Académique Documents
Professionnel Documents
Culture Documents
Think tanks
Ali Ashtiani, Frank Robinson and Barbara Weber, CB&I, USA, use a
recently completed project in Papua New Guinea to highlight
key considerations when executing a large engineering,
procurement and construction project in refinery tanking.
apua New Guinea (PNG) occupies the eastern portion To capture opportunities for exporting oil not consumed in
Figure 1.
Construction of
storage tanks in
Papua New
Guinea.
conditions. Since the area is seismically active, the tank risk of fire and limit the amount of vapour that evapourates,
designs were based on the requirements for building struc- when compared with open top tanks.
tures that might experience an earthquake of the magnitude However, if the vapour pressure is higher than 1.5 psia,
and duration that could occur at a Zone 4 site. the space between the product and the roof exposes the liq-
The type of roof used on petroleum storage tanks pre- uid to high evapourative losses. Additionally, the probability of
sents another important design consideration. Tanks at a combustible gas mixture increases for certain volatile petro-
refineries are generally fixed roof tanks, external floating roof leum products. For this reason, products that have a vapour
tanks and internal floating roof tanks (Figure 2). pressure higher than 1.5 psia generally use a floating roof
If vapour pressure is less than 1.5 psia, open top tanks or design (Figure 3).
fixed-roof tanks work well. Fixed-roof tanks greatly reduce the The design of the tank also affects its operational costs
and future maintenance costs. For example, if a floating roof
design is used, the mechanical stability of the floating roof is
critical. The floating roof must remain balanced to prevent it
from tilting or sinking.
For volatile products, such as gasoline, pressure is
applied to limit the evapouration of the product. Low pressure
tanks designed for pressures up to 15 psig can be used for
Figure 2. Fixed roof tank, external floating roof these products. For highly volatile products that require a
design pressure greater than 15 psig, such as butane, the
tank and an internal floating roof tank.
storage tank is designed as a spherical pressure vessel (see
sphere in foreground of Figure 4).
Procurement: ensuring on time
deliveries
Securing the materials to build 28 storage tanks in a region as
remote as Papua New Guinea can provide logistical chal-
lenges for the most seasoned EPC contractor. Virtually all the
material needed for the project had to be obtained and
shipped from outside the country. The project team had to
locate the best source for purchasing each item needed to
build the tanks and then determine the most cost-effective
means of getting the material to the location in time to meet
the construction schedule. The team decided the best way to
handle these logistics was to divide the task into three sepa-
rate procurement activities, one of which was focused on
procuring the steel needed to build the tanks. This activity was
handled out of the CB&Is Dubai office.
Figure 3. Large diameter floating roof tank. Approximately 5000 mt of steel was required to erect the