Académique Documents
Professionnel Documents
Culture Documents
CONCRETE WORKS
ESTIMATES
By
June Marie R. Javier
USING CLASS A
FOOTING 1 FOOTING 2
AREA AREA
1.4 1.4 = 1.96 m2 2.3 2.3 = 5.29 m2
VOLUME VOLUME
1.96 0.3 = 0.588 m3 5.290 0.3 = 1.587 m3
TOTAL VOLUME TOTAL VOLUME
0.588 11 = 6.468 m3 1.587 11 = 17.457 m3
CEMENT CEMENT
6.468 9 = 58.212 bags 17.457 9 = 157.113 bags
GRAVEL GRAVEL
6.468 1 = 6.468 m3 17.457 1 = 17.457 m3
SAND SAND
6.468 0.5 = 3.234 m3 17.457 0.5 = 8.7285 m3
By estimate using class A will give me By estimate using class A will give me
58.212 bags of cement, 6.468 m3 of gravel 157.113 bags of cement17.457 m3 of gravel
3.234 m3 of sand. 8.7285 m3 of sand.
Concluding it will cost me 58.5 bags of Concluding it will cost me 157.5 bags of
cement, 6.5 m3 of gravel, 3.5 m3 of sand. cement, 17.5 m3 of gravel, 9 m3 of sand.
COMPUTATIONS
USING CLASS A
FOOTING 3
AREA
2.1 2.1 = 4.41 m2
VOLUME
4.41 0.3 = 1.323 m3
TOTAL VOLUME
1.323 11 = 14.553 m3
CEMENT
14.553 9 = 130.98 bags
GRAVEL
14.553 1 = 14.553 m3
SAND
14.553 0.5 = 7.2765 m3
USING CLASS A
COLUMN 1 COLUMN 2
AREA AREA
0.35 0.35 = 0.1225 m2 0.35 0.35 = 0.1225 m2
VOLUME VOLUME
0.1225 7.925 = 0.9708125 m3 0.1225 7.925 = 0.9708125 m3
TOTAL VOLUME TOTAL VOLUME
0.9708125 11 = 10.6789375 m3 0.9708125 11 = 10.6789375 m3
CEMENT CEMENT
10.6789375 9 = 96.11 bags 10.6789375 9 = 96.11 bags
GRAVEL GRAVEL
10.6789375 1 = 10.68 m3 10.6789375 1 = 10.68 m3
SAND SAND
10.6789375 0.5 = 5.34 m3 10.6789375 0.5 = 5.34 m3
By estimate using class A will give me By estimate using class A will give me
96.11 bags of cement 10.68 m3 of gravel 96.11 bags of cement 10.68 m3 of gravel
5.34 m3 of sand. 5.34 m3 of sand.
Concluding it will cost me 96.5 bags of Concluding it will cost me 96.5 bags of
cement, 11 m3 of gravel, 5.5 m3 of sand. cement, 11 m3 of gravel, 5.5 m3 of sand.
COMPUTATIONS
USING CLASS A
COLUMN 3
AREA CEMENT
0.35 0.35 = 0.1225 m2 10.6789375 9 = 96.11 bags
VOLUME GRAVEL
0.1225 7.925 = 0.9708125 m3 10.6789375 1 = 10.68 m3
TOTAL VOLUME SAND
0.9708125 11 = 10.6789375 m3 10.6789375 0.5 = 5.34 m3
By estimate using class A will give me 96.11 bags of cement 10.68 m3 of gravel 5.34 m3 of
sand.
Concluding it will cost me 96.5 bags of cement, 11 m3 of gravel, 5.5 m3 of sand.
BEAMS, GIRDERS
COMPUTATIONS
USING CLASS A
GIRDER 1 GIRDER 2
AREA AREA
0.2 0.4 = 0.08 m2 0.2 0.4 = 0.0.08 m2
VOLUME VOLUME
0.08 4.15 = 0.332 m3 0.08 4.15 = 0.332 m3
TOTAL VOLUME TOTAL VOLUME
0.332 10 = 3.32 m3 0.332 10 = 3.32 m3
CEMENT CEMENT
3.32 9 = 29.88 bags 3.32 9 = 29.88 bags
GRAVEL GRAVEL
3.32 1 = 3.32 m3 3.32 1 = 3.32 m3
SAND SAND
3.32 0.5 = 1.66 m3 3.32 0.5 = 1.66 m3
By estimate using class A will give me By estimate using class A will give me
29.88 bags of cement, 3.32 m3 of gravel 29.88 bags of cement, 3.32 m3 of gravel
1.66 m3 of sand. 1.66 m3 of sand.
