Académique Documents
Professionnel Documents
Culture Documents
Construction Progress
The details of construction progress is tabulated on Appendix A
NO DESCRIPTION LOCATION/REMARKS
1 Soil Investigation
7 Bored Pile Total Bored Pile have been casting are 388 holes
Section 5
Location : Sec - 5
Period : May 26th 2017 - June 20 th 2017
Manpower MC Manpower SC
1 Project Director 1 Site Engineer 1
2 Deputy Project Director 2 Site Agent (Sub-con) 1
3 Senior Project Manager 3 Site Suoervisor 4
4 Project Manager 1 4 Land Surveyor
5 Construction Manager 1 5 Chainmen
6 Interfacing Manager 1 6 Site Foreman
7 Contract Manager 7 Carpenter
8 Project Engineer 1 8 Door/Window Installer
9 Engineer 4 9 Concretor 15
10 Contract Executive 1 10 General Labour 75
11 Senior Program Manager 11 Skill labour 6
12 Planning Engineer 12 Crane Operator 4
13 M&E Manager, Engineer 13 Backhoe Operator
14 QA/QC Manager 1 14 Excavator Operator 4
15 QA/QC Engineer 6 15 Truck driver 3
16 Doc Controller 1 16 Paver Operator
17 PR Executive 17 Moto Graders Operator
18 Environment Manager 18 Backpusher Operator
19 Environment Officer 19 Tamping Roller Operator
20 Safety Manager 20 Roller Operator
21 Safety & Health Officer 3 21 Bulldozer operator
22 Safety & Health Supervisor 1 22 Tandom Roller Operator
23 Site Supervisor 8 23 Piling Operator
24 Suveyor 3 24 Bar Bender 2
25 Assistant Surveyor 11 25 Water Browser Operator
26 Autocad Asst Manager 26 Drilling Machine Operator
27 Administration Officer 1 27 Welder 2
28 Account Executive 28 Road Cutter Operator
29 Clerk 29 Pneumatic Tyre Roller Operator
30 Assistant Planner 30 Mobile Crusher Operator
31 Traffic Manager 31 Hydraulic Breaker Operator
32 Traffic Management Officer 32 Hole Digger
33 Foreman 33 Shovel Operator
34 Electrician 34 Mechanic 4
35 Purchasing & Storekeeper 35 Banksmen
36 Lab Supervisor 36 PIT Tester
37 Lab Technician 37 Skylift Operator
38 Lab Assistant 38 Boring Rig Operator 4
39 Chainman 39 Security Guard 3
40 Receptionist 1
41 Despatch
42 Lorry Driver
43 Driver 6
44 Backhoe Operator
45 Tea Lady 1
46 General Worker
47 Traffic Flagman 19
48 Training
Total 71 Total 128
APPENDIX C
Summary of Equipment On Site
Summary of Equipment on Site
Location : Sec - 5
Period : May 26th 2017 - June 20 th 2017
Total 98