Académique Documents
Professionnel Documents
Culture Documents
Appendix I
Report
on
Integral Abutment Bridge Design
by
VTranstructures Section
Montpelier, Vermont
4 Summary ............................................................................................................. 14
2.1 Structural/Geometrical
Preferably, skew angles shall be limited to 20 degrees.
Curved bridges with straight beams are allowed. Curved
bridges with curved girders are not allowed.
The difference in profile grade elevation at the abutments
shall not exceed 5% of the bridge length, measured at the
centerline of bearing.
Abutments and piers shall be parallel with each other. Piers
should be in-line with the thalweg (main flow path) of the
stream. All beams shall be parallel with each other.
Limit abutment height to a maximum of 13' (4 m) from
finished grade to reduce the passive earth pressure acting
against each abutment. It is preferable to keep abutment
heights equal on each side of the bridge.
The total maximum bridge lengths, measured centerline
of bearing to centerline of bearing, are as follows:
Steel bridges: 330' (100 m)
Concrete bridges: 590' (180 m)
Preferably, abutments shall have a U-wingwall configura-
tion. Flared wingwalls may be considered at the discretion
of the designer. When very short wingwalls are needed, in-
line wingwalls may also be considered.
Construction joint between the pile cap and the curtain wall:
The designer may either slope the top surface of the pile cap with the cross
slope of the final grade, make it level or step it.
Place a shear key just behind the girders so that it will be continuous along
the entire abutment.
Detail a score mark on front face along the construction joint.
Detail a minimum of 4" (100 mm) from theoretical seat elevation (bottom of
girder flange) to the joint elevation.
3.1.4 Analysis and Design for Frame Action (Negative Moment) at Ends of Deck
The pile cap should be analyzed with the following criteria:
The pile cap shall resist the shear from the passive earth pressure.
The pile cap shall resist the combined moment from passive earth pressure, live
load and superimposed dead load rotation.
Additional steel in the deck at each end may need to be designed to resist the above.
3.2 Substructure
3.2.1.1 Thermal
Thermal movement is caused when the structure expands and contracts due to fluctuations in the ambient
temperature. Because the deck is monolithically connected to the abutments, the abutments move with this
expansion and contraction. Concrete bridges tend not to expand or contract to the same magnitude as steel
bridges. This is due to the heat sink nature of the mass of concrete that comprises the superstructure. The
following may be used for calculating thermal movement:
Steel
Thermal range is 150 F (83 C.)
With the coefficient of thermal expansion being 0.0000065/F (0.0000117/
C), use 0.936"/100' (78 mm/100 m) of bridge length.
For the maximum bridge length of 330' (100 m), this equates to 3.1" / 2 abut-
ments or 1.55" (40 mm) total movement throughout the thermal extremes at
each abutment.
Concrete
Thermal range is 90 F (32 C.)
With the coefficient of thermal expansion being 0.0000060/F (0.0000168/
C), use 0.648"/100' (54 mm/100 m) of bridge length.
For the maximum bridge length of 590' (180 m), this equates to 3.82" / 2
abutments or 1.91" (49 mm) total movement throughout the thermal extremes
at each abutment.
3.2.2 Piles
up, the designer can use the file to make minor modifications, as necessary, including modifying
pile geometry and orientation (strong/weak axis) and modifying the soil profile to analyze the scour
condition. The important elements of the design that are drawn from this output are the following:
LATERAL LOAD AT PILE HEAD: This is the lateral load required to gener-
ate the design thermal movement demand, or deflection, due to tempera-
ture loading.
PILE DEFLECTION AND MOMENT: The deflection and moment throughout
the pile due to temperature loading can be output both in graphical (Fig-
ure 6 and 7) and tabular (Figure 8) formats. Included in the tabular out-
put are the maximum negative moment at the pile head (X = 0 in.) and the
maximum positive moment within the pile unbraced length. The location
of the maximum positive moment is dependent upon the soil conditions
and will vary from project to project.
UNBRACED LENGTH: The length along the pile, between inflection points,
or points of moment reversal (see Figures 7 and 8). This is the length
used to calculate buckling stresses in the pile.
DEPTH TO FIXITY: The effective pile length, or the depth to zero deflection
in the pile. (See Figures 4 and 6). The effective pile length shall be be-
tween the bottom of the pile cap to the depth of fixity.
The threshold for using the beam/column specifications of AASHTO 10.54.2 is 0.15FyA (AASHTO
10.48). If the factored axial load on the pile exceeds the values in Table 2 the designer is required
to design the pile as a beam/column.
Piles meeting the requirements of the applicable column or beam/column analysis are considered to
be acceptable for use on the project.
4 Summary
Jointless bridges have proven to be significant sources of cost
savings in bridge programs across the nation. The implementa-
tion of a bridge program that supports and encourages the use of
jointless bridges as the primary design option will inevitably save
thousands of dollars and allow for better uses of the programs
economic resources. Savings experienced in both initial construc-
tion and reduced maintenance costs will translate into additional
bridges being built, resulting in an improved integrated transpor-
tation system responsible for the transport of goods and services
in a safe, efficient, cost effective, and environmentally sensitive
manner.