Concluding it will cost me 30 bags of Concluding it will cost me 30 bags of
cement, 3.5 m3 of gravel, 2 m3 of sand. cement, 3.5 m3 of gravel, 2 m3 of sand.
COMPUTATIONS
USING CLASS A
GIRDER 3 GIRDER 3A
AREA AREA
0.2 0.4 = 0.0.08 m2 0.2 0.8 = 0.16 m2
VOLUME VOLUME
0.08 4.15 = 0.332 m3 0.08 4.15 = 0.664 m3
TOTAL VOLUME TOTAL VOLUME
0.332 8 = 2.656 m3 0.664 2 = 1.328 m3
CEMENT CEMENT
2.656 9 = 23.904 bags 1.328 9 = 11.952 bags
GRAVEL GRAVEL
2.656 1 = 2.656 m3 1.328 1 = 1.328 m3
SAND SAND
2.656 0.5 = 1.328 m3 1.328 0.5 = 0.664 m3
By estimate using class A will give me By estimate using class A will give me
23.904 bags of cement, 2.656 m3 of gravel 11.952 bags of cement, 1.328 m3 of gravel
1.328 m3 of sand. 0.664 m3 of sand.
Concluding it will cost me 24 bags of Concluding it will cost me 12 bags of
cement, 3 m3 of gravel, 1.5 m3 of sand. cement, 1.5 m3 of gravel, 1 m3 of sand.
COMPUTATIONS
USING CLASS A
GIRDER 4 GIRDER 5
AREA AREA
0.2 0.4 = 0.0.08 m2 0.25 0.5 = 0.125 m2
VOLUME VOLUME
0.08 2.15 = 0.172 m3 0.125 6.65 = 0.83125 m3
TOTAL VOLUME TOTAL VOLUME
0.172 2 = 0.344 m3 0.83125 2 = 1.665 m3
CEMENT CEMENT
0.344 9 = 3.096 bags 1.665 9 = 14.96 bags
GRAVEL GRAVEL
0.344 1 = 0.344 m3 1.665 1 = 1.665 m3
SAND SAND
0.344 0.5 = 0.172 m3 1.665 0.5 = 0.83125m3
By estimate using class A will give me By estimate using class A will give me
3.096 bags of cement, 0.344 m3 of gravel 14.96 bags of cement, 1.665 m3 of gravel
0.172 m3 of sand. 0.83125 m3 of sand.
Concluding it will cost me 3.25 bags of Concluding it will cost me 15 bags of
cement, 0.5 m3 of gravel, 0.25 m3 of sand. cement, 1.75 m3 of gravel, 1 m3 of sand.
COMPUTATIONS
USING CLASS A
GIRDER 6 GIRDER 7
AREA AREA
0.2 0.4 = 0.08 m2 0.25 0.5 = 0.125 m2
VOLUME VOLUME
0.08 2.15 = 0.172 m3 0.125 6.65 = 0.83125 m3
TOTAL VOLUME TOTAL VOLUME
0.172 9 = 1.548 m3 0.83125 9 = 7.48125 m3
CEMENT CEMENT
1.548 9 = 13.992 bags 7.48125 9 = 67.33 bags
GRAVEL GRAVEL
1.548 1 = 1.548 m3 7.48125 1 = 7.48 m3
SAND SAND
1.548 0.5 = 0.774 m3 7.48125 0.5 = 3.74 m3
By estimate using class A will give me By estimate using class A will give me
13.992 bags of cement, 1.548 m3 of gravel 67.33 bags of cement, 7.48 m3 of gravel
0.774 m3 of sand. 3.74 m3 of sand.
Concluding it will cost me 14 bags of Concluding it will cost me 67.5 bags of
cement, 1.75 m3 of gravel, 1 m3 of sand. cement, 7.75 m3 of gravel, 4 m3 of sand.
COMPUTATIONS
USING CLASS A
BEAM 1 BEAM 2
AREA AREA
VOLUME VOLUME
CEMENT CEMENT
GRAVEL GRAVEL
SAND SAND
By estimate using class A will give me By estimate using class A will give me 6.48
23.904 bags of cement, 2.656 m3 of gravel bags of cement, 0.72 m3 of gravel 0.36 m3
1.328 m3 of sand. of sand.
