1 2 3 4 5 6 7 8

CONSIDERACIONES SEDIMENTADOR Vs = 9 m/d PREFILTRO Vf = 0,40 m/h FILTRO LENTO Vf = 0,30 m/h
Caudal Poblacin Familias Ancho Altura Altura de grava Altura del Filtro
Orden 5 hab/fam B H H H
Lts/seg Habitantes Unidad m m m m

1.00 0.20 266 53 0.8 0.4 1.00 3.40


2.00 0.30 399 80 0.8 0.4 1.00 3.40
3.00 0.40 532 106 0.8 0.4 1.00 3.40
4.00 0.50 665 133 1.1 0.7 1.00 3.40
5.00 0.60 798 160 1.1 0.7 1.00 3.40
6.00 0.70 930 186 1.1 0.7 1.00 3.40
7.00 0.80 1,063 213 1.6 0.7 1.00 3.40
8.00 0.90 1,196 239 1.6 0.7 1.00 3.40
9.00 1.00 1,329 266 1.6 0.7 1.00 3.40
10.00 1.10 1,462 292 1.6 0.7 1.00 3.40
11.00 1.20 1,595 319 1.6 0.7 1.00 3.40
12.00 1.30 1,728 346 1.6 0.7 1.00 3.40
13.00 1.40 1,861 372 1.6 0.7 1.50 3.40
14.00 1.50 1,994 399 1.6 0.7 1.50 3.40
15.00 1.60 2,127 425 1.6 0.7 1.50 3.40
16.00 1.70 2,260 452 2.0 0.7 1.50 3.40
17.00 1.80 2,393 479 2.0 0.7 1.50 3.40
18.00 1.90 2,526 505 2.0 0.7 1.50 3.40
19.00 2.00 2,658 532 2.0 0.7 1.50 3.40
20.00 2.10 2,791 558 2.0 0.7 2.00 3.40
21.00 2.20 2,924 585 2.5 0.7 2.00 3.40
22.00 2.30 3,057 611 2.5 0.7 2.00 3.40
23.00 2.40 3,190 638 2.5 0.7 2.00 3.40
24.00 2.50 3,323 665 2.5 0.7 2.00 3.40
25.00 2.60 3,456 691 2.5 0.7 2.00 3.40
26.00 2.70 3,589 718 3.0 0.7 2.50 3.40
27.00 2.80 3,722 744 3.0 0.7 2.50 3.40
28.00 2.90 3,855 771 3.0 0.7 2.50 3.40
29.00 3.00 3,988 798 3.0 0.7 2.50 3.40
30.00 3.10 4,121 824 3.0 0.7 2.50 3.40
31.00 3.20 4,254 851 3.3 0.7 2.50 3.40
32.00 3.30 4,386 877 3.3 0.7 2.50 3.40
33.00 3.40 4,519 904 3.3 0.7 2.80 3.40
34.00 3.50 4,652 930 3.3 0.7 2.80 3.40
35.00 3.60 4,785 957 3.5 0.7 2.80 3.40
36.00 3.70 4,918 984 3.5 0.7 2.80 3.40
37.00 3.80 5,051 1,010 3.5 0.7 2.80 3.40
NOMBRE DEL PROYECTO :
CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y
LETRINAS EN LOS CAS. DE SAN MIGUEL DE SEREN, SAN
JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE
DE LOS INCAS DEL DIST. DE TAMBOGRANDE - PIURA -
PIURA

FECHA: JUNIO DEL 2011

DISEO DE SEDIMENTADOR

DESCRIPCION Und Clculos Criterio


CAUDAL DE DISEO, Qmd Q lts/s 3.20 3.2 31
ANCHO SEDIMENTADOR B mts 3.3
LONGITUD DE ENTRADA AL SEDIMENTADOR L1 mts 0.8 Asumido
ALTURA DEL SEDIMENTADOR H mts 0.7
PENDIENTE EN EL FONDO S dec. 0.1 Asumido
VELOCIDAD DE PASO EN C/. ORIFICIO Vo m/s 0.1 Asumido
DIAMETRO DE C/. ORIFICIO D mts 0.025 Asumido
SECCION DEL CANAL DE LIMPIEZA A2 m2 0.001963 Asumido

1 Velocidad de sedimentacion VS m/s 0.000104 Asumido


2 Area superficial de la zona de decantacin AS m2 30.720 AS=Q/VS
3 Longitud en la zona de sedimentacin L2 mts 9.400 L2=AS/B
4 Longitud total del sedimentador LT mts 10.200 LT=L1+L2
5 Relacin (L2/B) en la zona de sedimentacin L2/B adim 2.85 2.8<L2/B<6; verificar
6 Relacin (L2/H) en la zona de sedimentacin L2/H adim 13.43 6<L2/H<20; verificar
7 Velocidad horizontal del flujo, VH<0.55 VH cm/s 0.139 VH=100*Q/(B*H)
8 Tiempo de retencin de la unidad To hr 1.867 To=(AS*H)/(3600*Q)
9 Altura mxima en la tolva de lodos h mts 1.00 h=(S)*L2
10 Altura de agua en el vertedero de salida H2 mts 0.007 H2=(Q/1.84*B))^(2/3)
11 Area total de orificios Ao m2 0.032 Ao=Q/Vo
12 Area de cada orificio ao m2 0.00049 ao=0.7854*D^2
13 Nmero de orificios n adim 66 Asumir redondeo para N1 y N2
14 Altura de la cortina cubierta con orificios h mts 0.42 h=H-(2/5)*H
15 Nmero de orificios a lo ancho, B N1 adim 6
16 Nmero de orificios a lo alto, H N2 adim 6
17 Espaciamiento entre orificios a mts 0.084 a=h/(N2-1)
18 Espaciamiento lateral respecto a la pared a1 mts 1.44 a1=(B-a*(N1-1))/2
19 Tiempo de vaceado en la unidad T1 min 162 T1=(60*AS*(H)^(1/2))/(4850*A2)
20 Caudal de diseo en la tub. de desague q l/s 2.4250 q=(1000*LT*B*(H))/(60*T1)

21 OBSERVACIONES Y/O SUGERENCIAS

Fuente CEPIS
NOMBRE DEL PROYECTO:
CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE
SAN MIGUEL DE SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE
VALLE DE LOS INCAS DEL DIST. DE TAMBOGRANDE - PIURA - PIURA

FECHA: JUNIO DEL 2011

DISEO DEL PRE-FILTRO DE GRAVA


El pretratamiento
de la filtracin en arena utilizando
consta deprefiltros de grava
varias cmaras parade
llenas disminuir
piedrasladecarga de material
dimetro en suspensin
creciente, antes
en las cuales se retiene
la materia en suspensin con diam
cuales se retiene la materia en suspensin con dimetros hasta 10 mm

El caudal de diseo es el caudal mximo diario.

Qmd = 3.2 lts/seg


Qmd = 0.0032 m3/seg

El mnimo numero de unidades (N) es 2

N= 4 unidades

Se recomienda velocidades de filtracin de 0.10 - 0.60 m/h variables en razn inversa a la calidad del agua
Asumiremos:
Vf = 0.4 m/hora

El rea de filtracin viene dado por:


3600 *Q
A = = 7.20 m2
N * Vf

Considerando la profundidad de la grava de H = 2.00 m.

Entonces el ancho de la unidad ser B:

B= A/H = 3.60 m.

La longitud necesaria de Pre-Filtro viene dado por :

-ln (cl/co)
Li =
a
Siendo:
cl = Turbiedad de salida (UN)
co = Turbiedad de entrada (UN)
Li = Longitud del tramo i del Pre-Filtro
a= Modulo de Impedimento

El modulo de impedimento es funcin de la velocidad de filtracin y el dimetro de grava.


El CEPIS en plantas piloto ha elaborado el siguiente cuadro.

VALORES EXPERIMENTALES DEL MODULO DE IMPEDIMENTO (a)


Dimetro 1-2 2-3 3-4

Velocidad

0.1 1.00 - 1.40 0.70 - 0.90 0.40 - 0.80

0.2 0.70 - 1.00 0.60 - 0.80 0.30 - 0.70

0.4 0.60 - 0.90 0.40 - 0.70 0.25 - 0.60

0.8 0.50 - 0.80 0.30 - 0.60 0.15 - 0.50

Se ingresa con los valores de la velocidad de filtracin y el dimetro de la seccin.

PRIMER TRAMO:
Grava de 3 a 4 cm.
Vf = 0.40 m/h
Se obtiene: a= 0.425 y considerando una turbiedad
mxima co = 350.00 U.T. , y para el efluente una turbiedad cl = 190.00 U.T.

-ln (cl/co)
L1 =
a

Reemplazando valores
L1 = 1.50 m.

SEGUNDO TRAMO:
Grava de 2 a 3 cm.
Vf = 0.40 m/h

Se obtiene: a= 0.55 y la turbiedad al ingreso de este tramo ser igual a la


salida del tramo 1: 190.00 U.T. , y para el efluente una turbiedad cl = 85.00 U.T.

-ln (cl/co)
L2 =
a
Reemplazando valores
L2 = 1.50 m.

TERCER TRAMO:
Grava de 1 a 2 cm.
Vf = 0.40 m/h
Se obtiene: a= 0.75 y la turbiedad al ingreso de este tramo ser igual a la
salida del tramo 2: 85.00 U.T. , y para el efluente una turbiedad cl = 30.00 U.T.

