Vous êtes sur la page 1sur 4

COMMENTARY

220 MW PHWRS and they account for


Old Plans, Handouts, New Spin about 3,080 MW of the total installed
nuclear capacity of 6,780 MW, which in
Deciphering the Nuclear Construction turn constitutes 2.1% of the total electric-
Announcement ity generation capacity in the country.
Apart from a few other smaller and older
plants, the rest of this total capacity is
largely provided by the two 540 MW
M V Ramana, Suvrat Raju PHWRs operating in Tarapur, and the
two imported 1,000 MW light water

O
In May 2017, the union cabinet n 17 May 2017, the union cabinet reactors (LWRs) at Kudankulam.
approved the construction of 10 gave its approval for the construc- The DAE has been planning to build a
tion of 10 more 700 megawatt fleet of 700 MW PHWRs for a long time,
more 700 megawatt pressurised
(MW) pressurised heavy water reactors and so the governments decision is nei-
heavy water reactors. A careful (PHWRs) (IANS 2017). These PHWRs will ther bold nor new, and simply consti-
reading of this largely public be in addition to four such reactors tutes one more step in this direction. In
relations spin on existing plans already under construction. The cabinet 2007, the DAE announced that as part of
secretariats official press release read the Eleventh Five Year Plan (200712),
suggests that it chiefly hopes to
like a sales pitch, and claimed that the work on 8 700 MWe of indigenous
persuade the Nuclear Suppliers construction of these 10 reactors would reactors totalling 5,600 MWe capacity
Group to accept India as a help transform Indian nuclear industry would commence (NI 2007). Of these, four
member and attract capital that and that it would be a major step towards reactors are already under construction
strengthening Indias credentials as a two each at Kakrapar (Gujarat) and
aims to profit from supplying
major nuclear manufacturing power- Rawatbhata (Rajasthan). Construction
components for nuclear power house (Press Information Bureau 2017). of Kakrapar-3 and Kakrapar-4 began in
plants. Given our track record, the The Nuclear Power Corporation of India November 2010 and March 2011 respec-
prospects of it adding to the role Limited (NPCIL) and the Department of tively (NPCIL 2017a), whereas Rajasthan-7
Atomic Energy (DAE) put out their own and Rajasthan-8 began in July and Sep-
of nuclear power in India
press releases, profusely hailing the tember 2011 respectively (NPCIL 2017b).
appear bleak. decision (NPCIL 2017c; DAE 2017). In December 2012, the government stated
The reality underlying these announce- in the Rajya Sabha that work on eight
ments is far less spectacular. Plans for more 700 MW reactors would commence
building many PHWRS have been enunci- during the Twelfth Five Year Plan (2012
ated in the past, and have not material- 17) at Kaiga, Chutka, Gorakhpur, and
ised. A more careful reading of the Mahi Banswara (Narayanasamy 2012).
announcement suggests that it is tar- However, none of these projects began
geted at persuading the Nuclear Suppliers during the Twelfth Plan.
Group (NSG) to accept India as a member Although not mentioned in the official
and winning over sections of capital that press releases, media reports suggest
hope to profit from supplying compo- that these are the very sites targeted for
nents for nuclear power plants. This pub- the current approval. This history sug-
licity blitz notwithstanding, nuclear gests that the recent announcement is
power will continue to be an expensive largely a public relations spin on exist-
and relatively minor source of electricity ing plans that had already been set
This article was earlier published in the
Web Exclusives section of EPW website. for the foreseeable future. in motion by the United Progressive
Alliance (UPA) government.
