Vous êtes sur la page 1sur 8

Automation in Construction 17 (2008) 915922

Contents lists available at ScienceDirect

Automation in Construction
j o u r n a l h o m e p a g e : w w w. e l s ev i e r. c o m / l o c a t e / a u t c o n

Integrating design and construction through virtual prototyping


Heng Li a,, Ting Huang a, C.W. Kong a, H.L. Guo a, Andrew Baldwin b, Neo Chan a, Johnny Wong a
a
Department of Building and Real Estate, The Hong Kong Polytechnic University, Hong Kong
b
Department of Civil and Building Engineering, Loughborough University, UK

a r t i c l e i n f o a b s t r a c t

Article history: Construction Virtual Prototyping (CVP) is the use of integrated product, process and resource models of
Accepted 26 February 2008 construction projects to support the construction planning in virtual environment. This paper describes an
integrated framework and process for efcient application of CVP to support project teams on construction
Keywords: planning. It includes specic examples of models and objectives as well as detailed suggestions on how to
Construction planning implement CVP in practice.
3D modeling
2008 Elsevier B.V. All rights reserved.
Process simulation
Virtual prototyping

1. Introduction process of the new design is also a slight modication of the existing
process. In other words, the manufacturing industry is able to capture
A comparison of productivity data between manufacturing and and re-use its knowledge in design and production. New design and
construction industries is interesting and revealing. For example, Fig. 1 production processes are obtained through incrementally improving
indicates that within last 40 years, the non-farm industries, which existing versions. The construction industry, however, does not have
primarily refer to the manufacturing industry as it has a dominant this capacity. A design process in construction typically starts from a
share of over 80%, have made approximately 10% incremental annual blank sheet of paper. Although certain components and building
improvements while the construction industry continuously declined. details may be re-used, the design process differs signicantly from
This phenomenon is observable in almost every country, and it that of the manufacturing industry where only slight improvements
may be explained by the following three differences between the two are made on existing designs. This goes through the entire construc-
industries: tion process where new contract, new teams and processes are
formed. When the project is completed, little knowledge is captured
1. the construction industry does not have an effective platform to
and retained.
capture and re-use knowledge generated in design and construc-
In addition, the manufacturing industry has a xed production line
tion stages;
where the productivity is dominated by the speed of machinery [13];
2. the construction industry does not have a xed production line;
whereas the construction industry does not have a production line
and
and project participants have to exercise personal judgments to nd
3. the construction industry does not have the ability to try before
the best way to complete their tasks.
build.
Moreover, the lack of ability to try before build turns construction
It is necessary to note that the above differences are identied to a very risky business. A construction project is by and large an
through authors' own experience and knowledge. It is expected that experimental process guided by design and planning information
these can generate further research interests and discussions with in which is particularly full of incompleteness and mistakes. As a result,
the research community. many projects are completed at the expenses of ubiquitous time and
The manufacturing industry adopts a decomposition model in cost overruns.
which an artifact is decomposed into basic components which can be The authors propose that the above three issues are the bottleneck
designed in isolation. These basic components are frequently dened that hinders the incremental improvement of the construction
as shapeable blocks and stored in element libraries in graphical industry. In order to remove the bottleneck, research team at The
modeling systems. A new design is therefore a hierarchy of com- Hong Kong Polytechnic University started a research project in 2004
ponents which are modied to t new requirements. The production to develop the virtual prototyping technology. Virtual prototyping
(VP) is a computer-aided representational process concerned with the
construction of digital product models (virtual prototypes) and
Corresponding author. realistic graphical simulations that address the broad issues of
E-mail address: bshengli@polyu.edu.hk (H. Li). physical layout, operational concept, functional specications, and

0926-5805/$ see front matter 2008 Elsevier B.V. All rights reserved.
doi:10.1016/j.autcon.2008.02.016
916 H. Li et al. / Automation in Construction 17 (2008) 915922

Fig. 1. Productivity comparison between construction and manufacturing industries.

