ANNEX G KEY MILESTONE DATES

REV.0

The Contract Schedule and Milestones are to be inserted into the Contract at Award.
Project Milestones to be maintained by Contractor shall be as follows:

Number of Consecutive
Milestone Event Calendar Days after the
Effective Date of Contract

ENGINEERING
16 October 2011
Contract Award

Mobilization Complete / Engineering 15


Kickoff
Complete underground utilities
identification by Radiography survey up 60
to 20KMs from Transfer Pump station.
Complete identification of rocky area by
60
conducting Geophysical for the entire
pipeline up to Ad-Duaihi.
80
Issue 60% Detail Design Package

Hydraulic Calculations and Finalizing 120


the selection of Long Lead Items
140
Issue 90% Detail Design Package
180
Issue IFC Package

Design Completion 18 April 2012

Milestones BY Others
The following constitute the availability dates of services and/or systems on which
CONTRACTOR shall plan his work accordingly. The dates are to be provided by the
CONTRACTOR in order for the Employer to judge the work completion.

Table 1.1 Construction Milestone dates for Package-I

Item Description Completion Date

1.0 TRANSFER PUMP STATION

Mobilization
1.1

SAUDI ARABIAN MINING COMPANY (Page 1 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


Complete mobilization of camp with

Catering and accommodation facilities,

Complete temporary facilities, Site offices,


Satellite offices, and fabrication yards, lay
down area, all fences, roads, utilities, &
phone tie-ins, as per Contract terms and
conditions of the contract.

1.2 Complete construction of site development


Work including paving, grading,
excavation and backfill.
1.3 Complete construction of Civil Work,
including excavation, backfill for
foundations, Electrical, Mechanical
Equipments, pipe supports, and Building
and building-related Work.
1.4. Site development, storm water drainage,
Access asphalt road, Perimeter Fence,
Parking Lots and Security Gates.

1.5 Complete Construction of SEC room, Sum


Pit with monorail and Valve Boxes and
Septic Tank

1.6 Complete construction of raised floor for


the marshalling and control room.

1.7 Installation of Nozzles to existing


Secondary Storage tank including Valves
and associate fittings.

1.8 Complete Construction of Furnished


Operation Building including furniture for
SCADA

1.9 Complete Sanitary works & plumbing


works including Raw Water storage tanks,
water dispensers, Pantry equipments,
pumps, fixtures and associated fittings.

1.10 Complete HVAC works including controls,


ducting and all associated fitting &

SAUDI ARABIAN MINING COMPANY (Page 2 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


accessories.

1.11 Complete Installation of Vertical Turbine


Pumps, above ground Piping, pipe
supports, Valves, Automatic Air vents,
Vent/drain valves, MOVs, PCVs, FCVs,
Surge Relief Valve, and Tie-ins,

1.12 Complete installation of Electrical


equipments, including Switch Gear
Transformers, MCC, Disconnect Switches,
Distribution Boards, associate Accessories
and Interfacing with SEC (Saudi Electricity
Company)

1.13 Complete Installation of fire protection


equipments and detection system for the
operation building,

1.14 Complete Installation of all power Cable


including Medium and Low Voltage Cable
and Tie-in

1.15 Compete Installation of Lighting Poles


Including Under Ground Cabling and
associate Tie-ins

1.16 Installation of UPS System and Power


Supply to the Necessary
Equipments/valves/Controls &
Instruments,

1.17 Complete Installation of Emergency


Generator, Panel, Auto Changeable Panel,
Diesel Tanks and Diesel Pumps.

1.18 Complete Installation and termination of


junction boxes, Local control panels,
associated Instrument.

1.19 Complete Installation of Instruments and


control cables, cables trays, conduits,
supports and cable tags.

1.20 Provide power supply for field Instruments


and termination of cables inside junction
SAUDI ARABIAN MINING COMPANY (Page 3 of 13)
TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


and termination of cables inside junction
box, LCP and marshalling cabinet.

1.21 Installation of field instruments which


includes level transmitters, pressure
transmitters and pressure gauges, flow
transmitters.

1.22 Continuity check of cables, loop checks,


Testing and commissioning.

1.23 Complete Installation, testing,


commissioning of control system including
Field Instruments MOVs, PCVs FCVs,

1.24 Installation of Fiber distribution panel and


termination of 6 core single mode Fiber
Optic Cable into the fiber distribution
panel.

