Académique Documents
Professionnel Documents
Culture Documents
1
TO
BIDDING DOCUMENTS
FOR
REHABILITATION AND UPGRADING OF
PANJNAD BARRAGE
(CONTRACT NO. TPBIP/ICB-02)
ADDENDUM NO. 1
BIDDING DOCUMENTS FOR
REHABILITATION AND UPGRADING OF PANJNAD BARRAGE
ADDENDUM NO. 1
Following revisions and additions are made to the Bidding Documents for Rehabilitation and Upgrading
of Panjnad Barrage in terms of Sub-section 8 (Amendment of Bidding Document) of the Instructions to
Bidder Section 1 of Volume No. 1: -
1. Refer Section 2 (Bid Data Sheet), Part C (Preparation of Bids) Sub-section ITB 10.1
Add following at the end of the description text:
and attested by the embassy of the country of origin in Pakistan
2. Refer Section 2 (Bid Data Sheet), Part D (Submission and Opening of Bids) Sub-section ITB
22.1.
Replace the deadline date for Bid submission i-e. 21st July 2017 with 10th August 2017.
3. Refer Section 2 (Bid Data Sheet), Part D (Submission and Opening of Bids) Sub-section ITB
25.1
Replace the opening date of the Technical Bids 21st July 2017 with 10th August 2017.
4. Refer Section 4 (Bidding Forms), Sub-section Appendix to Bid (Tables of Adjustment Data).
Replace the Table A Local Currency with the Table A attached as Annexure-A
5. Refer Section 4 (Bidding Forms), Sub-section Appendix to Bid (Tables of Adjustment Data).
Replace the Table B Foreign Currency with the Table B attached as Annexure-B
6. Refer Section 4 (Bidding Forms), Sub-section Bill of Quantities.
Replace Bill of Quantities with the Annexure-C
Page 1 of 22
ADDENDUM NO. 1
Add following text at the end of the first paragraph: The Contractor shall provide required
resources/labour for operation of gates for main barrage and off taking canals since
commencement of the Works up to taking over certification at his own cost.
12. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-13, Sub-Clause 13.11.
Replace the following last sentence: The Contractor shall provide security guards and
watchmen, and other personnel and facilities required for security and public safety. With
the following sentence: The Contractor shall provide security guards, watchmen and other
personnel from Government approved security agency, CCTV cameras, walk through
gates, pop-up barriers and other facilities required for security and public safety.
13. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-14, Sub-Clause 14.4.
Replace the following text in line 1 and 2 of first paragraph: The Contractor shall service
and maintain the office and laboratory facilities for the Portable Field Office cabins,
Employer and Engineer in accordance with good standards as approved by the Engineer.
With the following text: The contractor shall serve and maintain Engineers/Employers
Office and Engineers Portable Field Office Cabins in accordance with standards approved
by the Engineer
14. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-14, Sub-Clause 14.7.
Delete the words Testing Laboratories from the heading of the Sub-Clause.
15. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-14, Sub-Clause 14.10.
Delete the entire Sub-Clause and replace with text 14.10 Not Used
16. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-24, Sub-Clause 24.2.
Replace the following text in second sentence of first paragraph The film shall be of 60
minutes duration fully edited and with commentary in English language. With the following
text The films shall be of 1 minute, 5 minute and 60 minutes duration fully edited and with
commentary in English language.
17. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-25.
Replace the following text in line 3 of first paragraph: and six other items with the following
text Two Gates Repairs Items, two items for modernization of Gates Hosing System, item
for strengthening of superstructure, and item for Rehabilitation of balancing
counterweights.
18. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-31, Sub-Clause 31.7, Sub-heading (Measurement).
Replace the following list at the end of first paragraph:
"1. Couloured Progress Photographs 25%
2. One Minute (Short Film for TV advertisement 5%
3. Sixty (60) Minute (Full detailed movie) 70%
With the following list:
"1. Colored Progress Photographs 25%
2. One Minute Movie (Short Film for TV advertisement) 5%
3. Five (5) Minute Movie 10%
4. Sixty (60) Minute Movie (Full detailed movie) 60%
19. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-31, Sub-Clause 31.9.
Replace the following words in the first line of first paragraph Sub-Clause SP-13.70 with
Sub-Clause SP-14.70
Page 2 of 22
ADDENDUM NO. 1
20. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-31, Sub-Clause 31.10.
Delete the following words from the first line of first paragraph specified in sub-clause 14.70
hereof
21. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-31, Sub-Clause 31.13, SPS-5.
Replace the following words A provisional sum and from third line of first paragraph with
the word A provisional sum for.
22. Refer Section 6 (Employers Requirements), Sub-section - Specifications (Part A) Special
Provisions, Clause SP-31, Sub-Clause 31.13, SPS-5.
Add following text at the end of the first paragraph Percentage (10%) as mentioned in
particular condition of Contract Part A against provisional sums shall not be applicable.
23. Refer Section 8 (Particular Conditions of Contract), Part B Specific Provisions, Sub-
section Ref.GCC 4.21.
Replace the size of photographs 6 x 5 with the 10 x 8.
E. VOLUME II (TECHNICAL SPECIFICATIONS AND ENVIRONMENTAL MANAGEMENT
PLAN) Part A. CIVIL WORKS
24. Refer Section 3 (Care and Handling of Water and Diversion Road), Sub-clause 3.2 (Scope
of Work).
Add the following at serial iv. at the end of the sentence:
by providing all kind of resources required.
25. Refer Section 3 (Care and Handling of Water and Diversion Road), Sub-clause 3.2 (Scope
of Work).
Add the following at serial vii. at the end of the list:
vii. Design, construct and maintain deep excavation support system like soldier piles or
other arrangements as approved by the Engineer
26. Refer Section 6 (Cement), Sub-clause 6.1 (Scope).
Replace the words Sulphate Resistant Cement in the first line of first paragraph with
Ordinary Portland Cement
27. Refer Section 6 (Cement), Sub-clause 6.2 (Requirements).
Replace the words Sulphate Resistant Cement in the second line of first paragraph with
Ordinary Portland Cement
28. Refer Section 6 (Cement), Sub-clause 6.2 (Requirements).
Add the following paragraph after the first paragraph:
Granulated blast furnace slag may be used to cater for S.A.R (Silica Alkali Reaction) and
to reduce Heat of Hydration, substituting equal quantity of cement.
29. Refer Section 7 (Earthwork, Excavation, Filling), Sub-clause 7.7.1 (General).
Add the words including compaction after the word structures in third line of paragraph at
serial ii.
30. Refer Section 8 (Concrete), Sub-clause 8.6.14.3 (Removal of Forms).
Replace the words Sulphate Resistant Cement in the second line of second paragraph
with Ordinary Portland Cement
31. Refer Section 8 (Concrete), Sub-clause 8.6.20 (Repairing of Concrete Surfaces).
Replace the words Sulphate Resistant Cement in the third line of description at serial iii.
with Ordinary Portland Cement.
32. Refer Section 8 (Concrete), Sub-clause 8.6.26.1 (Concrete).
Replace the words 150 sq. in the third and fourth line with the following: 100 sq.
Page 3 of 22
ADDENDUM NO. 1
33. Refer Section 9 (Building Concrete under Floor Slabs and Foundations of Structures), Sub-
clause 9.2 (General).
Replace the words Sulphate Resistant Cement in the first line of description at serial iii.
with Ordinary Portland Cement.
34. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.2 (Reinforced Concrete using Sulphate Resistant Cement).
Replace the words Sulphate Resistant Cement under the title of the sub-clause with
Ordinary Portland Cement
35. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.2 (Reinforced Concrete using Sulphate Resistant Cement).
