bentonite that is impervious and potentially suitable for use in Zone 22. It
has a small organic content. Procedures have been developed for blending
use. Laboratory tests indicate that the material is ductile and studies have
PI 50%
has been developed and are embraced in the method statement of the
Contractor.
15
From a practical perspective, the Panel is content that a suitable material has
However the project specifications required that the Zone 22 material have a
In Report No. 6 the Panel recommended that the stiffness ratio requirement
modeling.
demonstrate that the introduction of Zone 22 shields the core from potential
introduced into the model and the potential for local slip between the core
and the COW was also considered. The modeling was conducted with a high
degree of skill.
16
As an aside, the model prediction of foundation settlement predicts the trend
reliability of the model. The model also illustrates how yielding and any
potential for cracking are reduced by the presence of the cushion material as
a result of its enhanced ductility. The Engineer concludes that the Zone 22
material is fit for purpose and the Panel agrees with this conclusion. Careful
control in the stockpile and as-placed in the dam will have to be maintained.
The Engineer also noted that instrumentation at and near the top of the COW
17
7. CFRD
7.1 Status
Very low progress has been reported for rock fill placing at the left
abutment. Only 200,000 m3 were placed since the past Panel visit in March,
At the right bank 600,000 m3 were placed for a total of 3 million. m3.
both banks has affected the placing of rockfill, since the inclined ramping to
The irrigation structures at the left bank is 55% complete and in the right
bank is almost complete but no activity was observed during the field
inspection.
Construction of the Face slab is 40% complete at the left bank and 75% at
the right bank. An analysis presented by the Engineer indicates that the
CFRD is becoming on the critical path due to the very low progress during
the past 8 months The Panel recommends again to analyze the progress of
18
these structures with the Contractor aiming to speed up the works in the
Quality of the rockfill is very well controlled and the results presented
The Panel is pleased with the quality control and results for the CFRD
materials.
19
7.3 Construction Issues
as follows:
Left Bank:
Trim and compose the fill close to the transition wall located at 6+217
approximately.
Trim and replace fine fockfill where the temporary access was placed.
Repair zone close to 7+807 where a temporary access was located in area
IV.
Build the rockfill at each side of the IOL (7+324) with rockfill giving similar
Right Bank:
20
IOL structure 3+150 approximately, build and repair the slope of areas IV
Trim the remainder of the fill which has been completed to El. 300.8
The specifications for the outer zone materials differ between the ECRD and
the CFRD. Accordingly, the Engineer has developed guidelines for the slope
finish requirement in accordance with the specification for the outer zones.
Although this work has not high priority the Panel would like to see positive
partially the rockfill at the right abutment, against the spillway wall located
at 4+814 approximately.
This is technically feasible and will help to give access to build the face slab
in this zone. The Panel has no objection to this procedure, providing that all
21
It is common practice to inspect the face slab recording cracks or retraction
fissures before impoundment. Since the face slab is very long it is wise to
start inspecting the face recording areas where the fissures exceeds 0.3mm.
Generally fissures wider than 0.3mm are treated with epoxy or non-
7.4 Leakage
There are some points at the right abutment where piezometers have been
installed to monitor the position of the water level downstream of the face
slab.
Readings at 4+220 and 4+390 indicate some potential pressure over the
slab, when the slab is built. The Panel recommends continuing monitoring
these piezometers to register the position of the water table. During the
release any potential back pressure, which may affect the behaviour of the
slab.
22
The number of holes will be duly registered and plugged before applying
leakage zones.
face rockfill dam, shows the alternative of building the parapet wall with the
Pre-cast parapets have been built in other dams to speed up construction and
release the Contractor to place concrete at the end of the job when
The Contractor has proposed to cast the vertical piece of the parapet wall
23
The Panel has no objection to this procedure although it visualizes that this
pour will be time consuming due to the length of the CFRD in both
7.6 Performance
During this meeting records were presented of the settlement plates located
Settlement plates are stable, showing very low creep of the rockfill for a
constant load.
Modulus of compressibility for the rockfill of areas VI, VII of the right bank,
Modulus of compressibility for the rockfill of area II, of left bank are giving
erratic very high values, but those located at 6+650 are ranging between 50-
150MPa.
24
In general the appearance of the face slab is very good with low presence of
The Panel is pleased with the performance of the fill from the view point of
25
8. CONCRETE STRUCTURES
8.1 Status
Power Intake.
Power House.
Non-overflow Dam.
Spillway.
Retaining Walls.
Power Intake:
Concrete has been raised up to Elv. 278/281 upstream and Elv. 269/281
downstream.
Power House
completed and concrete progressed from Elv. 227 (March) to Elv. 239 in
all units.
26
Non-Overflow Dam
Spillway:
The irrigation outlet at the left bank was 55% complete. Progress has
been slow.
Transition Structure:
The structure between the ECRD and left bank CFRD remains to be
completed.
Retaining Walls:
m3 have been completed which represents more than 75% of the total
volume.
27
8.2 Construction Schedule
progress is compared with the revised Baseline Schedule (Nov. 06) some
Embankments 3 months.
safety were computed against the uplift for different stages of construction
The critical situation appears when the stability is checked for overturning.
