Vous êtes sur la page 1sur 22

BASIC DATAS

1. Density of cement -----------------------------------------------1400 kg/m3

2. River sand ------------------------------------------------------- 1840 ,,

3. Stone Aggregate ------------------------------------------------ 2250 ,,

4. Pumice ------------------------------------------------------------ 700 ,,

5. Mass Concrete --------------------------------------------------- 2300 ,,

6. Reinforced Concrete -------------------------------------------- 2400 ,,

7. Lime ------------------------------------------------------------- 1900 ,,

8. Steel ------------------------------------------------------------ 7850 ,,

9. Cement Mortar ------------------------------------------------- 2300 ,,

10.Compo Mortar ------------------------------------------------- 1700 ,,

11.Basaltic Stone ------------------------------------------------- 2700 ,,

12.Trachetic Stone ---------------------------------------------- 2600 ,,

13.Pumice Stone ------------------------------------------------ 950 ,,


CONTENTS

1. Nails-----------------------------------------------------------------------------2

2. Ceiling ------------------------------------------------------------------------- 2

3. Nails for form-work --------------------------------------------------------- 3

4. Standard concrete mix ------------------------------------------------ 3

5. Form- work ------------------------------------------------------------------- 5

6. Walling materials ------------------------------------------------------------ 8

7. Pointing, plastering, rendering & smoothening ------------------------ 11

8. Roofing materials ---------------------------------------------------------- 14

9. Flooring materials ---------------------------------------------------------- 16

10. Painting materials --------------------------------------------------------- 18

11.Dump-proofing ------------------------------------------------------------ 20

12.Site-work ------------------------------------------------------------------- 21
BREAK DOWN OF CONSTRUCTION

MATERIALS

PREPARED BY ETHIOPIAN BUILDING

CONSTRUCTION AUTORITY
ITEM DESCRPTION QUANTITY REMARK
1 Roof nails 9 or 15 pcs / sheet
2 Plaster washer 500 pcs / pakt
3 Purlin nails 10-12cm 2pcs/pc (8 nails/truss)
4 Truss nails 12-15cm 100 pcs / truss
5 Form-work nails 10cm 2pcs/ pc
6 Purlin nails 8cm 4pcs/pc
7 Ceiling batten 8cm 50pcs / chip board
8 F.W nails 4cm 12pcs/ pc
9 Chip board nails 1-2cm 80pcs / chi board
10 Truss nail 4cm 50 pcs/ truss
11 F.W nails 6cm 8pcs/ pc
12 Purlin nails 4cms 15pcs/pc
13 Band iron 16mm 3-5kgs/ truss
14 1cm nails 950 pcs/kg
15 2 ,, ,, 815 ,,
16 4 ,, ,, 546 ,,
17 6 ,, ,, 275 ,,
18 7 ,, ,, 180 ,,
19 8 ,, ,, 127 ,,
20 10 ,, ,, 63 ,,
21 12 ,, ,, 44 ,,
22 15 ,, ,, 29 ,,
23 Roofing nails 105,,
24 Band iron 16mm 15m/kg
25 Wire diam 2mm 50m/kg
26 ,, beam 10x40 0.3kgs/m3
27 ,, slab c/c 30cm 0.1kgs/m2
28 Zigba truss 4mm long 13pcs/truss (5m. span)
cave 1.7cm
29 ,, purlin 4m long 12pcs/ truss c/c 2.4m
6x2 purlins
ITEM DESCRPTION QUANTITY REMARK
30 Preservative 0.2 gal/truss
31 Eucal. Truss diam 8-10 6.7ml. 4pcs/ truss
7m. span-cave 1.7cm
32 ,, purlin ,, 6-8 5-7ml . 16 pcs/ truss
c/c 24-8x2 purlin
33 Roofing nail 6cm 315pcs/ pakt
34 Plastic washer 500 pcs / pakt
35 Roofing nail 14 pcs/ C.I.S
36 Turss 10 or 12 cm nails 20 to 35 pcs/ truss
37 Purlin 8mm nails 8 pcs/ml
CEILING
38 Battens 8cm nails 16 pcs /m2
39 Chip wood 4cm nails 80 pcs/pc or chip wood
or 25 pcs /m2
40 Beams pin works
6cm nails 60 pcs/ml
12cm nails 6-8 pcs/ml (stiffening)
41 1 gallon of paint 4kgs
42 1 liter 0.22gallon
43 25mm band iron 1kg/7ml 1.2ml/joint=0.17kg/ join.
44 16mm ,, ,, 1kg/15ml 1.2ml/joint=0.08kg/joint