dynamics analysis under various operating environments [13]. es standardization and prefabrication. Prefabrication indirectly in-
Dedicated VP technology has been extensively and successfully troduces a production line into the construction industry. VP can
applied to the automobile and aerospace elds [4,14,15]. However, realistically simulate construction processes and effectively capture
the development and application of VP technology in the construction design and construction knowledge which can be re-used in future
industry (i.e. construction process simulation) has been limited. This is projects. In addition, VP provides the platform for practitioners to try
probably because that each construction project is unique in terms of before build the project.
the site conditions, requirements, and constraints. Sarshar et al. [5]
identied three major industrial barriers to uptake VP technology, 2. Process modeler as a new employment classication
including cultural and risk issues related to information sharing,
fragmentation of business interests and the lack of piloting on real The Construction Virtual Prototyping Laboratory (CVPL) at The
construction projects. Hong Kong Polytechnic University has applied VP technology to se-
3D/4D models support planners by relating building components veral real construction projects in Hong Kong. VP technology enables
from a 3D CAD system to construction activities from a project plan- contractors to construct the building many times in the computer.
ning system, using a graphical interface. The construction process can All sorts of scenarios can be previewed and potential problems iden-
then be simulated by executing the process modeler built in the VP tied in advance in this simulation process. The simulation process
system and the user can visually check how the process proceeds. 4D performs such tasks as production, transportation, handling and
CAD systems can be used for construction analysis and communica- assembly of different construction components, including all the
tion [6]. Hartmann and Fischer [7] developed an integrated process of associated operational processes. All the variables affecting the con-
how project teams can use 3D/4D models efciently to support the struction processes, such as site layout, plant locations, rate of ma-
knowledge communication and generation needed during the con- chinery operation, quantities of resources, etc., can be considered in
structability review on construction projects. Although 3D/4D model order to evaluate the feasibility of the proposed construction methods
can help the planners to analyze the design, nd out the collision and and sequences, and to explore possible solutions and improvements to
discover missing or conversed sequence, the 4D process developed by the methodology prior to actual work beginning.
Hartmann and Fischer emphasized the knowledge transfer to However, the VP technology is unfamiliar to contractors. Contrac-
engineer or non-construction managers during the construction tors expected but doubted the VP application on their projects in the
planning. This application is quite useful because efcient commu- beginning. General contractors and their planners often have little
nication is the key factor of successful construction. However, iden- idea about how construction VP can help them. Some regard VP
tifying appropriate construction methods and preparing feasible technology as only animation tools that better represent their plan-
construction schedules are the most important concerns of the plan- ning ideas. Although the new technology is useful to construction
ner. The application of VP technology should thus assist the planner to planning and project management, the misunderstanding of planners
identify suitable construction methods and prepare construction can be a major impediment for the adoption of the VP technology in
schedules. the industry. In order to demonstrate the usefulness of the technology,
This paper presents a case study of applying virtual prototyping researchers of the Construction Virtual Prototyping Lab at The Hong
technology to a real life construction project. It identies the need of Kong Polytechnic University have worked very closely with contrac-
virtual prototyping technology and presents a new profession which is tors of several real life projects in Hong Kong. In fact, for each project, a
named process modeler. The role of the process modeler in the project researcher has been seconded to the site ofce to assist the planning
procurement process is discussed. Skill set for the process modeler and project monitoring process.
is dened. The paper concludes that the virtual prototyping tech- Due to the fact that neither the design team nor the construction
nology can remove the bottleneck of the construction industry. As VP team has the capacity to apply the virtual prototyping technology,
technology requires designers to modularize design into BIM (Build- researchers of the Construction Virtual Prototyping Lab act as the
ing Information Management) models which are 3D models with process modeler to connect the design and construction teams. The
information for performance evaluation of the models, this encourag- process modeler accepts the BIM model from the designer, and
H. Li et al. / Automation in Construction 17 (2008) 915922 917