For some load cases the resultant force migrates out of the middle third of
28
The Panel observed the theoretical criteria applied for computing the uplift
pressure and believes that the efficiency of the drainage and grouting could
the grout curtain and the drainage gallery, during the construction of Blocks
4 and 5.
The reservoir level of 285 should be investigated as well as Elv. 290. If the
reduction in uplift forces are not enough to meet the requirements of stability
evaluated.
8.4 Blasting
A careful method statement for removal the cofferdam and rock excavation
29
concrete structures. Particle velocities should be well defined according to
the age of the concrete and the distance of the required blasting. The Panel
safe particle velocity, for the removal of this rock close to the concrete
structures. The Panel recommends that small blasts be used at the outset to
confirm control.
A report about concrete quality control was presented to the Panel during the
control of the batching plants have continued and the records indicate good
pre-stressed steel anchors were not accepted by the Engineer due to failure
30
9.0 INSTRUMENTATION
9.1 Status
The Panel was advised on the status of the installation and its quality.
A careful audit procedure reviews all steps in the installation process. There
31
9.2 Review of Data
At this time measurements are usually made once every 10 days by the
Engineer has identified the main problems associated with taking the
measurements. The Panel was pleased to learn that all data/observations are
For the embankment dams, the Engineer is comparing measured data with
modulus values, water levels and pore water pressures. The Panel
performance reports.
32
The Panel is concerned that observation on the efficiency of the COW
cannot be made and evaluated due to interference from pumping wells. The
For the concrete structures, the Panel has been advised that the Engineer will
discharge, after the 2007 summer flow. The Panel looks forward to receiving
galleries.
following spillway closure and the 2008 summer flow, when the structures
33
A 20m rise will occur between July and September. This is a challenging
The draft Plan is well-conceived and the Panel commends the effort made by
the Engineer. The following comments are presented to guide the revision of
the draft:
appropriate response?
the event that an emergency occurs; while there does not appear to
of assistance.
34
9.5 Long-term Monitoring and Systems
must be accomplished with high quality to ensure the long-term safety and
operations at Merowe and the provisions being made within it to assure dam
safety.
35
10. HEALTH, SAFETY AND ENVIRONMENT
Five NCR were issued related with better accommodation, system of water
These NCR were sent to the Contractor indicating the target date to
The Panel is pleased to register the positive action from DIU and the
Engineer to request these actions which benefit the execution of the contract.
36
11. DIVERSION AND SPILLWAY CLOSURE
11.1 Sequence
discussed during the Panel meeting. The sequence follows the spillway
Engineer.
The drawings show clearly the position of the stop logs to allow the
construction of the weirs, during the remaining months of 2007 and the
beginning of 2008.
The situation becomes critical in May 2008 when the water level jumps from
about Elv. 260 to about Elv. 271 over passing the stop logs placed in weir
During the increase of flow in the river it is foreseen that additional stop logs
a head of about 30m will develop over the stop log closure. The Panel has
been advised that the spillway closure concept as proposed by the Contractor
37
has not been approved by the Engineer pending receipt of further
information.
To the knowledge of the Panel, managing such high flows over the stop logs
assess aeration and to evaluate the effects of energy dissipation which can be
in the order of 180-200 MW. Additional analysis in support of the design are
needed. The Engineer should approve both the technical design of the model
Since the handling of the river through the partially completed spillway,
over the stop logs is an important and critical issue, the Panel recommends
38
11.3 Construction Issues
The construction of the Ogee profile of each weir has been proposed by slip
forming. This method has been used in other projects with success. An early
start is recommended.
39
12. RISK MANAGEMENT PLAN
The spillway closure diversion involves both technical risk and schedule
risk. Technical risk arises from the extreme case of passing large floods over
Schedule risk has been of concern to the project and the Panel for some time.
example, excessive delay in the Power Intake as the ECRD could result in
further year delay of power production. Hence, every effort must be made to
The Engineer has updated the risk management plan associated with the
40
Contractor in Method Statement No. 82, Revision B. There has been no
change in the simulation model and the hydrological data inputs previously
Based on the new risk analysis and the construction progress forecast by the
Contractor for all structures, the 2008 milestones if honoured, the risk
any of the structures could alter this perspective and therefore it is necessary
the implications of excessive delay. At this time the Panel is not optimistic
productivity.
Hence, the project may face the prospect of aborting the diversion plan for
41
12.2 Risk Management Strategy
ii) Maintain detailed construction records for all fronts with emphasis
on production rates.
productivity.
forward.
