Implementation of
Volume II
Scope of Work
State IT Centre, 47-A Arera Hills, Bhopal High Court Premises, Jabalpur, MP
RFP for Case Management & Tracking System in AG Office MP Volume II
ACRONYMS
RFP Request for Proposal
AG Advocate General
BG Bank Guarantee
EMD Earnest Money Deposit
IA Implementing Agency
SLA Service Level Agreement
GAD General Administration Department
BOM Bill of Material
OIC Officer Incharge
COTS Commercial of the Shelf
VAT Value Added Tax
LAN Local Area Network
WAN Wide Area Network
SDC State Data Centre
SWAN State Wide Area Network
SRS Software Requirement Specification
FRS Functional Requirement Specification
DFD Data Flow Diagram
UML Unified Modeling Language
UI User Interface
DB Database
OOA Object Oriented Architecture
ICT Information Communication Technology
SMS Short Messaging Service
MP Madhya Pradesh
CCTNS Crime and Criminal Tracking Network System
DIT Department of Information Technology
HLD High Level Diagram
NeGP National eGovernance Plan
NIC National Informatics Centre
SAN Storage Area Network
SOA Service Oriented Architecture
SDD System Definition and Design
PeMT Project eMission Team
SeMT State eMission Team
PSC Project Steering Committee
POC Project Operations Committee
PMU Project Management Unit
RFP for Case Management & Tracking System in AG Office MP Volume II
Table of Contents
1 Introduction ................................................................................................... 1
1.1 About Office of Advocate General .................................................................... 1
1.2 MP High Court, Jabalpur ................................................................................... 2
1.3 About MAP_IT ................................................................................................. 3
2 RFP STRUCTURE ............................................................................................. 3
3 Project Background ........................................................................................ 4
3.1 Reform areas ................................................................................................... 5
3.2 GAD establisment in AG Office ......................................................................... 6
3.3 targets envisaged to be achieved...................................................................... 6
4 Project Objectives .......................................................................................... 7
5 Scope of Services ............................................................................................ 7
5.1 Preparation of the Inception Report ................................................................. 7
5.2 Preparation of Detailed Project Plan ................................................................. 8
5.3 Definition & Design .......................................................................................... 8
5.4 Development & Installation ........................................................................... 10
5.5 Setting-up Data Center ................................................................................... 10
5.6 Procurement & Installation of Client side hardware ........................................ 13
5.7 Data Digitization and Migration...................................................................... 14
5.8 Change Management and Capacity Building ................................................... 14
5.9 Operation and Maintenance .......................................................................... 15
5.10 Documentation of the Project ........................................................................ 15
6 Project Timelines.......................................................................................... 16
7 Stakeholders Analysis .................................................................................. 18
8 Project Management Arrangement .............................................................. 19
9 Existing System of Functioning in AG Offices ................................................. 23
9.1 Case File Management ................................................................................... 23
9.2 Petition Receiving .......................................................................................... 23
9.3 Preparation of Return .................................................................................... 24
9.4 Hearing of Petitions ....................................................................................... 26
9.5 Final Court Order ........................................................................................... 28
9.6 Filing fresh appeal/review petition/caveat in the Court .................................. 28
10 System Requirements................................................................................... 29
10.1 Functional Requirements (Application Level) .................................................. 29
10.2 Functional Performance Requirements ........................................................... 46
10.3 Technical Requirements ................................................................................. 47
11 Testing and Quality Assurance Requirements ............................................... 52
11.1 Inspection ...................................................................................................... 53
11.2 Operational Acceptance Test .......................................................................... 54
11.3 Test Documentation....................................................................................... 55
11.4 Complete System Acceptance......................................................................... 55
11.5 Audit & Certification ...................................................................................... 56
12 Data Digitization and Migration................................................................... 57
13 Change Management & Capacity Building ................................................... 60
13.1 Change Management ..................................................................................... 60
13.2 Capacity Building ........................................................................................... 61
14 Operations and Maintenance Support .......................................................... 64
RFP for Case Management & Tracking System in AG Office MP Volume II
1 Introduction
The Advocate General Office for Madhya Pradesh came into existence on November
1956 upon the formation of the State of when the High Court of M.P. was established. The
principal activity of this department is to conduct the cases pertaining to the cases before
the Honble High Court of Madhya Pradesh at its Principal Bench, Jabalpur, Circuit Benches
at Indore and Gwalior, Madhya Pradesh Administrative Tribunal, Consumer Disputes
Redressal Forums, Consumer Disputes Redress Commission of State/National and the
Honble Supreme Court of India where the interest of State of Madhya Pradesh and its
Departments needs to be defended. It is the duty of the Advocate General to advice the
other law officers if consulted; the Advocate General shall advice the Government upon
such legal matters including legislative projects which are referred to him by the
Government. The Advocate General shall represent the Government whether civil, criminal,
original, appellate or otherwise before the MP High Court or any other High Court or the
Supreme Court where the Government is a party. The Advocate General can also represent
the Government before any Tribunal or authority or any Court subordinate to High Court if
specially required by the Government.
