Académique Documents
Professionnel Documents
Culture Documents
PROJECT
NGHI SON 1 THERMAL POWER PLANT
CONSTRUCTION PROJECT
(CONTRACT NO. 010610/NS1-EVN-MC)
OWNER
VIETNAM ELECTRICITY
CONSULTANT
MARUBENI CORPORATION
REV. NO.
PROJECT CONTROL NO. NS1-18PAB-M-JEE-1002
1
Title:
Revised as per MC
1
Proposed Format
Lau B J SS 16 Sep 11 Document No.: NS1-JEE-MCP-MS-003 Rev.: 1
0 First Issue Lau JRaj 05 Sep 11 Scale: None Date: 16 Sep 2011
CONTENTS
1. INTRODUCTION
2. DOCUMENTS/DRAWINGS REFERENCES
3.1 Transportation
3.2 Material Receiving
3.3 Material Handling/Unloading
3.4 Material Storage/Preservation
1
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
7. CONTENTS OF APPENDIX
2
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
1. INTRODUCTION
This procedure covers the field assembly and installation for Circulating Water Pipes
(CW Pipes) of Nghi Son 1 Thermal Power Plant Project.
3
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
2. DOCUMENTS/DRAWINGS REFERENCES
4
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
3.1 Transportation
In principle, suitable transport such as trailers, low bed trailers, dollies or other types
shall be selected and used for transportation. Road survey for transportation access shall
be conducted.
5
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
6
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- Set out sufficient boundary line from centre pipe for working space
- Excavation work is carried out by excavator from start point to boundary line
- Trimming level that ant work to be carried out after excavation by using hand tools
- Excavated material/soil shall be temporary stock at suitable designated area and to be
utilized for back-filling in future.
- According to drawings and design, Case 1 > 1000M depth, shall be the excavation case
for CW pipe installation works, as shown in below diagram.
- Excavation shall be conducted by civil team, with the preparation of Back-Hoe, Dump
Truck, Survey Equipment, PPE, Plate Compactor, Hand Tools.
7
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- An area to be excavated for pipe trench and pipe support foundation by civil contractor
and reference points to be marked on site.
- The area of excavation can be separated in different designated area from Area 1 to Area
19, as shown in the attached Installation Sequence ( Area by Area ).
- The foundation or excavated area shall be checked for design elevation, centre line,
master reference point/lines, shall be confirmed before handover to CW pipes installer to
proceed for installation works.
Estimated CW pipes with Dia 2400mm, Length 7200mm, its Max Weight is 9.40 Ton.
Rigging Gears
Sling Wire: SWL 5 Ton x 4 sets
Shackle: SWL 5 Ton x 4 sets
Tag line/Tail rope: 2 sets
Chain Block ( if required ): 3 Ton/5 Ton per set
8
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
Figure 1
- Prior to pipe lower in, the trench shall be checked for sufficient depth to achieve the
centre line of pipe routing. The depth shall be provided minimum 1500mm from the
Pipe Bottom of Steel (B.O.S), at pipe joints area, in order to accommodate enough
working space for fit-up and welding.
- The pipes shall be visually examined to check if there would be some defects on the
surface, rectification or repair shall be applied accordingly.
- Touch-up of damaged area and painting or coating except joints to be welded shall be
carried out in accordance with painting schedule and coating procedure at field.
9
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- Welding joints shall be painted internally and externally coated according to Painting
Specification for CW Piping.
- After cleaning of both internal and external surface of pipes, the pipes are to be unloaded
and placed on temporary pipe support by crane.
- The elevation of pipe shall be adjusted by using chain block and sand bags and/or other
equivalent temporary support between bottom of pipes and excavated foundation.
- At excavated trench, sufficient temporary support such as Sheet Piles or others
equivalent structures shall be prepared and confirmed completion prior to handover, and
shall be in proper and safe condition for the installer to on base the pipes.
- Crane parking position to be checked and confirmed by the competent engineer and
supervisors prior lifting to commence.
- Lifting gears and appliances shall be similar as unloading the pipes during material
handling, however, such lifting gears and appliances shall be in accordance to basic
lifting plan of the pipes.
- The CW pipes shall be on base above of the temporary supports such as sand bags
( Figure 2 ). Sufficient sand bags shall be ready before CW pipes installation.
