Académique Documents
Professionnel Documents
Culture Documents
CURVA S
Taller de Aplicacin
Mediante este taller usted aprender a realizar el control de obra, los costos, la programacin, a
travs del mtodo de la curva S, utilizando la informacin de su proyecto y la valiosa ayuda del
programa MS Project.
CONTROL Y AVANCE DE LA OBRA
Ingrese las siguientes tareas en la parte de texto de la pantalla de trabajo del programa, indique la duracin y
la relacin de las tareas en la columna Predecesoras.
Los recursos mquina 1 y mquina 2 se pagaran a diario, para ello bastar con digitar en la columna tasa
estndar 250/d y el programa escribe 250.00/da.
2.- Regresamos a la vista Gantt e ingresamos los recursos a cada una de las tareas de acuerdo al siguiente
cuadro:
ARENA GRUESA
CHANCADA 1/2"
MAQUINA 1
MAQUINA 2
OPERARIO
CEMENTO
MADERA
PIEDRA
ACERO
AGUA
PEON
DESCRIPCION
MOVIMIENTO DE TIERRAS
INICIO
CORTE DE MATERIAL SUELTO 2 4 1
CORTE DE MATERIAL SEMIROCOSO 2 4 1
RELLENO CON MATERIAL PROPIO 2 4 1
RELLENO CON MATERIAL
SELECCIONADO 2 4 1
FIN
ESTRUCTURAS
CANAL
INICIO
EXCAVACION DE ZANJAS 2 5
CONCRETO EN LA BASE 2 4 200 10 10 4
ACERO Fy 4200 2 1500
ENCOFRADO DE ALAS 2 1500
CONCRETO EN LAS ALAS 2 4 400 20 20 8
FIN
REPRESA 1 NORTE
INICIO R1
EXCAVACION DE ZANJAS 2 5 1
ACERO Fy 4200 2 15000
ENCOFRADO 2 15000
CONCRETO f'c=245 kg/cm2 2 4 1 500 25 25 9
FIN R1
REPRESA 2 SUR
INICIO R2
3.- Cuando termine de ingresar los recursos, verifique los costos y las horas de trabajo, adicionando 02
columnas con los campos costo y trabajo.
3. Obsrvese que el 15 de junio el avance de obra tiene un costo de S/.15,240.00 y un costo restante
de S/.373,100.00.
4. Ahora simularemos avances los 15 y fines de mes:
a. 15 de Junio
b. 30 de Junio
c. 15 de Julio
d. 31 de Julio
e. y 17 de Agosto.
Proyecto 1 S/. 388,340.00 S/. 0.00 S/. 15,240.00 S/. 32,004.00 S/. 79,014.67 S/. 294,032.34 S/. 388,340.00
MOVIMIENTO DE TIERRAS S/. 38,100.00 S/. 15,240.00 S/. 32,004.00 S/. 38,100.00 S/. 38,100.00 S/. 38,100.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
CORTE DE MATERIAL SUELTO S/. 7,620.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00
CORTE DE MATERIAL SEMIROCOSO S/. 15,240.00 S/. 7,620.00 S/. 15,240.00 S/. 15,240.00 S/. 15,240.00 S/. 15,240.00
RELLENO CON MATERIAL PROPIO S/. 7,620.00 S/. 0.00 S/. 4,572.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00
RELLENO CON MATERIAL
S/. 7,620.00 S/. 0.00 S/. 4,572.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00
SELECCIONADO
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
ESTRUCTURAS S/. 350,240.00 S/. 0.00 S/. 0.00 S/. 40,914.67 S/. 255,932.34 S/. 350,240.00
CANAL S/. 33,310.00 S/. 0.00 S/. 0.00 S/. 5,692.00 S/. 20,026.00 S/. 33,310.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 2,960.00 S/. 0.00 S/. 0.00 S/. 2,960.00 S/. 2,960.00 S/. 2,960.00
CONCRETO EN LA BASE S/. 6,830.00 S/. 0.00 S/. 0.00 S/. 2,732.00 S/. 6,830.00 S/. 6,830.00
ACERO Fy 4200 S/. 6,960.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,960.00 S/. 6,960.00
ENCOFRADO DE ALAS S/. 5,460.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,276.00 S/. 5,460.00
CONCRETO EN LAS ALAS S/. 11,100.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,100.00
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
