Vous êtes sur la page 1sur 7

Design and Construction

Overview of the Biggest Coal


Fired Power Plant in Thailand
(BLCP Power Plant),
Developed by Private
Companies as IPP Business

EISUKE ASADA*1 ITSUO KOUHARA*1


KOICHIRO HONDA*1 TAKESHI WATANABE* 1
HIROTAKE KAWASHIMA*2

In Thailand, private IPP (Independent Power Producers) businesses are increasing and booming. Mitsubishi
Heavy Industries, Ltd. (MHI) received under Mitsubishi Corporation an order from BLCP Power Limited for a power
plant which will be Thailand's first large scale bituminous coal-fired power plant on a full turn-key (FTK) basis to
conduct Engineering, Procurement and supply of equipment, and Construction including civil work. In this report,
we would like to introduce our valuable experiences which successfully contributed to the accelerated completion of
the project, jointly accomplished with the Owner. The report also includes various counter measures and consider-
ations for IPP project which are not usually encountered in power plants for governments or authorities.

bituminous coal-fired power plant on a full turn-key


1. Introduction (FTK) basis to conduct Engineering, Procurement and
Thailand, after overcoming the legacy of the fast- supply of equipment, and Construction including civil
est currency crisis in Southeast Asia, has maintained work.
very steady economic growth by making the use of
political stability, a plentiful labor force and the in- 2. Project overview
troduction of proactive foreign capital. The demand The BLCP power plant is situated in the Map Ta Phut
for electricity has shown steady growth along with Industrial Estate which is located in Rayong Province
economic growth and in addition to the development in the southeast of Thailand. It takes about two and a
of facilities by the government-run public electricity half hours by car from the capital city Bangkok. The
corporation, private IPPs (Independent Power Produc- construction site is located on reclaimed land 3 km away
ers) have become active. Mitsubishi Heavy from the eastern coastline of Map Ta Phut Port and is
Industries, Ltd. (MHI) received under Mitsubishi Cor- surrounded by sea, considering the entry of large coal
poration an order from BLCP Power Limited for a ships. Figure 1 shows the BLCP power plant construc-
power plant which will be Thailand's first large scale tion site and Fig. 2 is an overview of the power plant.

Bangkok

Cambodia Vietnam

BLCP power plant

Fig. 1 Construction site of BLCP power plant Fig. 2 Overview of the power plant

*1 Nagasaki Shipyard & Machinery Works Mitsubishi Heavy Industries, Ltd.


*2 Power Systems Headquarters Technical Review Vol. 44 No. 4 (Dec. 2007)
1
Table 1 Major specifications of plant

Equipment Specification
Rated output 717 MW (at Generator terminal)
16.7 MPa (a) x 538oC
Steam condition
(Turbine inlet)
Fuel Coal (Bituminous coal), Diesel oil (for start-up)
Plant Cooling system Seawater cooling system
Condenser vacuum 0.006931MPa (a)
Feed water heater 8 stages (LP: 4 stages + deaerator + HP: 3 stages)
Water
Low-phosphate treatment
treatment system
Pulverized coal fired, forced circulation, single drum,
Boiler Type radiant reheat type boiler
(Maximum Continuous Rating: 2285 t/h)
Tandem-compound quadruple exhaust flow reheat
Turbine Type regenerating condensing turbine
3000 min-1, 35.4 inch last stage blade
Type Water cooled generator
Generator Capacity 844 MVA
Excitation system Brushless excitation system
Substation Type GIS (Gas Insulated Switchgear)
Complete coal unloading facility, coal storage and
Coal handling system Type transport system and conveyor system
Electrostatic Precipitator Type Fixed electrode system
Fly ash: vacuum transportation,
Ash handling system Type
Bottom ash: conveyor transportation
Flue Gas Desulfurization
Type Seawater desulfurization system
system

