Académique Documents
Professionnel Documents
Culture Documents
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
Page 1 of 23
8th November, 2016
Report No. SS-144/2016
INDEX
List of Annexure
Annex
1 CSTE/NCRs letter dt. 27.05.2016 16 - 17
2 CSE/NCRs letter dt. 26.06.2016 18
3 Letter to CEL dt 14.07.2016 19
4 Letter to GG Tronics dt 14.07.2016 20
5 Copy of safety case [ M/s CEL] 21 - 35
Page 2 of 23
8th November, 2016
Report No. SS-144/2016
1.1.1 VPR of Track Section controlling berthing portion of Signal didnt drop
after the passage of train 13008 on 24.06.2016. As a result, Signal was
showing GREEN with the train on berthing track portion of Automatic
Signal A76A @ RH 38 in Palwal - Rundhi section of Agra Division, North
Central Railway.
1.1.2 As per NCR report the wheel sensor (receiver portion) of M/s GG
Tronics SSDAC, was lying broken after being crushed by some boulder
on the train movement. It is reported that some miscreant has put
boulder on receiver coil and in between rail head creating such a
situation causing crushing of track device and creating such scenario.
Page 3 of 23
8th November, 2016
Report No. SS-144/2016
Note: Although this observed scenario is already discussed in the safety case of M/s
CEL and other OEMs hazards log under the category of SABOTAGE while
designing the system. However, being a safety related issue and its criticality; it
has been taken-up as a special case, for detailed analysis/investigation.
Page 4 of 23
8th November, 2016
Report No. SS-144/2016
2.2.1 Scenario 1:
Loosen the Track Device and tilt one side
2.2.2 Scenario 2 :
Put the Track Device on rail foot.
2.2.3 Scenario 3:
Put the Track Device below the rail foot.
Page 5 of 23
8th November, 2016
Report No. SS-144/2016
2.2.4 Scenario 4:
Take the Track Device receiver carefully 6 to 10 inches away.
2.2.5 Scenario-:
Take the track device receiver carefully and put the Track Device
inverted away from rail.
Page 6 of 23
8th November, 2016
Report No. SS-144/2016
3.1.1 Condition -1 :
Sensor receiver taken beneath the foot of the rail or around 4 to 6
inches away from the Rail very carefully.
Result:
System does not go into error.
VR remains pick up (CLEAR) condition
No counting even when simulation of train movement
(through dummy wheel) takes place.
3.1.2 Condition-2 :
Wheel sensor (RX) is removed from the rail in CLEAR state and taken
away about 6 inches and kept inverted position with great caution. VR
remains in picked up condition. (This was possibly the scenario which
happened in NCR case)
Result:
When movement with Dummy wheel on the rail was done the
VR remains in picked up condition ().
Page 7 of 23
8th November, 2016
Report No. SS-144/2016
Observations [Result]:
System does not go into error.
VR remains in picked up (CLEAR) condition
No counting takes place even with simulation of train movement with
Dummy wheel.
3.3.1 If both the RX sensors are taken away together very carefully beneath
the foot of the rail or around 4 to 6 inches away
Page 8 of 23
8th November, 2016
Report No. SS-144/2016
3.4.1 In M/s Medha make SSDAC no such scenario was possible and if any such
scenarios are created by any means, system goes into Error mode within 2
seconds.
3.5.1 Sensor is removed from rail & Kept on foot of the rail.
System normally goes to error.
However if it is done very carefully, then system remains in clear condition
i.e VR remains in picked up condition.
If movement is done with dummy wheel counting does not take place.
Page 9 of 23
8th November, 2016
Report No. SS-144/2016
If sensor is removed from rail claw & kept on the foot of the rail, immediately VR
drops.
4.0 From the above tests/simulations carried out in the RDSO/Lab considering
the wheel sensors are removed from the Rail and kept at ground carefully
in CLEAR condition, it is observed that the reported situation is prevailing
in the systems of two OEMs i.e. M/s CEL and M/s GGTronics.
Accordingly for further understanding , the safety documents of OEMs were also
scrutinized in addition to tests/simulations done in Signal lab.