Sand Bags
Figure 2
10
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- In some locations, the CW pipes will be supported by Type-A piles and Type-B piles
( Figure 3 ) with RC Foundation, with an elastic material supplied by vendors.
Figure 3
- For External shall be prepared appropriate and sufficient scaffolding and/or walkway for
protection coating.
- For Internal shall be protected by the soft mats, that welder can walk around.
11
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
2 +3/-2
External Pipe
Internal Pipe
60 degree +5 degree
tolerance/side
Figure 4
- Normal piece shall be coated except about 150mm from the bevel end. Besides, the
adjusting piece shall also be coated and space to be accommodated for field cut and
beveling.
- Alignment shall be made using external and internal line-up clamp until enough welding
preparation can be done in accordance with the relevant welding procedure specification.
Alignment tools shall use Auto Level, for pipe elevation adjustment.
- After checking edge preparation, off-set and gap, the tack welding shall be made by the
qualified welder.
- Nozzles DN100 & Manholes DN600 locations shall be dimensionally measured to
ensure in accordance to approved drawings before aligning of pipes.
- Pipe flanges orientation shall be confirmed before pipe installation and alignment.
- Dimensional check measurement by scale tape for nozzle, flange, etc, generally shown
in Figure 5 after fit-up prior to welding commences.
12
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
Figure 5
Figure 6
13
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- All welding works shall be complied in accordance with the applicable welding
procedure.
- After welding, to inspect the welding point by NDT inspection, and ensure that welding
points quality shall within acceptable criteria.
- Pressure test will be carried out 1.5 times the design pressure and shall be hold for 10
minutes. If found leaks, the system shall be terminated by draining water and repair shall
be implemented.
Figure 7
14
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
- To ensure the successful operation of a CP system, it shall be necessary for the entire
pipe system to behave as a homogenous cathode. To be assured of this requirement, it
shall be necessary to perform a continuity survey between adjacent sections.
- Anode and other CP material shall be stored in a secure place at site. Care shall also be
taken during loading and unloading from warehouse to site.
- The locations of the Aluminum Alloy (Galvanic Anode) are indicated in the attachment
drawings. It is located at internal side of the CW pipes.
- Anode shall be installed at the standard position, as indicated in Figure 8;
Figure 8
Figure 9
15
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
Figure 10
16
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
17
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
Refer to APPENDIX - E
18
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
Refer to APPENDIX - F
19
JURONG ENGINEERING LTD.
ERECTION PROCEDURE FOR CIRCULATING WATER PIPING
INSTALLATION REV : 1
NGHI SON 1 300MW x 2 UNITS THERMAL POWER PLANT PROJECT, VIETNAM
7. CONTENTS OF APPENDIX
20
APPENDIX - A
GENERAL ARRANGEMENT DRAWINGS
APPENDIX - B
INSTALLATION SEQUENCE
APPENDIX - C
CATHODIC PROTECTION SPECIFICATION
FOR APPROVAL
1 REVISED AS PER CaRs 1088 T.Yamano Y.Ito Y. Iijima Jul.11,2011
PROJECT
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT
OWNER
VIETNAM ELECTRICITY
CONSULTANT
J-POWER / AF-COLENCO and PECC3
CONTRACTOR
MARUBENI CORPORATION
REV. NO.
PROJECT CONTROL NO. 18PUR-M-TPS-2100 1
PAGE
1. GENERAL 3
4. MATERIALS SPECIFICATION . 6 8
5. DESIGN CALCULATION .. 9 10
6. BILL OF MATERIALS . 11 12
ATTACHMENTS
2
1. GENERAL
This specification covers the basic design and materials for the cathodic protection (CP)
system to be applied to the external surfaces of CW piping for NGHI SON 1 THERMAL
POWER PLANT CONSTRUCTION PROJECT in Vietnam.
The design and materials shall comply with the following codes and standards.
Impressed Current System using high silicon cast Iron anode packaged with backfill shall
be adopted.
Electrical insulating flanges shall be installed in CW piping system to isolate a cathodically
protected piping from aboveground structures, as well as re-bars in concrete structures.
3
3. BASIC DESIGN CONDITIONS (continued)
Impressed Current Cathodic Protection System shall be designed for a minimum life of
fifteen (15) years.
