Académique Documents
Professionnel Documents
Culture Documents
June, 2017.
1. Definition of Project
2. Identification and formulation of project
Activities take place within an integrated process known as the project cycle,
which involves a series of stages: planning, implementation, evaluation and feedback
into the planning stage at the start of the next project cycle. To improve the content of
these activities and to enhance the effect of Technical Cooperation, each stage in the
project cycle requires appropriate monitoring and management. The following items
are particularly important at each stage.
(1) Planning:
Study and analysis of the needs and requests of developing countries; definition of
target groups; specification of the purpose, targets and resources to be used (required
fields of specialization, number of experts to be dispatched, costs required for the
projects as a whole, etc.) and details of activities.
(2) Implementation:
Assessment of whether the results of a project accord with the original targets;
measurement of the effects of the project; investigation of how results have been
achieved; and feedback of the findings into future project planning.
In accordance with the following four items (i.e., the three stages of the project cycle
and efforts to strengthen the foundations of program implementation):
In a broader approach,
POST-PRODUCTION = Post-deployment
ADDIE MODEL
ANALYSIS = PRE-PRODUCTION
DESIGN = PRODUCTION
DEVELOPMENT = PRODUCTION
IMPLEMENTATION = POST-PRODUCTION
EVALUATION = POST-PRODUCTION
This approach will give one of three discounted cash flow measures of
project worth:
The Net Present Value (NPV)
The Internal Rate of Return (IRR)
The Net Benefit Ratio or Profitability Index (NBR or PI)
The Discounted Payback Period
() = + ()
0
EXAMPLE
Three projects have the following cash flows
A Initial outlay of N10,000 in return for an annual income of N1,000
paid 6-monthly in arrears for 12 years.
B Initial outlay of N1,000 in return for an annual income of N200 at the
end of each of the next 20 years.
C Initial outlay of N5,000 in return for a continuous payment stream of
N2,000 per annum for 3 years, deferred for 2 years.
If the investor can borrow and invest money at 5% per annum, rank the projects under
the NPV measure at this rate
Solution:
The NPVs are computed as follows
NPVA(i) = 10; 000 + 1; 000a12
NPVB(i) = 1; 000 + 200a20
At i1 = 5%
NPVA(i1) = N1; 027:26
NPVB(i1) = N1; 492:44
NPVC(i1) = N62:55
and so
NPVB(i1) > NPVC(i1) > NPVA(i1)
Project B is therefore the best under the NPV measure at i = 5%. Project A is not
profitable at this rate.
INTERNAL RATE OF RETURN
The internal rate of return (IRR) of a project y is the annualized yield obtained over the
projects lifetime.
() = + () = 0
0
The IRR is therefore an additional measure of the profitability of a project and can be
incorporated into project appraisals.
EXAMPLE
Three projects have the following cash flows
A Initial outlay of N10,000 in return for an annual income of N1,000
paid 6-monthly in arrears for 12 years.
B Initial outlay of N1,000 in return for an annual income of N200 at the
end of each of the next 20 years.
C Initial outlay of N5,000 in return for a continuous payment stream of
N2,000 per annum for 3 years, deferred for 2 years.
Assuming that the investor is able to fund the initial outlay from existing funds,
calculate the IRR in each case.
EXAMPLE
Answer
The IRRs are computed by solving the following equations of value
A 10; 000 + 1; 000a(122) = 0 B 1; 000 + 200a20 = 0
C 5; 000 + 2j2; 000a3 = 0
These can be solved using trial and error (or Goalseek) to show
A IRRA = 3:05% per annum B IRRB = 19:43% per annum C IRRC = 5:38%
per annum
Project B is therefore the best under the IRR measure
DISCOUNTED PAYBACK PERIOD
In many practical problems the net cash flow changes sign only once, from negative to
positive. In this case, the balance in the investors account will change from negative to
positive at a unique time t1 or it will always be negative (in which case the project is not
viable).
If t1 exists, it is called the discounted payback period (DPP) and is defined as the
smallest value of t1 such that the accumulation of all prior cash flows is first greater
than zero.
Although the DPP is defined on the accumulation, it can equivalently be obtained by
finding t1 such that the present value of prior cash flows is first greater than zero.
A project with a lower DPP starts to generate a profit more quickly and this can be
important in project appraisals.
EXAMPLE
Three projects have the following cash flows
A Initial outlay of N10,000 in return for an annual income of N1,000
paid 6-monthly in arrears for 12 years.
B Initial outlay of N1,000 in return for an annual income of N200 at the
end of each of the next 20 years.
C Initial outlay of N5,000 in return for a continuous payment stream of
N2,000 per annum for 3 years, deferred for 2 years.
If the investor can borrow and invest money at 5% per annum, rank the projects under
the DPP measure at this rate.
EXAMPLE
Answer
The DPPs are obtained from t1 such that
A 10; 000 + 1; 000a(2) = 0
t1
B 1; 000 + 200at1 = 0
C 5; 000 + 2j2; 000at1 2 = 0 At i1 = 5%
A t1 = 13:96 i.e. DPP is 14 years which is greater than the term of the project. Project A
is therefore not viable at i = 5%.
B t1 = 5:90 i.e. DPP is 6 years (since the payments are at integer times).
C t1 = 4:96 i.e. DPP is 4.96 years.
Project C is therefore the best under the DPP measure at i = 5%.