Vous êtes sur la page 1sur 15

NeGP in Mizoram

Department of ICT
Govt of Mizoram
Major Projects
 State Mission Mode Projects:
 Capacity Building
 Mizoram SWAN
 Stata Data Centre (SDC)
 Common Service Centre (CSC)
 Integrated Mission Mode Projects
 State Service Delivery Gateway & State Portal
 National Portal of India
 Other Projects
 Digital Land Resource Information System
Capacity Building
 Total Project Cost - Rs. 428.60 lakhs
 Preparation of DPRs
 Six DPRs completed:
 Land Records,
 Finance/Treasuries,
 Taxation, Food & Civil Supl,
 MLA,
 Planning
 All DPRs have been submitted to the concerned departments
 It was learnt that the line ministries are not ready with
implementation plan
 DIT, GoI may coordinate with such line ministries so that
projects will be funded and executed in time
Capacity Building
 Training at the level of PeMT, Clericals, Middle
level officers had been done
 Top level official training for secretaries, MLAs
is being processed
Progress of State MMPs
 Core Infrastructure Project
 Mizoram State Wide Area Network (SWAN)
 Project Cost - Rs. 20.59 Crore
 Implementing Agency - ZENICS
 Technical Consultant- M/s Wipro Infotech.
 Projects Cost - Rs. 20.59 Crores
 Total number of POPs - 42 POPs
 Site preparation status - 26 POPs completed.
 Current Status - RFP Floated, Pre-bid
meeting completed and queries will be submitted to DIT
for approval
Progress of State MMPs
 Core Infrastructure Project
 State Data Centre (SDC)
 Project Cost - Rs. 30.88 Crore
 Implementing Agency - MSeGS
 Technical Consultant - M/s Wipro Infotech.
 Identification of Site - Identified
 Current Status - RFP being vetted by Law
Dept, GoM and DIT, GoI
Progress of State MMPs
 Core Infrastructure projects
 Common Service Delivery Centre (CSC)
 Projects cost - Rs. 2.16 Crores
 Implementing Agency - MSeGS
 Service Center Agency - Zoom Developers Ltd
 National Level Service Agency - IL & FS

 Number of CSCs approved - 136 sites

 Signing of Agreement - 29th April, 2009


 Current Status - No CSC is certified
Progress of State MMPs
 E-District
 Project cost - Rs. 315.88 Lakh
 Implementing Agency - MSeGS
 Consultant - M/s Wipro Pvt Ltd
 Pilot Project - Aizawl District
 Status
 Selection of Vendor Finalized with M/s Teledata
Informatics Ltd
 Work order is to be issued
Progress of Integrated Project
 National Portal of India
 Implementation
 M/s Zolife Infotech has been selected as Content Service
Provider (CSP)
 Contract Agreement signed on 1st Sept 2008 for a period
of 1 year, with contract price of Rs. 9.6 Lakhs
Progress of Integrated Project
 State Service Deliver Gateway (SSDG) and State
Portal (SP)
 DPR Amounting to Rs. 8.61 Cr has been submitted
to DIT for approval
Other Projects
 Digital Land Resource Information System
(DLRIS)
 Project Cost - Rs. 220.00 lakhs
 Prime Executing Agency- CDAC-Kolkata
 Implementing Agency - MSeGS
 Management Consultant – M/s Wipro Ltd
 Project Status:
 Recruitment of Project Staffs completed
 Preparation of documents – As-Is, SRS completed
 Acquisition of equipments processed
Telecommunication Problems
 Telecommunication problems being major hindrance
for IT development
 Main reasons: Power, Hilly area, Infrastructure
 Being hilly area,
 problems arises with landslide and jhumming
 Coverage of wireless network is an issue
 Cost of getting connected is more
 Penetration of IT infrastructure in rural area is minimal
 Broadband connectivity is still not available for some
districts
Telecommunication-Current status
 There are many service providers all of which
have bandwidth problems due to non availability
of reliable OFC i.e., PGCIL
 Rural connectivity is a problem due to sparse
population
 71 USOF towers are to be built but reduced to
38 due to lack of road connectivity
How can it be improved
 PGCIL may take hasten laying of overhead OFC
from Kumarghat to Aizawl
 Intra-State communication backbone needs to
be improved
 The number of USOF towers reduced to 38 due
to poor or non-availability of road connectivity
may be again increased to 71 because the
condition of roads are improving
Thank You
Department of ICT,
Govt of Mizoram