-ln (cl/co)
L3 =
a
Reemplazando valores
L3 = 1.40 m.
LONGITUD TOTAL DE LA UNIDAD SIN CONSIDERAR ANCHO DE MUROS:
Lt = L1 + L2 + L3

Reemplazando valores
L= 4.40 m. (Longitud total de la Unidad).

1.50 0.00

PLANTA

1.50 0.00

1.40 0.00

3.60 3.60 3.60 3.60

CORTE
h = 2.00 h = 2.00
NOMBRE DEL PROYECTO:

CONST. DEL SIST. DE ABAST. DE AGUA POTABLE


Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE
SEREN, SAN JOSE, JESUS DEL VALLE Y
CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL
DIST. DE TAMBOGRANDE - PIURA - PIURA

FECHA : JUNIO DEL 2011

DISEO DE FILTRO LENTO


Datos Unidad Criterios Clculos
1 Caudal de diseo Q lts/seg 3.2
2 Altura de cada unidad H m 3.4
3 Nmero de unidades N adim Asumido 2
4 Velocidad de filtracin Vf m/h Asumido 0.3
5 Espesor capa de arena extrada en
E m Asumido 0.02
c/raspada
6 Nmero de raspados por ao n adim Asumido 6
7 Area del medio filtrante de cada unidad AS m^2 AS = Q / (N*Vf) 19.20
8 Coeficiente de mnimo costo K adim K = (2*N) / (N+1) 1.33333333
9 Largo de cada unidad L m L =(AS*K)^(1/2) 5.10
10 Ancho de cada unidad B m B = (AS/K)^(1/2) 3.80
11 Espesor del muro T m 0.25
12 Volumen del depsito para almacenar
V m^3 V = 2*L*B*E*n 4.6512
arena durante 2 aos
13 Vel.de Filtracin Real VR m/h V = Q/(2*L*B) 0.297

Criterio de diseo para filtro lento


Parmetros Unidad Valores
1 Velocidad de filtracin m/h 0.10 - 0.30
2 Area mxima de cada unidad m^2 10 - 200
3 Nmero mnimo de unidades 2
4 Borde Libre m 0.20 - 0.30
5 Capa de agua m 1.0 - 1.5
6 Altura del lecho filtrante m 0.80 - 1.00
7 Granulometra del lecho mm 0.15 - 0.35
8 Altura de capa soporte m 0.10 - 0.30
9 Granulometria grava mm 1.5 - 40
10 Altura de drenaje m 0.10 - 0.25

Fuente CEPIS
1.00
05.- Hoja de Metrados de Sedimentador

Proyecto : "CCONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE
SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE
TAMBOGRANDE - PIURA - PIURA
FECHA : Jun-11

Dimensionamiento de Sedimentador
Caudal lts/seg 3.20
TERRENO
Largo LTE 16.00
Ancho BTE 9.00
Profundidad de excavacionhe (mnimo h+0.15) 0.80 1.15 mnimo
Factor de esponjamiento f 1.30
CAJA DE EVACUACION
Espesor de muros EME 0.15
Espesor de losa ELE 0.20
Alto HE 1.10
Largo LE 1.50
Ancho BE 0.85
SEDIMENTADOR
Ancho B 3.30
Largo L2 9.40
Largo entrada L1 0.80
Altura de sedimentador H 0.70
altura de tolva de lodos h 1.00

PARCIAL TOTAL UND.


01.00.00 TRABAJOS PRELIMINARES
01.01.00 Limpieza manual de terreno LTExBTE 144.0000 144.00 m2

01.02.00 Trazo, nivel y replanteo 144.0000 144.00 m2

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 Corte de terreno para la conformacin de terrapln 50.0000 50.00 m3

02.02.00 Relleno y compactacin con material propio 21.8400 21.84 m3

02.03.00 Excavacin en terreno normal S/equipo 1.03(B+0.3)((L1+L2)h/2+0.2((0.35+(L1^2+h^2)^0.5+((L2+0.15)^2+h^2)^0.5 27.2411


1.03x1.5x0.85(he+0.05) 1.1163
28.36 m3

02.04.00 Nivelacin y Compactacin de terreno 144.0000 144.00 m2.

02.05.00 Acarreo de material excedente Dp=30 m. 36.86 m3.

03.00.00 OBRAS DE CONCRETO SIMPLE


03.01.00 Solado de Concreto 1:4:8, con mezcladora (B+0.3)(0.35+(L1^2+h^2)^0.5+((L2+0.15)^2+h^2)^0.5)+1.5x0.85 41.7132 41.71 m2.

04.00.00 OBRAS DE CONCRETO ARMADO


CIMENTACION
04.01.00 Cimentacin, concreto f'c=210 kg/cm2, c/ m 1.05(B+0.3)x0.2((L2^2+h^2)^0.5+0.15+0.35+0.05) 7.5623
1.05x0.2x(B+0.3)(((L1-0.225)^2+(h-0.1)^2)^0.5+0.05) 0.8452 8.41 m3

04.02.00 Cimentacin, encofrado y desencofrado 0.25(B+0.3)+0.2x2(0.59+(L2^2+h^2)^0.5+((L1-0.225)^2+(h-0.1)^2)^0.5) 5.1944 5.19 m2

04.03.00 Cimentacin, acero Fy=4,200kg/cm2


1/2" 1.05 ((B+0.2)/0.25+1)(L2+75+0.45) 159.0000 166.9500
1/2" 1.05 ((B+0.2)/0.25+1)(((L1-0.225)^2+(h-0.1)^ 16.0200 16.8210
1/2" 1.05 (L2/0.25+2)(B+0.8) 162.3600 170.4780
1/2" 1.05 ((((L1-0.225)^2+(h-0.1)^2)^0.5)/0.25+1) 21.6152 22.6960 376.94 kg

MUROS
04.04.00 Muros, concreto f'c=210 kg/cm2, conn mezc1.05x0.15((B+0.3)(0.6+H+0.2+H+0.75+0.2)-2(0.3x0.15+0.15^2)) 1.7648
1.05(2x0.15(0.15x0.35+0.6x0.35+Hx(L1+L2))-0.15x0.3x0.35) 2.3153
1.05x0.15xhx(L1+L2) 1.6065 5.69 m3

04.05.00 Muros, encofrado y desencofrado (B+0.3)(2H+1.3)+B(2H+1.5)+2(0.5(0.6+0.75)+1.05x0.2+2x0.3x0.15) 21.2400


4(L1+L2)(H+h/2) 48.9600 70.20 m2

04.06.00 Muros, acero Fy=4,200kg/cm2


1/2" 1.05 ((B+0.2)/0.25+1)(2H+3.2)+2(2B+1.55) 85.3000 89.5650
1/2" 1.05 8(B+L1+L2+1.1) 116.8000 122.6400
1/2" 1.05 2((H+h-0.3)/0.25+1)(B+.2+L1+L2) 180.8400 189.8820
1/2" 1.05 2((L1+L2)/0.25+1)(H+h+0.65) 196.4600 206.2830 608.37 kg

CAJA DE EVACUACION
04.07.00 Caja, concreto f'c=210 kg/cm2, con mezcla 1.05(ELExLExBE+(HE-ELE)EME(LE+3x(BE-EME))) 0.7781
1.05((0.21+h)0.65/2x0.15+.5x0.05x0.15/2) 0.0639 0.84 m3
1.00
05.- Hoja de Metrados de Sedimentador

Proyecto : "CCONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE
SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE
TAMBOGRANDE - PIURA - PIURA
FECHA : Jun-11

04.08.00 Caja, encofrado y desencofrado HE(2BE+LE)+(HE-ELE)(4(BE-EME)+(LE-3EME)) 6.9850 6.99 m2

04.09.00 Muros, acero Fy=4,200kg/cm2


3/8" 0.59 10(2BE+LE-0.2)+4(3HE+LE-0.1)+8(HE+ 63.2000 37.2880 37.29 kg

05.00.00 REVOQUES Y ENLUCIDOS


05.01.00 Tarrajeo int. c/ impermeabilizante 1:1, e=1.5 B(2H+2.2)+2x(0.2x0.45+2x0.3x0.15+0.6x0.2) 12.4800
2H(L1+L2)+(L1+L2)h 24.4800 36.96 m2

05.02.00 Tarrajeo exterior de muros (mortero 1:5) 2(0.6(B+1.3+L1+L2)+0.15(B+095+L1+L2)+(H-0.45))(B+0.6+L1+L2)) 29.1450


0.15x2(B+1+L1+L2) 4.3500
(HE-he)(2BE+LE)+(HE-ELE)(2BE-5EME+LE)+EME(LE+3BE-3EME) 3.7050 37.20 m2

06.00.00 VARIOS
06.01.00 Vlvula esfrica bridada 6" y accesorios 1.00 und.

06.02.00 Rompe agua 4" 1.00 und.

06.03.00 Tubera PVC-SAP 6" 22.00 ml

06.04.00 Tapa metlica de 0.80X0.80 1.00 und.

06.05.00 Pantalla difusora (madera 1") (B+0.05)(H+0.3) 3.3500 3.35 m2


1.00
06.- Hoja de Metrados de Pre-Filtro de Grava
PROYECTO
CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE SEREN, SAN JOSE, JESUS
DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE TAMBOGRANDE - PIURA - PIURA
Fecha: JUNIO 2011

Dimensionamiento de Pre Filtros de Grava, mdulo de 02 unidades


Caudal lts/seg 3.20
TERRENO
Largo LTE 12.00
Ancho BTE 14.00
Profundidad de excavacion he 1.00
Factor de esponjamiento f 1.30
CAJA DE ENTRADA
Espesor de muros EME 0.15
Espesor de losa ELE 0.15
Alto muro HE 1.78
Largo LE 0.60
Ancho BE 1.20
CAJA DE SALIDA
Largo LS 0.75
Ancho BS 3.50
Alto HS 1.50
Espesor de losa ELS 0.15
Espesor de muro EMS 0.15
PRE-FILTROS
Ancho B 3.60
Altura de grava H 2.00
Largo cmara 1 L1 1.50
Largo cmara 2 L2 1.50
Largo cnara 3 L3 1.40 Nmero de mdulos Und 2

PARCIAL SUB TOTAL TOTAL UND.