Table 2 Environmental limitations (at the stack outlet) system. Tables 1 and 2 show the specifications of the ma-
jor systems and the environmental limitations respectively.
Environmental limitations
Item
(7 % O2 , Dry, 1atm, 25 deg. C)
3. Outline of major power generating installation
Nitrogen oxides (NOx) (ppm) 241
Sulfur dioxides (SO2) (ppm) 262 3.1 Boiler
Carbon monoxide (CO) (ppm) 94 The boilers are forced circulation, exclusively coal-fir-
Dust (mg/m3) 43 ing boilers designed and manufactured based on MHI's
previous long experience. Performance-based design is
adopted for the furnace and layout of the heat transfer
The power plant consists of two coal fired conven- surface fitting for the bituminous coal, while burner tilt
tional plants, each composed of Boiler, Steam turbine, mechanism to adjust the steam temperature is also in-
and Generator. The rated output per plant is 717 MW stalled to cope with the heat absorption differences in
and the total power generation capacity of the two plants the furnace caused by the variation of coal properties.
amounts to 1,434 MW. The coal used as fuel is bitumi- For the combustion facility, Mitsubishi vertical pulver-
nous coals produced in Australia and Indonesia, while izer fitted with MRS (Mitsubishi Rotary Separator),
diesel oil is used as the start-up fuel. MHI supplied all having good separation performance and high-fineness,
the equipment relating to power generation including is adopted. The CUF (Circular Ultra Firing) burner is
the major BOP systems such as Coal unloading pier, Coal selected and located in each corner of the furnace wall,
handling system, Electrostatic Precipitator, Ash handling which provides effective utilization of circular firing char-
system, and Flue Gas Desulfurization system and also acteristics in the entire furnace. Figure 3 shows a side
ancillary facilities such as Water treatment system, view of the boiler.
Waste water treatment system, Circulating water sys- Further, as an environmental measure, A-PM (Ad-
tem, and Ventilation and Air Conditioning system and vanced-Pollution Minimum) burner with a good track
Fire fighting systems. record as a pulverized coal-firing burner, is adopted
In the design stage, 3D-CAD was employed for all the together with the in-furnace NOx reduction system (A-
power plant systems including those above. In addition, MACT), enabling low NOx operation for a wide range
the integrated control of the layout plan, detailed engi- of coal properties. During the performance test, good
neering, and interference checks were implemented not boiler efficiency result was confirmed, which is higher
only for the power generation system but also for the BOP than the design value.

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
2
Fig. 4 Cross section of steam turbine

Fig. 5 Cross section of generator


Fig. 3 Side view of boiler

3.2 Steam turbine 4. Characteristics of project


The turbine has a rated output of 717 MW and is the 4.1 Permits and licenses from Authorities
tandem compound type with a high-pressure (HP) / inter- As for the permits and licenses relating to the construc-
mediate-pressure (IP) turbine casing and two low-pressure tion of infrastructures which tend to be omitted
(LP) turbine casings connected by one shaft. The HP tur- conventionally in public works in developing countries due
bine and IP turbine are combined into one casing. The HP to the governmental operating authority, we were required
turbine is of single-flow design, consisting of one control to obtain all the Thai legal permits and licenses concern-
stage and nine reaction stages. The IP turbine is also of ing construction of power plants strictly in accordance with
single-flow design consisting of seven reaction stages, and the respective laws and regulations. Of these, those which
arranged opposite to the HP turbine. The LP turbine is of could only be applied for and obtained by the contractor,
double-flow, where each flow consists of seven reaction such as building permits for the power plant buildings were
stages including the 35.4 inch ISB (Integral Shroud Blade) totally entrusted to the contractor and MHI also played a
last stage blades. Figure 4 shows a cross-sectional view role. The application for a building permit to the Indus-
of the turbine. The performance improvement is attained trial Estate Authorities of Thailand ("IEAT") which had
through the utilization of advanced fully three-dimen- jurisdiction over the power plant site was an important
sional designed reaction blades for all the reaction stages issue. Its major objective was the establishment of safety
including the LP turbine last stage. of all structures (including foundations for the equipment)
After operation started, various supervisory data includ- and buildings to be constructed on the site and no con-
ing the shaft vibration were sufficiently lower than the struction work could be started without this formal permit
allowable values and stable operation was observed. Fur- even after all the design work was completed. The im-
ther, during the performance test, the turbine achieved portance of this approval was fully recognized from the
higher levels of efficiency that exceeded the design value. start of the project by us. Dedicated engineers and coor-
3.3 Generator dinators were frequently dispatched to Thailand, even
For the type of Generator, a stator water cooling sys- before start of the actual application process, to discuss
tem is adopted to achieve the increased capacity of the with the officers with concerned details of the contents of
generators. Figure 5 shows a cross section of the gen- the application procedure and the drawings and docu-
erator. The capacity increase of the generator has been ments to be submitted. Further the fact that the design
worked on since the 1980s targeting a tandem type 1,000 process had been scheduled to allow sufficient time be-
MW class generator. In this project, a structure which fore the start of construction and that the engineers and
had already been verified with the 990 MVA generator coordinators were stationed in Thailand to promote com-
f o r E G AT ( E l e c t r i c i t y G e n e r a t i n g A u t h o r i t y o f munication with the authorities contributed to the
Thailand) (Note 1) is adopted. With regard to operating successful acquisition of over 80 approvals without caus-
performance, it was confirmed from actual loading tests ing any essential effect on the work process. Until the
conducted at the site that the rotor shaft vibration, and completion of the construction work, this permit contin-
coil temperature rise satisfied their planned values. ued to be a major issue of concern for not only the MHI
Note 1: Currently owned by RGCO (Ratchaburi Electricity engineers and those in charge of the work but also all the
Generating Co., Ltd.) other concerned parties including the Owner.