1.25 Complete PCS Modification/SAT

1.26 Mechanical Completion certificate

1.27 PIPELINE (71Kms) CONSTRUCTION

1.27.1 From Transfer pump station up to 10KM

Complete Installation of underground


Pipeline, Fiber Optic Cable up to 4.8km,
right of way, Valves, Air release chamber
with Vacuum breakers, washout chambers
and Construction all associated works
Including and trenching, Bedding,
Compacting, Thrust Blocks, Culverts, road
& Wadi crossings, Hydro Testing, Back
Filling, Pipe Line KMs Markers, Valve
Fencing, Valves & Vents Boxes and
reinstate of ground to its as found state

1.27.2 From 10KM to 20KM

Complete Installation of underground


Pipeline, right of way, Valves, Air release
chamber with Vacuum breakers, washout
chambers and Construction all associated

SAUDI ARABIAN MINING COMPANY (Page 4 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


works Including and trenching, Bedding,
Compacting, Thrust Blocks, Culverts, road
& Wadi crossings, Hydro Testing, Back
Filling, Pipe Line KMs Markers, Valve
Fencing, Valves & Vents Boxes and
reinstate of ground to its as found state

1.27.3 From 20KM to 30KM

Complete Installation of underground

Complete Installation of underground


Pipeline Cost for every increment of 10KM
from 20KM up to 71KM

Complete Installation of underground


Pipeline, right of way, Valves, Air release
chamber with Vacuum breakers, washout
chambers and Construction all associated
works Including and trenching, Bedding,
Compacting, Thrust Blocks, Culverts, road
& Wadi crossings, Hydro Testing, Back
Filling, Pipe Line KMs Markers, Valve
Fencing, Valves & Vents Boxes and
reinstate of ground to its as found state

1.27.4 Complete PCS Modification/SAT

1.27.5 Mechanical Completion

2.0 Complete PCS Modification/SAT

3.0 Partial Mechanical Completion

4.0 Final Mechanical Completing (MCC)

5.0 Third Party Testing and Commissioning

6.0 Final Testing *

7.0 Demobilization 15 February 2014

Complete demobilization and site clean-up


activities per Contract terms and
conditions, including all WORK site

SAUDI ARABIAN MINING COMPANY (Page 5 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


locations, office locations, and construction
camp.

Table 1.2 Construction Milestone dates for Package-II

Item Description Completion Date

2.0 MASTER PUMP STATION

2.1 Mobilization

Complete mobilization of camp with


Catering and accommodation facilities,
Complete temporary facilities, Site offices,
Satellite offices, and fabrication yards, lay
down area, all fences, roads, utilities, &
phone tie-ins, as per Contract terms and
conditions of the contract.

2.2 Complete construction of Civil Work,


including excavation, backfill, foundations
for Electrical, Mechanical Equipments, pipe
supports, paving and grading, and
Buildings and buildings-related Work.

2.3 Complete Construction of Furnished


Operation Building including all furniture

2.4 Complete Construction SEC Room, Security


Guard house, Complete Construction of
Valve Boxes and Septic Tank

2.5 Complete Construction Pump house


building with Over Head Crane, SCADA &
Electrical room with all furniture & pantry
equipments.

2.6 Complete Construction of Civil work


including site development, storm water
drainage, Access asphalt Road, Security
fence and marl road along the fence,
Parking Lots, Land Scaping and Security

SAUDI ARABIAN MINING COMPANY (Page 6 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


Gate.

2.7 Complete construction of raised floor for


the marshalling and control room.

2.8 Complete construction of Sanitary works &


plumbing works including Raw Water
storage tanks, pumps, fixtures and
associated fittings.

2.9 Complete HVAC works including HVAC


Equipment, ducting, Controls and all
associated accessories and fittings.

2.10 Complete Installation of shipper Pumps,


Jokey pump, Valves, MOVs, FCVs, Surge
Relief Valves and all associated piping and
accessories.