01.00.00 TRABAJOS PRELIMINARES
01.01.00 Limpieza manual de terreno LTExBTE 168.0000 168.00 336.00 m2

01.02.00 Trazo, nivel y replanteo 168.0000 168.00 336.00 m2

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 Corte de terreno para la conformacin de terrapln 350.0000 350.00 350.00 m3

02.02.00 Relleno y compactacin con material propio 57.6190 57.62 115.24 m3

02.03.00 Excavacin terreno normal (0.77x1.20x(L1+L2+L3+1)+0.27x2(2B+1.40))x1.03 9.8114


(0.3(L1+L2+L3+1)(2B+2.6)+(he-1.02)(2.40+L1+L2+L3)(2B+2.6))x1.03 14.6738 24.49 48.97 m3

02.04.00 Refine nivel y compactacion 168.0000 168.00 336.00 m2.

02.05.00 Eliminacin de material excedente Dp=5 km. 411.93 823.85 m3.

03.00.00 OBRAS DE CONCRETO SIMPLE


03.01.00 Solado de Concreto 1:4:8, con mezcladora (L1+L2+L3+1)(2B+2.4)+1.4(2B+2.4)+2x0.2 65.6800 65.68 131.36 m2.

04.00.00 OBRAS DE CONCRETO ARMADO


PLATEA DE CIMENTACION
04.01.00 Cimentacin, concreto f'c=210 kg/cm2, c/mezcladora (0.2x1.20x(L1+L2+L3+1)+2x0.15(2B+1.4)+0.72x0.15x(2B+1.2))x1.05 5.0110
(0.2(L1+L2+L3+0.7)(2B+1.2)+2x1x0.2(2B+2.4)+2x0.32x1.1x0.2)x1.05 11.9414 16.95 33.90 m3

04.02.00 Cimentacin, encofrado y desencofrado 0.2x2x(2.20+L1+L2+L3)+2(0.27x2+0.2(L1+L2+L3+3.5)) 6.8800


2(0.15x0.2x3+(B+0.6)(0.2+0.4+0.27x6+6x0.3)+0.32x2) 35.2280
2x0.2(2B+2.4) 3.8400 45.95 91.90 m2

04.03.00 Cimentacin, acero Fy=4,200kg/cm2


5/8" 1.64 (1.10/0.2+1)(L1+L2+L3+0.9) 34.4500 56.4980
5/8" 1.64 2x0.90(0.6/0.2+2x0.55/0.2+3) 20.7000 33.9480
5/8" 1.64 2((B+0.5)/0.2+1)(1.54+1.49) 130.2900 213.6756
5/8" 1.64 2(0.6/0.2+2x0.55/0.2+3)(B+1.05) 106.9500 175.3980
5/8" 1.64 2((B+0.5)/0.2+1)(2.1+L1+L2+L3) 279.5000 458.3800
5/8" 1.64 2(6.2+(L1+L2+L3)/0.2)(B+1) 259.4400 425.4816
5/8" 1.64 2(2B+2.3)(0.9/0.2+2) 123.5000 202.5400 1,565.92 3,131.84 kg

CAJA DE ENTRADA
04.04.00 Caja de Entrada, concreto f'c=210 kg/cm2, c/mezcl. (EMExHExLE+ELExBExLE)1.05 0.2816 0.28 0.56 m3

04.05.00 Caja de Entrada, encofrado y desencofrado 2xLExHE+(BE-EME)LE+2ELExLE 2.9460 2.95 5.89 m2

04.06.00 Caja de Entrada, acero Fy=4,200kg/cm2


3/8" 0.59 1.5(1.1/0.25+1)+1.5(HE/0.2+1) 22.9500 13.5405
3/8" 0.59 1.3(0.6/.25+1)+(HE+.65)(0.6/0.25+1) 12.6820 7.4824 21.02 42.05 kg

PRE-FILTRO
04.07.00 Muros, concreto f'c=210 kg/cm2, c/ mezcladora 2x1.05x0.2((H+0.77)x(L1+L2+L3+1.2)+(H+0.73)(L1+L2+L3+2)) 13.7189
2x1.05x0.2(0.3(L1+L2+L3)+0.8*0.05+.4*.05) 0.5796
1.05x0.20(2x((2B+2.4)(H+0.73)-0.6x0.83)+1.2(H+1.8+1.07)) 12.0254 26.32 52.65 m3

04.08.00 Muros, encofrado y desencofrado 2(2(H+0.73)(2B+L1+L2+L3+4.4)+0.6(L1+L2+L3)) 180.0000


2(2(H+0.82)(L1+L2+L3+1.2)+1.2(H+1.8+1.07)) 74.8560 254.86 509.71 m2

04.09.00 Muros, acero Fy=4,200kg/cm2


5/8" 1.64 2((2B+2.3)/0.2+1)(H+2.13)+(1.2/0.2+ 401.8000 658.9520
3/8" 0.59 2((L1+L2+L3+2.4)/0.2+1)(H+1.8) 266.0000 156.9400
3/8" 0.59 2((H+1.5)/.2+1)(2B+2.3+L1+L2+L3+2 599.4000 353.6460
3/8" 0.59 2((H+0.67)/0.2+1)(2.6+L1+L2+L3) 200.9000 118.5310
3/8" 0.59 2((L1+L2+L3+1.2)0.2+1)(H+0.77+0.5 192.5600 113.6104 1,401.68 2,803.36 kg

CAJA DE SALIDA
04.10.00 Muros, concreto f'c=210 kg/cm2, c/mezcladora 1.05EMS(HS-ELS)(2(LS-EMS)+BS) 0.9993 1.00 2.00 m3
1.00
06.- Hoja de Metrados de Pre-Filtro de Grava
PROYECTO
CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE SEREN, SAN JOSE, JESUS
DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE TAMBOGRANDE - PIURA - PIURA
Fecha: JUNIO 2011

04.11.00 Muros, encofrado y desencofrado 2(HS-ELS)(2(LS-EMS)+BS-EMS) 12.2850 12.29 24.57 m2

04.12.00 Muros, acero Fy=4,200kg/cm2


3/8" 0.59 ((BS-.1)/0.2+1)(HS+0.4+LS) 47.7000 28.1430
3/8" 0.59 ((LS-0.05)/0.2+1)(2HS+BS-0.1) 28.8000 16.9920
3/8" 0.59 ((HS-ELS)/0.2+1)(2LS+BS+0.7) 44.1750 26.0633 71.20 142.40 kg

04.13.00 Losa, concreto f'c=210 kg/cm2, c/mezcladora 1.05xELSxLSxBS 0.3938 0.39 0.79 m3

04.14.00 Losa, encofrado y desencofrado LSxBS+ELS(BS+2LS) 3.3750 3.38 6.75 m2

COLUMNAS
04.15.00 Columnas, concreto f'c=210 kg/cm2 con mezcladora 1.05(H-0.5)x0.2x0.2x16 1.0080 1.01 2.02 m3

04.16.00 Columnas, encofrado y desencofrado (H-0.5)x0.51x16 12.2400 12.24 24.48 m2

04.17.00 Columnas, acero Fy=4200kg/cm2


3/8" 0.59 16x2x(H+0.4) 76.8000 45.3120
1/2" 1.05 16x4x(H+0.4) 153.6000 161.2800
1/4" 0.26 16x2(0.34+0.14+0.05)(6+(H-0.5)/0.2 186.5600 48.9720 255.56 511.13 kg

VIGAS
04.18.00 Vigas, concreto f'c=210 kg/cm2, c/mezcladora 1.05x0.2x0.25x(B+0.4)x8 1.6800 1.68 3.36 m3

04.19.00 Vigas, encofrado y desencofrado 8(0.5(B+0.4)+0.2B) 21.7600 21.76 43.52 m2

04.20.00 Vigas, acero Fy=4200kg/cm2


1/2" 1.05 4x8(B+1) 147.2000 154.5600
1/4" 0.26 8x0.76x(7+(B-0.5)/0.25) 117.9520 30.9624 185.52 371.04 kg

05.00.00 REVOQUES Y ENLUCIDOS


05.01.00 Tarrajeo int. c/ impermeabilizante 1:1. e=1.5 cm (H+0.73)(3(2B+2)+2(L1+L2+L3+2))+2(L1+L2+L3)(0.3+H)-4x0.6x0.83 128.5400
2x1.1x0.32+1.2(2H+3.6)+(H+0.77)(L1+L2+L3+1.2) 25.3360
(2LS+BS-4EMS)(HS-ELS)+LE((BE-EME)+2(LE+HE)) 9.4260
2x6x(B+0.4)(0.3+0.32) 29.7600
0.2x2(2B+L1+L2+L3+4.4) 6.4000
0.2x2(L1+L2+L3+2.23)+1.2x0.2 2.8920 202.35 404.71 m2