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
3
4.2 Environmental Impact Assessment (EIA) the entire area of the coal yard. Through the discus-
As this project was the first large-scale coal fired s i o n w i t h t h e O w n e r, H D P E ( H i g h D e n s i t y
power plant in Thailand, a strict Environmental Impact PolyEthylene) sheet was laid on the entire area of the
Assessment (EIA) was introduced to minimize the pos- coal yard to prevent rainwater seepage to the soil. Fur-
sible environmental impact on the surrounding areas ther, to collect rainwater from the coal yard, a coal yard
caused by the construction and operation of the power pond and a specific coal yard wastewater treatment sys-
plant. The EIA covered not only conformity with the tem were constructed. Wastewater after treatment
environmental quality standards in Thailand (wastewa- satisfying standard values in Thailand will be reused
ter, air quality and noise) but also various measures to as water spray for the dust suppression at the coal yard.
mitigate the environmental load inherent in a large-scale (3) Measures for dust dispersion in the coal yard
thermal coal fired power plant. Some typical examples A windbreak fence was built along the entire south
of these measures are described below: side of the coal yard to prevent dust dispersion from
(1) Compliance with various regulations through the con- the coal yard to the sea or other facilities. Further,
struction period by installing a wind meter in the vicinity of the coal
In order to demonstrate compliance with the EIA yard, automatic control of watering based on the wind
during the construction period, fully implemented air velocity was conducted. Implementation of intermit-
quality observation inside and outside the site at regu- tent watering by means of a chemical sprinkler vehicle
lar intervals, wastewater quality control and (polymeric coating material), and compaction using a
monitoring, were conducted. Briefing sessions for out- bulldozer for dust dispersal prevention were also con-
line of construction to community residents was ducted. The measures for dust dispersal prevention
organized and monitoring results were reported in relation to the coal handling facility are use of a
monthly to a committee established by the munici- covered conveyor, provision of a watering system in
pality. Typical measures implemented within the site the Transfer towers and Screen house, and provision
are watering the temporary construction road for dust of dust collection facilities.
suppression, provision of a wheel cleaning system and (4) Restrictions on discharge of condenser cooling water
controlling the speed of vehicles shuttling to and from The discharge system is designed based on the
the site, and provision of windbreak covers on con- simulation results of "A three-dimensional modeling
struction material and equipment and on truck beds. assessment of the cooling water discharge from the
Also, it was strictly enforced that wastewater gener- power plant" attached in the EIA so that the discharge
ated during construction was first collected into velocity shall be 1.5 m/s or above in order to prevent
multiple temporary water sedimentation basins lo- the temperature rise more than 3 oC at any point in a
cated on the site and, after sedimentation and radius of 500 m from the discharge point comparing
confirmation that the wastewater quality met the EIA with the ambient seawater temperature. Further,
standard requirement, it was finally discharged into because of the adoption of the seawater desulfuriza-
Fig. 6
the sea (Fig. 6). tion system, pH requirement (pH=7.0 or above) was
additionally imposed along with the other general
requirements at the discharge point (residual chlo-
ride concentration Cl: less than 1.0 ppm, discharged
seawater temperature: 40 oC or less). The requirement
of pH is relatively more stringent than the require-
ment in the other countries.
4.3 Application of tax exemption system by the Board
of Investment of Thailand (BOI)
In general, a certain amount of custom duty is imposed
on the equipment imported into Thailand. In this respect,
as this project concerned the construction of public infra-
Fig. 6 Sedimentation basin
structure, the tax exemption system of the Board of
Investment of Thailand (BOI) was applied. However, this
(2) Use of impermeable sheets at the coal yard tax exemption benefit is no more than a basic principle
In this project, the power plant was constructed and, in order to avoid the actual imposition of import du-
on reclaimed land and the coal yard is located out- ties and taxes at Customs, it was necessary for us to
doors. Therefore, as it was thought that a large establish a perfect list of every equipment imported, to
amount of rainwater falling on the coal yard would explain its non-availability in Thailand, and to obtain the
seep underground and finally flow out into the sea, particular approval of the Board of Investment prior to
the EIA specified impermeable sheets laid down over first importation of the equipment.