2.11 Complete installation of Electrical


equipments, including Switch Gear
Transformers, VFDs, MCC, Starters,
Disconnect Switches, Distribution Boards,
associate Accessories and Interfacing with
SEC (Saudi Electricity Company)

2.12 Complete Installation of fire protection


equipments and detection system for the
operation building,

2.13 Complete Installation of all power Cable


including Medium and Low Voltage Cable
and Tie-in

2.14 Compete Installation of Lighting Poles


Including Under Ground Cabling and
associate Tie-ins

2.15 Installation of UPS System and Power


Supply to the Necessary
Equipments/Instruments,

2.16 Complete Installation of Emergency


Generator, Panel, Auto Changeable Panel,
Diesel Tanks and Diesel Pumps.

SAUDI ARABIAN MINING COMPANY (Page 7 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


2.17 Complete Installation and termination of
junction boxes, Local control panels,
associated Instrument.

2.18 Complete Installation of Instruments and


control cables, cables trays, conduits,
supports and cable tags.

2.19 Provide power supply for field Instruments


and termination of cables inside junction
box, LCP and marshalling cabinet.

2.20 Installation of field instruments, which


includes level transmitters, pressure
transmitters and pressure gauges, flow
transmitters.

2.21 Continuity check of cables, loop checks,


Testing and commissioning.

2.22 Complete installation of overhead


transmission line and Tie-in to the SEC
transmission line

2.23 Complete Installation, testing,


commissioning of control system, Fiber
Optic Cables, including Field Instruments,
MOVs, control valves,.

2.24 Installation of Fiber distribution panel and


termination of 36 core single mode Fiber
Optic Cable into the fiber distribution
panel.

2.25 Complete PCS Modification/SAT

2.26 Partial Mechanical Completion

2.27 WATER PIPELINE FROM MASTER PUMP


STATION TO KM 304 MARKER(RTR
233Kms)

2.27.1 From Master Pump station to 10KM

Complete Installation of underground

SAUDI ARABIAN MINING COMPANY (Page 8 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


Pipeline, right of way, Valves, and
Construction all associated works
Including and trenching, Thrust Boring,
Bedding, Compacting, Thrust Blocks,
Culverts, Wadi crossings, Hydro Testing,
Back Filling, Pipe Line KMs Mark-ups, Valve
Fencing Valves & Vents Boxes and
reinstate of ground to its original
Conditions.

2.27.2 Complete Installation of underground


Pipeline Cost for every increment of 10KM
pipeline up to 233KM

Which including right of way, Valves, and


Construction all associated works,
trenching, Thrust Boring, Bedding,
Compacting, Thrust Blocks, Culverts, Wadi
crossings, Hydro Testing, Back Filling, Pipe
Line KMs Mark-ups, Valve Fencing Valves
& Vents Boxes and reinstate of ground to
its original Conditions.

2.28 Warning Tape & Associate Accessories.

Installation of Fiber Optic Cable in the


pipeline trench approximately 120m,
including Splicing Enclosures, Marker Post

2.29 Installation of 36 core single mode Fiber


Optic Cable above the pipeline in the
pipeline trench, Install splicing enclosures
and splice the FOC at both ends, install
identification tags and color bands, backfill
and install back fill grade marker, splicing
marker post, Warning Tape and associate
accessories.

2.30 Demobilization

3.0 Complete PCS Modification/SAT

4.0 Partial Mechanical Completion

SAUDI ARABIAN MINING COMPANY (Page 9 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


5.0 Final Mechanical Completing (MCC)

6.0 Third Party Testing and Commissioning

7.0 Final Testing

8.0 Complete demobilization and site clean-up 15 February 2014


activities per Contract terms and
conditions, including all WORK site
locations, office locations, and construction
camp.

Table 1.2 Construction Milestone dates for Package-II


Item Description Completion Date
3.0 AD-DUAIHI STORAGE FACILITY

3.1 Complete mobilization of camp with


Catering and accommodation facilities,
Complete temporary facilities, Site offices,
Satellite offices, and fabrication yards, lay
down area, all fences, roads, utilities, &
phone tie-ins, as per Contract terms and
conditions of the contract.
3.2 Complete construction of Civil Work,
including excavation, backfill, foundations
for Electrical, Mechanical Equipments, pipe
supports, paving and grading, and
Buildings and buildings-related Work.

3.3 Complete Construction of Furnished


Operation Building including all furniture

3.4 Complete Construction SEC Room, Security


Guard house, Complete Construction of
Valve Boxes and Septic Tank

3.5 Complete Construction Pump house


building with Over Head Crane, SCADA &
Electrical room with all furniture & pantry
equipments.

