Vous êtes sur la page 1sur 6

STATE OF KUWAIT TENDER NO.

KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 1 of 6

METHOD STATEMENT FOR INSTALLATION


OF FEEDER PILLARS

0 Issued for Review & Comments


Eng. A.H
Prepared by Checked by Approved by
Rev. Date Description
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 2 of 6

REVISION CONTROL SHEET

REV. NO. DATE PAGE NO. DESCRIPTION


STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 3 of 6

TABLE OF CONTENTS

1 Purpose.. 4
2 Scope of Work.. 4
3 Responsible Personnel on Site.. 4
4 Storage.. 4
5 Pre-Installation 4
6 Installation 5
7 Reference Documents. 5
8 Safety 6
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 4 of 6

1. Purpose

This method of statement covers the in-site installations of Feeder Pillars as defined in
the General Specification.

2. Scope of Work

This procedure will define the method to be used to ensure that the Feeder Pillars
installations, on-site assembly, final connection and workmanship are acceptable,
correct, safe and conforms the Contract Documents and Specification.

3. Responsible Personnel on Site

3.1. Construction Manager


3.2. Electrical Field Engineers
3.3. Safety Officer
3.4. QA/QC Engineer
3.5. Electrical Supervisors

4. Storage

4.1 Unload the Feeder Pillars to the designated unloading area. Use fork lift or mobile crane
to unload self standing panels.

4.2 Ensure that the Feeder Pillars are stored in dry and clean locations.

4.3 Make sure that the storage area is safe.

5. Pre-Installation

5.1 All materials and documentation relevant to this particular section of works shall be
checked prior to installation.

5.2 Ensure that the location wherein the Feeder Pillars were installed are accessible, clean
and free of debris and foreign materials and suitable for installations.
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 5 of 6

6. Installation

6.1 Check the cable trenches and supports are painted and ready for permanent installation
of the said equipment.

6.2 Move the Feeder Pillars from the storage area to their designated Locations. Fully
crated panels shipped on a timber sub-base shall be lifted under the sub-base.

6.3 When moving the fully crated Feeder Pillars from the storage area to their Locations of
installation using fork lifts, the mast must be as close as possible to the face of the crate
and forks must be fully projected under the crate. Lift the fully crated Feeder Pillars
squarely.

6.4 Uncrate, unpack and remove the Feeder Pillars from its timber base. Care must be
taken to protect the Feeder Pillars from unnecessary scratches or bents on the panels.

6.5 Move in the Feeder Pillars using steel pipe rollers to its final location. Care must be
taken to ensure that the Feeder Pillars does not over balanced while being moved to
its final locations.

6.6 Align the Feeder Pillars horizontally and vertically.

6.7 Secure the Feeder Pillars assembly and ensure that it is fixed properly on its base.

6.8 Remove all unused bolts, nuts, washers and clean the Feeder Pillars. Feeder Pillars
side covers and doors shall be put back. Ensuring that it is properly tightened.

6.9 Conduct insulation resistance test on the Feeder Pillars to ensure that all joints are
properly insulated.

6.11 Raise Request for Inspection for switchgear installation.

6.12 After all the testing has been successfully sign-off and accepted by the Consultant,
cable dressing and termination will commence.

7. Reference Documents

7.1 Approved Electrical Shop Drawings


7.2 Approved Material Submittals for Feeder Pillars
7.3 Approved QA/QC Installation and Test Plan
7.4 Factory Test Certificates of the said equipments
7.5 Operation and Maintenance Manuals for Feeder Pillars
7.6 Approved Material Inspection Report
7.7 Approved Safety Plan
STATE OF KUWAIT TENDER NO.
KUWAIT UNIVERSITY KU/KUCP/C0251/10-11

ELECTRICAL
METHOD STATEMENT Page 6 of 6

8. Safety

8.1 All safety precautions shall be followed as per approved safety plan & procedure.
Ensure all involved persons are aware of the same.

8.2 Ensure that tradesman will keep their working places clean, tidy and free from
rubbish.

------------------------ Procedure End----------------------

Vous aimerez peut-être aussi