decomposes it into formats required by the main contractor, sub- 3. Traditional construction planning process
contractors and consultants. At the same time, the process modeler
integrates information provided by the construction team into the BIM Construction project planning has been considered as a critical
model to create a virtual prototyping of construction processes. Infor- process in the early project phases that determines the successful
mation from the construction team typically includes temporary de- implementation and delivery of project. During this stage, project
signs, preliminary planning and costing information. Through an planners need to develop main construction strategies, to esta-
iterative process, the process modeler enables the construction team blish construction path and assembly sequences, to arrange con-
to conduct what-if analyses of different construction methods in the struction methods and resources required for the execution of
virtual prototyping environment, until a satisfactory method is obtained. work packages, and even to write daily work instructions for eld
From our experience of conducting virtual prototyping studies of crews [810]. The left part of Fig. 2 is a diagram representing the
over 10 real life construction projects, we consider that the process process of construction planning. The planning process requires the
modeler needs skills that can be categorized under three headings: transformation of information into analysis, decisions and actions.
The general process of the VP models application is showed as the
2.1. Technical skill right part of Fig. 2. Within this process, VP models support the
knowledge generation and transformation at each of the planning
This requires the process modeler to understand construction step.
processes, to have a strong hands-on knowledge of virtual prototyping In the rst step of the application process, static 3D product models
software systems, are built to help the project team analyze and communicate design
information. The design errors can be detected in 3D product models.
2.2. Human skill The preparation of 3D product models also includes the modeling of
site environment that can be used to study the site layout and review
The ability to work with other people of the construction team. The the constructability.
process modeler needs to be self-aware, understanding and sensitive The 3D models are created using the CATIA system which is
to the feeling and thoughts of others to maintain a healthy compatible with the process simulation package used in this study.
interpersonal relationship with the rest of construction team. However, if the 3D models are created using other CAD systems, such
as AutoCAD, there may need to be converted into the DASSAULT
2.3. Conceptual skill system by reloading the models in the CATIA environment.
The second step is to build static 3D resource models including
The process modeler needs to understand the schematic repre- construction equipment and temporary works. Planners will propose
sentations for process, product and resource models. These schematic some potential construction methods which may be suitable for the
models provide a theoretical underpinning for construction virtual uniqueness of project design and construction site. Using the 3D
prototyping technology. resource models with the previous product models, the optional
These three categories of skill need to be presented in different construction methods can be expressed in the virtual platform.
proportion. In a very empirical sense, the technical skill dominates and The third step is to simulate the construction process. The dynamic
should be within the range of 40%; the human skill 35% and the process simulation is a series of activities, each of which can have a
conceptual skill 25%. It is necessary to note that the skill category and dened duration, linked with construction components and resources
distributions are generalized from personal experiences of the (Fig. 3). First, the abstract construction methods can be visualized by
authors. Substantial research and investigations are needed to verify assigning the 3D product and resource models. Then the visualized
the skill category and further develop measures for the proposed new methods can be tested and veried by integrating temporal and
employment classication. spatial considerations.

Fig. 2. Underpinning the construction planning with VP.


918 H. Li et al. / Automation in Construction 17 (2008) 915922

Fig. 3. Integrated product, process and resource models of the construction project.

In the nal step of the construction planning process, the project content of VP models. In the following part, we will present a case
team needs to submit or deliver the developed construction method study of applying virtual prototyping technology to a real life
to other participants such as project client, subcontractors and eld construction project and describe the content of VP models for
crews. The visualized schedule and work instruction can help the different stages in this project. The detail approach for 3D modeling
construction planning effectively communicated and implemented. and process simulation are skipped over in this paper and can be
The CVPL researcher's experience on the several real construction found in Huang et al. [11].
projects shows that the above described integrated process effectively
supported the construction planning of project teams. However, due 4. Case study
to the pressure of planning time, the timeliness of VP models is quite
important for the efciency and effectiveness of construction project Island East project consists of the development of a 70-story ofce
management. VP models which require information cannot be built building located in a central business area of Hong Kong. The
after the information is complete. Therefore, the content of VP models structural type is core wall with eight mega columns in the typical
varied to satisfy with the different stages of construction planning. The oor. One outrigger is designed for strengthening the structural
construction planning process usually is broken down into two stages: system between the core wall and columns from the 34th oor to 40th
macro and micro planning processes [8]. Although the main process of oor. And oor area reduced from 55th oor to the roof by incline the
the planning is the same, the tasks of the planning are different. column. The research works in this project include planning the
During the preconstruction stage, the macro planning process typical oor construction, and resolve the constructability problems
involves reviewing the design for constructability improvement, during the outrigger installation (Fig. 4).
selecting major construction methods and resources, and planning In this project, the duration is of paramount important, because the
site layout. During the construction stage, the micro planning process delay could result in potential claim from the client. In order to win the
develops detail schedules to instruct the day-to-day operation. The project in the tendering stage, general contractor has committed a
above integrated process in Fig. 2 can meet the different planning pressing schedule to client. Therefore, the four-day typical oor cycle
tasks in the preconstruction and construction stages by adjusting the and the outrigger installation will be big challenges for the general
H. Li et al. / Automation in Construction 17 (2008) 915922 919

