Académique Documents
Professionnel Documents
Culture Documents
This document contains proprietary information belonging to Blue Projects and/or affiliated companies and shall be used only for the purpose for which it
was supplied. It shall not be copied, reproduced or otherwise used, nor shall such information be furnished in whole or in part to others, except in
accordance with the terms of any agreement under which it was supplied or with the prior written consent of Blue Projects and shall be returned upon
request.
To:
PORTLAND TRUST DEVELOPMENT TWO,
Floreasca Park, 43 Sos. Pipera, Entrance A, Ground Floor, 014254, Bucharest 2, Romania
We have examined the Conditions of Contract, Specification, Drawings, Bill of Quantities, the other
Schedules, the attached Appendix and Addenda No. _________ for the execution of the above-named
Works. We offer to execute and complete the Works and remedy any defects therein in conformity with
this Tender which includes all these documents, for the sum of:
(Euro)____________________________________________
or such other sum as may be determined in accordance with the Conditions of Contract.
We agree to abide by this Tender until __________________ and it shall remain binding upon us and
may be accepted at any time before that date. We acknowledge that the Appendix forms part of this
Letter of Tender.
If this offer is accepted, we will provide the specified Performance Security, commence the Works as
soon as is reasonably practicable after the Commencement Date, and complete the Works in
accordance with the above-named documents within the Time for Completion.
Unless and until a formal Agreement is prepared and executed this Letter of Tender, together
with your written acceptance thereof, shall constitute a binding contract between us.
We understand that you are not bound to accept the lowest or any Tender you may receive.
Date: _____________________________
[Note: with the exception of the items for which the Investors requirements have been inserted, the following
information must be completed before the Tender is submitted]
Item Data
Time for Completion of the Works Refer to Volume 01, Section 01 Clause 19.5
/
/
/
/
/
/
/
/
/
/
/
/
/
/
1
Not the whole fleet of equipment owned by the Contractor
/
/
/
/
/
C) OTHER EQUIPMENT
/
/
/
/
/
/
Signature: ...........................................................
(a person or persons authorized to sign on behalf of the Tenderer)
Date: ...........................................
5.2.1 State the proposed location of your Main Site Office, your site organization and the Investors site office
(sketches to be attached as required)
5.2.2. The tenderer must submit with his bid the signed and editable versions of the Graphic Work Schedule (MS
Project) showing times and duties allocated for employees for this Contract. The programme shall comprise:
a brief outline of your programme for the completion of the Works, along with a description of the main
stages / milestones.
an overall Construction Programme and critical milestone bar chart (Schedule of Execution), based on
the stated dates for possession and completion, which is sufficiently detailed to show the Contractor's
sequence of working compatible with the Method Statement provided in the bid. The Programme shall
identify all major construction
Procurement / Material approval schedule. The Tenderer shall indicate on his schedule the latest dates
by which he requires final information to enable procurement of sub-contracts or supplies and the latest
dates by which he requires comments (if any) from Blue Projects on samples and mock-ups.
A Design Programme and Design Approval Programme (coordinated with the Construction Programme)
which shall include sub-contract design and identify dates by which orders are to be placed with sub-
contractors, suppliers, and statutory undertakers. The Design Programme shall indicate the dates by
which information is required to enable procurement of sub-contracts or supplies, as well as a design
review plan.
Resources schedule setting out the level of and the allocation of management to the project for both
pre-and post-contract phases. The following resource schedule shall address the contract participation
of following:
Project Manager
Design Manager
Site Manager
Health & Safety Manager
QA Manager
Programmer / Planner
Structural Engineers
Mechanical Engineers and Electrical Engineering Supervisor and Coordinator
A schedule of anticipated weekly labor to be employed on the Contract in the form of a histogram
including a statement of working days and hours to be worked within those weeks.
Cash Flow Schedules
Estimated testing and commissioning programme.
The tenderer is liable to keep in the programme the same structure proposed for the BoQ and to add an
additional column, in which to mention the corresponding unique code from the BoQ for all the works
described in the programme.
% Value of Subcontract as
Work intended to Name and details of Sub- Experience in Similar Work
Percentage of Total Cost
be sub-contracted Contractor (Details to be Specified)
of the Project
Signature: ...........................................................
(a person or persons authorized to sign on behalf of the Tenderer)
Date: ...........................................
Please attach sketches and data detailing the method of works you will adopt during construction.
Methods proposed for the main construction activities and the resources to be used on them (labor
and Contractors equipment, including any temporary works) should be described.
i - Overall
- Foremen ........................
- Mechanics ........................
- Technicians ........................
- Drivers ........................
___________________________________________________
- Surveyors ........................
- Foremen ........................
- Mechanics ........................
- Technicians ........................
- Drivers ........................
___________________________________________________
Total ===========
Signature: ...........................................................
(a person or persons authorised to sign on behalf of the Tenderer)
Date: ...........................................
Years of
experience Major Works for
Function/Name Nationality Age Education (with the which Responsible
Company/ in (Project/Value)
construction)
Project Manager
Assistant Project
Manager
Design Manager
Construction Manager
Area Engineers
Works Manager /
General Foreman
H&S Officer (one full
time per 50 workers)
...
Signature: ...........................................................
(a person or persons authorized to sign on behalf of the Tenderer)
Date: ...........................................
1. Surname:
2. Name:
4. Nationality:
5. Civil Status:
6. Address (phone/fax/e-mail):
7. Education:
Institutions:
Date:
From (months/year)
To (months/year)
Degree
14. Specific experience in projects similar to the project subject to this tendering:
Country (Romanian based Date: from (month/year) to Name and brief
preferred) (month/year) description of the project
16. Others
16a. Publications and Seminars:
16b. References:
The personnel defined in the organizational chart of the Contractor, for which he will submit the
corresponding CVs, will be permanently and actively involved in the project execution. No other
personnel will be considered as approved, if not included in the organizational chart.
Signature: ...........................................................
(a person or persons authorised to sign on behalf of the Tenderer)
Date: ...........................................
Form 5.5
QUALITY ASSURANCE SYSTEM(S)
Please provide hereunder details of the Quality Assurance System(s) it is proposed to use to
ensure successful completion of the Works.
Tenderers may add here any further information that they may deem useful for the
evaluation of their Tenders.