Académique Documents
Professionnel Documents
Culture Documents
REV
59/2009-EPC S-00-1360-001 0
Prepared D.T.VINH
Checked M. MORITA
FOR CONSTRUCTION
Distribution
PVC
PD
DPD (Site)
Proc M
JVC
PM
EM
PEN
CVL REV DATE PAGE DESCRIPTION PREPD CHKD APPD
PIP
A 15 JAN 10 ALL ISSUED FOR APPROVAL D.T. VINH M. MORITA C. HOSHINO
INST
ELC B 08 APR 10 ALL ISSUED FOR APPROVAL D.T. VINH M. MORITA M. MORITA
DHT
C 08 JUL 10 AS MARKUP ISSUED FOR APPROVAL D.T. VINH M. MORITA M. MORITA
CONTENTS
1. SCOPE ........................................................................................................................... 3
2. GENERAL ..................................................................................................................... 3
3. PIPING MATERIAL.................................................................................................... 4
7. ABOVEGROUND PIPING.......................................................................................... 7
1. SCOPE
1.1. This standard specification covers the general requirements for the design of B.O.P. piping
system in BIO FUEL ETHANOL PLANT IN NORTHERN REGION PROJECT.
1.2. The intent of this standard is not to supersede ASME piping code, but only to supplement
it as requested.
2. GENERAL
3. PIPING MATERIAL
3.1. Pipe
The pipe wall thickness shall be calculated in accordance with ASME B31.3 using the
following basic.
Carbon steel piping:
Size: DN15 to DN300 On the basis of P-T rating indicated on ASME B16.5
Size: DN350 and larger On the basis of design condition
Stainless steel piping:
Size: DN15 to DN150 On the basis of P-T rating indicated on ASME B16.5
Size: DN200 and larger On the basis of design condition
3.2. Fitting
(1) Socket welded joint should be limited to DN40 and less. Socket welding and its
preparation shall confirm to ASME B16.5 for flanges and ASME B16.11 for other
components.
(2) Threaded joints may generally be used for water and air service in DN80 and less.
Threading and its preparation shall confirm to ASME B1.20.1.
(3) Butt-welded joints are preferred. End preparation shall confirm to ASME B16.25
Fig. 2(a) or Fig. 3(a).
(4) Cold bend piping will apply to carbon steel pipe and stainless steel pipe of DN15
through DN40.
Bio-Fuel Ethanol Plant in Northern Region Project Contract No.: 59/2009-EPC
General Specification for Piping Design Doc No.: S-00-1360-001 Rev.0
SHEET : 5 of 11
3.3. Valve
(1) Valve type shall be in accordance with specified in P&ID.
(2) Gear operators shall be furnished for valve the following sizes:
RATING GATE GLOBE BALL&PLUG BUTTERFLY
CL.150 450 & Larger - 200 & Larger 200 & Larger
CL.300 350 & Larger - 150 & Larger 150 & Larger
CL.600 200 & Larger 150 & Larger 100 & Larger -
4.1. Sizing
(1) Nominal size 32, 58, 65, 90, 125, 178, 230 and 550 DN shall be not used, and
equipment or instrument connections of these size shall be change to permissible
sized immediately adjacent to equipment or instrument.
(2) The minimum size of piping components should be DN15. (Except for steam trace
tracer piping)
(3) Minimum size on pipe-rack or sleeper to be DN40.
4.2. Distances between Pipes
(1) For non-insulated piping, a minimum clearance of 25 mm shall be provided
between the outside diameter of pipe flanges and adjacent pipes or a minimum
clearance of 25 mm shall be provided between the outside surfaces of pipes. For
insulated piping, the insulation thickness shall be taken into consideration.
(2) The minimum clearance between pipes which are subject to expansion and
contraction should be determined as required.
(3) The minimum clearance between a valve hand-wheel and another hand-wheel shall
be 100 mm.
4.3. Typical Piping (Sampling, Drain and Vent)
4.3.1. Sampling piping should be arranged as per the following requirements.
(1) All sampling points should be located at grade or at a platform.
(2) Sampling piping should be as short as possible.