05.02.00 Tarrajeo columnas c/impermeabilizante 1:1, e=1.5 cm. 16(H-0.5)x0.51 12.2400 12.24 24.48 m2

05.03.00 Tarrajeo vigas c/impermeabilizante 1:1, e=1.5 cm. 8x(0.7x(B+0.4)+0.11B) 25.5680 25.57 51.14 m2

05.04.00 Tarrajeo exterior de muros (mortero 1:5) 2(H+1.5-he)(L1+L2+L3+2B+4.8)+2LSxHS+BSxLS 86.8750


0.2x2(2B+L1+L2+L3+4.4)+0.15x(BS+2LS-2EMS) 7.1050 93.98 187.96 m2

06.00.00 MATERIAL FILTRANTE


06.01.00 Grava 4 a 3 cm 2L1x(B+0.4)xH 24.0000 24.00 48.00 m3.

06.02.00 Grava 3 a 2 cm 2L2x(B+0.4)xH 24.0000 24.00 48.00 m3.

06.03.00 Grava 2 a 1 cm 2L3x(B+0.4)xH 22.4000 22.40 44.80 m3.

07.00.00 MAMPOSTERIA
07.01.00 Muro con ladrillo maquinado con 18 huecos de
8(Bx(H-0.2)) 51.8400 51.84 m2
9x14x24 103.68

08.00.00 VARIOS
08.01.00 Falso piso con pendiente en filtros 1:4:8 0.2(L1+L2+L3-1.1)(B-0.4)+0.4(0.35+0.1425)(L1+L2+L3+1.2) 3.2152 3.22 6.43 m3
08.02.00 Vlvula esfrica bridada 4" y accesorios 9.00 18.00 und.
08.03.00 Rompe agua 2" 9.00 18.00 und.
08.04.00 Tubera PVC-SAL 4" 22.00 44.00 ml
08.05.00 Losas prefabricadas de 0.5x0.3x0.05m. (B+0.4)/0.32 (El valor que sale considerarlo doble) 12.5000 25.00 50.00 und.
08.06.00 Losas prefabricadas de 0.4x0.25x0.05m. (B+0.4)/0.26 (El valor que sale se considera cuadruple) 15.3846 62.00 124.00 und.
08.07.00 Water Stop 6" 2HS+BS 6.5000 7.00 14.00 ml
08.08.00 Escalines (1.5+H)/0.30 11.6667 12.00 24.00 und.
1.00
07.- Hoja de Metrados de Filtros Lentos

ROYECTO CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE
SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE
TAMBOGRANDE - PIURA - PIURA
FECHA JUNIO DEL 2011

Dimensionamiento de Filtros Lentos


Caudal lts/seg 3.20
TERRENO
Largo LTE 13.00
Ancho BTE 13.00
Dametro de tubera de
4.00
conduccin en pulgadas
Profundidad de excavacion he 1.00
Factor de esponjamiento f 1.20
Nmero de raspados por ao n 6.00
Espesor de arena extrada
er 0.02
en cada raspado
CAJA DE ENTRADA
Espesor de muros EEM 0.10
Espesor de losa EEL 0.10
Alto h 0.80
Ancho BE 2.50
Largo LE 1.50
FILTROS
Espesor de muros EEF 0.25
Alto H 3.40
Largo L 5.10
Ancho B 3.80
Espesor de losa E 0.30
CAJA DE SALIDA
Espesor de muros EES 0.15
Largo LS 1.80
Ancho BS 3.15
Espesor de losa techo EET 0.15
Largo losa de techo LT 1.65
Ancho losa de techo BT 1.35

PARCIAL TOTAL UND.


01.00.00 TRABAJOS PRELIMINARES
01.01.00 Limpieza manual de terreno LTExBTE 169.0000 169.00 m2

01.02.00 Trazo, nivel y replanteo 169.0000 169.00 m2

02.00.00 MOVIMIENTO DE TIERRAS


02.01.00 Corte de terreno para la conformacin de terrapln 250.0000 250.00 m3

02.02.00 Relleno y compactacin con material propio 57.9550 57.96 m3

02.03.00 Excavacin de zanjas Terreno normal manual ((he+.05)x(L+2xEEF+0.80)x(2xB+3xEEF+0.80))x1.03 63.3326


((he+0.05)x(LS-.2)x(BS+0.20))x1.03 5.7968 69.13 m3

02.04.00 Refine nivel y compactacion 169.0000 169.00 m2.

02.05.00 Eliminacin de material excedente Dp=5 K m. 332.61 m3.

03.00.00 OBRAS DE CONCRETO SIMPLE


03.01.00 Solado de Concreto 1:4:8 con mezcladora (L+2xEEF+0.80)x(2xB+3xEEF+0.80) 58.5600
(LS-0.20)x(BS+0.20) 5.3600 63.92 m2.

05.00.00 OBRAS DE CONCRETO ARMADO


PLATEA DE CIMENTACION
05.01.00 Platea, concreto f'c=210 kg/cm2, con mezclad Ex((2xB+3xEEF+0.8)x(L+0.8+2xEEF)+(LS-0.2)x(BS+.2))x1.05 20.1348 20.13 m3

05.02.00 Platea, encofrado Ex(2x(2xB+3xEEF+0.8)+2x(L+0.6+2xEEF+LS)) 10.2900 10.29 m2

05.03.00 Platea, acero Fy=4,200kg/cm2


1/2" 1.05 ((L+2EEF+0.7)/0.15+1)x(2B+3EEF+1.80) 436.4500 458.2725
3/8" 1.05 (L/0.2+1)x(2B+3EEF+0.7) 239.8250 251.8163
1/2" 1.05 ((2B+3EEF+0.7)/0.15+1)x(L+2EEF+1.8) 453.8667 476.5600
3/8" 1.05 2x(B/0.2+1)x(L+2EEF+0.7) 252.0000 264.6000
1/2" 1.05 ((BS+0.2)/0.15+1)x(LS+0.5) 53.6667 56.3500
3/8" 1.05 ((BS+0.2)/0.2+1)x(LS+0.25) 36.3875 38.2069
1/2" 1.05 ((LS-0.2)/0.15+1)x(BS+0.5) 42.5833 44.7125
3/8" 1.05 ((LS-0.2)/0.2+1)x(BS+0.1) 29.2500 30.7125 1,621.23 kg

CAJA DE ENTRADA
05.04.00 Caja de Entrada, concreto f'c=210 kg/cm2, co BExLExEELx1.05 0.3938
EEMx(h-EEL)x(LEx2+(BE-2xEEM)x2+(LE-2xEEM-.30))x1.05 0.6321 1.03 m3

05.05.00 Caja de Entrada, encofrado y desencofrado BExLE+4xhx(BE+LE)+2xhx(EEM+LE-2xEEM-.30) 18.3100 18.31 m2

05.06.00 Caja de Entrada, acero Fy=4,200kg/cm2


3/8" 0.59 ((LE-0.1)/0.2+1)x(BE-0.3+2xh) 30.4000 17.9360
3/8" 0.59 ((BE-0.1)/0.2+1)x(LE+.3+h) 7.8000 4.6020
3/8" 0.59 ((h-0.10)/0.20+1)x(2xLE+BE+0.2) 25.6500 15.1335
3/8" 0.59 ((h-0.10)/0.20+1)x(BE+0.3) 12.6000 7.4340
3/8" 0.59 ((BE-0.2)/0.2+1)x(h+0.10) 11.2500 6.6375
3/8" 0.59 ((h-0.10)/0.20+1)x(LE-2xEEM+0.10) 6.3000 3.7170
3/8" 0.59 ((LE-2xEEM-.30)/0.20+1)x(h+.1) 5.4000 3.1860 58.65 kg

FILTROS
05.07.00 Muros, concreto f'c=210 kg/cm2 con mezclado (3x(L+2xEEF)xHxEEF+4xBxEEFxH)*1.05 28.5600 28.56 m3
1.00
07.- Hoja de Metrados de Filtros Lentos

ROYECTO CONST. DEL SIST. DE ABAST. DE AGUA POTABLE Y LETRINAS EN LOS CAS. DE SAN MIGUEL DE
SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DIST. DE
TAMBOGRANDE - PIURA - PIURA
FECHA JUNIO DEL 2011
05.08.00 Muros, encofrado y desencofrado Hx(4x((L+2xEEF)+(2xB+3xEEF))+2xL) 224.4000 224.40 m2

05.09.00 Muros, acero Fy=4,200kg/cm2


1/2" 1.05 6x((H-0.1)/0.2+2)x(L+2xEEF+0.5) 677.1000 710.9550
1/2" 1.05 4x((H-0.1)/0.2+2)x(2xB+3xEEF+0.5) 654.9000 687.6450
1/2" 1.05 6x((L+2xEEF-0.1)/0.2+1)x(H+E+0.4) 701.1000 736.1550
1/2" 1.05 4x((L+2xEEF-0.1)/0.2+1)x(1.2+E) 171.0000 179.5500
1/2" 1.05 2x((Bx2+3xEEF-0.1)/.2+1)x(1.2+E) 126.7500 133.0875
1/2" 1.05 4x((Bx2+3xEEF-0.1)/0.2+2)x(H+E+0.4) 709.3000 744.7650 3,192.16 kg