Fig. 4. The research works for Island East Project.

contactors. The VP technology is applied to support the contractor to close to the capacity of tower crane. The lifting path and hazardous areas
plan the detail schedule, generate shop drawings and instruct the are built in 3D models. In addition, vehicles for carrying outrigger
construction work. The following subsection will describe the product members might have clashes with concrete mixer trucks. The paths of
modeling process, resource modeling process, detail method simula- these vehicles are also built in the site model (Fig. 5b).
tion process, and work instruction process in the construction stage. 3D product models and site model assisted the planners to analyze
the site constraint, identify the potential problems, and plan possible
4.1. Construction components modeling construction methods. These modeling efforts also reduced the
number of review sessions to a minimum and ensured that the
To select the construction equipment and method, the project team detailed design was well coordinated and maximized prefabrication
needs to review the design drawings and breaks down the building or opportunities and eld productivity and safety.
facility into major components such as columns, beams, slabs, and walls.
The 3D component models, from which attributes such as length, 4.3. Construction equipment modeling
volume and weight can be directly measured, can assist planners to
study how these components will be built and controlled on site. Construction methods are determined by building products and
3D product model is also good at analyzing the spatial relationship the use of construction equipment. The installation and dismantle-
of the construction components. In this work, the reinforcement ment of equipment, site layout, loading limits, and space requirement
embedded in the outrigger are difcult to design and x because steel dominate the selection of construction equipment. In this project, the
members' shape are irregular and working space is strait in the climb climb form was xed at the core wall by supporting pins and beams
form. The contractor needed to make sure that the reinforcement which were inserted into the pockets reserved on the wall. The
detailing was extremely well coordinated with steel members so that precision of location of the pockets was important in order to ensure a
it could ensure on-time installation of the outrigger. The process smooth climb of the climb form. The 3D models of supporting pins and
modeler used detailed, parametric 3D models to support the design of beams were thus modeled (Fig. 5c). Once the planners adjusted the
the reinforcement embedded in the outrigger. The 3D model lifting height of climb form, possible clashes between the locations of
prototype was used for design coordination of this complicated area the pockets and reinforcement members could be identied.
as well as detail drawing production and prefabrication. Over a two
week period, the rebar detailer built the virtual 3D prototype model 4.4. Temporary works modeling
with the aid of our process modeler on the computer (Fig. 5a).
Temporary works are usually very expensive items. Failure in
4.2. Site modeling planning appropriate temporary works affects safety, quality, and
productivity adversely [12]. To build the 3D temporary works model is
In Hong Kong, the construction site is often quite conned. Site useful to the contractor because the design error and the collision with
investigation usually occurs at the beginning of the project and includes construction components can be checked. In addition, the safety
major issues such as site access and planning [8]. Planners study the provided by the temporary works can be reviewed by safety con-
location of unloading area and the entrance of vehicles. In addition, sultants before the commencement of the construction project.
hazardous areas around materials lifting need to be examined in In this case study, the wall formwork designed for the typical oor
planning. In this project, the weight of some outrigger steel members is did not t non-typical oors. Temporary formworks were used to
920 H. Li et al. / Automation in Construction 17 (2008) 915922

Fig. 5. 3D product and resource models of Island East project.