45 1mm thick steel sheet 7.85 kgs/m2

46 1mm thick aluminum sheet 2.75 ,,

47 1mm thick galvanized iron sheet 0.381 kgs/m2

48 8mm thick angle iron 7.09 kgs/ml

49 3mm thick angle iron 2.79 ,,

50 6mm nails for band iron 20pcs/joint

51 ceiling battens 1pc/m2

52 8cm.nails 12 pcs/m2

52 Abujeded cover 1roll=28m2


1kg animal glue /5m2

53 Ceiling fillets of 1pc 4ml.cover/m2

54 putty 0.25kg /m2


ITEM DESCRPTION QUANTITY REMARK
55 1-3mm thick glass 1.10m2/m2
56 6mm thick chip wood 1.05 m2/m2
57 H.C.B production
Cement .02 pt/m2 of H.C.B
Sand 0.04m3/m2 ,, ,,
Fine aggregate 0.14m3/m2 ,, ,,
58 Bituminous damp proofing for
floor 0.42 kg/m2
59 H.C.B bituminous on to of
ground slab 45% 1.58 pcs/ truss
NAILS FOR RORM WORK
60 6cm . nails 75pcs/m2
61 12cm nails 15pcs/m2 for stiffening
62 Eucalyptus 10cm nail 20-25 pcs/truss
63 J hooks for asbestos sheet 9-10 pcs/sheet
64 Wire mesh 1roll=25ml
65 Barbed wire 1roll=200ml
66 U-nails 480 pcs/kg
67 3mm thick glass=130x120cm 1 pakt = 5kgs
68 4mm ,, ,, =120x240cm 1case=15pcs=41m2
69 5mm ,, ,, =200x300cm 1case=14pcs=40m2
70 15cm thick light weight concert 1case=6pcs=30m2
Mortar 0.16m3/m2
Cement 0.403qts/m2
Sand pumice 0.19m3/m2

STANDARD CONCRETE MIX PER BAG OF CEMENT:-


STANDARD BOX SIZES:- 40 x 50 x 16cm. A

40 x 50 x 18cm. B

40 x 50 x 20 ,, C

MINUMUM SLUMP HELGHT 30mm

MAXLMUM ,, ,, 60mm

CON-GRA MATERALS SIZE & NO BOXS REMARK


C-5 Sand 4C
Crushed Agg. 6C
Water 60LIT
C-10 Sand 3B
Crushed Agg. 6B
Water 50LIT
C-15 Sand 2C
Crushed Agg. 4C
Water 40LIT
C-20 Sand 2C
Crushed Agg. 3C
Water 34LIT
C-25 Sand 2B
Crushed Agg. 3B
Water 31LIT
C-30 Sand 2A
Crushed Agg. 3A
Water 29LIT