CAJA DE SALIDA
05.10.00 Muros, concreto f'c=210 kg/cm2 con mezclado HxEESx(BS+4x(LS-EES))x1.05 5.2211 5.22 m3

05.11.00 Muros, encofrado y desencofrado Hx2x(BS+2xLS+2*(LS-EES)) 68.3400 68.34 m2

05.12.00 Muros, acero Fy=4,200kg/cm2


3/8" 0.59 4x((H-0.1)/0.25+1)x(LS+EEF+0.5) 144.8400 85.4556
3/8" 0.59 ((H-0.1)/0.25+1)x(BS-.1) 43.3100 25.5529
1/2" 1.05 4x((LS-0.1)/0.25+1)x(H+E+0.3) 124.8000 131.0400
1/2" 1.05 ((BS-0.1)/0.25+1)x(H+E+0.3) 52.8000 55.4400 297.49 kg

05.13.00 Losa, concreto f'c=210 kg/cm2, con mezclador (EETx(BTxLT-0.7x0.7)+0.1x0.1x2x(0.9+0.7))x1.05 0.3073 0.31 m3

05.14.00 Losa, encofrado y desencofrado BTxLT+EETx2x(BT+LT)+2x(1.4x(0.1+EET)+1.8x0.1) 4.1875 4.19 m2

05.15.00 Losa, acero Fy=4,200kg/cm2


3/8" 0.59 ((LT-0.1)/0.25+1)x(BT+2xEES+0.2) 13.3200 7.8588
3/8" 0.59 ((BT-0.1)/0.25+1)x(LT+2xEES+0.2) 12.9000 7.6110 15.47 kg

05.16.00 Vertedero, concreto f'c=210 kg/cm2 con mezcl (BS-4xEES-BT)x0.15x(1.055+0.65) 0.3069 0.31 m3

05.17.00 Vertedero, encofrado y desencofrado (BS-4xEES-BT)x(1.055+0.80+0.65+.905) 4.0920 4.09 m2

05.18.00 Vertedero, acero Fy=4200kg/cm2


3/8" 0.59 ((BS-4xEES-BT-0.1)/.25+2)x2.005 12.8320 7.5709
3/8" 0.59 8x(BS-4*EES-BT+1.2) 19.2000 11.3280 18.90 kg

05.00.00 REVOQUES Y ENLUCIDOS


05.01.00 Tarrajeo int. c/ impermeabilizante 1:1, e=1.5 cm(h-0.1)(4(LE-2EEM)-1.6+3(BE-2EEM)) 7.3500
(LE-2EEM)(BE-3EEM)+0.8EEM+0.25(BE-2EEM) 3.5150
4H(L+B) 121.0400
4H((LS-EES)+(BS-4EES-BT)/2) 30.6000
3.41(BS-4EES-BT) 4.0920
EEFxBE+EEM(BE-4EEM+LE-0.80)+4EEFx0.30 1.2050 167.80 m2

05.02.00 Tarrajeo exterior de muros (mortero 1:5) (h+EEM)(BE+2LE)+BExLE+0.3*EEM 8.7300


(H-he)(2(L+2EEF+LS)+2(2B+3EEF)-BE) 69.6000
(H-he-h)BE 4.0000
2H(BT+LT)+BTxLT 22.6275
EEF(2(L+2B+3EEF)-BS)+EES(BS+2(LS-EES)) 6.9050
4(0.7(EET+0.1)+0.1x0.9)+2x0.1x1.6 1.3800 113.24 m2

06.00.00 MATERIAL FILTRANTE


06.01.00 Grava 1/8" 2LxBx0.05x1.05 1.9380 1.94 m3.

06.02.00 Grava 1/4" 2LxBx0.05x1.05 1.9380 1.94 m3.

06.03.00 Grava 1/2" 2LxBx0.08x1.05 3.1008 3.10 m3.

06.04.00 Grava 1" 2LxBx0.12x1.05 4.6512 4.65 m3.

06.05.00 Arena C.U. = 2 2LxBx(1.20+nxer)x1.05 53.7214 53.72 m3.

07.00.00 MAMPOSTERIA
07.01.00 Ladrillo maquinado sin huecos de 9x14x24 2((L/0.24)(B/0.15)+(L/.24)(B-0.09)/0.24)*1.05 1,820.3281 1,820 und

08.00.00 VARIOS
08.01.00 Falso piso con pendiente en filtros 1:4:8 (0.1+0.05)xLxB 2.9070 2.91 m3
08.02.00 Compuerta de limpieza de 0.50m 1.00 und.
08.03.00 Compuertas canal de distribucin de 0.30m 2.00 und.
08.04.00 Vlvula esfrica bridada 4" 2.00 und.
08.05.00 Vlvulas esfricas 4" 5.00 und.
08.06.00 Codo PVC-SAL 2" 8.00 und.
08.07.00 Tee PVC-SAL 2" 6.00 und.
08.08.00 Tubera PVC-SAL 2" 29.4550 30.00 ml
08.09.00 Rompe agua 2" 4.00 und.
08.10.00 Unin mixta PVC 2" 4.00 und.
08.12.00 Unin universal FG 4" 10.00 und.
08.13.00 Codo FG 4" 12.00 und.
08.14.00 Tee FG 4" 5.00 und.
08.15.00 Tubera FG 4" 6.00 ml
08.16.00 Niple FG 3"x 4" 24.00 und.
08.17.00 Losas prefabricadas de 0.5x0.7x0.10m. 2.00 und.
08.18.00 Water Stop 6" 2(2B+3EEF)+3L+2h+BE+2H+4LS+(BS-4EES-BT) 51.3000 52.00 ml
08.19.00 Tapa metlica de 0.80X0.80 1.00 und.
08.20.00 Escalines H/0.3 11.3333 12.00 und.
PROYECTO "CONSTRUCCIN DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE Y LETRINAS EN EL C.P. SAN MIGUEL DE SERN Y LOS CASEROS SAN JOS, JESS DEL VALLE Y CAHUIDE - VALLE DE LOS INCAS, DEL DISTRITO DE TAMBOGRANDE -
PIURA - PIURA"
FECHA JUNIO DEL 2011

VALORES DE LOS COHEFICIENTES (k) PARA EL CALCULO DE MOMENTOS - TAPA LIBRE Y FONDO
DISEO ESTRUCTURAL DEL SEDIMENTADOR EMPOTRADO