REPRESA 1 NORTE S/. 135,050.00 S/. 0.00 S/. 0.00 S/. 18,278.00 S/. 113,213.00 S/. 135,050.00
INICIO R1 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 8,420.00 S/. 0.00 S/. 0.00 S/. 5,894.00 S/. 8,420.00 S/. 8,420.00
ACERO Fy 4200 S/. 61,920.00 S/. 0.00 S/. 0.00 S/. 12,384.00 S/. 61,920.00 S/. 61,920.00
ENCOFRADO S/. 46,920.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 37,536.00 S/. 46,920.00
CONCRETO f'c=245 kg/cm2 S/. 17,790.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,337.00 S/. 17,790.00
FIN R1 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
REPRESA 2 SUR S/. 181,880.00 S/. 0.00 S/. 0.00 S/. 16,944.67 S/. 122,693.34 S/. 181,880.00
INICIO R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 12,630.00 S/. 0.00 S/. 0.00 S/. 5,894.00 S/. 12,630.00 S/. 12,630.00
ACERO Fy 4200 S/. 82,880.00 S/. 0.00 S/. 0.00 S/. 11,050.67 S/. 71,829.34 S/. 82,880.00
ENCOFRADO S/. 62,880.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 33,536.01 S/. 62,880.00
CONCRETO f'c=245 kg/cm2 S/. 23,490.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 4,698.00 S/. 23,490.00
FIN R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
6. De la misma forma que encontramos los costos quincenales, se puede encontrar la cantidad de
materiales quincenales que utilizamos.
7. Para ello nos ubicamos en la fila 1 del proyecto y volvemos al 0% en el avance de obra.
8. En la vista diagrama de Gantt avanzamos al 15 de junio y luego vamos a la vista hoja de recursos y a
la tabla de trabajo.
9. En esta tabla se observa el porcentaje de avance de los recursos y en la columna Real la cantidad de
recursos usados en el avance de la obra.
10. De la misma forma se procede para el resto de quincenas y hacemos un nuevo cuadro en la hoja de
clculo, para luego insertar un grfico con la curva S de cada material.
30000
Kilogramos
20000
10000
0
15-jun 30-jun 15-jul 30-jul 14-ago
30000
P2
20000
Series1
10000
0
15-jun 30-jun 15-jul 30-jul 14-ago
800 Series1
600
400
200
0
15-jun 30-jun 15-jul 30-jul 14-ago
11. Con los datos anteriores se puede construir una tabla valorizada quincenal_
a. Insertar una columna adicional por quincena.
b. La quincena del 15 de junio es el costo acumulado.
c. La quincena del 30 de junio es costo acumulado del 30 de junio menos el costo acumulado al 15
de junio.
d. Las quincenas siguientes son similares a la ltima.
DESCRIPCION Costo total ACUMULADO QUINCENA ACUMULADO QUINCENA ACUMULADO QUINCENA ACUMULADO QUINCENA ACUMULADO QUINCENA
Proyecto 1 S/. 388,340.00 S/. 15,240.00 S/. 15,240.00 S/. 32,004.00 S/. 16,764.00 S/. 79,014.67 S/. 47,010.67 S/. 294,032.34 S/. 215,017.67 S/. 388,340.00 S/. 94,307.66
MOVIMIENTO DE TIERRAS S/. 38,100.00 S/. 15,240.00 S/. 15,240.00 S/. 32,004.00 S/. 16,764.00 S/. 38,100.00 S/. 6,096.00 S/. 38,100.00 S/. 0.00 S/. 38,100.00 S/. 0.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
CORTE DE MATERIAL SUELTO S/. 7,620.00 S/. 7,620.00 S/. 7,620.00 S/. 7,620.00 S/. 0.00 S/. 7,620.00 S/. 0.00 S/. 7,620.00 S/. 0.00 S/. 7,620.00 S/. 0.00
CORTE DE MATERIAL SEMIROCOSO S/. 15,240.00 S/. 7,620.00 S/. 7,620.00 S/. 15,240.00 S/. 7,620.00 S/. 15,240.00 S/. 0.00 S/. 15,240.00 S/. 0.00 S/. 15,240.00 S/. 0.00
RELLENO CON MATERIAL PROPIO S/. 7,620.00 S/. 0.00 S/. 0.00 S/. 4,572.00 S/. 4,572.00 S/. 7,620.00 S/. 3,048.00 S/. 7,620.00 S/. 0.00 S/. 7,620.00 S/. 0.00