Replace the words Sulphate Resistant Cement in the first line of description at serial i.
with Ordinary Portland Cement.
36. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.2 (Reinforced Concrete using Sulphate Resistant Cement).
Replace the words Sulphate Resistant Cement in the first line of description at serial vi.
with Ordinary Portland Cement.
37. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.3 (Measurement and Payment).
Replace the words Sulphate Resistant Cement in the first line of description at serial i.
with Ordinary Portland Cement.
38. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.3 (Measurement and Payment).
Replace the words Sulphate Resistant Cement in the second line of description at serial
ii. with Ordinary Portland Cement.
39. Refer Section 10 (Reinforced Concrete Excluding Cost of Steel Reinforcement), Sub-
clause 10.3 (Measurement and Payment).
Replace the words Sulphate Resistant Cement in the third line of description at serial iii.
with Ordinary Portland Cement.
40. Refer Section 15 (Drilling and Grouting), Sub-clause 15.4.3 (Grout Materials).
Replace the words Sulphate Resistant Cement in the first line of second paragraph with
Ordinary Portland Cement.
41. Refer Section 15 (Drilling and Grouting), Sub-clause 15.7.1 (General).
Add following description at the end of the list:
Core samples from existing concrete shall be extracted and tested in laboratory as
per the instructions of the Engineer at the cost of the Contractor.
F. VOLUME II (TECHNICAL SPECIFICATIONS AND ENVIRONMENTAL MANAGEMENT
PLAN) Part B. MECHANICAL AND ELECRTRICAL WORKS
42. Refer Section 2 (General), Sub-clause 2.1 (Introduction).
In the fourth (4th) line of first paragraph, replace the words; 04 bays with the following
words: 03 bays.
43. Refer Section 2 (General), Sub-clause 2.1 (Introduction), Table (New Gate Equipment after
Modification).
Replace the following value: 4 in the last row of column 3 (No. of Bays) with the following
value: 3
44. Refer Section 2 (General), Sub-clause 2.1 (Introduction), Table (New Gate Equipment after
Modification).
Replace the following value: 54.5 in the last row of column 4 (Span) with the following
value: 60
45. Refer Section 2 (General), Sub-clause 2.1 (Introduction).
Delete the following word: (Equipment) in the third line of last paragraph
46. Refer Section 2 (General), Sub-clause 2. (Introduction).
Page 4 of 22
ADDENDUM NO. 1
Add the word: etc. after the words: and transportation in the 5th line of last paragraph.
47. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), a. (Embedded
Parts).
Add the following word: associated before the following words: civil works, in the 2nd line
of serial 1.
48. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), a. (Embedded
Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 2.
49. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), a. (Embedded
Parts).
Replace the following words in the second line of description at serial 3: up to 14 Ft. height
with the following words: up to groove height
50. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), b. (Gate Leaf
Assemblies).
Delete the following words in the first line of serial 1: check the stability of the existing gates
and.
51. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), b. (Gate Leaf
Assemblies).
Replace the following sentence at serial 6: Removal of existing rocker assemblies and
provision of new rocker assemblies as per existing design,. With the following sentence:
Rehabilitation/ Repair of rocker assemblies as per existing design.
52. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), b. (Gate Leaf
Assemblies).
Replace the word grit in the first line of serial 7 with the word sand.
53. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), c. (Hoisting
Equipment).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
54. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the words all the bays of barrage in the second line of serial 1 with 4 bays of Left
Under-sluice
55. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the words all bays in the first line of serial 2 with 4 bays of Left Under-sluice
56. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the words all bays in the last line of serial 4 with 4 bays of Left Under-sluice
Page 5 of 22
ADDENDUM NO. 1
57. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), A. (60ft. SPAN
STONEY TYPE LEFT UNDERSLUICE GATE EQUIPMENT, 04 BAYS), e. (Credit to old
materials/equipment).
Replace the words received in the second line of serial 1 with retrieved
58. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 2nd line
of serial 1.
59. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 2.
60. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), a. (Embedded Parts).
Replace the following words in the second line of description at serial 3: up to 14 Ft. height
with the following words: up to groove height
61. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), b. (Gate Leaf Assemblies).
Delete the following words in the first line of serial 1: check the stability of the existing gates
and.
62. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), b. (Gate Leaf Assemblies).
Replace the following sentence at serial 6: Removal of existing rocker assemblies and
provision of new rocker assemblies as per existing design,. With the following sentence:
Rehabilitation/ Repair of rocker assemblies as per existing design.
63. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), b. (Gate Leaf Assemblies).
Replace the word grit in the first line of serial 7 with the word sand.
64. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), c. (Hoisting System).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
65. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the second line at serial 1: all the bays of barrage with the
following words: 29 bays of Main Weir.
66. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the first line at serial 2: all bays with the following words:
29 bays of Main Weir.
67. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the second line at serial 3: all the bays of barrage with the
following words: 29 bays of Main Weir.
68. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Delete the description at serial 4 and rearrange the serial nos. accordingly
Page 6 of 22
ADDENDUM NO. 1
69. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Add the following words at the end of the description of serial no. 5: of Main Weir complete
in all respect
70. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the word fiber glass in the first line of serial 6 with Wooden
71. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), B. (60 ft. SPAN
STONEY TYPE MAIN WEIR GATE EQUIPMENT, 29 BAYS), e. (Credit to old
materials/equipment).
Replace the word received in the second line of paragraph with the following word:
retrieved
72. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 2nd line
of serial 1.
73. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 2.
74. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), a. (Embedded Parts).
Replace the following words in the second line of description at serial 3: up to 14 Ft. height
with the following words: up to groove height
75. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), b. (Gate Leaf
Assemblies).
Delete the following words in the first line of serial 1: check the stability of the existing gates
and.
76. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), b. (Gate Leaf Assemblies).
Replace the following sentence at serial 6: Removal of existing rocker assemblies and
provision of new rocker assemblies as per existing design,. With the following sentence:
Rehabilitation/ Repair of rocker assemblies as per existing design.
77. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), b. (Gate Leaf
Assemblies).
Replace the word grit in the first line of serial 7 with the word sand.
78. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), c. (Hoisting System).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
79. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the second line at serial 1: all the bays of barrage with the
following words: 14 bays of Annexe Weir.
Page 7 of 22
ADDENDUM NO. 1
80. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the first line at serial 2: all bays with the following words:
14 bays of Annexe Weir.
81. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Replace the following words in the second line at serial 3: all the bays of barrage with the
following words: 14 bays of Annexe Weir.
82. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Delete the description at serial 4 and rearrange the serial nos. accordingly
83. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Add the following words at the end of the description of serial no. 5: of Annexe Weir
complete in all respect
84. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (60 ft. SPAN
STONEY TYPE ANNEXE WEIR GATE EQUIPMENT, 14 BAYS), e. (Credit to old
material/equipment).
Replace the word received in the second line of paragraph with the following word:
retrieved
85. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 2nd line
of serial 1.
86. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 2.
87. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 3.
88. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), b. (Gate Leaf
Assemblies).
Replace the word grit in the second line of serial 1 with the word sand.
89. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), b. (Gate Leaf
Assemblies).
Replace the word grit in the first line of serial 7 with the word sand.
90. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), b. (Hoisting
Equipment).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
Page 8 of 22
ADDENDUM NO. 1
91. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), D. (PANJNAD
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 12), b. (Credit to old
material/equipment).
Replace the word received in the second line of paragraph with the following word:
retrieved
92. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), E. (ABBASIA
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 2), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 1.
93. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), E. (ABBASIA
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 2), b. (Gate Leaf
Assemblies).
