Construction Progress
The details of construction progress is tabulated on Appendix A

1.1. Problems and Disruption During Reporthing Month


The major issues of some disruption and problems during reporting period are
as mentioned below:

1. Design of P163 and P164 to accommodate road lanes as required by


Dinas Bina Marga
2. Shifting the BTS Tower due to P163 new design
3. Escalator 1 of KGM Station located near the Trafo Box of RW 18 and need
to adjust its door type
4. Letter from Hotman Paris who seems unhappy with the location of KGM
Station entrance in front of his office-store

1.2. Action Plan


1. Sent the proposed layout of new borepile, pilecap & column position to the
designer and keep chase
2. Coordinate with MMI, JakPro and BTS Tower Owner
3. Coordinate with MMI, JakPro and PLN and proposed to changed the door
type to accommodate during trafo box maintenance
4. Reply his letter and explain if the entrance position are still within the RoW
(not exceed his parking area). WIKA also had given socialization to the
residents and office-store owners nearby before starting the constructions.
1.3. Summary Man Power
The details of Summary Man Power is tabulated on Appendix B

1.4. Plan and Equipment on Site


The details of Plan and Equipment on Site is tabulated on Appendix C
2. Executive Summary
This progress report presents the progress of the Contruction of LRT Jakarta Corridor
1 (Phase1): Kelapa Gading Velodrome, Package P102: Main Works as of June 25th,
2017.

2.1. Summary of Major Events

NO DESCRIPTION LOCATION/REMARKS

1 Soil Investigation

2 Surveying Activities still on going to section 5 and, refer


to design submission

3 Mobilization of Bored Pile Machine

4 Mobilization of Service Crane Up to June 20th, 2017, Total Service Crane


mobilized are 4 Crane, spread to Section 5

5 Mobilization of Silo - Section 5

6 Installation of Silo - Section 5


Up to June 20th, 2017, Total Sully Silo setting
are 1 Silo, spread to Section 5.

7 Bored Pile Total Bored Pile have been casting are 388 holes
Section 5

8 Pile Cap Total Pilecap have been casting are 31 Nr


Section 5
9 Pier Total Pile have been casting are 22 Nr
Section 5
10 Pier Head Total Pile have been casting are 10 Nr
Section 5
APPENDIX A
Contruction Progress
CONSTRUCTION PROGRESS
Location : Sec - 5
Period : May 26th 2017 - June 20th 2017
PROGRESS
LOCATION
NO TOTAL QTY. UNTIL LAST PROGRESS INFORMATION
Sec 5 WORK ITEM REMAINING % FINISH
(Point) MONTH THIS MONTH
1 P.123 Bored Pile 4 4 0 100.0%
2 P.124 Bored Pile 8 8 0 100.0%
3 P.125 Bored Pile 20 13 3 4 80.0%
4 P.126 Bored Pile 24 15 9 0 100.0%
5 P.127 Bored Pile 24 15 9 0 100.0%
6 P.128 Bored Pile 18 15 3 83.3%
7 P.129 Bored Pile 24 15 6 3 87.5%
8 P.130 Bored Pile 8 8 0 100.0%
9 P.131 Bored Pile 8 8 0 100.0%
10 P.132 Bored Pile 8 8 0 100.0%
11 P.133 Bored Pile 6 6 0 100.0%
12 P.134 Bored Pile 6 6 0 100.0%
13 P.135 Bored Pile 6 6 0 100.0%
14 P.136 Bored Pile 6 6 0 100.0%
15 P.137 Bored Pile 6 6 0 100.0%
16 P.138 Bored Pile 6 6 0 100.0%
17 P.139 Bored Pile 6 6 0 100.0%
18 P.140 Bored Pile 6 6 0 100.0%
19 P.141 Bored Pile 6 6 0 100.0%
20 P.142 Bored Pile 6 6 0 100.0%
21 P.143 Bored Pile 6 6 0 100.0%
22 P.144 Bored Pile 6 6 0 100.0%
23 P.145 Bored Pile 6 6 0 100.0%
24 P.146 Bored Pile 6 6 0 100.0%
25 P.148 Bored Pile 8 8 0 100.0%
26 P.149 Bored Pile 8 8 0 100.0%
27 P.150 Bored Pile 8 8 0 100.0%
28 P.151 Bored Pile 8 8 0 100.0%
29 P.152 Bored Pile 8 8 0 100.0%
30 P.153 Bored Pile 8 8 0 100.0%
31 P.154 Bored Pile 8 8 0 100.0%
32 P.155 Bored Pile 8 8 0 100.0%
33 P.156 Bored Pile 8 8 0 100.0%
34 P.157 Bored Pile 10 10 0 100.0%
35 P.158 Bored Pile 10 10 0 100.0%
36 P.159 Bored Pile 10 10 0 100.0%
37 P.160 Bored Pile 10 10 0 100.0%
38 P.161 Bored Pile 8 8 0 100.0%
39 P.162 Bored Pile 8 8 0 100.0%
40 P.163 Bored Pile 8 8 0.0%
41 P.164 Bored Pile 8 8 0 100.0%
42 P.165 Bored Pile 16 16 0 100.0%
43 P.166 Bored Pile 8 8 0 100.0%
44 P.167 Bored Pile 8 8 0 100.0%

