< 100 VPD 6.00 4.50 Excludes width of
(see notes below) drain, parapet &
Traffic>100VPD< 6.75 5.25 retaining wall top
400VPD
4. Right of Way (m) 20.00 20.00 10m Right-of-Way
(ROW) on either side
from the road centre
line
#
Road Components Design Standards Remarks
Terai Hill /
Mountain
5. Corridor of Impact or As specified in as COI will be the
COI (see notes below) per the provision of minimum width to
the Environmental cover the actual road
and Social construction boundary
Management plus 1.00m on each
Framework (ESMF) side of the
of SNRTP construction line.