Replace the word grit in the second line of serial 1 with the word sand.
94. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), E. (ABBASIA
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 2), c. (Hoisting
Equipment).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
95. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), E. (ABBASIA
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 2), c. (Hoisting
Equipment).
Replace the word grit in the second line of serial 3 with the word sand.
96. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), E. (ABBASIA
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 TO 2), e. (Credit to old
material/equipment).
Replace the word received in the second line of paragraph with the following word:
retrieved
97. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), F. (ABBASIA LINK
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 to 6), a. (Embedded Parts).
Replace the word necessary in the second line of serial 2 with the following word:
associated.
98. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), F. (ABBASIA LINK
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 to 6), e. (Gate Leaf
Assemblies).
Delete the following words from the first line of serial 1: and Wheel Assemblies including.
99. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), F. (ABBASIA LINK
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 to 6), b. (Gate Leaf
Assemblies).
Replace the word grit with the word sand in the last line of serial 1.
100. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), F. (ABBASIA LINK
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 to 6), d. (Hoisting
Platform/Superstructure, Stairs and Railing).
Add the following words at the end of the paragraph; complete in all respect.
101. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), F. (ABBASIA LINK
CANAL HEAD REGULATOR GATE EQUIPMENT - BAYS # 1 to 6), e. (Credit to old
material/equipment).
Replace the word received in the second line of paragraph with the following word:
retrieved
102. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT).
Page 9 of 22
ADDENDUM NO. 1
Replace the title of Sub-section C NEW GATE EQUIPMENT with the following: G
NEW GATE EQUIPMENT.
103. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT).
Replace the words 04 bays in the first line of first paragraph with the following words: 03 bays.
Replace the words span of 54.4 feet in the second line of first paragraph with the following
words: Span of 60.0 feet.
104. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), a. (Embedded Parts).
Add the following word: associated before the following words: civil works, in the 3rd line
of serial 1.
105. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), a. (Embedded Parts).
Add following words: for side seals after the words steel bearing plates in the second
line of serial 2.
106. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), b. (Gate Leaf Assemblies).
Replace the word grit with the word sand in the second line of serial 1.
107. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), c. (Hoisting Equipment).
Add following words at the end of description at serial 1: Lifting speed of the gate shall be
1 ft./min electrically and 4 inch/min manually.
108. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), c. (Hoisting Equipment).
Replace the word grit in the second line of serial 2 with the word sand.
109. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT), c. (Hoisting Equipment).
Add the following words at the end of the paragraph at serial 3: shall be provided to new
design for trouble free operation
110. Refer Section 2 (General), Sub-clause 2.2.2 (Barrage Gate Equipment), C. (NEW GATE
EQUIPMENT).
Add the following new sub-section after the sub-section d. Hoisting
Platform/Superstructure, Stairs and Railing:
e. Passage (Deck, Railing, Grating etc.)
Designing, fabrication, installation and painting of superstructure deck including hand
railing and galvanized steel grating (dimension as per site requirement) to link the Main
weir deck to new depressed bays deck and new depressed bays deck to Annexe weir deck.
Complete in all respect.
111. Refer Section 2 (General), Sub-clause 2.2.3 (Workshop Equipment).
Replace the quantity 2 Nos. of equipment at serial 1 Mobile Electric Welding Plant with
1 Nos.
112. Refer Section 2 (General), Sub-clause 2.2.3 (Workshop Equipment).
Replace the equipment description Electric Drill at serial 6 with the following: Bench
Drilling Machine
113. Refer Section 2 (General), Sub-clause 2.2.3 (Workshop Equipment).
Add the equipment following equipment at Serial No. 12, next to the equipment Mobile
Diesel Set Generator 10kVA and adjust remaining serial No. accordingly:
12. Truck Mounted Crane 1 No.
114. Refer Section 2 (General), Sub-clause 2.2.3 (Workshop Equipment).
Delete the equipment at serial 16 Blower and adjust remaining serial No. accordingly.
115. Refer Section 2 (General), Sub-clause 2.2.3 (Workshop Equipment).
Page 10 of 22
ADDENDUM NO. 1
Replace the equipment description at serial 18 Hammer Set (lbs Lbs). with the following:
Hammer set (from 0.5 lb to 6.0 lb)
116. Refer Section 2 (General), Sub-clause 2.2.5 (Basic Spare Parts).
Replace the entire table with the following table:
Rubber Seals
6 Grease 150 Kg
Overrunning Clutch
Couplings
8 Main Barrage
5 Sets
Page 11 of 22
ADDENDUM NO. 1
120. Refer Section 2 (General), Sub-clause 2.17.6 (Electric Motor).
Add following words at the end of second paragraph: The motor shall have in built
temperature sensor with its winding.
121. Refer Section 2 (General), Sub-clause 2.20.3 (Surface Preparation).
Replace the word grit with the word sand in the fourth line of serial B.
122. Refer Section 2 (General), Sub-clause 2.20.5 (Painting Schedule), System 1: Surface
in Contact with Water.
Replace the words sharp edged grit in second column with sand blasting.
123. Refer Section 2 (General), Sub-clause 2.20.5 (Painting Schedule), System 2: Surface
exposed to air.
Replace the words sharp edged grit in second column with sand blasting.
124. Refer Section 2 (General), Sub-clause 2.20.5 (Painting Schedule), System 1: Surface
exposed to oil.
Replace the words sharp edged grit in second column with sand blasting.
125. Refer Section 2 (General), Sub-clause 2.23.1 (Installation of Embedded Parts).
Replace Clause 1.16.8 in the second paragraph with Clause 2.18.8
126. Refer Section 2 (General)
Add the following sub-clause at the end of the section:
2.25 Training
The Contractor shall provide training at levels suitable for (a)Operators and (b)
Maintenance Personnel prior to issue of taking over certificate. The proposed
schedule and programme for the training shall be submitted to the Engineer for
approval prior to training taking place. The Operation and Maintenance Manuals
shall provide the basis for training and shall be available for reference during the
training sessions. The cost of training shall be included in the respective BoQ.
The contractor shall arrange training of staff at the site of work for the following:
1. Operation and Maintenance of all types of Gates.
2. Operation and Maintenance of control equipment.
3. Operation and Maintenance of new hoisting system.
4. Precaution and care during any type of operations.
5. Periodic maintenance
6. Annual maintenance
7. Essential replacement and their duration
127. Refer Section 3 (Gate Equipment), Sub-clause 3.2.1 (60 ft. Span Stoney Gate
Equipment, 47 Bays), A. (Embedded Parts).
Replace the words upto 14.0 ft height with the following: up to groove height
128. Refer Section 3 (Gate Equipment), Sub-clause 3.2.1 (B) (Gate Leaf Assemblies)
Replace the following words in the second line of paragraph four: These rocker
assemblies shall be replaced with new stainless steel (ASTM A 240 Type 304) rocker
assemblies. The design of new rocker assembly shall be according to the existing ones
with the following: The rocker assemblies shall be rehabilitated/repaired as per existing
design.
129. Refer Section 3 (Gate Equipment), Sub-clause 3.2.1 (E) (Painting).
Replace the word grit with the word sand in the first line.
130. Refer Section 3 (Gate Equipment), Sub-clause 3.2.1 (60 ft. Span Stoney Gate
Equipment, 47 Bays), B. (Gate Leaf Assemblies).
Replace the word grit with the word sand in the last paragraph.
131. Refer Section 3 (Gate Equipment), Sub-clause 3.3.1 (Panjnad Canal Head Regulator
Gate Equipment), B. (Gate Leaf Assemblies).
Replace the word grit with the word sand in the third line of first paragraph.
