Critical path by Total Float is wrong in multiple calendar project

In Primavera we can define Critical activities by 2 option:

There are many reasons why we should choose Longest Path instead of Total Float.
One of the reason is that when our project has multiple calendar.

We have 4 activities which have same calendar: Standard 5 day workweek. We use Total Float to
calculate Critical path. The result is this:
Critical path by Total Float is wrong in multiple calendar project

When I change A1020 activitys calendar to 1 Day Workweek. We use Total Float to calculate
Critical path. The result is this:

You can see its the wrong critical path.


Now when you choose longest path option. It will become like this:
Critical path by Total Float is wrong in multiple calendar project

Now the critical path is better

So when you have multiple calendar project, consider to use longest path option.