supplement the unt area. These areas were irregular due to the process including all 3D models of the design, the site environment
variable beam size and the location of original wall formworks. The 3D and the resources to be used in the project. The simulation cannot only
temporary formwork was built to cover the unt areas (Fig. 5d). The provide the same level of understanding to all project participants, but
quantity and dimensions of the temporary formworks needed were only facilitate effective communication among them. More impor-
thus generated from the model. tantly, the simulation model provides an in-expensive and safe
platform for project participants to evaluate different construction
4.5. Construction method visualization methods and identify possible risks and problems.
To develop the VP simulation model, the following information is
In a traditional planning process, planners need to construct a needed.
mental 3D model of the construction project by mentally integrating
2D drawings, CPM based schedules and other information. This is What construction equipment is used for specic component and
largely an experience based process, thus more experienced planners how does it operate?
often construct more comprehensive mental models and therefore How construction components are installed and what is the
generate better construction plans. The VP technology overcomes this installation sequence?
weakness as it provides a platform to visually simulate construction What kind of temporary works are needed and where to install them?

Fig. 6. Identied problems during the method verication process.


H. Li et al. / Automation in Construction 17 (2008) 915922 921

Fig. 7. Visualized work instruction versus the real installation.

With the above information and 3D models of the design and site 4.8. Working space visualization
environment, the construction project can be digitally represented
and its processes digitally simulated and evaluated. In detailed planning process, planners need to optimize time and
resource use based on the master program. Detailed method can be
4.6. Method verication process developed to provide work instruction to crews. The working space is
an important factor affecting the efciency of construction work.
Virtual prototyping technology can help planners to study every Planners must develop the detail method and schedule to allow safe
step of the construction activities by running through the whole working spaces. However, it is difcult for planners to image a
construction process in the simulation system. If problems are found, working space in his/her mental model. In addition, once the
planners need to propose remedial actions and then re-run the construction joint or the location of the construction equipment is
simulation process to verify if the proposed remedial actions are changed, the working space will be different. The VP technology can
workable. This trial and error process continues until the whole help planners to visualize and examine the working space.
construction process is evaluated. Thus, with the use of VP technology, As an example, Fig. 7 indicates how the VP technology is used to
most construction risks and problems can be identied and solved examine the availability of working space.
before the commencement of the project. Further information related
to the implementation of VP technology is available in Huang et al., 5. Conclusions
2006 [11].
In this project, table formworks were selected for the slab con- The development and application of the Virtual Prototyping (VP)
struction and the climb form for the core wall construction. Planners technology in the construction industry is still relatively new. This
must ensure the safe and smooth operation of the four-day oor cycle paper describes an integrated framework and process for general
by using the detailed, step-by-step, simulation of the construction contractors to apply the VP technology. The process described in this
process. During this simulation, many problems were identied and paper can assist planners to verify their plans so that construction
corrective measures were taken. Fig. 6 shows some examples of risks can eliminated before the commencement of the project.
identied problems such as collision between the table formwork and The benets of using VP can be summarized as follows:
column working platform and conict between tower crane and climb
form. After going through the whole project, the contractor has gained the creation, analysis and optimization of construction schedules
sufcient condence of the selected construction method. effective constructability analysis
elimination of construction risks through digital mockup of
4.7. Visualization of construction process as a communication tool processes
between project participants clearer understanding of project scope and better work instruction
from main contractor to subcontractors
Once the simulation is completed, it can be used for many purposes. effective communication between the client and contractors
For example, as the simulation visually presents the construction effective management of design changes and,
process, it can be easily understood by the client and contractors. better capture and re-use of knowledge
Without such a visual representation, eld crews often go through a
learning period in which mistakes are made and time and cost are The application of VP trims down the managerialism but
wasted. The visual representation of the work schedule as an effective introduces a new profession, process modeler, into the industry; the
work instruction shortens this learning period. In this case study, skill set required by the process modeler has been identied. The
pictures extracted from the VP model were given to subcontractors and process modeler may act as an independent consultant to different
eld crews as visualized work instructions. parties at different stages. At the tendering stage, the process modeler
922 H. Li et al. / Automation in Construction 17 (2008) 915922