Current density (CD) shall be of 0.5 mA/m2 provided that CW pipes to be protected are
isolated from other metallic structures such as casing and aboveground pipes by
insulating flange or equivalent.
The design protection current shall be 50 percent greater than design requirement to
compensate for coating deterioration and future adjustments for environmental changes.
(1) Pipe-to-soil potential shall be made at least -0.85 volts in reference to a permanent
copper-copper sulfate electrode (CSE) installed in the vicinity of underground pipe to be
protected when providing cathodic protection current.
(2) Alternatively, a minimum negative (cathodic) polarization voltage shift of at least 0.1
volts is measured before and after application of the cathodic protection current.
The soil resistivity to be applied for designing cathodic protection system, such as
calculation of the anode grounding resistance, determination of the size and required
number of sacrificial anode, shall be of 5,000 ohm-cm according to NS1-18U-C-JEL-0007,
Report on Measurement of Soil Resistivity (on shore portion), Rev.0.
4
3. BASIC DESIGN CONDITIONS (continued)
Test points shall be provided at three (3) locations in total along with the piping to be
protected.
Test points shall have a permanent reference electrode in addition to the test lead cable.
The A.C. (input) power supply of 230 volts, 1 phase, 50 hertz shall be available for all
transformer-rectifier units of cathodic protection system.
Refer to Appendix-2.
Anodes shall be installed horizontally at least 50 meters away from the CW piping to be
protected.
The depth of burial shall be basically GL.-1.2 meters from existing ground level.
Each anode lead cable shall be connected to the terminal board in the junction box.
5
4. MATERIALS SPECIFICATION
Anode shall be of tubular high silicon cast iron packaged with backfill and lead cable.
Gross weight shall be approximately 70 kg and sizing approximately 200mm, 1,500mm
long.
Each anode shall have single core 8 sq-mm XLPE/PVC cable composed of stranded and
annealed copper wire which is covered by polyethylene), direct burial cable.
The permanent reference electrode shall be of copper/copper sulfate electrode (CSE) and
approx. 70 mm diameter by 380 mm long.
Each electrode shall have a single core AWG #12 (3.5 mm2) stranded copper cable with
cross-linked polyethylene jacket (XLPE), direct burial cable.
Test station shall be made from FRP (BIG FINK), and shall be installed in non-hazardous
area.
4.4 Cables
All cables for D.C. sides shall be compacted circular stranded copper conductor, composed
of plain annealed copper wire in accordance with IEC standards.
All cables for anode, drainage terminal and main cable (positive and negative sides) for
sacrificial anode system shall be of 600 volts cross-linked polyethylene insulated and PVC
sheathed power cable (XLPE).
(1) Conductor:
A suitable separator tape may be applied over the conductor.
(2) Insulation:
The insulation shall consists of extruded layer of natural colored XLPE (cross-linked
polyethylene) complying with IEC 60502.
(3) Sheath:
The sheath shall be of an extracted layer of black PVC compound complying with
type ST2 of IEC 60502.
(1) Tolerance:
Insulation:
The thickness at any place shall not be less than the nominal value provided
that the difference does not exceed 0.1 mm +10% of the nominal value.
Sheath:
The minimum thickness shall not be less than 85% of the nominal value by
more than 0.1 mm.
6
4. MATERIALS SPECIFICATION (continued)
(1) For Lead Cable of Packed High Silicon Cast Iron Anode:
Mold shall be made of semi-permanent graphite with a high temperature type that lasts for
an average of 50 to 100 thermit weld connection under normal usage, and shall be
suitable for all pipe sizes to be protected.
Weld material shall be of a mixture of copper oxide and aluminum, packaged in ceramic
capsule.
Each capsule contains the starting powder at the top of the ceramic capsule, with the weld
metal.
A tough igloo-shaped plastic cap is used as an outer shell to provide maximum protection
from immediate backfilling.
The dome of the igloo is filled with compounds, which is 100 percent solid, to avoid any
evaporation or shrinkage which can cause air pockets for moisture to enter.
The base surrounding the igloo is placed on a 100 mm by 100 mm pad of compounds
tape, which is 3 mm thick.
The center of this pad can be removed to form an open circle around the raised section of
the igloo.
7
4. MATERIALS SPECIFICATION (continued)
4.8.1 General
The transformer-rectifier unit (hereinafter called T/R unit) shall comprise a main
transformer and a bridge connected silicon rectifier with automatic potential control
equipment.