Page 12 of 22
ADDENDUM NO. 1
132. Refer Section 3 (Gate Equipment), Sub-clause 3.3.2 (Abbasia Canal Head Regulator
Gate Equipment Bays # 1 to 2), B. (Gate Leaf Assemblies).
Replace the word grit with the word sand in the second line of first paragraph.
133. Refer Section 3 (Gate Equipment), Sub-clause 3.3.3 (Abbasia Link Canal Head
Regulator Gate Equipment Bays # 1 to 6), B. (Gate Leaf Assemblies).
Replace the word grit with the word sand in the second line of first paragraph.
134. Refer Section 3 (Gate Equipment), Sub-clause 3.3.4 (New Gate Equipment).
Replace the word Four 4 in the first line with the following: Three 3.
135. Refer Section 3 (Gate Equipment), Sub-clause 3.3.4 (New Gate Equipment).
Replace the words New four Fixed Wheel Gate Equipment (span of 54.5 ft wide by 15.5
ft high) with the following: New thee Fixed Wheel Gate Equipment (span of 60 feet
wide 16.5 feet high).
136. Refer Section 3 (Gate Equipment), Sub-clause (Shop Painting).
Replace the Tittle Shop Painting with I. Shop Painting.
137. Refer Section 3 (Gate Equipment), Sub-clause (Shop Painting).
Replace the word grit with sand in the first line of first paragraph.
138. Refer Section 4 (Workshop Equipment), Sub-clause 4.4 (Lath Machine), ii.
(Performance Characteristics).
Replace the serial 4. With the following:
4. Distance between centers Not less than 6.23 feet
139. Refer Section 4 (Workshop Equipment), Sub-clause 4.5 (Bench Grinder).
Add following specifications for this sub-clause:
Bench Grinder should be a Powerful 5/8 HP induction motor for heavy-duty grinding
operations. Motor runs at 3,450 rpm for high-speed material removal also have Rear
exhaust ports in wheel guards for smoother operation. Durability from rugged cast iron
base to prolong life. 12-1/2" distance between wheels for longer and larger grinding
applications. Bench grinder should have 36 grit wheel, 60 grit wheel, Eye shields, Spark
deflectors and toll reset. The Bench grinder shall be complete with manufacturing
standard equipment including but not limited to the following
140. Refer Section 4 (Workshop Equipment), Sub-clause 4.7 (Electric Drill Machine).
Replace the entire specification under this Sub-clause with the following:
Electric Bench drill Machine to be procured under these specifications with standards
accessories and two drill Bit set.
Specifications
Drilling Capacity in Steel 20MM
Morse taper in spindle MT 2
Spindle travels 130MM
Vertical adjustment of Spindle head 425MM
Pillar diameter 80MM
Distance between center of spindle and Column front 200MM
Max. Distance between spindle and table 340MM
Max. Distance between spindle and base 700MM
Table working Surface 300MM
No. of Spindle Speeds 5 Nos.
Range of Spindle Speeds (rpm) 375,700,1170,1900,3220
Page 13 of 22
ADDENDUM NO. 1
Power of Spindle drive motor 0.75kw/1HP,1425 rpm,
220Volt, AC, 50 Hz
141. Refer Section 4 (Workshop Equipment), Sub-clause 4.11 (Diesel Engine Generator Set
50 kVA).
Replace the words 50 kVA under the title of sub-clause and second line of first
paragraph with 25 kVA.
142. Refer Section 4 (Workshop Equipment), Sub-clause 4.14 (Snap-on Tool Set).
Add following sub-clause after the sub-clause 4.14:
4.14.1 A. ELECTRIC HAND DRILL MACHINE
Electric hand drill to be procured under these specifications shall be 9 Amp motor,
forcible power combines high speed with optimal torque, designed to comfortably fit in
hand for improved control with minimal vibration and shall conform to the following
specifications: -
Tool Weight 4.6lbs.
Chuck 1/2.
No Load Speed 0-850rpm.
Max Torque 416.6in-lbs.
Amps 9
Capacity Wood 2-1/8.
Capacity Steel 1/2
Capacity Hole Saw 4
Voltage 220 Volt.
Standard Accessories shall be supplied with machines.
Page 15 of 22
ADDENDUM NO. 1
Item No. A.10.119, 10.120, 10.121, 10.122, 10.123, 10.124, 10.125, 10.126,
10.127, 10.128
Percentage of Tendered Amount
1. On Approval of design and drawing 10%
2. On delivery of fabricated / assembled sets at barrage site 40%
3. On installation 30%
4. On final testing of the assembled equipment 20%
NOTE:
BoQ items not covered above shall be measured and paid after completion of
required work / activities as per quoted rates of respective items by the bidder.
144. Refer Section 8 (Low Voltage Switchgear Panel(s) [Control Panel(s)]), Sub-clause 8.4
(Local Control Panel(s)).
Add the following word: and tested after the word: built in the 2 nd line of last
paragraph.
145. Refer Section 8 (LOW VOLTAGE SWITCHGEAR PANEL(S) [CONTROL PANEL(S)]),
Sub-clause 8.4.1.7 (Voltmeters).
Add the following word: or analogue, weather proof (industrial) after the word: digital
in the 1st line of first paragraph.
146. Refer Section 8 (LOW VOLTAGE SWITCHGEAR PANEL(S) [CONTROL PANEL(S)]),
Sub-clause 8.4.1.8 (Ammeters).
Add the following word: or analogue, weather proof (industrial) after the word: digital
in the 1st line of first paragraph.
147. Refer Section 10 (PVC PIPES), Sub-clause 10.4 (Measurement and Payment (Ref: Bill
No. 11 Item No. F)).
Replace at the end of the title of Sub-clause word F with G.
148. Refer Section 11 (MAIN/SUB-MAIN POWER CABLES FOR LOW VOLTAGE
SWITCHGEAR PANELS), Sub-clause 11.7 (Measurement and Payment (Ref: Bill No.
11 Item No. G)).
Replace at the end of the title of Sub-clause word G with H.
149. Refer Section 12 (JUNCTION/PULL BOX FOR MAIN AND SUB-MAIN POWER
CABLES (GATE HOISTING AND LIGHTING SYSTEM)), Sub-clause 12.1 (Scope of
Work).
Add following sentence at the end of the third paragraph: including maintenance plate
form for Junction Box where required.
150. Refer Section 12 (JUNCTION/PULL BOX FOR MAIN AND SUB-MAIN POWER
CABLES (GATE HOISTING AND LIGHTING SYSTEM)), Sub-clause 12.2
(Measurement and Payment (Ref: Bill No. 11 Item No. H)).
Replace at the end of the title of Sub-clause word H with I.
151. Refer Section 13 (EXTERNAL LIGHTING NETWORK), Sub-clause 13.5.6
(Measurement and Payment (Ref: Bill No. 11 Item No. I)).
Replace at the end of the title of Sub-clause word I with J.
152. Refer Section 14 (LUMINARIES), Sub-clause 14.6 (Measurement and Payment (Ref:
Bill No. 11 Item No. I)).
Replace at the end of the title of Sub-clause word I with J.
153. Refer Section 15 (CONTROL BUILDING), Sub-clause 15.13.1.1 (Measurement).
Replace the words per square foot (sft) with construction area complete at the end of
first line of first paragraph.
154. Refer Section 15 (CONTROL BUILDING), Sub-clause 15.13.1.2 (Payment).
Page 16 of 22
ADDENDUM NO. 1
Replace the words number of units (sft.) measured with constructed area complete
in the first line of first paragraph.
155. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.2 (Summary of Scope of Work).