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
4
It was extremely difficult to prepare such a perfect the seawater quality became one of the most important
list before the design was completed. As custom duties tasks for the design conditions. For this project, peri-
and taxes had to be borne by the contractor if the tax odic analyses of the seawater in the surrounding ocean
exemption was not contractually approved by the area took place through a year and the fluctuation ranges
contractor's act or omission, we tried to establish a work of the major parameters (alkalinity, pH, temperature)
system with all the necessary details, make the list, and that affect the desulfurization performance were defined.
prepared a huge volume of effective explanatory materi- The major equipment of the system consists of Absorber,
als for submission to the authorities as soon as the BUF (Boost Up Fan), Seawater pump for desulfuriza-
Contract was put into effect. The completed list con- tion, Seawater treatment system and Oxidization system.
sisted of 2,000 items and the explanatory material was For the exhaust gas, by adopting a partial desulfuriza-
composed of 10 large files, each 8 cm thick. It took three tion system (70% desulfurization, 30% bypassed), the flue
full months for three specialized staff members to com- gas temperature could increase more than EIA guide-
plete them. Even after the application, as in the case of line by mixing with untreated flue gas and treated flue
the building permits, a number of explanations had to gas at the FGD outlet, satisfying SO 2 limitation. For
be given to the officers concerned. We hired an experi- the seawater system, approximately 20% of the seawa-
enced customs agent to act for us in the application for ter from the exit of the condenser is taken by Seawater
and acquisition of approval and successfully obtained the pump and is fed into the absorber to be used for the des-
right of tax exemption on all the applied items within ulfurization process in the absorber. As the seawater at
two months from application. the absorber exit had a low pH, it shall be aerated through
4.4 Plan of seawater desulfurization system the Seawater treatment system by oxidization and to re-
This system is characterized by the reuse of a part of cover the pH level to satisfy the EIA standard value
the cooling water (seawater) from the outlet of the con- (pH=7.0 or above). The system and equipment specifica-
Figs. 7 & 8 ).
denser as an absorbent for desulfurization (Figs. tions were determined after various tests and simulations
This is more advantageous compared with the lime/lime- were conducted by the MHI Research and Development
stone gypsum process, as there is no need for additional Center and other external research institutes.
absorbent or treatment of by-products, simplifying equip- 4.5 Design and construction of coal unloading pier
ment and reducing the operating power consumption. (1) Design of pier (mooring conditions in consideration
However, the desulfurization performance largely de- of heavy storms)
pends on the seawater quality and therefore determining The coal carriers to be moored are Cape-size ves-
sels (170,000 DWT, DWT: dead weight tons) and
Panamax-size vessels (70,000 DWT). In the event of
heavy storms, they are not usually moored at the pier
but are evacuated offshore. However, due to insuffi-
cient depth of the navigation channel, the vessels are
to approach the pier during high tide and moored at
the specified berthing place which is dredged 2 m
deeper than the navigation channel. Therefore, in
designing the pier it was necessary for us to include
the maximum design wind velocity and the specified
waves in discussing the mooring draft conditions, as-
suming a situation where a coal carrier would
Fig. 7 Seawater desulfurization system (absorber)