The views expressed are personal. Planning History
M V Ramana (m.v.ramana@ubc.ca) and The chosen designs for the 10 reactors, The Export Story
Suvrat Raju (suvrat.raju@gmail.com) are
the 700 MW PHWR, is one that the Indian The governments announcement also
physicists associated with the Coalition for
Nuclear Disarmament and Peace, and nuclear establishment has evolved over recycles other old tropes. For example, it
currently based in Princeton and Bengaluru, the decades, starting with the original plays up the role of this effort in
respectively. Ramana is the author of The 220 MW design imported from Canada strengthening Indias credentials as a
Power of Promise: Examining Nuclear Energy in (Bhardwaj 2006). Of the 22 nuclear major nuclear manufacturing power-
India (Penguin India, 2012).
reactors operating in India today, 14 are house. This is the latest in a long
14 JUNE 24, 2017 vol lIi nos 25 & 26 EPW Economic & Political Weekly
COMMENTARY

sequence of efforts by the nuclear estab- is it likely that there will be any sales in Many of these companies had been
lishment to position itself as an exporter the near future. Around the world, hoping for major contracts from imported
of nuclear reactors. nuclear power, as a share of electricity reactors. Take the case of L&T. In 2008,
The DAEs rhetorical desire to export generated, is on the decline, from the its top official had publicly expressed the
nuclear technology dates back to the historical maximum of 17.6% in 1996 to expectation that it would get offers of
early 1990s (see, for example, ToI 1990). under 11% in 2015 (BP 2015; Ramana around `24,000 crore per year for 10
But claims about the potential for 2016). Although there is much talk of years (MC 2008). In April 2015, L&T
nuclear reactor exports multiplied dur- new countries adopting nuclear power, signed a memorandum of understanding
ing the debate over the USIndia nuclear as of 2016, only two new countries were (MoU) with French company Areva to
deal between 2005 and 2008, and have actually building reactorsBelarus and carry out some of the manufacture for
continued since then. the United Arab Emirates (Schneider the EPR reactor planned for construction
The rationale for these claimsapart and Froggatt 2016: 13). Just about every in Jaitapur (PTI 2015). Kalyani Group
from burnishing the institutional cre- reactor sold in the last decade or more company Bharat Forge had earlier signed
dentials of the DAEwas to persuade has been a LWR and prospects for the an MoU with Areva for the manufacture
members of the NSG to see India as good export of Indian PHWRs are bleak. of forgings related to nuclear plants
enough to be admitted to the club. This (Staff 2009). Tata Consulting Engineers
diplomatic effort, initiated by the UPA Corporate Handouts had signed a preliminary contract with
government, has been adopted by the A second target for the announcement is General Electric Hitachi to collaborate
Narendra Modi government. Despite its evidently the various corporations that in areas such as workforce skills identifi-
embarrassing failure to do so last year, profit from supplying equipment to cation and development, as well as early
the government appears to be launching a nuclear power plants. All of the official feasibility design studies, product and
renewed effort to join the NSG by making announcements specifically mentioned project engineering work (GEH 2010).
claims about exports of Indian PHWRs. these companies. NPCIL commented on In late 2015, in anticipation of reactor
However, the nuclear establishments the approval generating confidence in imports from the US, the chairman of
efforts at obtaining export orders for its the Indian nuclear industry about the the Godrej Group, Adi Godrej, excitedly
reactors have not been particularly continuity of business as it would provide said, There will be a huge opportunity.
successful. orders over a period of time and how it And the chief executive officer (CEO) of
In 2007, for example, the chairman would also help the Indian industry the Walchandnagar Group was very
of NPCIL announced that the company evolve, augment its capacities and capa- hopeful that before the end of the finan-
was considering exporting small and bilities (NPCIL 2017c). The DAEs press cial year enquiries [would] start to
medium reactors (220 MW to 700 MW) to release, a statement from a group of come in (Reuters 2015).