RELLENO CON MATERIAL SELECCIONADO S/. 7,620.00 S/. 0.00 S/. 0.00 S/. 4,572.00 S/. 4,572.00 S/. 7,620.00 S/. 3,048.00 S/. 7,620.00 S/. 0.00 S/. 7,620.00 S/. 0.00
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
ESTRUCTURAS S/. 350,240.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 40,914.67 S/. 40,914.67 S/. 255,932.34 S/. 215,017.67 S/. 350,240.00 S/. 94,307.66
CANAL S/. 33,310.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,692.00 S/. 5,692.00 S/. 20,026.00 S/. 14,334.00 S/. 33,310.00 S/. 13,284.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 2,960.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,960.00 S/. 2,960.00 S/. 2,960.00 S/. 0.00 S/. 2,960.00 S/. 0.00
CONCRETO EN LA BASE S/. 6,830.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 2,732.00 S/. 2,732.00 S/. 6,830.00 S/. 4,098.00 S/. 6,830.00 S/. 0.00
ACERO Fy 4200 S/. 6,960.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 6,960.00 S/. 6,960.00 S/. 6,960.00 S/. 0.00
ENCOFRADO DE ALAS S/. 5,460.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,276.00 S/. 3,276.00 S/. 5,460.00 S/. 2,184.00
CONCRETO EN LAS ALAS S/. 11,100.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,100.00 S/. 11,100.00
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
REPRESA 1 NORTE S/. 135,050.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 18,278.00 S/. 18,278.00 S/. 113,213.00 S/. 94,935.00 S/. 135,050.00 S/. 21,837.00
INICIO R1 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 8,420.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,894.00 S/. 5,894.00 S/. 8,420.00 S/. 2,526.00 S/. 8,420.00 S/. 0.00
ACERO Fy 4200 S/. 61,920.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 12,384.00 S/. 12,384.00 S/. 61,920.00 S/. 49,536.00 S/. 61,920.00 S/. 0.00
ENCOFRADO S/. 46,920.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 37,536.00 S/. 37,536.00 S/. 46,920.00 S/. 9,384.00
CONCRETO f'c=245 kg/cm2 S/. 17,790.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,337.00 S/. 5,337.00 S/. 17,790.00 S/. 12,453.00
REPRESA 2 SUR S/. 181,880.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 16,944.67 S/. 16,944.67 S/. 122,693.34 S/. 105,748.67 S/. 181,880.00 S/. 59,186.66
INICIO R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 12,630.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,894.00 S/. 5,894.00 S/. 12,630.00 S/. 6,736.00 S/. 12,630.00 S/. 0.00
ACERO Fy 4200 S/. 82,880.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,050.67 S/. 11,050.67 S/. 71,829.34 S/. 60,778.67 S/. 82,880.00 S/. 11,050.66
ENCOFRADO S/. 62,880.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 33,536.01 S/. 33,536.01 S/. 62,880.00 S/. 29,343.99
CONCRETO f'c=245 kg/cm2 S/. 23,490.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 4,698.00 S/. 4,698.00 S/. 23,490.00 S/. 18,792.00
FIN R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
12. Una vez establecida la lnea base, se modificar los costos de algunos recursos y la duracin de
algunas tareas.
13. En la vista Hoja de recursos / Tabla de entrada cambiamos los costos de los recursos de trabajo
como se muestra a continuacin.
14. Una vez realizados los cambios nos ubicamos en la vista diagrama de Gantt / Tabla costo y observe
los cambios efectuados.
