Vous êtes sur la page 1sur 15

Al-Zour Refinery Project

(Contract No. : ZOR/EPC - 0045)


Material Approval Request Page
Title
for concrete repair - SIKA 1 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Engineering, Procurement, Construction,


Pre-Commissioning and Assistance during
Commissioning / Start-up / Performance Testing of the
Al-Zour Refinery Project, Kuwait

Contract No.: ZOR / EPC 0045

Material Approval Request


for concrete repair - SIKA

O 19-11-2016 Issue for Approval R. BOUCHER C. ROBERT M. YON

Revision
Rev. Date Prepared by Checked by Approved by
Description

Document Number

Project Identifier Area/Unit No. Group Code No. Document Type Sequence No.

P4045ZOR PMR PM CM 729

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 2 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Change Log
Rev. Section Change Description

O Issue for Approval

Document Holds
Section Description

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 3 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

TABLE OF CONTENTS
1 INTRODUCTION ........................................................................................................................4
1.1 PROJECT DESCRIPTION ................................................................................................4
1.2 PURPOSE OF THE DOCUMENT .....................................................................................4
Attachment 1. Subcontractors material approval request concrete repair SIKA ...............5

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 4 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

1 INTRODUCTION

1.1 PROJECT DESCRIPTION

Al-Zour Refinery Project (ZOR) is one of the strategic initiative projects of Kuwait National Petroleum
Company (a Subsidiary of KPC) to expand the refining capacity in Kuwait.

It is one of the worlds largest grass root refinery project with a refining capacity of 615,000 BPD.

The refinery is designed to process different types of Kuwaiti Crude oils, having full flexibility to
process 615,000 BPD of Kuwait Export Crude oil (KEC) or 535,000 BPD of a mixture of Kuwait
Heavy Crude (KHC) oils with KEC oil.

1.2 PURPOSE OF THE DOCUMENT

This document is prepared for the approval request for Concrete repair which will be utilized for Unit
98 Small Boat Harbour and Unit 99 Land Reclamation Phase I. Contractor submits the request for
the proposed material in order for Companys kind review and approval as the attachment of this
document.

This product will be used and strictly followed as per the suppliers specification

This Material Approval Request will be regularly reviewed and/or updated whenever it is deemed to
be necessary in order to ensure the implementation and improvement of the works on the project.

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 5 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Attachment 1. Subcontractors material approval request concrete repair SIKA

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 6 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 7 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 8 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 9 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 10 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 11 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 12 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 13 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O
Al-Zour Refinery Project
(Contract No. : ZOR/EPC - 0045)
Material Approval Request Page
Title
for concrete repair - SIKA 14 of 14

No. P4045ZOR-PMR-PM-CM-729 Rev. O

Method Statement Repair of concrete


P4045ZOR-PMR-PM-CM-729_O