USING CLASS A
AREA AREA
0.2 0.4 = 0.08 m2 0.2 0.4 = 0.08 m2
VOLUME VOLUME
0.08 2.5 = 0.2 m3 0.08 4.15 = 0.332 m3
TOTAL VOLUME TOTAL VOLUME
0.2 2 = 0.4 m3 0.332 2 = 0.664 m3
CEMENT CEMENT
0.4 9 = 3.6 bags 0.664 9 = 5.976 bags
GRAVEL GRAVEL
0.4 1 = 0.4 m3 0.664 1 = 0.664 m3
SAND SAND
0.4 0.5 = 0.2 m3 0.664 0.5 = 0.332 m3
By estimate using class A will give me By estimate using class A will give me 5.98
23.904 bags of cement, 2.656 m3 of gravel bags of cement, 0.664 m3 of gravel 0.332
1.328 m3 of sand. m3 of sand.
Concluding it will cost me 24 bags of Concluding it will cost me 6 bags of cement,
cement, 2.75 m3 of gravel, 1.5 m3 of sand. 0.75 m3 of gravel, 0.5 m3 of sand.
COMPUTATIONS
USING CLASS A
AREA AREA
0.2 0.5 = 0.10 m2 0.3 0.5 = 0.15 m2
VOLUME VOLUME
0.10 4.15 = 0.415 m3 0.15 2.15 = 0.3225 m3
TOTAL VOLUME TOTAL VOLUME
0.415 2 = 0.83 m3 0.3225 7 = 2.2575 m3
CEMENT CEMENT
0.83 9 = 7.47 bags 2.2575 9 = 20.3175 bags
GRAVEL GRAVEL
0.83 1 = 0.83 m3 2.2575 1 = 2.2575 m3
SAND SAND
0.83 0.5 = 0.42 m3 2.2575 0.5 = 1.12875 m3
By estimate using class A will give me 7.47 By estimate using class A will give me
bags of cement, 0.83 m3 of gravel 0.42 m3 20.32 bags of cement, 2.26 m3 of gravel
of sand. 1.13 m3 of sand.
Concluding it will cost me 7.50 bags of Concluding it will cost me 20.5 bags of
cement, 1 m3 of gravel, 0.5 m3 of sand. cement, 2.5 m3 of gravel, 1.5 m3 of sand.
COMPUTATIONS
USING CLASS A
AREA AREA
0.3 0.5 = 0.15 m2 0.3 0.5 = 0.15 m2
VOLUME VOLUME
0.15 6.65 = 0.9975 m3 0.15 4.15 = 0.6225 m3
TOTAL VOLUME TOTAL VOLUME
0.9975 7 = 6.9825 m3 0.6225 30 = 18.675 m3
CEMENT CEMENT
6.9825 9 = 62.8425 bags 18.675 9 = 168.075 bags
GRAVEL GRAVEL
6.9825 1 = 6.9825 m3 18.675 1 = 18.675 m3
SAND SAND
6.9825 0.5 = 3.49125 m3 18.675 0.5 = 9.3375 m3
By estimate using class A will give me By estimate using class A will give me
62.8425 bags of cement, 6.9825 m3 of 168.075 bags of cement, 18.675 m3 of
gravel 3.49125 m3 of sand. gravel 9.3375 m3 of sand.
Concluding it will cost me 63 bags of Concluding it will cost me 168.25 bags of
cement, 7 m3 of gravel, 3.5 m3 of sand. cement, 19 m3 of gravel, 9.5 m3 of sand.
COMPUTATIONS
USING CLASS A
AREA AREA
0.2 0.4 = 0.08 m2 00.2 0.4 = 0.08 m2
VOLUME VOLUME
0.08 4.15 = 0.332 m3 0.08 2.15 = 0.172 m3
TOTAL VOLUME TOTAL VOLUME
0.332 30 = 9.96 m3 0.172 11 = 1.892 m3
CEMENT CEMENT
9.96 9 = 89.64 bags 1.892 9 = 17.028 bags
GRAVEL GRAVEL
9.96 1 = 9.96 m3 1.892 1 = 1.892 m3
SAND SAND
9.96 0.5 = 4.98 m3 1.892 0.5 = 0.946 m3
By estimate using class A will give me By estimate using class A will give me
89.64 bags of cement, 9.96 m3 of gravel 17.028 bags of cement, 1.892 m3 of gravel
4.98 m3 of sand. 0.946 m3 of sand.