Total Progress 353 35


388
Construction Progress Monitoring Section
Period: June 20th, 2017

ACTUAL PLAN NEXT 3 MONTH


PLAN UP TO UP TO
No MAJOR ITEM UNIT THIS UP TO THIS VAR 1st 2nd 3rd REMARKS
THIS MONTH LAST
MONTH MONTH MONTH MONTH MONTH
MONTH
1 Viaduct & Station
a. Bored Pile nr 370.00 353.00 35.00 388.00 18.00 10.00 8.00 -
b. Pile Cap nr 22.00 20.00 11.00 31.00 9.00 12.00 12.00 14.00
c. Pier nr 20.00 17.00 5.00 22.00 2.00 10.00 10.00 10.00
d. Pier Head nr 8.00 3.00 7.00 10.00 2.00 8.00 8.00 8.00
e. Box Girder lm - - - - 0.00 - - -
f. Bearing Pad nr - - - - 0.00 - - -
g. Parapet lm - - - - 0.00 - - -
h. Box Conduit lm - - - - 0.00 - - -
i. Piling Test nr - - - - 0.00 - - -
APPENDIX B
Summary of Man Power
Summary of Manpower

Location : Sec - 5
Period : May 26th 2017 - June 20 th 2017

Manpower MC Manpower SC
1 Project Director 1 Site Engineer 1
2 Deputy Project Director 2 Site Agent (Sub-con) 1
3 Senior Project Manager 3 Site Suoervisor 4
4 Project Manager 1 4 Land Surveyor
5 Construction Manager 1 5 Chainmen
6 Interfacing Manager 1 6 Site Foreman
7 Contract Manager 7 Carpenter
8 Project Engineer 1 8 Door/Window Installer
9 Engineer 4 9 Concretor 15
10 Contract Executive 1 10 General Labour 75
11 Senior Program Manager 11 Skill labour 6
12 Planning Engineer 12 Crane Operator 4
13 M&E Manager, Engineer 13 Backhoe Operator
14 QA/QC Manager 1 14 Excavator Operator 4
15 QA/QC Engineer 6 15 Truck driver 3
16 Doc Controller 1 16 Paver Operator
17 PR Executive 17 Moto Graders Operator
18 Environment Manager 18 Backpusher Operator
19 Environment Officer 19 Tamping Roller Operator
20 Safety Manager 20 Roller Operator
21 Safety & Health Officer 3 21 Bulldozer operator
22 Safety & Health Supervisor 1 22 Tandom Roller Operator
23 Site Supervisor 8 23 Piling Operator
24 Suveyor 3 24 Bar Bender 2
25 Assistant Surveyor 11 25 Water Browser Operator
26 Autocad Asst Manager 26 Drilling Machine Operator
27 Administration Officer 1 27 Welder 2
28 Account Executive 28 Road Cutter Operator
29 Clerk 29 Pneumatic Tyre Roller Operator
30 Assistant Planner 30 Mobile Crusher Operator
31 Traffic Manager 31 Hydraulic Breaker Operator
32 Traffic Management Officer 32 Hole Digger
33 Foreman 33 Shovel Operator
34 Electrician 34 Mechanic 4
35 Purchasing & Storekeeper 35 Banksmen
36 Lab Supervisor 36 PIT Tester
37 Lab Technician 37 Skylift Operator
38 Lab Assistant 38 Boring Rig Operator 4
39 Chainman 39 Security Guard 3
40 Receptionist 1
41 Despatch
42 Lorry Driver
43 Driver 6
44 Backhoe Operator
45 Tea Lady 1
46 General Worker
47 Traffic Flagman 19
48 Training
Total 71 Total 128
APPENDIX C
Summary of Equipment On Site
Summary of Equipment on Site

Location : Sec - 5
Period : May 26th 2017 - June 20 th 2017

No Plant Machinery SC IDLE


1 Mobile Crane 3
2 Excavator 6
3 Concrete Mixer 58
4 Genset 3
5 Bar bending Machine 3
6 Bar Cutting Machine 1
7 Concrete Vibrator (poker) 2
8 Portable Toilet 3
9 Welding Set 5
10 Crawler Crane 4
11 Rotary Boring Machine 4
12 Slury Tanker 2
13 Boring Rig 4

Total 98