Add the following sentence at the serial n) below the serial m): n) Construction of
Control Building as per specification and drawing including furnishing
156. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.4.1.4 (Control Building and Barrage Local Area Network
(LAN)), a) (Dual redundant SCADA Server).
Replace the words 16GB RAM, 2X1TB HDD (RAID Configuration), Dual power supply,
24 SXGA VDU with the following words: 64GB RAM, 2X1TB HDD (RAID
Configuration), Dual power supply, 24 1920 x 1080 VDU in the second line of second
paragraph.
157. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.4.1.4 (Control Building and Barrage Local Area Network
(LAN)), a) (Dual redundant SCADA Server).
Add following after the second paragraph:
These specifications are also applicable for the following:
Historian Server
Web Server
SCADA HMI
158. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.4.1.4 (Control Building and Barrage Local Area Network
(LAN)), d) (Engineer/Operators Workstation).
Change the heading of the Sub-clause from Engineer/Operators Workstation to
Engineer/Operator/Piezometer Workstation.
159. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.4.1.4 (Control Building and Barrage Local Area Network
(LAN)), d) (Engineer/Operators Workstation).
Replace the words 8GB RAM, 1TB HDD, 24 SXGA VDU with the following words:
64GB RAM, 1TB HDD, 24 1920 x 1080 VDU in the second line of first paragraph.
160. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.4.5 (Uninterruptable Power Supply).
Add the word redundant before the word: battery in the first line of second paragraph.
161. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.5.1.1 (General).
Add the following paragraph at the end of the Sub-Clause: All applicable software
licenses shall be procured in the name of Client
162. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.5.1.3 (Processing Units).
Add the following sentence after the first sentence in the second line of first paragraph:
The Servers shall be minimum 1-2x Intel Xeon latest version.
163. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.5.2.1 (General).
Replace the words 0 to 60 C in the sentence at serial f) with the following words: -10
to +70 C.
164. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.5.6.2 (Outdoor/Indoor Day & Night IP Networking Cameras).
Replace the description at bullet point (13) Digital Zoom: 270x Digital Zoom or higher
with the following description: Optical Zoom: 30x or higher
165. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Sub-clause 16.5.8.2 (Instrumentation System).
Page 17 of 22
ADDENDUM NO. 1
Add the following sentence at the end of first paragraph: The complete system shall be
on line data acquisition with immediate alarming in the Control Room if any piezometer
reading goes out of range.
166. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
Serial No. A / (1) Programmable Logic Controller (PLC), Under the column Required
value (minimum) at Sr. No. 27, substitute 570 C with 70 C
167. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
At Serial No. A / (2) Servers and Workstations, Under the column Required value
(minimum) at Sr. No. 10: Add 64 GB RAM
168. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
At Serial No. A / (4) Operator Terminal, Under the column Required value (minimum)
at Sr. No. 7: Replace 16GB with 64GB
169. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
Replace the title at Serial No. A / (5) 80 LED VDU with the following:80 LED VDU
AND MIMIC SCREEN.
170. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
At Serial No. A / (5) 80 LED VDU, Under the column Required value(minimum) at
Sr.No.4, Add UHD 4k
171. Refer Section 16 (MONITORING, CONTROL AND TELECOMMUNICATION SYSTEM
(MCTS)), Schedule of Technical Data.
Serial No. B/ (1) Water Level Sensor (Ultrasonic), Add the following row after serial 19
Sr. No. Parameter Typical Required Value Offered
Value (minimum) value
20 Operating -10 C to 70 C
Temperature
Page 19 of 22
ADDENDUM NO. 1
Construction materials mentioned above should fulfill technical requirement/detail
stipulated under Technical Specification Civil
187. Section 14 (Health, Safety and Environment (HSE) Plan, Sub-clause (Emergency
Response Plan).
Add following text before start of first paragraph:
The Plan will be prepared by the Contractor and approved by the CSC.
188. Section 15 (Tree Plantation Plan), Sub-clause.
Delete the 3rd, 4th and 5th line related to public park from second paragraph of the sub-
clause.
189. Section 19 (Cost Estimate for EMP Implementation).
Add following text at the end of the first paragraph:
The Contractor will give a detailed break up of HSE implementation cost under the head
Implementation of Environmental Management Plan (EMP) provision for Health,
Safety and Environment measures included in the Contract under BOQ item 1.7. No
additional cost shall be paid to the Contractor other than quoted under related BOQ
item.
190. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Environmental Audit Cost.
Replace the title of the sub-clause with Environmental Audit
191. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Environmental Audit Cost.
Replace the entire text under the sub-clause with the following:
Two environmental Audit will be carried out by an independent consultant hired by the
Client.
192. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Training Cost.
Replace the title of the sub-clause with Training
193. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Plantation/Environmental Improvement Cost.
Replace the title of the sub-clause with Plantation/Environmental Improvement
194. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Plantation/Environmental Improvement Cost.
Replace the words four new bays in the first sentence with three new bays.
195. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Plantation/Environmental Improvement Cost.
Replace the last sentence of paragraph with the following;
New plantation should be undertaken near the area cleared of vegetation for project
execution and in this regard the contractor will plant 30,000 (at least 3 to 4 height) trees
of various locally available species on available space in and around project area as
directed by CSC.
196. Section 19 (Cost Estimate for EMP Implementation), Sub-clause 19.1 (Environmental
Effects Monitoring), Public Park Development.
Delete the entire text under the heading Public Park Development.
197. Section 20 (Contractors Obligation), Sub-clause (Adjustment with unstable locations
appearing during construction especially the foundation).
Delete the entire text under the heading Adjustment with unstable locations appearing
during construction especially the foundation.
I. VOLUME III (TENDER DRAWINGS)
198. Existing List of Tender Drawings (6 Pages) to be replaced by the Amended List of
Tender Drawings (5 Page) included in the Annexure F of Addendum No. 1.
Page 20 of 22
ADDENDUM NO. 1
199. Following Drawings shall be replaced, added and deleted as included in Annexure F of
Addendum No.1
*Old **New
Count Drawing No.
Sr. No. Sr. No.
Replacement (44 No. of Drawings)
1 14 14 PB-TD-CIV-05
2 15 15 PB-TD-CIV-06
3 16 16 PB-TD-CIV-06A
4 17 17 PB-TD-CIV-06B
5 18 18 PB-TD-CIV-06C
6 19 19 PB-TD-CIV-06D
7 20 20 PB-TD-CIV-07
8 21 21 PB-TD-CIV-07A
9 22 22 PB-TD-CIV-07B
10 23 23 PB-TD-CIV-08
11 24 24 PB-TD-CIV-09
12 25 25 PB-TD-CIV-09A
13 26 26 PB-TD-CIV-09B
14 46 45 PB-TD-STR-01
15 47 46 PB-TD-STR-02
16 48 50 PB-TD-STR-03
17 49 51 PB-TD-STR-04
18 50 52 PB-TD-STR-05
19 51 53 PB-TD-STR-06
20 52 54 PB-TD-STR-07
21 53 55 PB-TD-STR-08
22 54 56 PB-TD-STR-09
23 55 57 PB-TD-STR-10
24 61 64 PB-TD-STR-16
25 64 71 PB-TD-MECH-01
26 65 72 PB-TD-MECH-02
27 66 73 PB-TD-MECH-03
28 67 74 PB-TD-MECH-04
29 68 75 PB-TD-MECH-05
30 69 76 PB-TD-MECH-06
31 70 77 PB-TD-MECH-07
32 71 78 PB-TD-MECH-08
33 72 79 PB-TD-MECH-09
34 73 80 PB-TD-MECH-10
35 74 81 PB-TD-MECH-11
36 75 82 PB-TD-INS-01
37 76 83 PB-TD-INS-02
38 77 84 PB-TD-INS-03
39 78 85 PB-TD-INS-04
40 79 86 PB-TD-INS-05
41 80 87 PB-TD-INS-06
42 149 149 PB-TD-BUILD-42A
43 150 150 PB-TD-BUILD-42B
44 155 155 PB-TD-BUILD-46
Addition (8 No. of Drawings)
1 47 PB-TD-STR-02A
2 48 PB-TD-STR-02B
3 49 PB-TD-STR-02C
4 63 PB-TD-STR-15A
Page 21 of 22
ADDENDUM NO. 1
*Old **New
Count Drawing No.