VOLUMEN V= 84.15 m3
LONGITUD DE ENTRADA L1 = 0.80 m
LONGITUD DE SEDIMENTADOR L2 = 9.40 m
ANCHO DEL SEDIMENTADOR B= 3.30 m
ALTURA DE TOLVA DE LODOS h= 1.00 m
ALTURA DEL SEDIMENTADOR Ha = 0.70 m
PROFUNDIDAD DE CIMENTACION he = 1.00 m (Igual a Altura de Tolva de Lodos)
BORDE LIBRE BL = 0.30 m
ALTURA TOTAL H= 2.00 m
PESO ESPECIFICO DEL AGUA ga = 1,000.00 kg/m3
CAPACIDAD PORTANTE st = 0.71 kg/cm2
RESISTENCIA DEL CONCRETO f'c = 175.00 kg/cm2 y=0 y = B/4 y = B/2
B/(Ha+h) x/(Ha+h)
ESFUERZO DE TRACCION POR FLEXION ft = 11.24 kg/cm2 (0.85f'c^0.5) Mx My Mx My Mx My
ESFUERZO DE FLUENCIA DEL ACERO Fy = 4,200.00 kg/cm2 0 0.000 0.025 0.000 0.014 0.000 -0.082
FATIGA DE TRABAJO fs = 1,680.00 kg/cm2 0.4Fy 1/ 4 0.010 0.019 0.007 0.013 -0.014 -0.071
RECUBRIMIENTO r= 5.00 cm 3.00 1/ 2 0.005 0.010 0.008 0.010 -0.011 -0.055
3/ 4 -0.330 -0.004 -0.018 0.000 -0.006 -0.028
1 -0.126 -0.025 -0.092 -0.018 0.000 0.000
0 0.000 0.027 0.000 0.013 0.000 -0.074
1/ 4 0.012 0.022 0.007 0.013 -0.013 -0.066
DISEO DE LOS MUROS 2.50 1/ 2 0.011 0.014 0.008 0.010 -0.011 -0.053
3/ 4 -0.021 -0.001 -0.010 0.001 -0.005 -0.027
RELACION B/(Ha) (0.5<=B/(Ha)<=3 1 -0.108 -0.022 -0.077 -0.015 0.000 0.000
1.94 TOMAMOS 2 0 0.000 0.027 0.000 0.009 0.000 -0.060
1/ 4 0.013 0.023 0.006 0.010 -0.012 -0.059
MOMENTOS EN LOS MUROS M=k*ga*(Ha)^3 ga*(Ha)^3 = 343.00 kg 2.00 1/ 2 0.015 0.016 0.010 0.010 -0.010 -0.049
3/ 4 -0.008 0.003 -0.002 0.003 -0.005 -0.027
y=0 y = B/4 y = B/2 1 -0.086 -0.017 -0.059 -0.012 0.000 0.000
B/(Ha+h) x/(Ha+h)
Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m) 0 0.000 0.025 0.000 0.007 0.000 -0.050
0 0.000 9.261 0.000 3.087 0.000 -20.580 1/ 4 0.012 0.022 0.005 0.008 -0.010 -0.052
1/ 4 4.459 7.889 2.058 3.430 -4.116 -20.237 1.75 1/ 2 0.016 0.016 0.010 0.009 -0.009 -0.046
2.00 1/ 2 5.145 5.488 3.430 3.430 -3.430 -16.807 3/ 4 -0.002 0.005 0.001 0.004 -0.005 -0.027
3/ 4 -2.744 1.029 -0.686 1.029 -1.715 -9.261 1 -0.074 -0.015 -0.050 -0.010 0.000 0.000
1 -29.498 -5.831 -20.237 -4.116 0.000 0.000 0 0.000 0.021 0.000 0.005 0.000 -0.040
1/ 4 0.008 0.020 0.004 0.007 -0.009 -0.044
1.50 1/ 2 0.016 0.016 0.010 0.008 -0.008 -0.042
MAXIMO MOMENTO ABSOLUTO M= 29.498 kg-m 3/ 4 0.003 0.006 0.003 0.004 -0.005 -0.026
ESPESOR DE PARED e = (6*M/(ft))^0.5 e= 3.97 cm 1 -0.060 -0.012 -0.041 -0.008 0.000 0.000
PARA EL DISEO ASUMIMOS UN ESPESO e= 15.00 cm 0 0.000 0.015 0.000 0.003 0.000 -0.029
MAXIMO MOMENTO ARMADURA VERTICA Mx = 29.498 kg-m 1/ 4 0.005 0.015 0.002 0.005 -0.007 -0.034
MAXIMO MOMENTO ARMADURA HORIZON My = 20.58 kg-m 1.25 1/ 2 0.014 0.015 0.008 0.007 -0.007 -0.037
PERALTE EFECTIVO d = e-r d= 10.00 cm 3/ 4 0.006 0.007 0.005 0.005 -0.005 -0.024
AREA DE ACERO VERT Asv = Mx/(fs*j*d) Asv = 0.196 cm2 1 -0.047 -0.009 -0.031 -0.006 0.000 0.000
AREA DE ACERO HORI Ash = My/(fs*j*d) Ash = 0.136 cm2 0 0.000 0.009 0.000 0.002 0.000 -0.018
k = 1/(1+fs/(n*fc) k= 0.306 1/ 4 0.002 0.011 0.000 0.003 -0.005 -0.023
j = 1-(k/3) j= 0.898 1.00 1/ 2 0.009 0.013 0.005 0.005 -0.006 -0.029
n = 2100/(15*(f'c)^0.5) n= 10.5830 3/ 4 0.008 0.008 0.005 0.004 -0.004 -0.020
fc = 0.4*f'c fc = 70.00 kg/cm2 1 -0.035 -0.007 -0.022 -0.005 0.000 0.000
r = 0.7*(f'c)^0.5/Fy r= 0.0022 0 0.000 0.004 0.000 0.001 0.000 -0.007
Asmin = r*100*e Asmin = 3.307 cm2 1/ 4 0.001 0.008 0.000 0.002 -0.002 -0.011
DIAMETRO DE VARILL F (pulg) = 1/2 1.29 cm2 de Area por varilla 0.75
Asvconsid = 3.87 cm2 1/ 2 0.005 0.010 0.002 0.003 -0.003 -0.017
Ashconsid = 3.87 cm2 3/ 4 0.007 0.007 0.003 0.003 -0.003 -0.013
ESPACIAMIENTO DEL ACERO espav 0.333 m Tomamos 0.25 m 1 -0.024 -0.005 -0.015 -0.003 0.000 0.000
PROYECTO "CONSTRUCCIN DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE Y LETRINAS EN EL C.P. SAN MIGUEL DE SERN Y LOS CASEROS SAN JOS, JESS DEL VALLE Y CAHUIDE - VALLE DE LOS INCAS, DEL DISTRITO DE TAMBOGRANDE -
PIURA - PIURA"
FECHA JUNIO DEL 2011

espah 0.333 m Tomamos 0.25 m 0 0.000 0.001 0.000 0.000 0.000 -0.002
1/ 4 0.000 0.005 0.000 0.001 -0.001 -0.004
CHEQUEO POR ESFUERZO CORTANTE Y ADHERENCIA 0.50 1/ 2 0.002 0.006 0.001 0.001 -0.002 -0.009
3/ 4 0.004 0.006 0.001 0.001 -0.001 -0.007
CALCULO FUERZA CORTANTE MAXIMA Vc = ga*(Ha)^2/2 = 245.00 kg 1 -0.015 -0.003 -0.008 -0.002 0.000 0.000
CALCULO DEL ESFUERZO CORTANTE NO nc = Vc/(j*100*d) = 0.27 kg/cm2
CALCULO DEL ESFUERZO PERMISIBLE nmax = 0.02*f'c = 3.50 kg/cm2
Verificar si nmax > nc Ok
CALCULO DE LA ADHERENCIA u= Vc/(So*j*d) = uv = 2.27 kg/cm2 uh = 2.27 kg/cm2
Sov = 12.00
Soh = 12.00
CALCULO DE LA ADHERENCIA PERMISIB umax = 0.05*f'c = 8.75 kg/cm2
Verificar si umax > uv Ok
Verificar si umax > uh Ok

DISEO DE LA LOSA DE FONDO

Considerando la losa de fondo como una placa flexible y empotrada en los bordes

MOMENTO DE EMPOTRAMIENTO EN EL EXTREMO M(1) = -W(L1+L2)^2/192


M(1) = -1,181.29
MOMENTO EN EL CENTRO M(2) = W(L1+L2)^2/384
M(2) = 590.64 kg-m
ESPESOR ASUMIDO DE LA LOSA DE FONDO el = 0.20 m
PESO SPECIFICO DEL CONCRETO gc = 2,400.00 kg/m3
CALCULO DE W W= ga*(h+Ha)+gc*el
W= 2,180.00 kg/m2
Para losas planas rectangulares armadas con armadura en dos direcciones Timoshenko recomienda los siguientes coheficientes

Para un momento en el centro 0.0513


Para un momento de empotramiento 0.529

MOMENTO DE EMPOTRAMIENTO Me = 0.529*M(1) = -624.90 kg-m


MOMENTO EN EL CENTRO Mc = 0.0513*M(2) = 30.30 kg-m
MAXIMO MOMENTO ABSOLUTO M = 624.90 kg-m
ESPESOR DE LA LOSA el = (6*M/(ft))^0.5 = 18.26 cm
PARA EL DISEO ASUMIMOS UN ESPESOR el = 20.00 cm
d= el-r = 15.00 cm
As = M/(fs*j*d) = 2.761 cm2
Asmin = r*100*el = 4.410 cm2
DIAMETRO DE VARILLA F (pulg) = 1/2 1.29 cm2 de Area por varilla
Asconsid = 5.16
espa varilla = 0.25 Tomamos 0.25 m
PROYECTO "ONSTRUCCION DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE Y LETRINAS EN LOS CASERIOS DE SAN MIGUEL DE SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DISTRITO DE
TAMBOGRANDE - PIURA - PIURA
FECHA JUNIO DEL 2011