4.8.2 Type
4.8.3 Rating
Continuous A.C. input voltage (230V, 1 phase, 50 hertz) up to +/- 10% fluctuation from
the normal rated voltage shall not damage the equipment.
4.8.4 Enclosure
The main transformer shall be double wound type with an electrically grounded screen
between primary and secondary windings, continuously rated and suitable for connection
to the nominal input power of 230 volts, 1 phase and 50 hertz.
4.8.6 Rectifier
The rectifier stacks shall be of silicon diodes, connected for full wave rectification with a
suitable surge protection network.
Diodes fuses with alarm indicator shall be provided on the secondary of the step down
transformer and mounted on the control panel.
The full rated D.C. output shall be obtainable with input voltage 10% below the specified
input voltage.
Two 100% duty rectifier units shall be provided.
The automatic potential control equipment by thyristor control shall be provided on the
front panel in the control cabinet to allow for on-load variation of output.
8
5. SUMMARY OF DESIGN CALCULATION
The following formula shall be applied for the cathodic protection design and calculation.
All calculation results will be submitted separately after completing detail design.
in which
N = I Ia .(2)
in which,
4L2 + 4L S 2 + L2 S S 2 + L2
Rh = [2.3 log + 1]
2LN dS L L (3)
in which,
9
5. SUMMARY OF DESIGN CALCULATION (continued)
D.C. output voltage of T/R is determined by the summary of voltage drops which are
calculated with circuit resistance as follows.
V = Va + Vc + Vd (4)
in which,
Rated D.C. output voltage of T/R shall be basically within the limits of 50 volts to avoid
the danger of possible harm to persons due to the voltage gradient at the surface of the
soil, in consideration of more safety operation.
In the event that the D.C. output voltage exceeds the limits of 50 volts from calculated
results, number of anode shall be increased to meet allowable D.C. output voltage.
10
6. BILL OF MATERIALS
11
6. BILL OF MATERIALS (continued)
12
THE NIPPON CORROSION
NCE APPENDIX-1
ENGINEERING CO., LTD.
TRANSFORMER-RECTIFIER (1 unit)
ANODE JUNCTION BOX (1 set) NEGATIVE JUNCTION BOX (1 set)
cable tray
G.L.
D.C.MAIN CABLE
3-ANODES (XLPE/PVC 14aq-mm) U/G C.W.PIPE
XLPE/PVC 8sq-mm
MONITORING CABLE
(XLPE/PVC8sq-mm)
TEST STATION BOX(3set) BONDING BOX (4 sets)
NEGATIVE CABLE
(XLPE/PVC 14aq-mm)
G.L G.L.
THERMIT WELDING
13
FOR APPROVAL
PROJECT
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT
(CONTRACT NO. 010610/NS1-EVN-MC)
OWNER
VIETNAM ELECTRICITY
CONSULTANT
MARUBENI CORPORATION
REV. NO.
PROJECT CONTROL NO. NS1-18PUR-M-TPS-5000
0
TITLE
QPDXVG10008 0
APPROVED: M.Morita 13/Aug/11
JOB NO.
CHECKED: M.Morita 13/Aug/11
DESIGNED: K.Nakazawa 13/Aug/11 KE1000140H01
0 13/Aug/11 First Issue M.M M.M K.N
FOR APPROVAL
PROJECT
NGHI SON 1 THERMAL POWER PLANT CONSTRUCTION PROJECT
(CONTRACT NO. 010610/NS1-EVN-MC)
OWNER
VIETNAM ELECTRICITY
CONSULTANT
MARUBENI CORPORATION
REV. NO.
PROJECT CONTROL NO. NS1-18PAB-G-TPS-9000
5
0 - First Issue - - -
1. GENERAL
1.1. This list covers the specification of painting and coating to be applied to Main Circulating Water
Piping for Nghi Son 1 Thermal Power Plant Construction Plant.
3
Outdoor carbon steel Sand blast to SSPC-SP10 Inorganic Zinc-Rich Primer NA NA NA min.
(Underground & Near White Metal Blast Cleaning [D.F.T min. 50m /coat x 1coat] 50m NA
Concrete Encasement)
Product: interzinc 12
*: A COAT OF PRIMER IS FOLLOWED BY A HOT COAT OF COAL TAR ENAMEL INTO WHICH SHALL BE BONDED A DOUBLE LAYER OF GLASS FIBER WRAP.