Note:-
1. Volume of water given is for surface dry aggregate. The actual volume will be
depending on the water content of the aggregate. Adjustments should be made
based on the slump.
2. Concrete grade C-25 & C-30 require class II work-man ship i.e Mixer vibrator &
qualified supervisor.
GENERAL FORMAL
Assumed concrete mix ratio 1:2:4
Volume of concrete Xm3
a) Cement ..= 1/7 x Xm3 x 1400kg/m3 x 1.30 shrinkage x 1.05 wastage
b) Sand .. =2/7 x Xm3 x 1.30 shrinkage x 1.55 wastage
c) Gravel ...= 4/7 x Xm3 x 1.3 ,, x 1.15 wastage
Assumed mortar mix ratio 1:2:9
Volume of cement lime mortar= Xm3 Zm3
a) Cement = 1/12 x Zm3 x 1.2 shrinkage x1400kg/m3 x 1.05 wastage
b) Lime = 2/12 x Zm3 x 1.2 ,, x 1100kg/m3 x1.05 ,,
c) Sand .= 9/12 x Zm3 x 1.2 ,, x 1.2 wastage
1 Cart away (with 25% bulkage ) 1.25 m3/m3
2 Back fill ( with 15% decrease ) after
consolidation. 1.15 m3/m3
CONCRETE C-7
3 Mechanical mix 1:2.5:6 cement = 1.5 qt/m3
sand = 0.50m3/m3
gravel = 0.80 ,,
Hand mix 1:2:3.5 cement = 1.8 qt/m3
sand = 0.50m3/m3
gravel = 0.85 ,,
4 CONCRETE C-15
Mechanical 1:2.5:3.5 cement = 2.8 qt/m3
sand = 0.53m3/m3
gravel = 0.90 ,,

Hand mix 1: 2 : 3.5 cement = 2.94 qt/m3


sand = 0.46m3/m3
gravel = 0.80 ,,
5 CONCRETE C-20
Mechanical mix 1:2:3 cement = 3.1 qt/m3
sand = 0.5m3/m3
gravel = 0.90 ,,
6 CONCRETE C-25
Mechanical mix 1 : 1.5 : 3 cement = 3.6 qt/m3
sand = 0.5m3/m3
gravel = 0.90 ,,
7 CONCRETE C-30
Mechanical mix 1 : 1.5 : 3 cement = 4 qt/m3
sand = 0.45m3/m3
gravel = 0.75 ,,
8 Reinforcement-bar 1.05kg/kg