countries in the Asian region and that retired nuclear bureaucrats, talked about Although this bonanza from imported
Thailand and Cambodia have held pre- new enthusiasm and optimism among reactors has not materialised, contracts
liminary talks with NPCIL for reactors as equipment manufacturing industry, pre- for nuclear plants can still be very large
they are satisfied with NPCILs safety dicting that it is poised to grow in tandem and profitable. For example, in March
and operational capabilities (Wadke with our programme, bringing India to 2009, L&T received a `345 crore order for
and Subramanian 2007). In 2009, it was the frontline of global nuclear manufac- four steam turbines for Kakrapar-3 and
the turn of a different country and NPCIL turing and supply chain (DAE 2017). Most Kakrapar-4, and in September 2009,
announced that a proposal for reactor importantly, the government press release two orders worth `405 crore (Larsen &
sales to Kazakhstan is already on the talked about likely manufacturing orders Toubro 2009a, b). In December 2012, it
anvil, with discussions between NPCIL of close to 70,000 crores being given received an order valued at over `732
and the Central Asian nations nuclear to domestic industry (Press Information crores (Larsen & Toubro 2012). It is likely
utility Kazatomprom at an advanced Bureau 2017). that the number of large private-sector
stage (Bureau 2009). The same year, DAE Although there are a number of such companies involved in the nuclear reac-
Secretary Anil Kakodkar announced corporations, a few of them capture most tor business will expand in the coming
that India had made an export version of the contracts. Historically, some of years, and the recent announcement
of its advanced heavy water reactor the prominent companies involved in should be seen as a strategy to win over
design, called the AHWRLEU, which such supplies are Larsen & Toubro (L&T), those sections of capital.
would use low enriched uranium (LEU) Walchandnagar, and Tata Consulting
instead of the plutonium used in the Engineers. Most of these corporate enti- Cost
original AHWR design. The target for ties naturally welcomed the governments Ultimately, the cost of these handouts
this reactor design was to be developing announcement. The director of L&T called and efforts to woo NSG members will
countries with modest industrial infra- the move bold and historic (Reuters be paid by the public. Each of these 10
structure (WNN 2009).1 2017). Likewise, the chief operating officer reactors will be hugely expensive pro-
None of these countries have so far of Godrej & Boyce termed it a visionary positions, as suggested by the `70,000
purchased any reactors from India. Nor step (Bureau 2017). crore figure for manufacturing orders
Economic & Political Weekly EPW JUNE 24, 2017 vol lIi nos 25 & 26 15
COMMENTARY

mentioned in the official announcement. the heavy water that is used in PHWR s. assume that all the 10 PHWRs will be
Although the government has not so far We will explore this issue in a forthcom- constructed. It is almost certain, going
provided a cost projection, we can come ing article. by history, that they will not be con-
up with a rough estimate on the basis of structed on time. The four 700 MW
earlier experience. Evaluation PHWRs under construction have all been
We can start with the last two PHWR s Announcements are, of course, easier delayed. The initial commissioning dates
under construction, Rajasthan-7 and than delivery. There has been a history of were December 2015 for the two Kakrapar
Rajasthan-8. Construction of these began the nuclear establishment setting ambi- units and December 2016 for the Rajast-
six years ago and they were estimated tious targets and making tall claims. A han units (Ministry of Statistics and Pro-
to cost `12,320 crore or about `6,160 crore particularly relevant example dates back gramme Implementation 2012: 32). As of
per reactor (Ministry of Statistics and to 1984, when the DAE announced that it December 2016, Unit 3 at Kakrapar was
Programme Implementation 2012). These would be constructing a number of PHWRs expected to become critical by Novem-
projects have been delayed by at least (CAG 1999). That plan involved building ber 2017, and Unit 4 is expected to start
two years due to what the government twelve 235 MW PHWR units and ten 500 six to seven months later (IANS 2016).
terms major equipments supply con- MW units by 2000, which were to bring The Rajasthan units are expected to
straints, referring to the inability of the countrys nuclear power generation start about a year later (Chaffee 2016).
commercial manufacturers to manufac- capacity to 10,000 MW by the turn of the Practically all reactors constructed by
ture components for these reactors on century (Ramanna 1985). That did not the DAE and NPCIL have suffered delays
schedule. This itself suggests that the happen. Instead, as the Comptroller and and cost overruns (Ramana 2012).
