Académique Documents
Professionnel Documents
Culture Documents
In 12 Months
The First Year of Southern Companys AWP Journey
AWP Conference 2015
2
About Southern Company
3
Goal For Today
4
AWP Timeline
5
Business Case
6
Business Case
Stage 2
Fully Automated
Metric: improved labor productivity Integrated Systems
Previous for WFP Contractors Continuous Improvement
Projects:
Baseline
8
Business Case
Quantifiable benefits
Assume ~$300M TIC per site $2B for the program
Of that $2B, $600M is direct labor
Of that $600M direct labor, $400M will be performing WFP
For every 1% increase in productivity, you avoid $4M
Soft benefits
Better project planning, accountability, responsiveness
Predictability of project performance, timeliness of deliverables
Safety a well-planned job is a safely executed job.
An hour not worked is an hour not at risk.
9
Business Case $40,000,000
Costs
$35,000,000
Savings
$30,000,000
$25,000,000
Costs
$20,000,000
AWP Project Manager $15,000,000
Consulting $10,000,000
Process development $5,000,000
Initial training $-
Technology
Simple relational database Direct Labor Productivity Increase
Contractors Workface
Planners
10
Process Development
11
Process Development:
Guiding Principles
Dont reinvent the wheel
BUT make sure you bite off enough to make it worth your while
12
Process Development:
Program Design Challenges AWP
Guideline
Multiple projects per site
13
Plant-Project
FAN12345
Process Development: LWP Labor Work Package
LPR01 Prime Package 01
Package Hierarchy
CWA Construction Work Area
A01.FAN12345
Contractor
EPCM
MRP Material Requirements Package TOP Turnover Package
MRP01.E01.MECH01.A01.FAN12345 KDES01 Instrument Air System 14
CWP Type DOW Code Description
STWK 001 Underground Investigations / Site Work
Process Development: RELO
DFDN
002
003
Relocations
Deep Foundations
01/11/2016 16
Process Development:
AWP Performance Levels
01/11/2016 17
Process Development:
AWP Performance Levels
18
Process Development:
AWP Performance Levels
19
Process Development:
Project Delivery Spectrum
AWP
BYO Process
Guideline
20
Process Development:
AWP Performance Levels
AWP
Number of
Site E P CM Performance
Projects
Level
A 3 In-house In-house In-house Level 2
B 2 In-house In-house In-house Level 1
C 2 In-house In-house In-house Level 1
D 1 In-house In-house In-house Level 1
E 2 Partner In-house Partner Level 2
F 2 Partner In-house In-house Level 1
G 3 Partner Partner Partner Level 2
21
Process Development:
Division of Responsibility
Projects & Construction
AWP
Lead PM Project Planning & Services
Design
Estimate
Project Startup Project
APM CM Schedule
Supply Chain Engineer CWA Manager Controls
EWP LWP Cost
TOP
PWP Engineer ASM ASM Startup
Buyer Expediter Designer CWP T Estimating Cost Schedule
A Engineer
Delivery WFP GF
22
Process Development:
Division of Responsibility
Projects & Construction
AWP
Lead PM Project Planning & Services
Design
Project Startup
APM CM
Engineer Manager
TOP
Startup
Engineer
Estimate
EPCM Partner Organization Contractor
Schedule
Fully Outsourced Cost CWA
EWP LWP
SUPT
Project Delivery Procurement Engineering
Project Construction
IWP
Controls Management
PWP
CWP WFP GF
WFP
Interface
23
Implementation and
Lessons Learned
24
Implementation:
Interactive Project Planning
Regular planning sessions (~bi-weekly) IPP Sessions are
working meetings,
IPP Core Team: not status updates!
PM, APM, PE, CM/ASM, SU mgr, Contractor mgt
IPP Supporting Team:
Engineers, construction leads, procurement, contractor WF Planners
Review project plan, package associations
Review upcoming packages to be completed
Set production goals to be completed before next session
25
Looking to the Future
On-boarding CM Productivity
Negotiating WFP teams and improvement
into contracts contractors into measurement
WFP against baseline
26
Lessons Learned
VP-level charge to do AWP
27
Q&A
28