FORM WORK
ITEM DESCRIPTION QUANTITY REMARK
1 F.W for column of 30 x 30cm
a) 2.5 cm thick boards 0.018m3/m2
b) 5x7 cm battens 1.4ml/m2
c)diam 6cm eucalyptus structure 1ml/m2
d)nail .30kg/m2
2 F.W for suspended beam of 25 x25cm height
above ground or floor not exceed 3m
a) 2.5 cm thick boards 0.013m3/m2
b) 5x7 cm battens 1.10ml/m2
c)diam 8cm eucalyptus structure 1.5ml/m2
d)nail 0.30kg/m2
3 F.W for flat surface of slab height not
exceeding 3m
a) 2.5 cm thick boards 0.025m3/m2
ITEM DESCRIPTION QUANTITY REMARK
b) 3x10cm battens 2ml/m2
c)diam 8cm eucalyptus props 1.50ml/m2
d)diam 6cm eucalyptus bracing 1ml/m2
e)nail 0.02kg/m2
4 F.W for edges
of slab, height not exceeding 20 cm
a) boards 0.001m3/ml
b) battens 0.003m3/ml
c)nail 0.05kg/ml
5 F.W for sides of the walls (2 usages for
boards)
a)2.5 cm thick boards with 5% wastage 0.53m2/m2
b) 50x75mm battens 5usages with 5%
wastage 0.84ml/m2
c)50x125mm beam with 5% wastage & 10
usage 0.10ml/m2
d)diam. 60mm eucalyptus strust. 10 Usages 0.10ml/m2
e)nails, clips, ----etc 0.30kgs/m2
f)Mould oil 0.06lit/m2
6 Soffit F.W for slab props height not
exceeding 300mm
a)2.5cm thick boards with 5% wastage & 4
usage 0.27m2/m2
b)30x100mm battens 10 usages 0.42ml/m2
c)75x125m beams 0.15ml/m2
d)20x100mm bracing of 20 usages 0.10ml/m2
e)Nails 0.20kg/m2
f)mould 0.06lit/m2
7 F.W for edges of the slab width not exceeding
200mm.
a) 2.5cm thick boards with 4 usages & 5%
wastage 0.53m2/m2
ITEM DESCRIPTION QUANTITY REMARK
b) 50x 50 mm battens 8 usage 0.25ml/m2
c)nails 0.05kgs/m2
8 F.W. for face of steps & edge of the slab
width over 20cm not exceeding 25cm.
a)25 x 250mm boards wing u usages 0.25m2/m2
b)50x50mm battens with 10 usages 0.25ml/m
c)Nails 0.05kg/m
d)Mould oil 0.015lit/m
9 F.W for sides of the footing width not
exceeding 25cm.
a)2.5 thick boards with 4 usages 0.07m2/m
b)50x50mm battens with 10 usages 0.32ml/m
c)Nails 0.05kg/m
d)mould oil 0.015lit/m
10 Ditto, but width over 25cm but not exceeding
35cm
a)2.5cm thick board with 4 usages 0.10m2/m.
b)50x50mm battens with 10usages 0.38ml/m
c)Nails 0.07kg/m
d)Mould oil 0.21lit/m
11 F.W for sides of the ground beam & footing
width over 45cm.
a)2.5cm thick boards with 4 usages 0.27m2/m2
b)50x100mm battens with 10 usages 0.32ml/m2
c)diam. 60mm struts with 10 usages 0.21ml/m2
d)nails 0.20kg/m2
12 e)Mould oil 0.06lit/m2
F.W for sides of the foundation wall
a)2.5cm thick board 4 usages 0.27m2/m2
b)50x75mm battens with 10 usages battens 0.47m/m2
c)50x125mm beams with 10 usages 0.11m/m2
d)diam60mm eucalyptus struts with 10 usage 0.10m/m2
ITEM DESCRIPTION QUANTITY REMARK
e)Nail 0.25kg/m2
f)mould oil 0.06lit/m2
13 F.W. for side of the foundation columns
a)2.5cm thick boards 0.27m2/m2
b)50x100mm beams with 10 usage 0.27m2/m2
c)diam 60cm eucalyptus struts of 10 usages 0.10m/m2
d)Nails 0.20kg/m2
e)Mould oil 0.06lit/m2
14 F.W for sides of the columns
a)2.5cm thick boards with 4 usages 0.27m3/m2
b)50x75mm battens with 10 usages 4.6ml/m2 0.46m2/m2
c)diam. 60 mm eucalyptus struts with 10
usage 0.20m2/m2
d)Nails 0.30kg/m2
e)Mould oil 0.06lit/m2
15 F.W for sides of the beam
a)2.5cm thick board with 1 usages 0.27m2/m2
b)50x75mm battens of 10usages 4.2m/m2 0.46/m/m2
c)50x100mm beam 10 usage 0.20m/m2
d)Nails 0.3kg/m3
e)Mould oil 0.06lit/m2
16 F.W for sides of the wall
a)2.5cm thick boards with 4 usages 0.27m2/m2
b)50x75mm battens 10 usages 0.46m/m2
c)50x125mm beam 10 usage 0.105m/m2
d)diam. 60mm eucalyptus struts with 10 0.10m/m2
usages 0.30kg/m2
e)Nails 0.06lit/m2
f)mould oil

WALLING MATERIALS
ITEM DESCRIPTION QUANTITY REMARK
1 50cm thick stone masonry foundation wall in
cement mortar of 1:4.
a)stone 1.31m3/m3
b)Mortar 0.36m3/m3
c)cement 1.01qr/m3
d)sand 0.29m3/m3
2 Dittto above foundation one side roughly
dressed
a)stone 1.40m3/m3
b)Mortar, cement & sand are similar to above
12cm thick brick wall in compo-mortar of
3 1:2:9 both sides left for plastering
a)Brick
b)Mortar ( with 15% wastage) 57.7pcs/m2
c)cement 0.0263m3/m2
d)Lime 0.031qt/m2
e)Sand 0.053qt/m2
Ditto 25cm brick wall 0.02m3/m2
4 a)Bricks
b)Mortar ( with 15%wastage) 115.4pc/m2
c)Cement 0.062m3/m2
d)Lime 0.07qt/m2
e)Sand 0.02qt/m2
Ditto 10cm hollow concrete block wall 0.05m3/m2
5 a)H.C.B
b)Mortar with 15% waste 12.3pc/m2
c)Cement 0.0092m3/m2
d)Lime 0.011qt/m2
e)Sand 0.02qt/m2
0.01m3/m2