Sr. No. Sr. No.
5 65 PB-TD-STR-16A
6 66 PB-TD-STR-16B
7 67 PB-TD-STR-16C
8 68 PB-TD-STR-16D
Deleted (8 No. of Drawings)
1 45 PB-TD-CIV-30
2 99 PB-TD-BUILD-01
3 100 PB-TD-BUILD-02
4 101 PB-TD-BUILD-03
5 114 PB-TD-BUILD-08
6 115 PB-TD-BUILD-09
7 116 PB-TD-BUILD-10
8 117 PB-TD-BUILD-11
*as per issued bidding document
**as per Addendum No. 1 to issued Bidding Document
Page 22 of 22
ANNEXURE A
TABLES OF ADJUSTMENT DATA
(TABLE A LOCAL CURRENCY)
Bidding Document for Rehabilitation and Upgrading of Panjnad Barrage Single-Stage: Two-Envelop
a Nonadjustable a:
0.40
General Consumer
g Miscellaneous Price Index of h:
Material and Plant Pakistan Bureau of
(0.02 to 0.06)
Statistics
Total 1.00
* Base Value to be entered by the Bidder in Column 4 shall be the Base Cost published by the specified source on the Base Date (i.e. 28 days
prior to the latest date for submission of the Bid) for each index for district Muzzafargarh. If the rate published by Pakistan Bureau of Statistics
(PBS), Government of Pakistan in Monthly Review on Price Indices for any indices is higher than the inserted rate, the published rate will then be
taken as the base rate. The index to apply shall be that for the month as stated in the relevant table.
** The sum of all weightings for adjustment quoted by the bidder should equal one (1.0). As guidance to the bidders and for the purpose of
checking their submissions, the Employer has estimated and provided a range of acceptable weightings for related major construction inputs in
accordance with the potential range of construction methodologies, based on estimated cost in a common currency.
If no weighting against some index is entered by the bidder in Column 6, the weighting relevant to that type of work shall be added to
the non-adjustable portion.
*** Ordinary Portland Cement (OPC) shall represent all types of cement as well as slag.
Note: Source of Index is Monthly Review on Price Indices for Muzaffargarh District issued by Pakistan Bureau of Statistics,
Government of Pakistan.
Bidders * Bidders
Index Code Index Description Source of * Base Value * Currency in
Equivalent * Proposed
Index and Date in FC1 Weighting
Type/Amount
Nonadjustable
a a:
0.40
Labour
b b:
(0.14 to 0.16)
Maintenance of
c Contractors c:
Equipment & Plant (0.12 to 0.16)
Miscellaneous
d Material and Plant d:
(0.14 to 0.22)
Structural Steel
e e:
(0.10 to 0.16)
Total 1.00
NOTE:
Base Value to be entered in Column 4 shall be the Base Cost published by the specified source on the Base Date (I.e. 28 days prior to the last date
of submission of bid) for each index.
* To be entered by the bidder. In case, no data is provided by the bidder, it will be inferred that the bidder is not interested in price adjustment
for foreign currency and in that case, the pertinent weighting shall be added to the non-adjustable portion.
** In case, no foreign labor/ staff is physically working at site, the bidders proposed weighting shall be added to the non-adjustable portion..
Single-Stage: Two-Envelope Bidding Document for Rehabilitation and Upgrading of Panjnad Barrage
ANNEXURE C
BILL OF QUANTITIES
Bidding Document for Rehabilitation and Upgrading of Panjnad Barrage (Addendum No. 1) Single-Stage: Two-Envelop
1 General Items
Care and Handling of Water for Works including Coffer Dam with
2
Diversion road
3 Repairing of Existing Barrage and Deck Slab
10 Mechanical Works
11 Electrical Works
Implementation of Environmental
Management Plan (EMP), provision for
1.7 health, safety and environment measures Months 36
included in the contract.
BILL NO. 2 - CARE AND HANDLING OF WATER FOR WORKS INCLUDING COFFER DAM WITH DIVERSION ROAD
Rate
Item Amount
Description Unit Quantity
No. (PKR)
In Figures In Words
Total Bill No 2
A Removal of silt, Raking and washing, Drilling and Grouting of Existing floor
Removal of deposited soil from barrage floor
3.1 including its disposal complete in all respect as 1000 Cft 1,952
directed by the Engineer
Raking and washing of surface area of
3.2 concrete floor complete in all respects as 100 Sft 6,508
directed by the Engineer
Condition survey of barrage floor including
arrangement of geophysical investigations (as
per specification) to assess the void and
3.3 cavities within the mass of barrage concrete Lump Sum 1
and beneath the floor complete in all respect
and in approved grid and pattern as directed
by the engineer.
Drilling for grouting 2" dia holes in concrete as
3.4 Lft 2,500
per drawings and specifications.
Drilling for grouting 2" dia holes in soil as per
3.5 Lft 477
drawings and specifications
Grouting cavities under the floor and voids in
3.6 100 Cft 47
concrete. (with contact grout material)
Grouting cavities under the floor. (with sand
3.7 100 Cft 77
material)
Sub Total A
Sub Total C
D Providing a Row of Steel Sheet Pile at the start of upstream floor (Left Undersluice)
Dismantling of plain concrete including its
3.32 disposal outside river bed and as directed by 100 Cft 21
the Engineer
Providing and installing AU 20 Steel Sheet
3.33 Piles or equivalent including driving, interlock Kg 64,156
sealing, complete in all respects.
Plain cement concrete, 1500 psi including
placing compacting, finishing and curing
(including screening and washing of stone
3.34 aggregate) in required shape and design, 100 Cft 3
including moulds, shuttering, lifting,
compacting, curing, rendering and finishing of
exposed surface, complete in all respects.
Groove formation 3" deep in existing RC Floor
3.35 for fixing the MS plate as per drawing and Lft 261
directed by the Engineer
Existing floor concrete surface to be
roughened by sand blasting or deleterious
concrete to be removed by chipping hammer,
3.36 high pressure washing for cleaning the 100 Sft 21
roughened surface and disposal of loose
material as per drawing or directed by the
Engineer.
Providing and fixing MS Plate 1/4" thick and 5"
3.37 wide between New and old concrete as per 100 Kg 176
drawing or directed by the Engineer
Sub Total E
Item Rate
Description Unit Quantity Amount
No. In Figures In Words
Borrow pit excavation in ordinary soil for
embankment from the areas up to any lead
and any lift including ploughing and mixing
with blade grader or disc harrow or other
4.1 suitable equipment and compaction by 1000 Cft 4,317
mechanical means and moistening to
optimum moisture contents and dressing to
designed section, complete in all respects for
90% maximum Modified dry density.
Providing and laying graded filter (crushed
stone) under spall layer as per drawings and
4.2 100 Cft 974
specifications for stone pitching including
carriage from approved quarry to site.
Providing and laying stone pitching for top
layer on slope including handling of material
4.3 100 Cft 2,784
as directed by the Engineer including carriage
from approved quarry to site.