Page 10 of 23
8th November, 2016
Report No. SS-144/2016
6.0 Summary
All the tests have been conducted by creating carefully the similar (to the
extent) situation (As reported in NCR) in RDSO/Signal lab.
However from the tests, it is observed that similar situation could be created
in M/s GGT and CELs make SSDAC.
In case of Thales and Siemens it was possible with lot of care. In Thales the
sensors are in 2 pieces which reduces the possibility of occurrence of such
incidence hence no change is required. In Siemens practically it was very
difficult to simulate in the field due to mechanical mounting arrangements
with track sensors, hence no change is required.
7.0 Although the possibility of this kind of incidence is highly remote in practical
conditions however having known based on the scenarios created in RDSO Signal lab ,
M/s GGTronics , Bangalore & M/s CEL, Sahibabad were advised vide letter dt
14.07.2016 to submit their comments along with their action plan to mitigate the
scenario- reported by NC Railway.
Page 11 of 23
8th November, 2016
Report No. SS-144/2016
8.0 Suggestions
8.1 Mitigation Plan 1
Provisions of stainless strip clamp as proposed by GGT
This is a temporary arrangement to mitigate the issue.
Using Spring Clamp :
Spring type clamp can be fixed to hold the Tx and Rx Wheel sensors. Hence,
falling of Rx wheel sensor can be avoided in damage condition. Spring clamp
will be fixed to the center bolt for higher tension.
Disadvantage
1. It is a difficult to fix at site because first balast needs to be removed and
then it may be clamped from bottom of the rail.
2. It attracts pilferage.
3. Maintenance of axle detector becomes cumbersome and requires
additional time.
Availability / Presence of the wheel sensor will be proven by the Limit switch
which makes the contact between Rail and wheel sensor.
Disadvantage:
1. It will require trials to ensure the functionality/workability of Switch.
Page 12 of 23
8th November, 2016
Report No. SS-144/2016
A photograph of newly developed Rx Coil using metal plate (M/s GG Tronicss axle
detector)
However, M/s CEL Rx is already having this arrangement. RX coil chipped to see
aluminum.
Disadvantage:
Primarily there is no disadvantage due to this arrangement however this needs to be
tried in field after a proto type is developed by GG Tronics.
Disadvantage:
2. This change will require climatic testing as well as extensive trials before
permitting for global use.
M/s CEL make Axle counter M/s GGT make Axle counter
Page 13 of 23
8th November, 2016
Report No. SS-144/2016
Disadvantage:
2. This change will require field trials before permitting for global use.
2. Once prototype is developed it will be tested in lab and will be put on field trial.
3. In addition to above the new system will be revalidated for hardware/softaware fail safety
by Independent agency before approving for regular use.
Page 14 of 23
8th November, 2016
Report No. SS-144/2016
After the reporting of incidence, several round of testings were done in the signal
lab and at site to simulate and observe the condition.
Based on the observations during the various testings and suggestion given by
RDSO M/s GGTronics demonstrated their modified software S003 and axle
detector 21/22.09.16.
In the new software and axle detector following main changes have been
incorporated:
(i) softawre upgaradtion S003 was already under process to improve the
reliability, same is further modified to mitigate this condiotion.
M/s CEL has designed a circuit for additionally taking care of the situation wher
the axle detectors / sensors are deliberately and carefully removed away from
the rail. This circuit is demostrated at RDSO lab and needs to be validated and
trialed out at field.
--------------------x---x--------------------
Page 15 of 23
8th November, 2016
Report No. SS-144/2016
Annexure-1
Page 16 of 23
8th November, 2016
Report No. SS-144/2016
Page 17 of 23
8th November, 2016
Report No. SS-144/2016
Annexure-2
Page 18 of 23
8th November, 2016
Report No. SS-144/2016
Annexure - 3
Page 19 of 23
8th November, 2016
Report No. SS-144/2016
Annexure - 4
Page 20 of 23
8th November, 2016
Report No. SS-144/2016
Annexure-5
Page 21 of 23
8th November, 2016
Report No. SS-144/2016
Page 22 of 23
8th November, 2016
Report No. SS-144/2016
Page 23 of 23