ITEM DESCRIPTION QUANTITY REMARK


6 Ditto 15 cm H.C.B
a)H.C.B 12.3pc/m2
b)Mortar with 15% waste 0.0138m3/m2
c)cement 0.016qt/m2
d)Lime 0.3 ,,
d)sand 0.1 m3/m2
7 Ditto 20cm H.C.B
a)H.C.B 12.3pc/m2
b)Mortar, with 15%waste 0.0184m3/m2
c)cement 0.021qt/m2
d)Lime 0.36 ,,
e)Sand 0.013m3/m2
8 40cm thick stone masonry wall in cement
mortar 1:4 both sides dressed & left for
pointing
a)Stone 1.46m3/m2
b)Mortar 0.274m3/m2
c)Cement 0.767qt/m2
d)Sand 0.219m3/m2
9 15c, thick H.C.B foundation wall bedded in
cement mortar 1:4
a)H.C.B 12.5pc/m2
b)Mortar (10% joints + 5%wastage) 0.0138m3/m2
c)Cement 0.04qt/m2
d)sand 0.01m3/m2
e)Hollows filled with concrete mortar 1:5 0.08m3/m2
-Cement 0.19qt/m2
-Sand 0.07m3/m2
10 Ditto, but 20cm thick H.C.B
a)H.C.B 12.5pc/m2
b)Mortar 0.0184m3/m2
c)Cement 0.05qt/m2
ITEM DESCRIPTION QUANTITY REMARK
d)Sand 0.10m3/m2
e)Hollows filled with concrete mortar 1:5 0.11m3/m2
*Cement 0.26qt/m2
*Sand 0.09m3/m2
11 Natural basaltic stone masonry foundation
40cm thick bedded in cement mortar 1:4 in
cement mortar 1:4 in full joints
a)basaltic stone 0.53m3/m2
1.25m3/m3*0.40m*1.05waste
b)Mortar 0.34m3/m3*0.407m*1.05 waste 0.14m3/m2
c)cement 0.392qt/m2
d)Sand 0.112m3/m2
12 Ditto but both sides are roughly dressed &
left for pointing:-
a)Basaltic stone
1.34m3/m3*0.407m*1.05waste 0.56m3/m2
b)Mortar
0.34m3/m3*0.407m*1.05 waste 0.14m3/m2
c)cement 0.392qt/m2
d)Sand 0.112m3/m2
13 Natural stone masonry for super structure:-
35cm thick tracheate stone wall bedded in
cement mortar 1:4 one side left for plastering
& one side dressed & left for pointing
a)Traceate stone
1.33m3/m3*0.65m*1.05waste 0.90 m3/m2
b)Cement-Mortar
0.264m3/m3*0.35m*1.05waste 0.10m3/m2
c)Cement 0.28qt/m2
d)Sand 0.80m3/m2
14 Ditto, but dressed & left for pinging

ITEM DESCRIPTION QUANTITY REMARK


a)Tracheate stone
1.33m3/m3*0.35m*1.10 waste 0.52m3/m2
b)Cement-Mortar 0.10m3/m2
0.264m3/m3*0.35m*1.05 waste 0.28qt/m2
c)Cement 0.028m3/m2
d)Sand 0.08m3/m2
15 6x150x150mm glazed ceramic wall tiles
bedded in cement-mortar 1:3
a)Ceramic tile with 2% waste 45.3pc/m2
b)Mortar for bedding with 10% wastage 0.011m3/m2
c)cement 0.049qt/m2
d)Sand 0.012m3/m2
e)Sand grout for pointing 0.001m3/m2
16 Ditto but 7x73x145mm ceramic wall tiles
a)Ceramic tiles with 2% waste 96.4pc/m2
b)Mortar for bedding with 10% wastage 0.011m3/m2
c)cement 0.049qt/m2
d)Sand 0.012m3/m2
e)Sand as above 0.001m3/m2
17 Ditto but 7x50x100mm ceramic wall ties
a)Ceramic tiles with 2% waste other as
above 204pc/m2