VALORES DE LOS COHEFICIENTES (k) PARA EL CALCULO DE MOMENTOS - TAPA LIBRE Y FONDO
DISEO ESTRUCTURAL DE PREFILTROS DE GRAVA EMPOTRADO
B/(Ha+h) x/(Ha+h) y=0 y = B/4 y = B/2
VOLUMEN V= 81.66 m3 Mx My Mx My Mx My
LONGITUD PRIMER TRAMO L1 = 1.50 m 3.00 0 0.000 0.025 0.000 0.014 0.000 -0.082
LONGITUD SEGUNDO TRAMO TRAMO L2 = 1.50 m 1/ 4 0.010 0.019 0.007 0.013 -0.014 -0.071
LONGITUD TERCER TRAMO L3 = 1.40 m 1/ 2 0.005 0.010 0.008 0.010 -0.011 -0.055
ANCHO DEL SEDIMENTADOR B= 3.60 m 3/ 4 -0.330 -0.004 -0.018 0.000 -0.006 -0.028
ALTURA DEL MATERIAL h= 2.32 m 1 -0.126 -0.025 -0.092 -0.018 0.000 0.000
LONGITUD A CONSIDERAR L= 1.50 m 2.50 0 0.000 0.027 0.000 0.013 0.000 -0.074
BORDE LIBRE BL = 1.03 m 1/ 4 0.012 0.022 0.007 0.013 -0.013 -0.066
ALTURA TOTAL H= 3.35 m 1/ 2 0.011 0.014 0.008 0.010 -0.011 -0.053
PROFUNDIDAD DE CIMENTACION he = 1.20 m (Mnimo 1.20 mts) 3/ 4 -0.021 -0.001 -0.010 0.001 -0.005 -0.027
PESO ESPECIFICO DEL MATERIAL HUMEDO gm = 1,000.00 kg/m3 1 -0.108 -0.022 -0.077 -0.015 0.000 0.000
CAPACIDAD PORTANTE st = 0.71 kg/cm2 2.00 0 0.000 0.027 0.000 0.009 0.000 -0.060
RESISTENCIA DEL CONCRETO f'c = 175.00 kg/cm2 1/ 4 0.013 0.023 0.006 0.010 -0.012 -0.059
ESFUERZO DE TRACCION POR FLEXION ft = 11.24 kg/cm2 (0.85f'c^0.5) 1/ 2 0.015 0.016 0.010 0.010 -0.010 -0.049
ESFUERZO DE FLUENCIA DEL ACERO Fy = 4,200.00 kg/cm2 3/ 4 -0.008 0.003 -0.002 0.003 -0.005 -0.027
FATIGA DE TRABAJO fs = 1,680.00 kg/cm2 0.4Fy 1 -0.086 -0.017 -0.059 -0.012 0.000 0.000
RECUBRIMIENTO r= 5.00 cm 1.75 0 0.000 0.025 0.000 0.007 0.000 -0.050
1/ 4 0.012 0.022 0.005 0.008 -0.010 -0.052
1/ 2 0.016 0.016 0.010 0.009 -0.009 -0.046
3/ 4 -0.002 0.005 0.001 0.004 -0.005 -0.027
1 -0.074 -0.015 -0.050 -0.010 0.000 0.000
DISEO DE LOS MUROS 1.50 0 0.000 0.021 0.000 0.005 0.000 -0.040
1/ 4 0.008 0.020 0.004 0.007 -0.009 -0.044
RELACION (L+0.2)/(h) 0.5<=(L+0.2)/(h)<=3 1/ 2 0.016 0.016 0.010 0.008 -0.008 -0.042
0.73 TOMAMOS 0.75 0.75 3/ 4 0.003 0.006 0.003 0.004 -0.005 -0.026
1 -0.060 -0.012 -0.041 -0.008 0.000 0.000
MOMENTOS EN LOS MUROS INTERIORES M=k*gm*(h)^3 gm*(h)^3 = 12,487.17 kg 1.25 0 0.000 0.015 0.000 0.003 0.000 -0.029
MOMENTOS EN LOS MUROS INTERIORES 1/ 4 0.005 0.015 0.002 0.005 -0.007 -0.034
y=0 y = B/4 y = B/2 1/ 2 0.014 0.015 0.008 0.007 -0.007 -0.037
B/(Ha+h) x/(Ha+h)
Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m) 3/ 4 0.006 0.007 0.005 0.005 -0.005 -0.024
0 0.000 49.949 0.000 12.487 0.000 -87.410 1 -0.047 -0.009 -0.031 -0.006 0.000 0.000
1/ 4 12.487 99.897 0.000 24.974 -24.974 -137.359 1.00 0 0.000 0.009 0.000 0.002 0.000 -0.018
0.75 1/ 2 62.436 124.872 24.974 37.462 -37.462 -212.282 1/ 4 0.002 0.011 0.000 0.003 -0.005 -0.023
3/ 4 87.410 87.410 37.462 37.462 -37.462 -162.333 1/ 2 0.009 0.013 0.005 0.005 -0.006 -0.029
1 -299.692 -62.436 -187.308 -37.462 0.000 0.000 3/ 4 0.008 0.008 0.005 0.004 -0.004 -0.020
1 -0.035 -0.007 -0.022 -0.005 0.000 0.000
0 0.000 0.004 0.000 0.001 0.000 -0.007
MAXIMO MOMENTO ABSOLUTO M= 299.692 kg-m 1/ 4 0.001 0.008 0.000 0.002 -0.002 -0.011
ESPESOR DE PARED e = (6*M/(ft))^0.5 e= 12.65 cm
PARA EL DISEO ASUMIMOS UN ESPESOR e= 30.00 cm 0.75 1/ 2 0.005 0.010 0.002 0.003 -0.003 -0.017
MAXIMO MOMENTO ARMADURA VERTICAL Mx = 299.692032 kg-m 3/ 4 0.007 0.007 0.003 0.003 -0.003 -0.013
MAXIMO MOMENTO ARMADURA HORIZONTAL My = 212.281856 kg-m 1 -0.024 -0.005 -0.015 -0.003 0.000 0.000
PERALTE EFECTIVO d = e-r d= 25.00 cm 0 0.000 0.001 0.000 0.000 0.000 -0.002
AREA DE ACERO VERTIC Asv = Mx/(fs*j*d) Asv = 0.795 cm2 1/ 4 0.000 0.005 0.000 0.001 -0.001 -0.004
AREA DE ACERO HORIZ Ash = My/(fs*j*d) Ash = 0.563 cm2 0.50 1/ 2 0.002 0.006 0.001 0.001 -0.002 -0.009
k = 1/(1+fs/(n*fc) k= 0.306 3/ 4 0.004 0.006 0.001 0.001 -0.001 -0.007
j = 1-(k/3) j= 0.898 1 -0.015 -0.003 -0.008 -0.002 0.000 0.000
n = 2100/(15*(f'c)^0.5) n= 10.5830
fc = 0.4*f'c fc = 70.00 kg/cm2
r = 0.7*(f'c)^0.5/Fy r= 0.0022
PROYECTO "ONSTRUCCION DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE Y LETRINAS EN LOS CASERIOS DE SAN MIGUEL DE SEREN, SAN JOSE, JESUS DEL VALLE Y CAHUIDE, ZONA DE VALLE DE LOS INCAS DEL DISTRITO DE
TAMBOGRANDE - PIURA - PIURA
FECHA JUNIO DEL 2011
Asmin = r*100*e Asmin = 6.614 cm2
DIAMETRO DE VARILLA F (pulg) = 5/8 2.00 cm2 de Area por varilla
Asvconsid = 8 cm2
Ashconsid = 8 cm2
ESPACIAMIENTO DEL ACERO espav 0.250 m Tomamos 0.20 m
espah 0.250 m Tomamos 0.20 m

CHEQUEO POR ESFUERZO CORTANTE Y ADHERENCIA

CALCULO FUERZA CORTANTE MAXIMA Vc = gm*(h)^2/2 = 2,691.20 kg


CALCULO DEL ESFUERZO CORTANTE NOMINAL nc = Vc/(j*100*d) = 1.20 kg/cm2
CALCULO DEL ESFUERZO PERMISIBLE nmax = 0.02*f'c = 3.50 kg/cm2
Verificar si nmax > nc Ok
CALCULO DE LA ADHERENCIA u= Vc/(So*j*d) = uv = 4.80 kg/cm2 uh = 4.80 kg/cm2
Sov = 25.00
Soh = 25.00
CALCULO DE LA ADHERENCIA PERMISIBLE umax = 0.05*f'c = 8.75 kg/cm2
Verificar si umax > uv Ok
Verificar si umax > uh Ok

DISEO DE LA LOSA DE FONDO


Considerando la losa de fondo como una placa flexible y empotrada en los bordes

MOMENTO DE EMPOTRAMIENTO EN EL EXTREMO M(1) = -W(L)^2/192


M(1) = -32.81 kg-m
MOMENTO EN EL CENTRO M(2) = W(L)^2/384
M(2) = 16.41 kg-m
ESPESOR ASUMIDO DE LA LOSA DE FONDO el = 0.20 m
PESO SPECIFICO DEL CONCRETO gc = 2,400.00 kg/m3
CALCULO DE W W= gm*(h)+gc*el
W= 2,800.00 kg/m2
Para losas planas rectangulares armadas con armadura en dos direcciones Timoshenko recomienda los siguientes coheficientes

Para un momento en el centro 0.0513


Para un momento de empotramiento 0.529

MOMENTO DE EMPOTRAMIENTO Me = 0.529*M(1) = -17.36 kg-m


MOMENTO EN EL CENTRO Mc = 0.0513*M(2) = 0.84 kg-m
MAXIMO MOMENTO ABSOLUTO M = 17.36 kg-m
ESPESOR DE LA LOSA el = (6*M/(ft))^0.5 = 3.04 cm
PARA EL DISEO ASUMIMOS UN ESPESOR el = 20.00 cm
d= el-r = 15.00 cm
As = M/(fs*j*d) = 0.077 cm2
Asmin = r*100*el = 4.410 cm2
DIAMETRO DE VARILLA F (pulg) = 5/8 2.00 cm2 de Area por varilla
Asconsid = 6
espa varilla = 0.33 Tomamos 0.20 m
Proyecto :
"CONSTRUCCIN DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE
Y LETRINAS EN EL C.P. SAN MIGUEL DE SERN Y LOS CASEROS SAN
JOS, JESS DEL VALLE Y CAHUIDE - VALLE DE LOS INCAS, DEL
DISTRITO DE TAMBOGRANDE - PIURA - PIURA"

Fecha : JUNIO DEL 2011

DISEO ESTRUCTURAL DE LOS FILTROS LENTOS

ANCHO DEL SEDIMENTADOR B= 3.80 m


ALTURA DEL MATERIAL Y AGUA h= 2.93 m
LONGITUD DEL SEDIMENTADOR L= 5.10 m
PROFUNDIDAD DE CIMENTACION he = 1.20 m (Mnimo 1.20 mts)
BORDE LIBRE BL = 0.47 m
ALTURA TOTAL H= 3.40 m
PESO ESPECIFICO PROMEDIO gm = 1,500.00 kg/m3
CAPACIDAD PORTANTE st = 0.71 kg/cm2
RESISTENCIA DEL CONCRETO f'c = 175.00 kg/cm2
ESFUERZO DE TRACCION POR FLEXION ft = 11.24 kg/cm2 (0.85f'c^0.5)
ESFUERZO DE FLUENCIA DEL ACERO Fy = 4,200.00 kg/cm2
FATIGA DE TRABAJO fs = 1,680.00 kg/cm2 0.4Fy
RECUBRIMIENTO r= 5.00 cm