16. Del mismo modo que realizo simulaciones quincenales, repita ahora con estos nuevos costos.
Proyecto 1 S/. 427,505.00 S/. 18,160.00 S/. 47,216.00 S/. 98,542.67 S/. 323,576.74 S/. 427,505.00
MOVIMIENTO DE TIERRAS S/. 54,480.00 S/. 18,160.00 S/. 47,216.00 S/. 54,480.00 S/. 54,480.00 S/. 54,480.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
CORTE DE MATERIAL SUELTO S/. 9,080.00 S/. 9,080.00 S/. 9,080.00 S/. 9,080.00 S/. 9,080.00 S/. 9,080.00
CORTE DE MATERIAL SEMIROCOSO S/. 18,160.00 S/. 9,080.00 S/. 18,160.00 S/. 18,160.00 S/. 18,160.00 S/. 18,160.00
RELLENO CON MATERIAL PROPIO S/. 13,620.00 S/. 0.00 S/. 9,988.00 S/. 13,620.00 S/. 13,620.00 S/. 13,620.00
RELLENO CON MATERIAL
S/. 13,620.00 S/. 0.00 S/. 9,988.00 S/. 13,620.00 S/. 13,620.00 S/. 13,620.00
SELECCIONADO
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
ESTRUCTURAS S/. 373,025.00 S/. 0.00 S/. 0.00 S/. 44,062.67 S/. 269,096.74 S/. 373,025.00
CANAL S/. 35,150.00 S/. 0.00 S/. 0.00 S/. 6,444.00 S/. 21,322.00 S/. 35,150.00
INICIO S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 3,520.00 S/. 0.00 S/. 0.00 S/. 3,520.00 S/. 3,520.00 S/. 3,520.00
CONCRETO EN LA BASE S/. 7,310.00 S/. 0.00 S/. 0.00 S/. 2,924.00 S/. 7,310.00 S/. 7,310.00
ACERO Fy 4200 S/. 7,120.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 7,120.00 S/. 7,120.00
ENCOFRADO DE ALAS S/. 5,620.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 3,372.00 S/. 5,620.00
CONCRETO EN LAS ALAS S/. 11,580.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 11,580.00
FIN S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
REPRESA 1 NORTE S/. 150,415.00 S/. 0.00 S/. 0.00 S/. 19,476.00 S/. 121,541.40 S/. 150,415.00
INICIO R1 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 15,060.00 S/. 0.00 S/. 0.00 S/. 7,028.00 S/. 15,060.00 S/. 15,060.00
ACERO Fy 4200 S/. 63,364.00 S/. 0.00 S/. 0.00 S/. 12,448.00 S/. 62,914.40 S/. 63,364.00
ENCOFRADO S/. 48,363.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 37,792.00 S/. 48,363.00
CONCRETO f'c=245 kg/cm2 S/. 23,628.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,775.00 S/. 23,628.00
FIN R1 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
REPRESA 2 SUR S/. 187,460.00 S/. 0.00 S/. 0.00 S/. 18,142.67 S/. 126,233.34 S/. 187,460.00
INICIO R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
EXCAVACION DE ZANJAS S/. 15,060.00 S/. 0.00 S/. 0.00 S/. 7,028.00 S/. 15,060.00 S/. 15,060.00
ACERO Fy 4200 S/. 83,360.00 S/. 0.00 S/. 0.00 S/. 11,114.67 S/. 72,245.34 S/. 83,360.00
ENCOFRADO S/. 63,360.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 33,792.01 S/. 63,360.00
CONCRETO f'c=245 kg/cm2 S/. 25,680.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 5,136.00 S/. 25,680.00
FIN R2 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00 S/. 0.00
17. Con los valores de costos totales de la primera programacin y la que acabamos de hacer, generar
una grfica de curva S planificada y de costo total (real).
100000 98,542.67
79,014.67
50000 47,216.00
32,004.00
18,160.00
15,240.00
0 0
01-jun 16-jun 01-jul 16-jul 31-jul 15-ago
En esta nueva grfica se observa que con los cambios realizados, la curva de costo total (nueva
programacin), en las dos primeras quincenas, se ha desplazado hacia arriba generando un gasto superior a
lo previsto.
En la tercera quincena y cuarta quincena no ocurre ningn ajuste y se muestra el constante aumento de
gastos no previstos, se prosigue hasta el final de la obra generando finalmente una diferencia de (427,505
388,340=39,165) ms de lo previsto.