FLOORING MATERIALS
ITEM DESCRIPTION QUANTITY REMARK
1 Hard-coaring 20cm thick basaltic stone
0.2x1.15 decrease & waste 0.23 m3/m2
2 Ditto but 25cm thick 0.28 m3/m2
3 Coarse gravel filling for hard core to a
finished thickness of 15cm + 15%decrease &
was 0.17m3/m2
4 20 x 200x200mm terrazzo tile (cement tile)
flooring bedded in cement-screed 1:3
a)Tile +2% waste 25.5pc/m2
b)20cm bedding screen +10%w 0.022m3/m2
c)cement 0.097qt/m2
d) sand 0.024m3/m2
e)cement grout +10% waste 0.001m3/m2
e)polish 0.04kg/m2
5 20x100x200mm terrazzo tile skirting bedded
in C:S of 1:3
a)Skirting + 5% waste 5.3pc/ml
b)Mortar for bedding+10%was 0.0011m3/ml
c)Cement 0.005qt/ml
d)sand 0.001m3/ml
e)Polish 0.01kg/ml
6 20mm thick marble slates flooring bedded in
cement
a)marble siates+20waste 1.02m2/m2
b)20mm thick bedding screed 1.3+10%
waste 0.022m3/m2
c)cement 0.097qt/m2
d)sand 0.097qt/m2
e)cement for grout + 20% wastage 0.001m3/m2
f)polishing 0.04kg/m2
7 15x75mm marble skirting bedded in

ITEM DESCRIPTION QUANTITY REMARK


Cement-mortar 1:3
a)marble slate + 5%waste 1.05m/ml
b)Mortar + 10%wastage 0.001m3/ml
c)Cement 0.004qt/ml
d)Sand 0.001m3/ml
e)Polish 0.01kg/ml
8 2x200x200mm plastic tiles
a)Plastic + 2% waste 25.5pc/m2
b)Adhesive including waste 0.40lit/m2
c)Polish 0.04kg/m2
9 10mm thick denial weira wood parquat
a)Weira wood + 3% waste 1.03m2/m2
b)Mastic including 1.66kg/m2
10 4mm thick Debre-Brehan carpet flooring
a)woolen carpet +3% waste 1.03m2/m2
b)Adhesive including wste 0.40lit/m2
11 15x100mm terrazzo skirting in white
cement marble chipping screed 1:3
a)Terrazzo screed + bmm thickness for
irregularities in base + 5 % waste 0.0022m3/m2
b)cement grout 1:1 0.11lit/ml
c)polish 0.01kg/ml
12 Wooden skirting in tid wood fixed on the
walls
a) 15x60mm tid wood 1.10m/ml
fixed on to walls 2.1pc/ml
13 b) fixture + 5% waste
wooden flooring 1.1m2/m2
a) Boarding 0.60kg/m2
b) Nail
ITEM DESCRIPTION QUANTITY REMARK
c) floor joist c/c30cm 2.20m/m2
d) Nails for floor joist 0.14kg/m2
14 a) 50x150mm zeigba wood ground floor
joint on plates plus 10% waste 1.10m/ml
b) Nails 0.07kg/ml
15 a)50x100mm zeigba wood stub (poles)
+10% waste 1.10m/ml
16 cement pumice light weight screed 1:6
a)cement 2.52qt/m3
b)sand-pumice 1.23m3/m3
17 Ditto but 1:8
a) cement 1.96qt/m3
b) sand 1.28m3/m3
18 Two coats of plaster in cement lime mortar
1:2:9 (13mm thickness for irregularities in
wall 10% wastage)
a) Mortar with 10% wastage 0.021m3/m2
b) Cement 0.03qt/m3
c) Lime 0.4 ,,
d) Sand 0.2 m3/m2
19 Second coat in cement lime mortar 1:1:6
a) Mortar 0.0066m3/m2
b) Cement 0.01qt/m2
c) Lime 0.1 ,,
d) Sand 0.01m3/m2
20 Two coats of plaster first-coat in cement
mortar 1:4:10-10mm thick +6mm
irregularities in wall + 10% waste
a)Mortar with 10% wastage 0.0176m3/m2
b)Lime 0.08qt/m2
c)sand 0.02m3/m2