DISEO DE LOS MUROS DE FILTROS LENTOS

RELACION B/(h-he) 0.5<=B/(h-he)<=3


2.20 TOMAMOS 2

MOMENTOS EN LOS MUROS M=k*gm*(h-he)^3 gm*(h-he)^3 = 7,766.58 kg

y=0 y = B/4 y = B/2


B/(Ha+h) x/(Ha+h)
Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m) Mx (kg-m) My (kg-m)
0 0.000 209.698 0.000 69.899 0.000 -465.995
1/ 4 100.965 178.631 46.599 77.666 -93.199 -458.228
2.00 1/ 2 116.499 124.265 77.666 77.666 -77.666 -380.562
3/ 4 -62.133 23.300 -15.533 23.300 -38.833 -209.698
1 -667.925 -132.032 -458.228 -93.199 0.000 0.000

MAXIMO MOMENTO ABSOLUTO M= 667.925 kg-m


ESPESOR DE PARED e = (6*M/(ft))^0.5 e= 18.88 cm
PARA EL DISEO ASUMIMOS UN ESPESOR e= 25.00 cm
MAXIMO MOMENTO ARMADURA VERTICAL Mx = 667.925493 kg-m
MAXIMO MOMENTO ARMADURA HORIZONTAL My = 465.99453 kg-m
PERALTE EFECTIVO d = e-r d= 20.00 cm
AREA DE ACERO VERTIC Asv = Mx/(fs*j*d) Asv = 2.214 cm2
AREA DE ACERO HORIZ Ash = My/(fs*j*d) Ash = 1.544 cm2
k = 1/(1+fs/(n*fc) k= 0.306
j = 1-(k/3) j= 0.898
n = 2100/(15*(f'c)^0.5) n= 10.5830
fc = 0.4*f'c fc = 70.00 kg/cm2
r = 0.7*(f'c)^0.5/Fy r= 0.0022
Asmin = r*100*e Asmin = 5.512 cm2
DIAMETRO DE VARILLA F (pulg) = 1/2 1.29 cm2 de Area por varilla
Asvconsid = 6.45 cm2
Ashconsid = 6.45 cm2
ESPACIAMIENTO DEL ACERO espav 0.200 m Tomamos 0.20 m
espah 0.200 m Tomamos 0.20 m

CHEQUEO POR ESFUERZO CORTANTE Y ADHERENCIA

CALCULO FUERZA CORTANTE MAXIMA Vc = gm*(h-he)^2/2 = 2,244.68 kg


CALCULO DEL ESFUERZO CORTANTE NOMINAL nc = Vc/(j*100*d) = 1.25 kg/cm2
CALCULO DEL ESFUERZO PERMISIBLE nmax = 0.02*f'c = 3.50 kg/cm2
Verificar si nmax > nc Ok
Proyecto :
"CONSTRUCCIN DEL SISTEMA DE ABASTECIMIENTO DE AGUA POTABLE
Y LETRINAS EN EL C.P. SAN MIGUEL DE SERN Y LOS CASEROS SAN
JOS, JESS DEL VALLE Y CAHUIDE - VALLE DE LOS INCAS, DEL
DISTRITO DE TAMBOGRANDE - PIURA - PIURA"

Fecha : JUNIO DEL 2011

DISEO ESTRUCTURAL DE LOS FILTROS LENTOS


CALCULO DE LA ADHERENCIA u= Vc/(So*j*d) = uv = 6.25 kg/cm2 uh = 6.25 kg/cm2
Sov = 20.00
Soh = 20.00
CALCULO DE LA ADHERENCIA PERMISIBLE umax = 0.05*f'c = 8.75 kg/cm2
Verificar si umax > uv Ok
Verificar si umax > uh Ok

DISEO DE LA LOSA DE FONDO DE FILTROS LENTOS

Considerando la losa de fondo como una placa flexible y empotrada en los bordes

MOMENTO DE EMPOTRAMIENTO EN EL EXTREMO M(1) = -W(L)^2/192


M(1) = -692.92 kg-m
MOMENTO EN EL CENTRO M(2) = W(L)^2/384
M(2) = 346.46 kg-m
ESPESOR ASUMIDO DE LA LOSA DE FONDO el = 0.30 m
PESO SPECIFICO DEL CONCRETO gc = 2,400.00 kg/m3
CALCULO DE W W= gm*(h)+gc*el
W= 5,115.00 kg/m2
Para losas planas rectangulares armadas con armadura en dos direcciones Timoshenko recomienda los siguientes coheficientes

Para un momento en el centro 0.0513


Para un momento de empotramiento 0.529

MOMENTO DE EMPOTRAMIENTO Me = 0.529*M(1) = -366.56 kg-m


MOMENTO EN EL CENTRO Mc = 0.0513*M(2) = 17.77 kg-m
MAXIMO MOMENTO ABSOLUTO M = 366.56 kg-m
ESPESOR DE LA LOSA el = (6*M/(ft))^0.5 = 13.99 cm
PARA EL DISEO ASUMIMOS UN ESPESOR el = 30.00 cm
d= el-r = 25.00 cm
As = M/(fs*j*d) = 0.972 cm2
Asmin = r*100*el = 6.614 cm2
DIAMETRO DE VARILLA F (pulg) = 1/2 1.29 cm2 de Area por varilla
Asconsid = 7.74
espa varilla = 0.17 Tomamos 0.15 m
VALORES DE LOS COHEFICIENTES (k) PARA EL CALCULO DE MOMENTOS - TAPA LIBRE Y FONDO
EMPOTRADO

y=0 y = B/4 y = B/2


B/(Ha+h) x/(Ha+h)
Mx My Mx My Mx My
0 0.000 0.025 0.000 0.014 0.000 -0.082
1/ 4 0.010 0.019 0.007 0.013 -0.014 -0.071
3.00 1/ 2 0.005 0.010 0.008 0.010 -0.011 -0.055
3/ 4 -0.330 -0.004 -0.018 0.000 -0.006 -0.028
1 -0.126 -0.025 -0.092 -0.018 0.000 0.000
0 0.000 0.027 0.000 0.013 0.000 -0.074
1/ 4 0.012 0.022 0.007 0.013 -0.013 -0.066
2.50 1/ 2 0.011 0.014 0.008 0.010 -0.011 -0.053
3/ 4 -0.021 -0.001 -0.010 0.001 -0.005 -0.027
1 -0.108 -0.022 -0.077 -0.015 0.000 0.000
0 0.000 0.027 0.000 0.009 0.000 -0.060
1/ 4 0.013 0.023 0.006 0.010 -0.012 -0.059
2.00 1/ 2 0.015 0.016 0.010 0.010 -0.010 -0.049
3/ 4 -0.008 0.003 -0.002 0.003 -0.005 -0.027
1 -0.086 -0.017 -0.059 -0.012 0.000 0.000
0 0.000 0.025 0.000 0.007 0.000 -0.050
1/ 4 0.012 0.022 0.005 0.008 -0.010 -0.052
1.75 1/ 2 0.016 0.016 0.010 0.009 -0.009 -0.046
3/ 4 -0.002 0.005 0.001 0.004 -0.005 -0.027
1 -0.074 -0.015 -0.050 -0.010 0.000 0.000
0 0.000 0.021 0.000 0.005 0.000 -0.040
1/ 4 0.008 0.020 0.004 0.007 -0.009 -0.044
1.50 1/ 2 0.016 0.016 0.010 0.008 -0.008 -0.042
3/ 4 0.003 0.006 0.003 0.004 -0.005 -0.026
1 -0.060 -0.012 -0.041 -0.008 0.000 0.000
0 0.000 0.015 0.000 0.003 0.000 -0.029
1/ 4 0.005 0.015 0.002 0.005 -0.007 -0.034
1.25 1/ 2 0.014 0.015 0.008 0.007 -0.007 -0.037
3/ 4 0.006 0.007 0.005 0.005 -0.005 -0.024
1 -0.047 -0.009 -0.031 -0.006 0.000 0.000
0 0.000 0.009 0.000 0.002 0.000 -0.018
1/ 4 0.002 0.011 0.000 0.003 -0.005 -0.023
1.00 1/ 2 0.009 0.013 0.005 0.005 -0.006 -0.029
3/ 4 0.008 0.008 0.005 0.004 -0.004 -0.020
1 -0.035 -0.007 -0.022 -0.005 0.000 0.000
0 0.000 0.004 0.000 0.001 0.000 -0.007
1/ 4 0.001 0.008 0.000 0.002 -0.002 -0.011
0.75
1/ 2 0.005 0.010 0.002 0.003 -0.003 -0.017
3/ 4 0.007 0.007 0.003 0.003 -0.003 -0.013
1 -0.024 -0.005 -0.015 -0.003 0.000 0.000
0 0.000 0.001 0.000 0.000 0.000 -0.002
1/ 4 0.000 0.005 0.000 0.001 -0.001 -0.004
0.50 1/ 2 0.002 0.006 0.001 0.001 -0.002 -0.009
3/ 4 0.004 0.006 0.001 0.001 -0.001 -0.007
1 -0.015 -0.003 -0.008 -0.002 0.000 0.000