governments plan to manufacture 10 Auditor General (CAG) found in 1999, the
reactors in fleet mode may be overly actual additional generation of power Changes in the Power Sector
ambitious. from this plan was nil in spite of having While nuclear power has been suffering
Delays inevitably lead to an escalation incurred an expenditure of `5,291.48 delays and overruns, an important
in cost. Although the government has crore. Installed nuclear capacity at the change has occurred on the supply side
not announced the precise cost escala- end of 2000 was 2,720 MW, less than a of Indias power sectora rapid increase
tion at the Kakrapar and Rajasthan proj- third of the target. in renewable energy. For many years
ects, even a very conservative estimate Plans to import LWRs from France and now, wind and solar power have deliv-
using just the additional cost of debt ser- the US have also failed. Plans for imported ered more electricity to the grid than
vicing in building the project over seven LWRs were announced at the beginning nuclear energy. The Central Electric
rather than five years suggests an esca- of the decade as part of a new target of Authority (CEA) reports that between
lation of about 15% in costs. In addition, 20,000 MW by 2020 (Chidambaram 2001). April 2016 and March 2017 renewable
the construction cost index for power But these import plans did not, for the energy sources together generated 81.9
sector projects has gone up by more than most part, become serious till the 2008 TWh, more than twice the 37.9 TWh gen-
20% (CIDC 2017). Putting these factors decision by the NSG to lift the ban on erated by nuclear power.
together suggests that even if construc- nuclear trade with India. At that time, According to the CEA, renewable
tion were to be started immediately, NPCIL assumed that construction of the energy is expected to contribute about
each new 700 MW PHWR would cost first imported LWR would start in 2008 20% and 24% of the total energy
about `8,500 crore, and 10 PHWRs would and the reactor would start operating in requirement in 202122 and 202627
cost `85,000 crore. The true cost is likely 2014 (Thakur 2008: 62). But, as of May respectively (Central Electric Authority
to be even higher. 2017, there has been no reactor imported 2016: 6.13). Even if these figures do not
This high-cost implies that the electri- as a result of the NSG waiver. come true, the direction in which
city from these reactors is likely to be Nuclear power targets have also renewable energy is heading is clear. In
more expensive than electricity from fallen. Following the 2008 NSG waiver, contrast, the CEA projects that the share
competing sources of energyeven if nuclear power targets swelled and, in of nuclear energy will stay roughly
the comparison is restricted to so-called 2010, the DAE secretary announced a constant, around 2% of all electricity
base load sources, such as coal, natural target of 35,000 MW by 2020 (PTI 2010). generated in the country. Nuclear
gas, and hydroelectric power. Renew- By 2015, the target was a mere 14,600 power, then, will continue to be a
able energy sources such as wind and MW by 202021 (Sasi 2015). Considering minor source of electricity for India.
solar power have also declined in cost. that the current official capacity is 6,780
As we have discussed earlier (Raju and MW, and that only the Rajasthan and Conclusions
Ramana 2013; Ramana 2007), the gov- Kakrapar projects and the prototype fast In its press release, NPCIL declared that
ernments tariff model for nuclear power breeder reactor are likely to be com- its mission was to produce nuclear
hides several indirect costs. These include pleted by then, total nuclear capacity power as a safe, environmentally benign
an inconsistent accounting of the time- will probably touch 10,080 MW by 2020. and economically viable source of elec-
value of the equity invested in nuclear The fruitless pursuit of imported LWRs trical energy to meet the increasing elec-
plants, and significant subsidies for suggests that it would be fallacious to tricity needs of the country (2017c). The
16 JUNE 24, 2017 vol lIi nos 25 & 26 EPW Economic & Political Weekly
COMMENTARY

reality, however, is that nuclear power is 10 New Indigenous Reactors, Department of Raju, S and M V Ramana (2013): Cost of Electricity
Atomic Energy, Mumbai, 19 May, http://dae. from the Jaitapur Nuclear Power Plant, Eco-
neither safe nor environmentally benign, nic.in/writereaddata/pr190517.pdf. nomic & Political Weekly, Vol 48, pp 5160.
given the risk of catastrophic accidents ET Bureau (2016): India Wont Need Extra Power Ramana, M V (2007): Heavy Subsidies in Heavy
and the production of radioactive waste. Plants for Next Three Years, Says Government Water, Economic & Political Weekly, Vol 42,
Report, Economic Times, 2 June. pp 348390.