Seawater from Seawater


condenser outlet desulfurization system
Exhaust gas
(EP outlet) To the stack

Oxidizing air
Absorber

Seawater
treatment To the outfall
system
Oxidizing air

Fig. 8 Seawater desulfurization system (system flow diagram) Fig. 9 Coal unloading pier

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
5
encounter heavy storms during low tide and not be system) was developed through the Internet.
able to be moved offshore because of its deep draft. The local procurement office played a significant role
Normally, the maximum design wind velocity in a case throughout the construction period, which not only worked
like this is taken into consideration when designing on delivery date control and management so that neces-
a pier without a vessel moored. The wind velocity sary materials could be obtained in time but also enabled
with rather high occurrence frequency (1/3 to 1/2 of prompt responses and quick material supply in the event
the maximum design wind velocity) is used as the of problems through the network of Thai suppliers which
design wind velocity when a vessel is moored. Ac- has been established by the VC. These efforts minimized
cordingly, the strength of this pier is substantially the loss of schedule and cost, contributing greatly to main-
higher than that of others. Further study for simu- taining the construction schedule.
lating the dynamic behavior of moored vessel at berth 4.7 Utilization of specialized local staff
in the above heavy storm conditions was conducted Along with the expansion in functions of the local pro-
to evaluate safety during mooring and the stability of curement office such as procurement control, document
the pier structure. control (drawings and correspondence), personnel and
(2) Construction of the pier labor control, and IT control (development, modification
The pier has a concrete deck (30 m W x 346 m L ) and maintenance of the document transfer system and
and a mooring dolphin supported by 326 steel pipe various IT tools), the local staff working in the office had
piles including battered piles, for which hardly any to naturally develop their ability from generalist to spe-
piling work could be performed during the summer cialist. In this project, through the local works and the
monsoon season especially from July to September. allocation of people in charge who were experienced in
In order to catch up with the construction schedule, each field, efficient site works and services could be suc-
we increased the number of piling vessels and intro- cessfully facilitated.
duced hollow precast concrete (PC) slabs as forms with
the strength to support the concrete weight before the 5. Outline of construction work
concrete hardened as a permanent part of the con- As this project has a number of large equipment and
crete deck section, thus having eliminated the time systems, minimizing the assembling work on site was
required for setting and removing the forms and shor- the most important key to shortening the construction
ings that would have been otherwise required in the schedule. Considering the efficiency and limitations of
conventional method. Further for the construction of marine and inland transportation, each piece of equip-
the 60 m long trestle roadway connecting the plant ment was maximized in knockdown size before shipment.
site and the pier, large PC girders were prefabricated, Also, some of the equipment was preassembled at the
carried onto and installed at the place. This contrib- ground level at construction site and lifted into place by
uted to an extensive reduction of the construction a large crane.
period in comparison with the usual case of cast-in As for local contractors of civil construction, consid-
place concrete. ering that the construction work was large scale, two
(3) Environmental measures civil constructors are selected dividing the work into land
In order to prevent coal dust discharge (conveyor construction work and sea construction work (coal un-
and transfer tower) to the sea through the rain wa- loading pier). The land construction work was awarded
ter, drain pits with sedimentation pit are provided on to Thai Nishimatsu Construction Co., Ltd. (TNC) whose
the pier. A large amount of rainwater drainage around subcontractors are two leading contractors in Thailand,
the pier is first collected in the drain pits on the pier, Sino-Thai Engineering & Construction (STECON) and
then pumped up to the Coal yard pond in the coal Italian-Thai Development (ITD) as well as a few other
yard, and finally treated in the Coal yard wastewater small-scale construction companies. Meanwhile, the sea
treatment system. construction work (coal unloading pier) was awarded to
4.6 Local procurement management Toa Corporation (TOA) which had experiences in marine
In this project, since most of the equipment was pro- construction work with ITD as its subcontractor. The
cured in Thailand, a local procurement office was built total amount of concrete for the land and sea construc-
in Thailand to conduct the process from placing orders tion work was 170,000 m3.
to shipment of products smoothly. Experienced staff in As for the mechanical installation and electrical in-
material procurement design and quality control was strumentation work, Thai Jurong Engineering (TJEL)
employed in the office managed by the Vender Control- was selected as the local contractor, which could deal
ler (VC). Also to improve the data transmission speed with all of the machinery, instrumentation and electric
between Japan and the local procurement office and to works. The total weights involved were 70,000 tons of
improve the efficiency of procurement work in the of- mechanical equipment and 1,400 tons of electric equip-
fice, special procurement system (FTK project support ment, and the total cable length was 1,960 km.