Concluding it will cost me 90 bags of Concluding it will cost me 17.25 bags of
cement, 10 m3 of gravel, 5 m3 of sand. cement, 2 m3 of gravel, 1 m3 of sand.
.
COMPUTATIONS
USING CLASS A
ROOM GIRDER 2
AREA
0.25 0.5 = 0.125 m2
VOLUME
0.125 6.65 = 0.83125 m3
TOTAL VOLUME
0.83125 11 = 9.14375 m3
CEMENT
9.14375 9 = 82.29 bags
GRAVEL
9.14375 1 = 9.14 m3
SAND
9.14375 0.5 = 4.57 m3
By estimate using class A will give me 82.29 bags of cement, 9.14 m3 of gravel 4.57m3 of sand.
Concluding it will cost me 82.5 bags of cement, 9.25 m3 of gravel, 4.75 m3 of sand.
SLABS
COMPUTATIONS
USING CLASS A
SLAB 1 SLAB 2
AREA AREA
4.5 4.5 = 20.25 m2 2.5 4.5 = 11.25 m2
VOLUME VOLUME
20.25 0.1 = 2.025 m3 11.25 0.1 = 1.125 m3
TOTAL VOLUME TOTAL VOLUME
2.025 16 = 32.4 m3 1.125 12 = 13.5 m3
CEMENT CEMENT
32.4 9 = 291.6 bags 13.5 9 = 121.5 bags
GRAVEL GRAVEL
32.4 1 = 32.4 m3 13.5 1 = 13.5 m3
SAND SAND
32.4 0.5 = 16.2 m3 13.5 0.5 = 6.75 m3
By estimate using class A will give me By estimate using class A will give me
291.6 bags of cement, 32.4 m3 of gravel 121.5 bags of cement, 13.5 m3 of gravel
16.2 m3 of sand. 6.75 m3 of sand.
Concluding it will cost me 292 bags of Concluding it will cost me 121.5 bags of
cement, 32.5 m3 of gravel, 16.5 m3 of sand. cement, 13.5 m3 of gravel, 6.75 m3 of sand.
.
SUMMARY
COLUMN FOOTING
FOOTING 1 6.468 58.212 3.234 6.468
FOOTING 2 17.457 157.113 8.7285 17.457
FOOTING 3 14.553 130.977 7.2765 14.553
9 0
COLUMNS 9 0
COLUMN 1 10.6789375 96.1104375 5.33946875 10.6789375
COLUMN 2 10.6789375 96.1104375 5.33946875 10.6789375
COLUMN 3 10.6789375 96.1104375 5.33946875 10.6789375
9
GIRDERS 9
GIRDER 1 3.32 29.88 1.66 3.32
GIRDER 2 3.32 29.88 1.66 3.32
GIRDER 3 2.656 23.904 1.328 2.656
GIRDER 3A 1.328 11.952 0.664 1.328
GIRDER 4 0.344 3.096 0.172 0.344
GIRDER 5 1.665 14.985 0.8325 1.665
GIRDER 6 1.548 13.932 0.774 1.548
GIRDER 7 7.48125 67.33125 3.740625 7.48125
ROOF GIRDER 1 9.96 89.64 4.98 9.96
ROOF GIRDER 1a 1.892 17.028 0.946 1.892
ROOF GIRDER 2 9.14375 82.29375 4.571875 9.14375
9 0
BEAMS 9 0
BEAM 1 2.656 23.904 1.328 2.656
BEAM 2 0.72 6.48 0.36 0.72
CANTILEVER BEAM 0.4 3.6 0.2 0.4
STAIRWELL BEAM 1 0.664 5.976 0.332 0.664
STAIRWELL BEAM 2 0.83 7.47 0.415 0.83
TIE BEAM 1 2.2575 20.3175 1.12875 2.2575
TIE BEAM 2 6.9825 62.8425 3.49125 6.9825
TIE BEAM 3 18.675 168.075 9.3375 18.675
9 0
SLABS 9 0
SLAB 1 32.4 291.6 16.2 32.4
SLAB 2 13.5 121.5 6.75 13.5