The high costs involved in generating GEH (2010): GE Hitachi Nuclear Energy and Tata (2012): The Power of Promise: Examining
nuclear energy imply that it cannot be an Consulting Engineers Exploring Potential Nuclear Energy in India, New Delhi: Penguin
economically viable means of meeting Design and Workforce Development Oppor- India.
tunities for New Reactor Projects, GE News- (2016): Second Life or Half-life? The Con-
the electricity needs of the millions in room, 17 August, http://www.genewsroom.com/ tested Future of Nuclear Power and Its Poten-
India without access to power. Press-Releases/GE-Hitachi-Nuclear-Energy- tial Role in a Sustainable Energy Transition,
and-Tata-Consulting-Engineers-Exploring- F Kern (ed), Energy Transitions, London:
The announcement about building 10 Potential-Design-and-Workforce-Develop- Palgrave Macmillan, pp 36396.
PHWRs fits a pattern, often seen with the ment-Opportunities-for-New-Reactor-Proj- Ramanna, R (1985): Can Nuclear Energy Claim to
ects-224707. be the Only Source of Power in the Future?,
current government, where it trumpets
IANS (2016): Trial Run of Indias First 700 MW C C Desai Memorial Lecture, Administrative
a routine decision to bolster its bold Reactor in 2017, Economic Times, 31 December. Staff College of India, Hyderabad, Bombay:
credentials. Most of the plants that were (2017): India to Build 10 Heavy Water Reactors Department of Atomic Energy.
to Boost Nuclear Power, Hindustan Times, Reuters (2015): Indian Manufacturers Like Larsen
recently approved have been in the pipe-
17 May. & Toubro and Walchandnagar Industries Tar-
line for years. Nevertheless, there is Larsen & Toubro (2009a): L&T Receives `345 Cr get Orders from Revived Nuclear Power Push,
good reason to be sceptical of these Order for Critical Equipment for Nuclear Project, Economic Times, 24 December.
press release, http://www.larsentoubro.com/ (2017): Indian Cabinet Approves Plans to build
plans given that similar plans to build media/28064/npcil345crorder300309.pdf. 10 Nuclear Reactors, Reuters India, 18 May.
large numbers of reactors have failed to (2009b): L&T Wins Repeat Order for Steam Sasi, A (2015): PMO Sets Target: Hike N-Power
meet their targets, often falling far Generators for Nuclear Power Projects, press Capacity Three-fold in 10 Years, Indian
release, http://www.larsentoubro.com/media/ Express, 2 February, http://indianexpress.com/
short. Neither is there a high likelihood 30321/lt-wins-repeat-order-for-steam-genera- article/india/india-others/pmo-sets-target-
of reactor exports. The media hype sur- tors-for-nuclear-power-projects.pdf. hike-n-power-capacity-three-fold-in-10-years/.
rounding this announcement, and the (2012): L&T Secures ` 732 Cr Order from Schneider, M and A Froggatt (2016): The World
Nuclear Power Corporation of India, press Nuclear Industry Status Report 2016, Paris:
effort and the expense invested in it, is a release, http://www.larsentoubro.com/media Mycle Schneider Consulting; http://www.
revealing indicator of the style of func- /28331/ltsecuresrs732croreorderfromnuclear- worldnuclearreport.org/The-World-Nuclear-
powercorporationofidia_-8588469091606587 Industry-Status-Report-2016-HTML.html.
tioning of the Modi government. 310.pdf. Singh, J (2016): Unstarred Question No 146:
MC (2008): NSG Waiver May Generate Orders Investment in Atomic Energy Sector, New
NOTE Worth Rs 2K Cr: L&T, Money Control, https:// Delhi: Lok Sabha, http://www.dae.nic.in/
moneycontrol.com/video/business/nsg-waiver- writereaddata/parl/winter2016/lsus146.pdf.
1 The purpose of the plutonium or the LEU is to may-generate-orders-worth-rs-2k-cr-lt_355257. Staff (2009): Bharat Forge and AREVA Sign MoU
provide the initial fi ssion reactions to pro- html. for Manufacture of Heavy Forgings in India,
duce neutrons that would go on to converting Ministry of Statistics and Programme Implemen- Forging, 6 February, http://forgingmagazine.
the thorium into uranium-233, which would tation (2012): 37th Report on Mega Projects com/materialsmro/bharat-forge-and-areva-
then undergo fi ssion reactions and produce (` 1000 Crores and above) June, 2012, New sign-mou-manufacture-heavy-forgings-india.
energy. Delhi. Thakur, S (2008): Economics of Nuclear Power in
NI (2007): Attainment of Self-sufficiency in the Indian Context, Atoms for Peace, Vol 2,
REFERENCES Nuclear Power Production, Nuclear India, No 1, pp 5967.
