Vous êtes sur la page 1sur 5

VAPOUR COMPRESSION

REFRIGERATION TEST RIG


Experimental Procedure:
Put the main Switch on.
Start the Condenser fan and wait for 5
minutes.
Switch ON Compressor.
Start the Evaporator fan.
Wait for 45 minutes to achieve steady state
condition.
Meassure time for 10 flashes of enrgy meter for
compresser.
Note down the reading in observation table.
REFRIGERATION TEST RIG
Experimental Procedure:
Put the main Switch on.
Start the water pump.
Start the Condenser fan and wait for 5
minutes.
Switch ON Compressor.
Wait for 45 minutes to achieve steady state
condition.
Meassure time for 10 flashes of enrgy
meter for compresser.
Note down the reading in observation table.
ICE PLANT TEST RIG
Experimental Procedure:
Check the Brine in the tank.
Fill the water in the ice can up to line mark.
Load the ice can on the frame.
Put the main Switch on.
Start the water pump.
Start the Condenser fan and wait for 5
minutes.
Switch ON Compressor.
Wait for 2-3 hours to achieve steady state
condition.
Meassure time for 10 flashes of enrgy meter
for compresser.
Note down the reading in observation table.
AIR CONDITIONER
TEST RIG.
Experimental Procedure:
Switch ON the power supply of unit and start
the duct fan.
Start the Condenser fan and wait for 5
minutes.
Switch ON Compressor and the flow of
liquid refrigerant will observed in the
rotameter.
Wait for 45 minutes to achieve steady state
condition.
Meassure time for 10 flashes of enrgy meter for
compresser.
Note down the reading in observation table.
For different processes start different
component and switch that after reading.
VAPOUR ABSORPTION
REFRIGERATION TEST RIG.
Experimental Procedure:
Put the main Switch on.
Switch ON generator.
Wait for 45 minutes to achieve steady state
condition.
Meassure time for 10 flashes of enrgy meter for
Heater/Generator.
Note down the reading in observation table.