0$;,080326,7,9(
96.00 .116E+00 .479E+03 .259E+05 .264E+01 .399E+03 .539E+07
020(17:,7+,1
102.00 .907E-01 .493E+03 .264E+05 .288E+00 .384E+03 .539E+07
3,/(81%5$&('
108.00 .684E-01 .493E+03 .264E+05 -.194E+01 .360E+03 .539E+07
114.00 .494E-01 .479E+03 .259E+05 -.400E+01 .327E+03 .539E+07
120.00 .336E-01 .453E+03 /(1*7+
.251E+05 -.574E+01 .251E+03 .539E+07
126.00 .208E-01 .417E+03 .239E+05 -.711E+01 .207E+03 .539E+07
132.00 .108E-01 .372E+03 .225E+05 -.819E+01 .153E+03 .539E+07
138.00 .331E-02 .322E+03 .208E+05 -.881E+01 .539E+02 .539E+07
144.00 -.206E-02 .270E+03 .191E+05 -.886E+01 -.350E+02 .539E+07
150.00 -.562E-02 .218E+03 .174E+05 -.846E+01 -.999E+02 .539E+07
156.00 -.774E-02 .169E+03
81%5$&('/(1*7+
.158E+05 -.773E+01 -.143E+03 .539E+07
162.00 -.872E-02 .126E+03 .144E+05 -.680E+01 -.168E+03 .539E+07
P -.177E+03
7+,6,67+(
168.00 -.886E-02 .881E+02 .132E+05 -.576E+01 .539E+07
174.00 -.842E-02 .567E+02 .122E+05 -.470E+01 -.175E+03 .539E+07
180.00 -.760E-02 .314E+02 /(1*7+%(7:((1
.113E+05 -.369E+01 -.163E+03 .539E+07
186.00 -.656E-02 .120E+02 =(52020(176
.107E+05 -.276E+01 -.146E+03 .539E+07
192.00 -.545E-02 -.217E+01 .104E+05 -.194E+01 -.125E+03 .539E+07
198.00 -.435E-02 -.118E+02 .107E+05 -.126E+01 -.103E+03 .539E+07
204.00 -.333E-02 -.177E+02 .109E+05 -.702E+00 -.817E+02 .539E+07
210.00 -.243E-02 -.207E+02 .110E+05 -.272E+00 -.614E+02 .539E+07
216.00 -.167E-02 -.214E+02 .110E+05 .423E-01 -.434E+02 .539E+07
222.00 -.105E-02 -.205E+02 .110E+05 .257E+00 -.281E+02 .539E+07
228.00 -.564E-03 -.185E+02 .109E+05 .387E+00 -.155E+02 .539E+07
234.00 -.204E-03 -.160E+02 .108E+05 .451E+00 -.578E+01 .539E+07
240.00 .487E-04 -.133E+02 .107E+05 .465E+00 .127E+01 .539E+07
246.00 .213E-03 -.105E+02 .107E+05 .444E+00 .572E+01 .539E+07
252.00 .307E-03 -.800E+01 .106E+05 .401E+00 .848E+01 .539E+07
258.00 .348E-03 -.575E+01 .105E+05 .346E+00 .987E+01 .539E+07
9(5<60$//
264.00 .351E-03 -.385E+01 .104E+05 .286E+00 .102E+02 .539E+07
270.00 .328E-03 -.231E+01 .104E+05 .226E+00 .977E+01 .539E+07
276.00 '()/(&7,21
.289E-03 -.112E+01 .103E+05 .170E+00 .884E+01 .539E+07
282.00 ,1',&$7,1*
.243E-03 -.250E+00 .103E+05 .121E+00 .761E+01 .539E+07
288.00
294.00
.195E-03
.149E-03
),;,7<
.350E+00
.723E+00
.103E+05
.103E+05
.794E-01
.459E-01
.625E+01
.491E+01
.539E+07
.539E+07
Page 14
References
GENERAL INFORMATION
ASCE/Civil Engineering, November 1985
Jointless Bridge Decks
Xanthakos, Petros P., Bridge Substructure and Foundation Design, Prentice Hall, 1995
7.16 Integral Abutments
DTI Management Best Practice, HTML Page from Internet, Feb. 1999
Design & Construction of Integral Bridges to the USA 10-21 Aug. 1997
Steel Works, High Performance Steel Bridge Concepts, HTML Page from Internet, Feb 1999
High Performance Steel Bridge Concepts, IV Integral Connections
Performance
TRB-TRR 903, 1983
Skewed Bridges with Integral Abutments
ASCE/Journal of Geotechnical and Geoenvironmental Engineering, Vol. 124, No. 5, May 1988
Centrifuge Modeling of Spread-Base Integral Bridge Abutments
TRB-TRR 1415, Field Performance of Structures and Non Destructive Evaluation of Subsurface Infrastructure, 1993
Skew Effects on Backfill Pressures at Frame Abutments
Design ISSUES
FHWA/RD-86/102, Seismic Design of Highway Bridge Foundations, June 1986
Vol. II, Design Procedures and Guidelines, 8.3 Integral Abutments
TRB-TRR 1223, Bridge Design and Performance and Composite Materials, 1989
Rational Design Approach for Integral Abutment Bridge Piles
ANALYSIS
ASCE/Journal of Structural Engineering, Vol. 112, No. 10, October 1986
Nonlinear Analysis of Integral Abutment Bridges
TRB-Conference Proceedings 7, 4th International Bridge Engineering Conference Vol. 2, Aug 1995
Application of Precast, Prestressed Concrete Piles in Integral Abutment Bridges
APPROACH SLABS
TRB-TRR 1113, Bridge Maintenance, Corrosion, Joint Seals, and Polymer Morter Materials, 1987
Bridge Approach Pavements, Integral Bridges and Cycle-Control Joints
FORCES
TRB-TRR 664, Bridge Engineering, 1978
Environmental Stresses in Flexibly Supported Bridges
STATE MANUAL REFERENCES
Illinois Department of Transportation, March 1995
Section 3 Design, 3.6.12 Integral Abutments
Semi-Integral Bridges
TRB-TRR 1460, Structures, 1994
Semi-Integral Bridges: Movements and Forces