Providing and laying shingle on top of Bank as
per drawings including handling of material as
4.4 100 Cft 1,472
directed by the Engineer including carriage
from approved quarry to site.
Earthwork excavation upto required level
4.5 including disposal of material upto any lead 1000 Cft 98
and lift as directed by the Engineer.
Rehandling of suitable excavated earth
including compaction of earthwork with power
road roller, including ploughing, mixing,
4.6 moistening earth to optimum moisture content 1000 Cft 98
in layers, etc. complete 90% maximum
Modified dry density (up to point of placement
as directed by the Engineer)
Total Bill No. 4
Rate
Item
Description Unit Quantity Amount
No.
In Figures In Words
DELETED
Total Bill No. 5 0 (Zero)
BILL NO. 7 - REHABILITATION OF HEAD REGULATOR OF PANJNAD CANAL, ABBASIA CANAL AND ABBASIA LINK CANAL
Lump
7.16 Credit of Dismantled material 1
Sum
a) 1st coat 35 lbs. Bitumen, and 4.0 cft bajri. 100 Sft 945
b) 2nd coat 18 lbs. Bitumen, and 2.0 cft bajri. 100 Sft 945
c) 3rd coat 14 lbs. Bitumen, and 1.5 cft bajri. 100 Sft 945
Sub-total C
Sub-total D
Note 1: Design, supply, transportation, storage, installation, testing and commissioning of the following items, consisting of but not limited to all material, labour, tools,
necessary furniture, accessories and Spare Parts etc. required for proper functioning of each item as per specifications, drawings and as directed by the Engineer.
Note 2: Items not listed here, but required for a fully functional system (including Spares) shall be deemed to be included.
Note 3: Of the Items listed here, only those shall be paid for which are actually supplied.
Note 4: For Optimal Performance, Bidders may propose different quantities than those listed here after giving solid justification.
Note 5: Bidders shall calculate I/0 requirements of PLCs according to their proposed hardware with at least 30% spare capacity for each type of I/O
9.1 Min. 80 LED HMI GUI for dynamic Mimic Board No. 1
Sub-total E
H Three Node Barrage Data WAN i.e. ESTABLISHMENT OF DATA MONITORING WORKSTATIONS
9.69 Lahore and 2 more nodes to be defined at design Stage
IBM Compatible PC configured as per current standards but not less
than Intel Core i7 CPU Latest version, 16Gb RAM, 1TB HDD, 24 inches
9.70 1920 x 1080 VDU, Keyboard, Mouse and Peripheral Interface Cards No. 3
loaded with MS WINDOWS latest Operating System for SCADA
Remote Monitoring System
9.71 Laser Printer, A4 No. 3
I Telecommunication System
Spread spectrum radio modem with 1/2 wave dipole antenna, male to
9.74 No 3
female serial cable, modem adapter and Power supply for piezometers
9.75 8 dynamic smart channel Multiplexer with cables for piezometers No 7
9.76 Fiber Optic Cable, including installation and services (estimated m) Rm 4000
Sub-total I
9.79 Process Connections, Instrument Power supply and Terminal Boxes Job 1
9.80 32" LED VDU for Surveillance Cameras (Video Display Workstation) No 1
Workstation for CCTV Video management configured as per current
Server standards but not with less than Intel core i7 CPU, 16Gb RAM,
9.81 2TB HDD, Latest powerful Graphics Card, Keyboard, Mouse and No 1
Peripheral Interface Cards loaded with MS WINDOWS 8 Operating
System
9.82 80" LED VDU for Surveillance Cameras (Multiple Camera Display) No 1
9.85 Interface hardware for smooth and easy camera PTZ control No 1
Sub-total J
K GENERAL
Sub-total K
H Workshop Equipment
Supplying, delivery to site, installing, testing including necessary civil work in accordance with the Specifications, removal of existing equipment where required
and commissioning, training of staff and maintenance till conclusion of Defect Notification Period of item but not limited to the following Equipment:
10.96 Mobile Electric Welding Plant No. 1
Sub-total H
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
Site survey, design, supply, manufacturing, transportation, storage, installation, earthing, testing and commissioning of the following items, consisting of but not limited to all
new branded fresh lot material, labour, tools and accessories etc. required for proper completion of each item/unit as per specification and drawings and/or as directed by
the Engineer.
A 11kV OVERHEAD NETWORK (HT/LT)
The new dedicated 11kV outgoing feeder from existing
132/11kV grid station Uch shareef MEPCO Bahawal pur
to control building of project premises / sites via barrage
colony , including MV panels (sending and receiving
end) underground cables and trenches, overhead
conductor with lattice steel structures poles associated
insulators and hardwares material complete as per
WAPDA/MEPCO prevailing rules and regulations . Site
survey, routing, spacing, design preparation,
submission, approval from MEPCO/WAPDA, execution,
testing and commissioning and associated works shall
be included in the Contractor's scope of work. All the
expenses of grid sharing, design vetting, material cost
and connection charges of WAPDA/MEPCO shall also
be borne by the contractor.
11.1 HT feeder/line as per site requirement km 15
HT/LT composite feeder/line as per site requirement
11.2 km 1.5
(from left to right side of barrage)
11.3 LT feeder/line as per site requirement km 2
Sub-total A
DISTRIBUTION TRANSFORMER
11/0.415 kV outdoor distribution transformer (pad or pole
mounted) complete with all other accessories as per
MEPCO/WAPDA standards procedures along with
demand notices charges and security deposits and
Section 4 Bidding Forms 4-78
Bidding Document for Rehabilitation and Upgrading of Panjnad Barrage (Addendum No. 1) Single-Stage: Two-Envelop
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
obtaining of 11 kV electrical connections, installation
material, energy meters, terminations kits (in and out)
cable boxes, earthing, D fuses fittings etc. complete in
all respect, ready for connection from relevant utility
company.
11.4 200 kVA rating as specified Each 1
Sub-total C
Sub-total D
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
E LOW VOLTAGE SWITCHGEAR PANEL
Sub-total E
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
G CABLE CONDUIT SYSTEM
The cable conduit shall be installed wherever required
for low voltage power/control cables as Complete Unit
System as defined herein and mentioned in the relevant
specification or drawings as directed by of the Engineer.
The mechanical strength/stability of existing steel
structure shall be checked prior to installations.
38 mm dia, GI conduit/flexible pipe complete with all
11.15 Rm 1500
accessories.
11.16 160 mm dia class-D, PVC pipe with all accessories Rm 110
Sub-total G
H POWER CABLES
Single/Multi core 3-Phase, 5 wire RYBN & E ,single core,
single phase 3 wires PNE pulled in cable tray/conduit as
specified requirements or detailed in drawing and as
directed by the Engineer. The mechanical
strength/stability of existing steel structure shall be
checked prior to installations.