3.6 Complete Construction of Civil work


including site development works, storm

SAUDI ARABIAN MINING COMPANY (Page 10 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


water drainage, Access asphalt Road,
Security fence and marl road along the
fence, Parking Lots, Land Scaping and
Security Gate.

3.7 Complete construction of raised floor for


the marshalling and control room.

3.8 Complete HVAC works including HVAC


Equipment, ducting, Controls and all
associated accessories and fittings.

3.9 Complete Installation of shipper Pumps,


Jokey pump, Valves, MOVs, FCVs, Surge
Relief Valves and all associated piping and
accessories.

3.10 Complete installation of Electrical


equipments, including Switch Gear
Transformers, VFDs, MCC, Disconnect
Switches, Distribution Boards, associate
Accessories and Interfacing with SEC
(Saudi Electricity Company)

3.11 Complete Installation of fire protection


equipments and detection system for the
operation building,

3.12 Complete Installation of all power Cable


including Medium and Low Voltage Cable
and Tie-in

3.13 Compete Installation of Lighting Poles


Including Under Ground Cabling and
associate Tie-ins

3.14 Installation of UPS System and Power


Supply to the Necessary
Equipments/Instruments,

3.15 Complete Installation of Emergency


Generator, Panel, Auto Changeable Panel,
Diesel Tanks and Diesel Pumps.

3.16 Complete installation of overhead


transmission line and Tie-in to the SEC
SAUDI ARABIAN MINING COMPANY (Page 11 of 13)
TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


transmission line and Tie-in to the SEC
transmission line

3.17 Complete Installation and termination of


junction boxes, Local control panels,
associated Instrument.

3.18 Complete Installation of Instruments and


control cables, cables trays, conduits,
supports and cable tags.

3.19 Provide power supply for field Instruments


and termination of cables inside junction
box, LCP and marshalling cabinet.

3.20 Installation of field instruments, which


includes level transmitters, pressure
transmitters and pressure gauges, flow
transmitters.

3.21 Continuity check of cables, loop checks,


Testing and commissioning.

3.22 Complete Installation, testing,


commissioning of control system, Fiber
Optic Cables, including Field Instruments,
MOVs, control valves,.

3.23 Complete Installation of junction boxes,


panels, associated Instrument and Control
Cables

3.24 Installation of Fiber distribution panel and


termination of 36 core single mode Fiber
Optic Cable into the fiber distribution
panel.

3.25 Complete PCS Modification/SAT

3.26 WATER PIPELINE FROM KM304 TO AD-


DUAIHI (116 kms)

3.26.1 Complete Installation of underground


Pipeline Cost for every increment of 10KM
pipeline up to Ad-Duaihi

SAUDI ARABIAN MINING COMPANY (Page 12 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715
ANNEX G KEY MILESTONE DATES
REV.0

Item Description Completion Date


Complete Installation of underground
Pipeline, Fiber Optic Cable, right of way,
Valves, and Construction all associated
works Including and trenching, Bedding,
Compacting, Thrust Blocks, Culverts, road
& Wadi crossings, Hydro Testing, Back
Filling, Pipe Line KMs Markers, Valve
Fencing, Valves & Vents Boxes and
reinstate of ground to its original
Conditions.

3.26.2 Installation of 3X6 core single mode Fiber


Optic Cable run above the pipeline in the
pipeline trench, Install splicing enclosures
and splice the FOC at both ends for Ad-
Duaihi, PRV and the cable for Mansourah
left spare at PRV station. Install
identification tags and color bands, backfill
and install back fill grade marker, splicing
marker post, Warning Tape and associate
accessories.

4.0 Complete PCS Modification/SAT

5.0 Partial Mechanical Completion

6.0 Final Mechanical Completing (MCC)

7.0 Third Party Testing and Commissioning

8.0 Final Testing

9.0 Demobilization 15 February 2014

Complete demobilization and site clean-up activities


per Contract terms and conditions, including all
WORK site locations, office locations, and
construction camp.

SAUDI ARABIAN MINING COMPANY (Page 13 of 13)


TRANSPORATION OF TREATED WATER FROM TAIF TO MAADEN MINE SITE
CONTRACT NO. 10-1448-HQ-715

Vous aimerez peut-être aussi