ITEM DESCRIPTION QUANTITY REMARK


21 3mm thick lime-mortar 1:2 plus 10%
wastage
a) Mortar 0.0033m3/m2
b) Lime 0.02qt/m2
c) sand 0.003 m3/m2
22 30mm thick cement-sand screed 1:3 + 6mm
thickness for irregularities + 5% wastage
a) mortar 0.038 m3/m2
b) cement 0.168qt/m2
c) sand 0.041 m3/m2
d) cement grout 1:1 1.5 lit/m2
23 Ditto but 40mm thick
a) mortar 0.048m3/m2
b) cement 0.212qt/m2
c) sand 0.052m3/m2
d) cement grout 1:1 1.5 lit/m2
24 Ditto but 30mm thick 1:4
a) Mortar 0.038m3/m2
b) Cement 0.134qt/m2
c) Sand 0.044m3/m2
d) Cement grout 1:4 1.5lit/m2
25 Ditto but 50mm thick 1:4
a) Mortar 0.059 m3/m2
b) Cement 0.208qt/m2
c) Sand 0.068 m3/m2
d) Cement grout 1:1 1.5lit/m2
26 50mm thick light weight spreading in cement
pumice 1:6 plus 6mm thick for irregularities
in slab + 5% wastage
a) Mortar 0.054 m3/m2
b) Cement 250kgs/m3 0.135 qt/m2
c) pumice 915kgs/m3 0.067m3/m2
ITEM DESCRIPTION QUANTITY REMARK
* (5mm thcick cement screed for smoothing
surfaced + 5% wastage
a) Mortar 0.0053 m3/m2
b) cement 0.018qt/m2
c) sand 0.007m3/m2
d) cement grout 1.5lit/m2
27 Ditto but 100mm or 95mm thick 1:6
a) mortar 0.106m3/m2
b) cement 0.267 qt/m2
c) pumice 0.131 m3/m2
28 One coat of Tyrolean rendering in cement
lime mortar 1:1:6 with cement color plus 5%
wastage
a) mortar 0.008m3/m2
b) cement 0.018qt/m2
c) lime 0.14 ,,
d) sand 0.009 m3/m2
29 Pointing of burmed brick wall with cement
mortar 1:3 with 15% waste & 10mm joint
a) Mortar 0.003 m3/m2
b) Cement 0.013qt/m2
30 Pointing of fair faced concrete block wall
with cement mortar 1:3
a) Mortar with 15% wastage 0.002 m3/m2
b) Cement 0.009qt/m2
c) Sand 0.002 m3/m2
31 Pointing of dressed stone masonry wall with
cement mortar of 1:3
a) Mortar + 15% wastage 0.0055 m3/m2
b) Cement 0.024qt/m2
c) Sand 0.006 m3/m2

ITEM DESCRIPTION QUANTITY REMARK


32 15 x75mm cement-sand skirting 1:3 finished
smooth with steel trout
a) Cement-sand screed 1:3 plus 6mm
thickness for irregularities in beds +
5% was. 0.0017 m3/ml
b) Cement 0.007qt/ml
33 20mm thick terrazzo flooring in cement
marble chipping screed 1:3
a) Mortar 0.27 m3/m2
c) Cement 0.119 qt/m2
d) Sand 0.029 m3/m2

Vous aimerez peut-être aussi