The Panel notes that many Stakeholders are involved in such a risk related
decision but the ultimate responsibility for accepting risk following a critical
42
Respectfully submitted,
43
Presidency of the Republic
DAMS IMPLEMENTATION UNIT
KHARTOUM, SUDAN
AGENDA
September 2007
0
Republic of the Sudan
Presidency of the Republic
DAMS IMPLEMINTATION UNIT
AGENDA
Item Topic Time Details Presenter
Day 1 Sunday 02.09.07
Arrival of participants at 7:00
Merowe Airport
Page 1 of 13
Item Topic Time Details Presenter
Day 2 Monday 03.09.07
Actions of Panel (6) 8:30 9:00
Meetings
5 PROJECT STATUS 9:00 10:30
6.1 Design
6.2 Materials
Page 2 of 13
Item Topic Time Details Presenter
Page 3 of 13
Item Topic Time Details Presenter
7.4 Filters materials, stockpiles, construction aspects
7.5 QC
Page 4 of 13
Item Topic Time Details Presenter
8.1 Trial Panels Report Trial panels findings and application to real
construction
Page 5 of 13
Item Topic Time Details Presenter
8.3 Analysis and Comparison of As-Built record, volume of concrete in panel
Bedrock as detected by the Vs. apparent volume of excavation; KODEN
Cutter and that obtained results week rock zones; incidents of steep
from the previous geological bedrock profiles, depths of rock penetration
investigations.
Page 6 of 13
Item Topic Time Details Presenter
8.9 Review of effects of sharing Effects of waiting times:
batching plant Between excavation and concreting;
During concreting;
Between casting primary and
secondary panels
8.12 Results of Non-linear FEA 17:00 19:00 Using the actual parameters, including
cushion on top of the wall, modeling of
joints and cake
Page 7 of 13
Item Topic Time Details Presenter
9.3 D/S Slope Trimming and adjustment, method of
construction, materials appearance, further
treatment.
9.5 QC
9.8 Filling on top of the plinth Timing and sequence in relation to water
rise
Page 8 of 13
Item Topic Time Details Presenter
Page 9 of 13
Item Topic Time Details Presenter
11 HEALTH SAFETY AND 14:30 15:30
ENVIRONMENTAL
11.1 Safety Issues
11.2 Environment Issues
11.3 Plans for Improvements
Page 10 of 13
Item Topic Time Details Presenter
14.2.1 ECRD
Page 11 of 13
Item Topic Time Details Presenter
14.2 Gaps of Left IO
14.2.3 Gap of CFRD
near transition structure
14.2.4 Power Intake gates
14.2.5 Spillway Gates
Page 12 of 13
Item Topic Time Details Presenter
Page 13 of 13
MD Interim Report on Plastic Concrete QC, Cover Page.doc
CCMD MS and Report on Zone 22 Embankment Trial, Cover
Page.doc
CCMD PoE Handouts Content List TE.doc
CCMD QC Interim Report on Plastic Concrete, 15 Aug.2007,
Cover page.doc
CCMD Report on Zone 1B (13L), Cover Page.doc
CCMD Report on Zone 22 Embankment Trial, Cover Page.doc
Joints in the COW, Prof. Brauns' Report, Cover Page.doc
PPP COW Construction,Handout TE.ppt
PPP COW Lab QC, Handout.ppt
PPP Zone 13 Solubility.ppt
PPP Zone 1B Air Shrinkage, TE.ppt
PPP Zone 22 Cushion Material for PoE No.7, Sept.2007,
Handout.ppt
QC Plastic concrete monthly interim report(15 Aug. 2007).doc
Solubility Zone 13L, Cover Page.doc
Technical Memorandium Solubility.TIF
Zone 13L PoE No. 6, CVI D-35 Test report(Add air voids
added).doc
Zone 1B Air Shrinkage CVI D-56 Test report(draft-add air
voids).doc
30-08-07 fe-report_fd.pdf
handout - ecrd progress.pdf
Concrete Graph Aug07.jpg
Concrete Graph Aug07.pdf
Concrete Graph Aug07.xls
Excavation Graph Aug07.xls
Filling Graph Aug07.xls
Intake Bar chart.jpg
Intake Bar chart.pdf
Plan_vs_Actual_Aug07.xls
Powerhouse and Intake Bar chart.pdf
Powerhouse and Intake Bar chart.xls
Powerhouse Bar chart.jpg
Powerhouse Bar chart.pdf
Presentation POE7 with revised page.ppt
Progress comparison BS vs Actual - Aug07 - Concrete.jpg
Progress comparison BS vs Actual - Aug07 - Concrete.pdf
Progress comparison BS vs Actual - Aug07 - Filling.jpg
Progress comparison BS vs Actual - Aug07 - Filling.pdf
Progress comparison BS vs Actual - Aug07.pdf
Progress comparison BS vs Actual - Aug07.xls
Spillway Closure Bar chart.jpg
Spillway Closure Bar chart.pdf
Spillway Closure Bar chart.xls
Summary Quantities - Progress status End Aug07.xls
Spillway Closure Scheme - MS82 Rev B
Project Status
Presentation Spillway closure.ppt
updated_risk_management_plan_gwjm070902.ppt
Updated_Risk_Management_Plan_
Attendees of the Panel of Expert No. 7
Page 1 of 2
30. Eng. Ali Mohammed Ali DIU
31. Eng. Saif Eldin Mohamed Elmahi DIU
32. Eng. Yasir Elmahi Hassan DIU
33. Eng. Musab Mokhtar DIU
34. Eng. Abd Elrahman Saghayroun DIU
Page 2 of 2