Vol 40, Nos 1112, p 20, dae.nic.in/sites/ ToI (1990): Export Nuclear Tech: Iyengar, Times
Bhardwaj, S A (2006): The Future 700 MWe Pres- default/files/nimay07.pdf. of India, 14 May.
surized Heavy Water Reactor, Nuclear Engi- Narayanasamy, V (2012): Unstarred Question Wadke, R and T S Subramanian (2007): 30,000
neering and Design, Vol 236, pp 86171. No 2949: Nuclear Power Plants in the Twelfth MW to be Added Using Imported N-Fuel,
BP (2015): Statistical Review of World Energy 2015, Plan, Rajya Sabha, New Delhi. Business Line, 16 Aug.
London: BP, http://www.bp.com/en/global/ NPCIL (2017a): Plants under Construction WNN (2009): Thorium-fuelled Exports Coming
corporate/about-bp/energy-economics/statis- Kakrapar Atomic Power Project, Nuclear From India, World Nuclear News, 17 September,
tical-review-of-world-energy.html. Power Corporation of India Ltd, http://www. http://www.world-nuclear-news.org/NP_Tho-
Bureau (2009): NPCIL Embarks on Marketing npcil.nic.in/main/ConstructionDetail.aspx? rium_exports_coming_from_India_1709091.
Drive for Reactors, Business Line, 21 June. ReactorID=91. html.
(2017): ` 70,000-crore Investment Proposal to (2017b): Plants under ConstructionRajasthan
Set Off Chain Reaction in N-Energy, Economic Atomic Power Project, Nuclear Power Corpora-
Times, 18 May. tion of India Ltd, http://www.npcil.nic.in/
Central Electric Authority (2016): Draft National main/ConstructionDetail.aspx?ReactorID=87.
Permission for Reproduction of
Electricity Plan, New Delhi, http://www.cea. (2017c): Mega Impetus for Nuclear Power Articles Published in EPW
nic.in/reports/committee/nep/nep_dec.pdf. Cabinet Approves 10 New Indigenous Pressur-
Chaffee, P (2016): Potential and Existing Global ised Heavy Water Reactors, Nuclear Power No article published in EPW or part thereof
Nuclear Newbuild Projects (non-Generation IV), Corporation of India Limited, 18 May, http://
Nuclear Intelligence Weekly, Vol 10, No 25, www.npcil.nic.in/pdf/news_18may2017_01.pdf. should be reproduced in any form without
pp 816. Press Information Bureau (2017): Press release on prior permission of the author(s).
Chidambaram, R (2001): Nuclear Energy Needs Cabinets decision to transform domestic nuclear
and Proliferation Misconceptions, Current industry, 17 May, Department of Atomic Energy, A soft/hard copy of the author(s)s approval
Science, Vol 81, No 1, pp 1721. http://dae.nic.in/?q=node/973. should be sent to EPW.
CIDC (2017): Construction Cost Indices, Construc- PTI (2010): N-Power Generation to Touch 35,000mw
tion Industry Development Council, http:// by 2020: AEC Chief, India Today, http://india- In cases where the email address of the
www.cidc.in/new/cci-new.html. today.intoday.in/story/N-power- generation-to-
CAG (1999): Report by the Comptroller and Audi- touch-35,000mw-by-2020:-AEC-chief/1/89269.
author has not been published along with
tor General of India, New Delhi. html. the articles, EPW can be contacted for help.
DAE (2017): Top Nuclear Scientists Hail the (2015): L&T, Areva Sign MoU for Cooperation
Cabinets Decision Regarding Mega-project on on Jaitapur Nuclear Plant, Livemint, 11 April.

Economic & Political Weekly EPW JUNE 24, 2017 vol lIi nos 25 & 26 17

Vous aimerez peut-être aussi