THE COATING SHALL BE THEN FINISHED WITH 1 COAT OF WHITE WASH.
4 / 27
Conceptual Figure for Exterior Surface Coating Layer
Coal-Tar Enamel
*1
Final Coat 0.05mm
*1
3. ATTACHMENT
P R O D U C T D A T A
Welding Inspection
Excavation Check
Earth work
3 1) Elevation check ITB 8.5.1.4 Working Plan & NOTE 1 Form No :ITP-C.1-002 H W M
(Others scope)
Base Plate
1) Elevation Check ITB 8.3.7.4 NOTE 1 Form No : ITP-C.8-010 H W R/W
2) Centre line check ITB 8.3.7.4 NOTE 1 Form No : ITP-C.8-010 H W R/W
4 Foundation Check Anchor Bolt Installation
4) Grouting Inspection ITB 8.5.8.7.5 NOTE 1 Form No : NS1/JEL/QCF/008 H W R/W
INSTALLATION CHECK
Welding Inspection
1) Fit-up inspection ITB 8.5.10.4.1 NOTE 1 & WPS Form no. NS1/JEL/QCF/004 H RW RA
- Edge Preparation
- Root Gap
- Mis alignment
ASME IX& NOTE-6-Drawing
2) WPS/PQR Review ITB 8.5.10.4.1 -PQR & WPS R R R
5 Circulating water piping
Dimension & Final inspection ITB 4.2.3.4 &
1) Dimension inspection ITB 8.5.10.3, Form no. NS1/JEL/QCF/006 W RW R
2) Visual inspection of welding ITB 8.5.10.6 Form no. NS1/JEL/QCF/005 W RW RA
Nondestructive Examination
1) Radiogaphic Testing -5% of entire weld length ITB 8.5.10.6.1 ANSI/AWWA C206 RT Report W W RA
6 Bolts & Nuts tightening Torque range ITB 8.5.8.6.3 NOTE 1 & 2 Form no. NS1/JEL/QCF/007 W W RW
Page 1 of 2
INSPECTION & TEST PLAN FOR " CIRCULATING WATER PIPING '' SITE INSTALLATION
RA-Review and Approve
CONTRACTOR : MARUBENI CORPORATION W-witness Point RW-Random witness
Documents
CONSULTANT : J-POWER/AF-COLENCO AND PECC3 H-Hold Point M-Monitor Activity S//W-Spot Witness ITP NO NS1-JEE-MCP-ITP-002
OWNER : VIETNAM ELECTRICITY LEGEND: R- Review S-Submit document N/A- Not Applicable
PROJECT : 2 x 300 MW Nghi son1 thermal power plant OWNER- VIETNAM
ELECTRICITY or Owner's
JEL-Jurong Engnieering Ltd MCP- Marubeni corporation REV.NO 1
Representative
HYDROSTATIC TEST:Note-7
1) Recording of all Pressure joints weld NDE,PWHT Charts. S W R
2) Line system check for Hydro test. H W R
3)Clearing of Punch list before hydro test which is releated to
H W R
hydro test essencial punch.
4)Test Pack Indicating Test boundary Limits in accordance ANSI/AWWA C206 &
8 Hydro static testing ITB 4.2.3.2 NOTE 7 & TEST PACK H W R
Hydrotest procedure Hydrotest Procedure
5) Ensure availability of Calibrated Pressure Gauges. S W R
6) Fill in complete system, check for leak. H W W
7) Pressure the system to hydraulic test pressure. H W W
NOTE:
1 MCP Drawings 4.General Material Control Procedure 7.General Pressure test procedure
2 Guide Line and Procedure for Piping Erection 5.General NDE Works Procedure
3 General Welding Control Procedure 6.General Welder Qualification Test Procedure
Page 2 of 2
APPENDIX - F
TENTATIVE ERECTION SCHEDULE
APPENDIX - G
CRANE CHART
APPENDIX - H
JOB SAFETY ANALYSIS
Appendix 4
CDC-9408D-213
Name of project: Nghi Son 1 TPP Project Name of Contractor: JEL Date: 30th Aug '11
Prepared By: Lau F.L Checked By: Joselito Approved By: B. Jebaraj
Describe briefly the works to be carried out: Circulating Water Pipes Field Erection
Control measures to Residual
Activities Hazards/Env Aspect L D Z minimise Risk/Env Impact L D Z
Hazard/Env Aspect
1. Mobilization -Unfamiliar with Tools, 2 4 8 All personnel info to be Rigger/Fitter should 2 3 6
and preparation using damage and unsafe properly explained and be
of Tools and tools, lifting gears and instruct the proper procedure competent/Trained
Lifting Gear and appliances. during rigging work person
appliances All lifting gears and Inspected by 2 2 4
appliancesmust be in good competent personnel
condition
Lifting device to be in good Proper maintenance 2 2 4
working condition.