may assist the client to translate tendering materials into easy-to- [2] W. Xiang, S.C. Fok, G. Thimm, Agent-based composable simulation for virtual
prototyping of uid power system, Computers in Industry 54 (2004) 237251
understand visual materials so that the client can conveniently assess Publisher: Elsevier.
and select the best tender. At the construction stage, the process [3] M.J. Pratt, Virtual prototypes and product models in mechanical engineering,
modeler may work with the main contractor in order to optimize Virtual PrototypingVirtual Environments and the Product Design Process,
Chapman and Hall, London, 1995, pp. 113128.
construction time and costs. [4] S.H. Choi, A.M.M. Chan, A virtual prototyping system for rapid product
In addition, the use of VP may enable the industry to remove the development, Computer-Aided Design 36 (2004) 401412 Publisher: Elsevier.
three bottleneck issues. As VP technology requires designers to [5] M. Sarshar, P. Christiansson, J. Winter, Towards virtual prototyping in the
construction industry: the case study of the DIVERCITY project, Proceedings of
modularize design into BIM (Building Information Management) the World IT Conference for Design and Construction, 1824 Feb 2004, Langkawi,
models which are 3D models with information for performance Malaysia, 2004, pp. 581588. Publisher: CIDB.
evaluation of the models, this encourages standardization and [6] B. de Vries, M.J. Harink, Generation of a construction planning from a 3D CAD
model, Automation in Construction 16 (2007) 1318 Publisher: Elsevier.
prefabrication. Prefabrication indirectly introduces a production line
[7] T. Hartmann, M. Fischer, Supporting the constructability review with 3D/4D models,
into the construction industry. VP can realistically simulate construc- Building Research & Information 35 (1) (2007) 7080 Publisher: Taylor & Francis.
tion processes and effectively capture design and construction [8] A.F. Waly, W.Y. Thabet, A virtual construction environment for preconstruction
knowledge which can be re-used in future projects. In addition, VP planning, Automation in Construction 12 (2002) 139154 Publisher: Elsevier.
[9] B. Koo, M. Fischer, Feasibility study of 4D CAD in commercial construction, Journal of
provides the platform for practitioners to try before build the project. Construction Engineering and Management 126 (4) (2000) 251260 Publisher: ASCE.
[10] A. Jaafari, K.K. Manivong, M. Chaaya, Interactive system for teaching construction
Acknowledgements management, Journal of Construction Engineering and Management 127 (2001)
6675 Publisher ASCE.
[11] T. Huang, C.W. Kong, H.L. Guo, A. Baldwin, H. Li, A virtual prototyping system for
Funding for data collection and analysis was supplied through the simulating construction processes, Automation in Construction (2006), doi:10.1016/j.
Research Grants Council of Hong Kong through allocation from the autcon.2006.09.007 Publisher: Elsevier.
[12] A. Chini, G. Genauer, Technical guidance available to designers of temporary
Competitive Earmarked Research Grant for 2005/06 under Grant structures, American Society of Civil Engineers Fifteenth Structures Congress,
Number PolyU5103/05E. The research has also been supported by Portland, Oregon, ASCE, 1997.
another Competitive Earmarked Research Grant for 2005/06 under [13] J. Atack, F. Bateman, R.A. Margo, Productivity in manufacturing and the length of
the working day: evidence from the 1880 census of manufactures, Explorations in
Grant Number PolyU 5209/05E. Economic History 40 (2) (2003) 170194 Publisher: Elsevier.
[14] S. Bing, J. Ye, A framework of virtual prototyping environment for the design and
References analysis of mechanical mechanism with clearance, Virtual and Physical Prototyp-
ing, vol. 2(1), Taylor&Francis, March 2007, pp. 2128.
[1] Q. Shen, J. Gausemeier, J. Bauch, C. Radkowski, A cooperative virtual prototyping [15] G.G. Wang, Denition and review of virtual prototyping, Journal of Computing and
system for mechatronic solution elements based assembly, Advanced Engineering Information Science in Engineering 2 (3) (September 2002) 232236 Publisher: KIISE.
Informatics 19 (2005) 169177 Publisher: Elsevier.

Vous aimerez peut-être aussi