FORMATO DE METRADO

OBRA : ALOJAMIENTO HOJA N : 1 DE 2


PROPIETARIO : SRA. TERESA DE JESUS RUIZ NAVARRO PLANO N : C-01
FECHA : HECHO POR : KARITO, TONNY, ANGGEL
REVISADO POR :

PART. ESPECIFICACIONES N DE METRADO


N VECES LARGO ANCHO ALTURA PARCIAL TOTAL UNID.
1 OBRAS PROVICIONALES, TRABAJOS PRELIMINARES
1.1.3 TRABAJOS PRELIMINARES
1.1.3.1 LIMPIEZA DEL TERRENO 1 41.75 9.5 - 396.625 396.625 M2
1.1.9 TRAZO, NIVELES Y REPLANTEO
1.1.9.1 TRAZO, NIVELES Y REPLANTEO PRELIMINAR 1 41.75 9.5 - 396.625 396.625 M2
2 ESTRUCTURAS
2.1 MOVIMIENTOS DE TIERRA
2.1.1 NIVELACION DE TERRENO
2.1.1.1 NIVELACION 1 41.75 9.5 - 396.625 396.625 M2
2.1.1.2 NIVELADO APISONADO 1 41.75 9.5 - 396.625 396.625 M2
2.1.2 EXCAVACIONES
2.1.2.1 EXCAVACIONES MACIVAS 143.14 M3
ZAPATA Z-1 7 0.80 0.80 1.20 5.38 M3
ZAPATA Z-2 3 2.00 2.00 1.20 14.40 M3
ZAPATA Z-3 21 2.00 1.50 1.20 75.60
ZAPATA Z-4 3 1.50 1.50 1.20 8.10 M3
CIMIENTO CORRIDO M3
EJE 3B, ENTRE A1-A2 1 2.05 0.40 0.70 0.57 M3
EJE 3B, ENTRE A2-A3 1 1.40 0.40 0.70 0.39 M3
EJE 3B, ENTRE A3-A4 1 1.00 0.40 0.70 0.28 M3
EJE 3B, ENTRE A4-A5 1 1.65 0.40 0.70 0.46
EJE 3B, ENTRE A5-A6 1 1.55 0.40 0.70 0.43 M3
EJE 3B, ENTRE B1-B3 1 3.47 0.40 0.70 0.97 M3
EJE 3B, ENTRE A3-A4 1 1.00 0.40 0.70 0.28 M3
1 0.88 0.13 0.70 0.08 M3
1 1.50 0.13 0.70 0.14 M3
EJE 3B, ENTRE A4-A5 1 1.65 0.40 0.70 0.46 M3
1 2.00 0.13 0.70 0.18 M3
EJE 3B, ENTRE A5-A6 1 1.55 0.40 0.70 0.43 M3
1 1.28 0.13 0.70 0.12 M3
EJE 3B, ENTRE A2-A3 1 1.65 0.40 0.70 0.46 M3
EJE 3B, ENTRE A4-A5 1 1.90 0.40 0.70 0.53 M3
EJE 3B, ENTRE A5-A6 1 2.05 0.40 0.70 0.57 M3
EJE 3B, ENTRE A2-A3 1 3.55 0.40 0.70 0.99 M3
EJE 3B, ENTRE A4-A6 1 7.50 0.40 0.70 2.10 M3
EJE 3B, ENTRE A3-A4 1 1.00 0.40 0.70 0.28 M3
EJE 3B, ENTRE A4-A5 1 1.65 0.40 0.70 0.46 M3
EJE 3B, ENTRE A5-A6 1 1.55 0.40 0.70 0.43 M3
EJE 3B, ENTRE A1-A2 1 2.05 0.40 0.70 0.57 M3
EJE 3B, ENTRE A2-A3 1 1.40 0.40 0.70 0.39 M3
EJE 3B, ENTRE A3-A4 1 1.00 0.40 0.70 0.28 M3
EJE 3B, ENTRE A4-A5 1 1.65 0.40 0.70 0.46 M3
EJE 3B, ENTRE A5-A6 1 1.55 0.40 0.70 0.43
EJE 3B, ENTRE B1-B3 1 3.47 0.40 0.70 0.97
EJE A1, ENTRE 3B-3B 1 2.50 0.4 0.7 0.70 M3
EJE A2, ENTRE 3B-3B 1 2.11 0.4 0.7 0.59 M3
EJE A2, ENTRE 3B-3B 1 1.20 0.4 0.7 0.34 M3
EJE A3, ENTRE 3B-3B 1 3.76 0.4 0.7 1.05 M3
FORMATO DE METRADO

OBRA : HOJA N : .................. DE ..............


PROPIETARIO : PLANO N :
FECHA : HECHO POR :
REVISADO POR :

PART. ESPECIFICACIONES N DE METRADO VANOS O DISMINUCIONES TOTAL UNID.


N VECES LARGO ANCHO ALTURA PARCIAL N DE VECES LARGO ANCHO ALTURA PARCIAL
FORMATO DE METRADO DE CONCRETO ARMADO

OBRA : HOJA N : .................. DE ..............


PROPIETARIO : PLANO N :
FECHA : HECHO POR :
REVISADO POR :

PART. ELEMENTO CONCRETO ENCOFRADO FIERRO LONGITUD TOTAL ( ( ML )


DESCRIPCION CANT. METRADO TOTAL METRADO TOTAL CANT. LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" N
N L A H ( M3 ) L A(H) ( M2 ) ( PULG.) C/ 16

1/4" 3/8" 1/2" 5/8" 3/4" 1" N 16 TOTAL

LONGITUD TOTAL x

PESO ( Kg / Ml ) 0.25 0.56 0.994 1.552 2.235 3.973 0.016

TOTAL ( Kgs )
TABLA DE ACERO SIDERPERU

BARRA NOMINAL AREA PERIMETRO PESO


N PULG. m.m. mm2 Cm2 m.m. Kg / Ml

2 1/4" 6.35 32.00 0.32 19.90 0.25

3 3/8" 9.52 71.00 0.71 29.90 0.56

4 1/2" 12.70 129.00 1.29 39.90 0.99

5 5/8" 15.88 200.00 2.00 49.90 1.55

6 3/4" 19.05 284.00 2.84 59.80 2.24

8 1" 25.40 510.00 5.10 79.80 3.97

11 1 3/8" 35.81 1006.00 10.06 112.50 7.91

ALAMBRE DE ACERO

N 8 0.1620 4.11 13.3 0.133 12.90 0.202

N16 0.0625 1.60 2.00 0.020 5.03 0.016