Page 1
RFP for Case Management & Tracking System in AG Office MP Volume II
AG Office
The Advocate General is the Head of the Department and he is the principal legal
advisor to the Government. There are in all 58 Law Officers and all of them work under the
guidance and supervision of the Advocate General. The Advocate General has been
endowed with all administrative and financial powers. The expenditure of this department is
meted out under non-plan expenditure as this Department does not come under planning.
Indore (Bench)
Gwalior (Bench)
Ashok Nagar, Bhind, Datia, Guna, Gwalior, Morena, Sheopur, Shivpuri and
Vidisha (Total 9 Districts)
MAP_IT has been entrusted to draft this RFP and conduct fair and transparent
bidding process to select Implementing Agency (IA). Representative of AG Office and Law
Department will remain in the technical screening and selection committee. After
conducting the bidding process, MAP_IT will submit technically qualified and financially
viable bidder's proposal before AG Office to release work order and sign MSA. MAP_IT will
also provide technical and project management support at time of project implementation
by providing a dedicated team of consultants named as Project eMission Team (PeMT) and
by providing it's representation in high level project management committees.
2 RFP STRUCTURE
This RFP is meant to invite proposals from interested agencies capable of delivering
the services described herein. The content of this RFP has been documented as a set of two
volumes (Volume I & II). Volume I comprises the Instruction to Bidder, SLA and General
Terms and Conditional and Volume II describes scope of work, desired solution, standards &
Page 3
RFP for Case Management & Tracking System in AG Office MP Volume II
3 Project Background
The office of the Advocate General handles legal cases of all the Govt. Departments,
Agencies, District Administrations in the High Court. At present the AG Offices have more
than 3 Lakh cases pending in the High Court. On an average 300 petitions/cases are filed in
AG Offices each day. Each petition comprises 20 to 150 pages. AG offices receive
daily/weekly cause list having hundreds of cases daily at 6:00 PM from High Court for next
day hearing. These cases are allocated to different advocates manually and relevant files are
provided to them. This exercise takes 3-4 hours after which relevant case files are
distributed even after midnight to the concerned advocates. Next day, advocates walks into
court rooms reading files and presents facts and arguments in favour of govt. of MP. More
than 3 lakh case files are stored in record rooms of AG Offices. These files are extracted,
delivered to OICs or Advocates, updated and stored back on regular basis. All the record of
file movement is recorded in various registers manually.
Due to excessive work load and limitation of manual system, every now and then
state government faces cost orders and contempt cases. Many times, returns are not filed in
due time and strong facts supporting government are not produced before court due to lack
of proper coordination and collaboration between AG Office and Govt. Departments.
Case Files are the Core of this Office Automation System. All the processes and
workflows act around Case Files. Legal Documents, Facts related to case, Court Orders, etc.
account for 90% of the contents in a Case File. A case file starts form a petition, appeal or
application filed in the High Court. Various other documents like notices, return,
vakalatnama, affidavit, adjoinders, rejoinders, letters, etc. are added in the file in due course
of Case Lifecycle. Keeping this in mind, the system should be designed on the concepts and
framework of e-File.
Page 4
RFP for Case Management & Tracking System in AG Office MP Volume II
Tracking of each and every case will be done in terms of due dates, compliances and
priority actions. This will reduce incidents of Contempt and ensure proper representation of
cases with all the facts and arguments in High Court within stipulated time frame. This will
also provide alerts to the concerned stakeholders to act positively in time. Real time status
of cases, action due at various levels, compliances of court orders, etc. should be shown on
a comprehensive dashboard.
All the case files information should be digitized and stored in central server.
Concerned officials will be able access entire or part files with proper permission online.
New content generated in due course should be added in the case file record online. All
these records should get synchronized with High Court Server.
All the case related processes are performed manually in AG Office and results
delays at various levels. The Project should automate the case processing functions like
preparation of returns, communication with respondents, obtain copies of court orders, etc.
This will enable AG office to respond quickly on crucial court cases, setting priorities and
take up more number of cases in process at same time.
AG office received cause list from high court on daily basis and allocate cased amont
Law Officer as per predefined roster. This exercise takes 3-4 hours after which relevant case
files are distributed even after midnight to the concerned advocates. The project should
automate the case allocation process and give more time to Advocates for studying the
cases by providing access to case files online. Also the system should provide intelligent
allocation according to the nature of case and expertise of advocates apart from roster.
To effectively handle the cases, Law Officers and concerned departments need
structured access of files and intelligent searching of legacy data. The system should provide
support in quick/effortless decision making.