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
6
In Thailand, since there are a few contractors who
are experts in the installation of coal fired power plants, 6. Conclusion
a detailed installation instruction manual was neces- In this project, our efforts were focused not only on
sary and prepared as a back-up support tool for overcoming the various problems and characteristics men-
construction work. This is referred to internally as tioned in Section 4 but also on promoting the
"HEITAN (strategic logistic services)" activities. This "Implementation of visual control management for each
instruction manual contained drawing numbers, draw- activity." This was achieved by the establishment of our
ing names, part numbers, part names, part quantities, unique Project Management Tools (PMT) which were origi-
and their weights which are necessary for the installa- nally developed with the aim of the smooth management
tion of each system. Thus, even if the person in charge of overseas FTK projects, based on the lessons learned
was inexperienced in the system during the installa- from large scale FTK projects. This enables us to conduct
tion work, they could smoothly carry out the integrated management of the various tasks, such as
preparatory work (drawings, parts, tools, heavy equip- Schedule control management, Drawing submission man-
ment, workers, etc.) and could utilize this manual when agement, Outstanding issues management, Quality
giving installation instructions on site. Although it took control management, Procurement management, and Risk
a long time to prepare this instruction manual, it was management. The total number of each PMT established
highly regarded by those involved during the construc- for this project is more than 30. These PMTs were con-
tion work and contributed effectively to the elimination stantly subject to review at appropriate times under the
of confusion and delays, and the observance of the qual- slogan of "more user-friendly and more effective" and
ity and construction schedule. thanks to the efforts of the people concerned, finally be-
For commissioning, the total period from Initial fir- came a truly useful project management tool. Accordingly,
ing to Steam admission, Synchronization and final Turn we achieved good results especially for the risk manage-
over is 6 months. Since this period is relatively short ment and delivery schedule management of equipment
for a 700 MW power station, commissioning staff par- and systems which have been important issues for many
ticipated in the design section from the early stages of years, contributing to the success of this project.
the project to learn about the basic plan, design and op- Finally, we would like to express our sincere grati-
eration concept of the plant and their requests and tude to the Owner and all the parties involved in this
propositions in terms of commissioning activity was also project for their hard work which led to the successful
fed back into the system design. Thus, mutual collabo- completion of this project.
ration was established between the engineers and
commissioning staffs, contributing to the realization of
an efficient and trouble-free commissioning resulting in
an accelerated completion of the project.
Further with regard to the Owner training, this was
conducted at the same time as commissioning, provid-
Eisuke Asada Itsuo Kouhara Koichiro Honda
ing comprehensive systematic instructions. The training
program is established based on our extensive experi-
ences with a complete review of not only the major
machinery such as the Boiler and Turbine supplied by
us but also other various equipment and systems sup-
plied by different manufacturers.
Takeshi Watanabe Hirotake Kawashima

Mitsubishi Heavy Industries, Ltd.


Technical Review Vol. 44 No. 4 (Dec. 2007)
7

Vous aimerez peut-être aussi