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
Single core Cu/PVC
11.22 Rm 102
16 mm2 (CPC)
Cu/XLPE/PVC Power Cable
11.23 Rm 532
Four Core 16 mm2 (R,Y,B& N)
Single core Cu/PVC
11.24 Rm 532
16 mm2 (CPC)
Cu/XLPE/PVC Power Cable
11.25 Rm 404
Four Core 6 mm2 (R,Y,B & N)
Single core Cu/PVC
11.26 Rm 404
6 mm2 (minimum)
Cu/XLPE/PVC Power Cable
11.27 Rm 413
Four Core 4 mm2 (R ,Y ,B & N)
Single core Cu/PVC
11.28 Rm 413
4 mm2 (CPC)
Sub-total H
I JUNCTION/PULL BOX
Sub-total I
Section 4 Bidding Forms 4-82
Bidding Document for Rehabilitation and Upgrading of Panjnad Barrage (Addendum No. 1) Single-Stage: Two-Envelop
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
J OUTDOOR LIGHTING POLES and FIXTURES
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
The lighting fixture complete with LV cables/wiring
(PNE), MCBs, 150W HPSV (High Pressure Sodium
Vapour) lamp, glass refractor, aluminum reflector,
ballast, p.f. correction capacitor etc. make Philips, SGP
328 (VeloCity) or Thorn (Triumph 2) or lndulux (IVH-1) or
11.37 approved equivalent. The protection class of lamp Each 126
compartment shall be IP-66 and gear compartment IP-
43, or better. The light luminaries/fixtures shall be
installed at divide walls, steel superstructures and roads
area with extended arm bracket etc. as per site
installation requirement.
Road lighting fixture complete with 250W H.P. sodium
vapour lamp, glass refractor, capacitor etc. Philips make
SGP 338 (VeloCity) or Thorn (Triumph 2) or lndulux
11.38 Each 30
(IVH-1) or approved equivalent. The protection class of
lamp compartment shall be IP-66 and gear compartment
IP-43, or better (For 10 meter poles).
Enclosed lighting fixture completes with Ballast, Igniter,
Capacitor and 250 watts SON-T PIA Plus Lamp make
Philips Tango-3 or approved equivalent along with
11.39 metallic junction box with MCB plus terminal blocks for Each 4
connection. The protection class of lamp compartment
shall be IP-66 and gear compartment IP-43, or better
(Surface Mounted)
Enclosed lighting fixture completes with Ballast, Igniter,
Capacitor and 400 watts SON-T PIA Plus Lamp make
Philips Tango-3 or approved equivalent along with
11.40 metallic junction box with MCB plus terminal blocks for Each 15
connection. The protection class of lamp compartment
shall be IP-66 and gear compartment IP-43, or better
(For 15 m high mast)
Sub-total J
Rate (PKR)
Item No. Description Unit Quantity Amount (PKR)
In Figures In Words
K CONTROL BUILDING ELECTRIFICATION -
Sub-total K
A Labour
12.1 Gang Leader Hr 800
Allow Ten percent of subtotal for Contractors overheads, profit etc. in accordance with paragraph 3(b) of the Daywork Schedule
B Materials
12.12 Cement, ordinary Portland in bags Ton 40
Sub Total B
Allow Ten percent of subtotal for Contractors overheads, profit etc. in accordance with paragraph 3(b) of the Day work Schedule
Note: Amounts for work executed under DAYWORKS shall be expended in whole or in parts at the discretion and as per direction of the Engineer.
BILL NO. 12
SUMMARY DAYWORKS
Item
Description Amount (PKR)
No.
Daywork Schedule
General
1. Reference should be made to Sub-Clause 13.6 of the General Conditions. Work shall not be executed on a Daywork
basis except by written order of the Engineer. Bidders shall enter basic rates for Daywork items in the Schedules,
which rates shall apply to any quantity of Daywork ordered by the Engineer. Nominal quantities have been indicated
against each item of Daywork, and the extended total for Daywork shall be carried forward as a Provisional Sum to
the Summary Total Bid Amount. Unless otherwise adjusted, payments for Daywork shall be subject to price
adjustment in accordance with the provisions in the Conditions of Contract.
Daywork Labour
2. In calculating payments due to the Contractor for the execution of Daywork, the hours for labour will be reckoned
from the time of arrival of the labour at the job site to execute the particular item of Daywork to the time of return to
the original place of departure, but excluding meal breaks and rest periods. Only the time of classes of labour directly
doing work ordered by the Engineer and for which they are competent to perform will be measured. The time of
gangers (charge hands) actually doing work with the gangs will also be measured but not the time of foremen or
other supervisory personnel.
3. The Contractor shall be entitled to payment in respect of the total time that labour is employed on daywork,
calculated at the basic rates entered by him in the Schedule of Daywork Rates for Labour, together with an additional
percentage payment on basic rates representing the Contractors profit, overheads, etc., as described below:
(a) The basic rates for labour shall cover all direct costs to the Contractor, including (but not limited to) the amount
of wages paid to such labour, transportation time, overtime, subsistence allowances, and any sums paid to or
on behalf of such labour for social benefits in accordance with the Pakistani law. The basic rates will be payable
in local currency only.
(b) The additional percentage payment and applied to costs incurred under (a) above shall be deemed to cover the
Contractors profit, overheads, superintendence, liabilities, and insurances and allowances to labour,
timekeeping, and clerical and office work, the use of consumable stores, water, lighting, and power; the use and
repair of staging, scaffolding, workshops, and stores, portable power tools, manual plant, and tools; supervision
by the Contractors staff, foremen, and other supervisory personnel; and charges incidental to the foregoing.
Payments under this item will be made in local currency only.
Daywork Material
4. The Contractor shall be entitled to payment in respect of materials used for Daywork (except for materials for which
the cost is included in the percentage addition to labour costs as detailed heretofore), at the basic rates entered by
him in the Schedule of Daywork Rates for Materials together with an additional percentage payment on the basic
rates to cover overhead charges and profit, as follows:
a) The basic rates for materials shall be calculated on the basis of the invoiced price, freight, insurance, handling
expenses, damage, losses, etc., and shall provide for delivery to store for stockpiling at the Site. The basic rates
shall be stated in local currency and payment shall be made in local currency only.
b) The additional percentage payment applied to the payments made under Sub-Para (a) above; and
c) The cost of hauling materials used on work ordered to be carried out as Daywork from the store or stockpile on
the site to the place where it is to be used will be paid in accordance with the terms for Labor and Contractors
Equipment in this Schedule.
5. The Contractor shall be entitled to payments in respect of Contractors Equipment already on the Site and employed
on Daywork at the basic rental rates entered by him in the Schedule of Daywork Rates for Contractors Equipment.
The said rates shall be deemed to include complete allowance for depreciation, interest, indemnity and insurance,
repairs, maintenance, supplies, fuel, lubricants, and other consumables, and all overhead, profit and administrative
costs related to the use of such equipment. The cost of drivers, operators and assistants will be paid for separately
as described under the section on Daywork Labour.
6. In calculating the payment due to the Contractor for Contractors Equipment employed on Daywork, only the actual
number of working hours will be eligible for payment, except that where applicable and agreed with the Engineer,
the travelling time from the part of the Site where the Contractors Equipment was located when ordered Engineer
to be employed on Daywork and the time for return journey thereto shall be included for payment.
7. The basic rental rates for Contractors Equipment employed on Daywork shall be stated in local currency and
payment shall be made in local currency only.
SPS. 1 Provide equipment and supplies for Engineer's / Employer's office and field survey and security arrangements. 65,000,000
SPS. 2 Maintain equipment for Engineer's / Employer's office and field survey. 5,000,000
SPS. 3 Provision of Spare parts and Testing and maintenance equipment as directed by the Engineer. 10,000,000
Adjustment of Contract Price for changes in legislation under sub-clause 13.7 of G.C.C., adjustment for changes in
SPS. 4 cost under sub-clause 13.8 of G.C.C. and any other authorized reimbursements under the Contract 600,000,000
SPS. 5 Payment to Dispute Board under Clause 20 of G.C.C. (Employer's share only) 8,000,000
Design, provision and installation of 11 kV HT/LT overhead network including energy meters through
SPS. 6 DISCO/WAPDA for existing Barrage Colony and offices 15,000,000
SPS. 7 Continuation of Contractor's provided services during Defects Notification Period. 2,000,000
705,000,000