(3) Where a sample connection connects to a horizontal run pipe, the tie-in should be
made at the side of the run pipe for liquid service, and at the top of the run pipe for
gas and vapor.
4.3.2. Drains and Vents other than indicated on P&ID shall be provided as per the following
requirements:
(1) Drains shall be provided at low points of all piping. Vents for hydrostatic shall be
provided at high points of DN50 and larger piping, and at vent pocket of all pump
suction piping if any.
(2) Vent shall be with valve for DN350 and larger liquid piping and pump suction piping.
Bio-Fuel Ethanol Plant in Northern Region Project Contract No.: 59/2009-EPC
General Specification for Piping Design Doc No.: S-00-1360-001 Rev.0
SHEET : 6 of 11
(3) Drains and Vents shall generally be in accordance with the followings:
Drains
(a) All piping: DN20 gate valve with threaded plug
Vents
(a) Valved vent: DN20 gate valve with threaded plug
(b) Required for hydrostatic testing purpose: DN20 threaded plug
(When run pipe size is DN15, the size of drain or vent valves shall be DN15.)
5. ACCESS REQUIREMENT
For underground buried steel piping, adequate corrosion protection shall be provided.
7. ABOVEGROUND PIPING
(d) The suction and discharge piping must be supported independently to minimize
load transmitted to the pump casing. Type of strainers used in pump suction
piping shall be as follows:
DN50 and smaller size Y type
DN80 and larger size T type
(3) Compressor
Reciprocating compressor piping shall be arranged and supported so as to prevent
fatigue failure due to the effects of possible vibration and pressure pulsation.
7.1.3. Shell and Tube Heat Exchanger Piping
(1) Piping should be arranged so as to allow removal of channel covers and tube
bundles and give easy access for bolting.
(2) Where practical, symmetrical piping is preferred for the inlet piping of heat
exchangers having multiple inlet nozzles.
(3) The configuration of piping connected to respective heat exchanger of the same
item arranged in parallel shall be symmetrical.
7.2. Tank Farm Piping
(1) Piping inside tank dikes should take the shortest possible route to the main pipe
way, with appropriate allowance for expansion and contraction.
(2) Piping shall be arranged to enable the absorption of nozzle displacement caused by
tank settlement, or piping displacement caused by nozzle rotation due to tank shell
deformation.
(3) Piping passing through dikes shall be adequately protected against external
corrosion, and shall be capable of absorbing any possible movement of piping due
to thermal expansion and contraction.
7.3. Pipe way piping
A pipe sleeper should be provided for the main pipe way of process units and B.O.P.
facilities.
If valve manifolds are located on pipe rack or sleeper, adequate access should be provided.
7.4. Utility piping
All branch piping from utility headers shall be taken from the top of the header to prevent
plugging, however, liquid service branch piping of DN50 and larger may be taken from
the bottom of the header.
7.5. Piping around Instruments
7.5.1. General
(1) Instruments should be so located that they will not be exposed to possible damage
during operation, inspection or maintenance of equipment.
(2) All measuring elements should be installed at locations where exact measurements
can be taken, free from disturbances due to access for operation and maintenance.
The positions of instruments should be selected so that their readings are visible
from ground level, platform, stairs, ladders, or steps.
Bio-Fuel Ethanol Plant in Northern Region Project Contract No.: 59/2009-EPC
General Specification for Piping Design Doc No.: S-00-1360-001 Rev.0
SHEET : 9 of 11
8. PIPE SUPPORT
Standard pipe support drawings and individual special pipe support shall basically be
prepared. It may be able to indicate support detail on isometric drawings or piping plan
drawings.
9. STRESS ANALYSIS
12.2. Scale
Tankage area and Pipe rack or Pipe sleeper
Plan drawing: 1:50 or 1:100
Partial detail drawing: Non scale
12.3. Letters
English shall be used for the drawings.
12.4. Size of drawings
A: A0 for Plan and Partial detail drawing, in principle
B: A1 for Plan and Partial detail drawing, supplementary
C: A2 others
D: A3 Isometric drawing and support drawing
E: A4 support drawing, specification and others.