METHOD STATEMENT FOR INSTALLATION


OF CABLE TRAY/TRUNKING/LADDER

PREPARED BY APPROVED BY
AMIT ENTERPRISES Doc. No : AE/HSM/10

ELECTRICAL Rev. No./Date:00/09.11.2016


METHOD STATEMENT Issue No./Date:01/09.11.2016

REVISION CONTROL SHEET


REV. NO. DATE PAGE NO. DESCRIPTION

00 09.11.2015 ALL FIRST ISSUE


AMIT ENTERPRISES Doc. No : AE/HSM/10

ELECTRICAL Rev. No./Date:00/09.11.2016


METHOD STATEMENT Issue No./Date:01/09.11.2016

TABLE OF CONTENTS

1. Purpose 4

2. Scope of Work 4

3. Responsible Personnel on Site 4

4. Storage 4

5. Pre-Installation 4

6. Installation 4

7. Reference Documents 5

8. Safety 5
AMIT ENTERPRISES Doc. No : AE/HSM/10

ELECTRICAL Rev. No./Date:00/09.11.2016


METHOD STATEMENT Issue No./Date:01/09.11.2016

1. Purpose :
This method of statement covers the on-site installation of Cable Trays, Trunking & Cable
Ladders as defined in the General Specification.

2. Scope of Works :
This procedure will define the method to be used to ensure that cable trays, trunking &
ladders installations are correct and acceptable and shall conform to the Contract
Documents and Specification.

3. Responsible Personnel on Site


3.1. Construction Manager
3.2. Electrical Field Engineers
3.3. Safety Officer
3.4. Electrical Supervisors

4. Storage
4.1 Cable Trays, Trunking and Ladders shall be properly supported and stacked on a flat
surface.
4.2 Cable Trays, Trunking and Ladders shall be protected from sunlight and moisture by
covering them with tarpaulin.
4.3 Cable Trays, Trunking and Ladders shall be stacked properly in neat and orderly
manner.
4.4 Cable Trays, Trunking and Ladders shall be stored and stacked in dry area and shall be
properly protected.

5. Pre-Installation
5.1 All materials and documentation relevant to this particular Section of works will be
checked by the Construction Department prior to the commencement of works
ensuring that these are correct type as reviewed.
5.2 Before any permanent works will proceed, pre-inspection on all materials, tools and
access for installation to be carried out.

6. Installation
6.1 Establish the Cable Trays, Trunking and Ladder route on slab soffit and walls, and
mark with chalk liner. Ensure that the route conform with the latest coordinated
services drawings.
6.2 Mark the locations of supports. For horizontal installation spacing between supports
shall not exceed 1.5m for trunking and 1.2m for cable trays and ladders and not
more than 150mm from all bends and tees. For vertical installation, spacing between
supports shall not exceed 3m for trunking and 1.5m for cable trays and ladders.
6.3 Install the threaded rod and angle bar supports for horizontal installation and
uni-strut channel for vertical supports. Make sure that the supports are properly
anchored, rigid and aligned.
AMIT ENTERPRISES Doc. No : AE/HSM/10

ELECTRICAL Rev. No./Date:00/09.11.2016


METHOD STATEMENT Issue No./Date:01/09.11.2016

6.4 Install Cable trays, trunking and ladders ensuring that it is properly fixed to its
supports. Where necessary to cut the cable trays, the cutting line of the cable trays
shall be through continuous metal parts and not through the perforation. Burrs and
sharp ends shall be removed prior to the installation of tray section or accessories.
6.5 Cable Trays, Trunking and Ladders shall be connected to adjacent lengths, tees, bends
and fittings with approved couplers and securely fastened by mushroom head steel
roofing bolts and nuts. Connection shall be mechanically strong so that there is no
relative movement between joints.
6.6 Earth links shall be fixed on the adjacent connection of Cable trays, trunking and
ladders and fittings to maintain the electro-mechanical continuity on the runs of
cable trays, trunking and ladders.
6.7 Where cable tray or cable ladder crosses, expansion joints, adjacent length of cable
tray or ladder shall not be joined and shall be bridged only with a flexible earth
connector.
6.8 A minimum clear space of 25mm shall be kept behind all installed runs of cable trays.
Where in a cable trays carrying power cables run in parallel with low current cable
trays, a 300mm minimum clear distance shall be kept throughout the installation.
6.9 Raise Request for Inspection for the Cable Trays, Trunking and Ladders Installation.

7. Reference Documents
7.1 Approved Electrical Drawings
7.2 Approved Material Submittals
7.3 Approved Material Inspection Report
7.4 Approved Safety Plan
7.5 Approved Inspection & Test Plan.

8. Safety
8.1 All safety precautions shall be followed as per approved safety plan & procedure.
Ensure all involved persons are aware of the same.
8.2 Safety Officer to ensure that all working flat forms shall be safe and in good condition.
8.3 Tradesman shall ensure that before leaving their working places, it must be clean,
tidy and free from rubbish.

------------------------ Procedure End----------------------