1.0 Purpose:
To lay down a Procedure for Preventive maintenance of High shear mixer granulator.
2.0 Scope:
This procedure applies to GEA Make High shear mixer granulator Installed at Shilpa
Medicare Limited, Unit-IV, Jadcherla.
3.0 Definitions: NA
4.0 Responsibility:
4.1 Asst. Manager/ Sr. Executive Engineering Shall co-ordinate with user dept to
make the equipment available for preventive maintenance purpose.
5.1 Precautions:
5.1.2 Follow electrical safety before starting the job. In case of electric shock
follow resuscitation first aid chart
5.2 Check the limit switches of the lid for safety and replace if not working properly.
5.3 Check all motors and gear box base bolts and tighten them if required.
5.4 Check the V belts for proper tension and alignment.
5.5 Check the pulley for its position on the shaft and tighten if required.
5.6 Check the earthling of the equipment.
5.7 Check all pneumatic interlocks.
8 Annexure:
8.2
ANEXURE ENG/PMT/038/A01
Equipment Name :
YLY: Yearly