Only trained/competent
persons are allowed to operate
and use of tools and lifting
equipments
Name of project: Nghi Son 1 TPP Project Name of Contractor: JEL Date: 30th Aug '11
Prepared By: Lau F.L Checked By: Joselito Approved By: B. Jebaraj
Describe briefly the works to be carried out: Circulating Water Pipes Field Erection
Control measures to Residual
Activities Hazards/Env Aspect L D Z minimise Risk/Env Impact L D Z
Hazard/Env Aspect
1. Lifting
2. Mobilization
of CW -Unfamiliar
Improper with Tools,
Rigging 32 4 8 All
12 personnel
Rigging info to be by
of Equipments Lack of supervision 2 4 8
and preparation
Pipe Spools using damage
Unfamiliar and
with unsafe
Tools and properlyand
trained explained andpersons
competent and Coordination
of Tools and tools, lifting
Equipment gears and instruct the proper procedure
Only trained fitter to operate with the site
Lifting Gear and appliances.
Falling objects during rigging
tools and work
equipments personnel's
appliances Falling from height To use safety belt/full body Collision/Hit on
Collisions/Hit a person (or) harness with adequate tie off person or other
other equipment and at proper anchor point equipments or
existing temporary To secure all loose materials temporary structures
structures To provide lifeline or secure
at proper strong anchorage
points
2/4
Appendix 4
CDC-9408D-213
Name of project: Nghi Son 1 TPP Project Name of Contractor: JEL Date: 30th Aug '11
Prepared By: Lau F.L Checked By: Joselito Approved By: B. Jebaraj
Describe briefly the works to be carried out: Circulating Water Pipes Field Erection
Control measures to Residual
Activities Hazards/Env Aspect L D Z minimise Risk/Env Impact L D Z
Hazard/Env Aspect
1. Mobilizationof
4.Completion -Unfamiliar
Falling with Tools,
objects 2 4 8 All personnel
To clear of allinfo to be
unwanted Lack of Supervision 2 3 6
and preparation
CW Pipes Lifting using damage and unsafe properly explained
materials on top of and
the lifting
of Tools and tools, lifting gears and instruct
object the proper procedure
Lifting Gear and appliances. during rigging work
appliances
Falling from height 2 4 8 To use full Body Harness with Lack of Supervision 2 3 6
proper tie off with proper
lifeline.
3/4
Appendix 4
CDC-9408D-213
Name of project: Nghi Son 1 TPP Project Name of Contractor: JEL Date: 30th Aug '11
Prepared By: Lau F.L Checked By: Joselito Approved By: B. Jebaraj
Describe briefly the works to be carried out: Circulating Water Pipes Field Erection
Control measures to Residual
Activities Hazards/Env Aspect L D Z minimise Risk/Env Impact L D Z
Hazard/Env Aspect
1. Mobilization -Unfamiliar with Tools, 2 4 8 All personnel info to be
Risk/Impact Criteria:
and preparation using damage and unsafe properly explained and
of Tools and tools, lifting gears and instruct the proper procedure
Likelyhood(L)
Lifting
05 - VeryGear and appliances.
frequent/continuous(on-going basis) during rigging work
Degree(D)
appliances
04 - Frequently(more than once a month) 05 - Catastropic(result in multiple death/impact)
03 - Occasionally(once a bi-monthly) 04 - Serious(result in major accident/impact or widespread)
02 - Remote(Once a year) 03 - Moderate(result in minor accident/impact)
01 - Never (never occurred or is highly unlikely) 02 - Minor(result in minor incident/impact)
01 - Risk/Impact not significant
4/4