Page 5
RFP for Case Management & Tracking System in AG Office MP Volume II
The system will support in monitoring of court orders and their status of compliance.
This will certainly reduce contempt cases and enable law experts to do needful on the cases
of high priority.
Digital Record Paper Records and Files Digitization/scanning of all the paper
Keeping only. records and files generated after project
implementation in structured manner.
Provision of concurrent updation and
addition in records. Storage of digital
record in Central Server accessible for all
the concerned officers.
Case tracking and No specific system for Automated system for tracking of
monitoring monitoring and tracking individual case on predefined stage
of individual case. parameters. Creation of compliance
Page 6
RFP for Case Management & Tracking System in AG Office MP Volume II
4 Project Objectives
To empower Office of Advocate General, Law Department and OICs of concerned
departments by providing technology enablers for quick, efficient and quality
functioning.
To Facilitate applicants and defendants to get hassle free access to the information
To have access to timely and accurate MIS Reports
To Efficiently manage case records
To monitor case status, compliance of court orders and time tracking.
To reduce workload for Law Officer and facilitate them to provide hassle-free legal
services.
5 Scope of Services
After performing a transparent and fair process of selection, a suitable and efficient
system integrator shall be identified and selected as Implementing Agency for the project.
The implementing agency shall be required to sign an agreement with AG Office, in which all
the terms and condition, project work, timelines, roles and responsibilities, etc., as defined
in this RFP, shall be included. It shall be over all responsibility of Implementing Agency to
study the existing system and requirements of AG Office before bidding. Requirements
mentioned in this part of RFP is indicative only and written purely for the purpose of making
the Implementing Agency able to estimate its efforts and costs required to achieve project
objectives successfully. Therefore, selected bidder i.e. Implementing Agency shall be
required to make a fresh assessment of AG Office requirements after winning the bid,
prepare detailed project plan, get it approved by AG office and perform project activities as
per detailed project plan. Following are the services to be rendered by selected bidder.
Page 7
RFP for Case Management & Tracking System in AG Office MP Volume II
responsibilities in the Inception Report. The acceptance of the Inception Report by AG Office
is necessary before proceeding to the next stage of the project.
The IA shall conduct requirements gathering exercise and prepare an SRS document,
for which the IA shall have a comprehensive discussion with the AG Office and other
stakeholders to ensure that each of the requirements mentioned in this RFP or identified
during study is covered.
Activities conducted as part of this task will result in the project deliverable
Software Requirement Specifications (SRS) document, which shall detail the requirements
of the complete solution up to the last detail. SRS document shall comply with the latest and
most relevant IEEE standards.
The following documents including, but not limited to, will be submitted for a sign-
off of application architecture and development methodology:
Details of validation rules and constraints like Integrity Checks etc. to be applied.
Page 8
RFP for Case Management & Tracking System in AG Office MP Volume II
Access control mechanisms, data security and audit trails to ensure that databases
are not tampered or modified by unauthorized users. The following guidelines need
to be observed for security:
Build a complete audit trail of all transactions (add, update and delete) using
transaction log reports, so that errors in data, intentional or otherwise, can
be traced and reversed.
The most appropriate level of security commensurate with the value to that
function for which it is deployed must be chosen
Access Controls must be provided to ensure that the databases are not
tampered or modified by the system operators.
Plans for User Acceptance Tests and System Integration Tests including Stress Tests
and plans.
Detailed Project Implementation Plan, component-wise activity schedule, etc.
The Implementation Agency shall be entirely responsible for the architecture of the
system implemented to satisfy all features, functions and performance as described in this
document including sizing of the required hardware. System architecture description
provided in this document is for reference only. The Implementation Agency should ensure
all possible and required improvements.
The application design will be such as to require the minimal installation, if at all, at
the users end, besides the Internet Browser and will be able to support all common
browsers (like Internet explorer, Mozilla, Chrome etc.). IA shall also design the Frontend and
Backend portals for the Project.
User's involvement will also be ensured during finalization of user interfaces, the
mode of data entry, storage and retrieval, outputs reports, queries and the application
design as a whole.
Page 9
RFP for Case Management & Tracking System in AG Office MP Volume II
IA must supply the application, database and related software, integration tools,
along with the source code and describing the process to be followed for installing and
operating the same. Software development methodology should be developed in a way that
ensures rapid deployment of the applications in such a way that the users are continually
involved in the development process.
Expected data size is approximately 500 GB for first 2 years in AG Office Jabalpur and
300 GB for first 2 years in AG office Indore and Gwalior each. Approximately 3 GB Data
would be required for AG Office Web portal in SDC. Data is expected to grow at the rate of
20% per year after 2 year. Solution will be scalable enough to accommodate minimum 10
years of data. Hence a provision of 3 TB storage space should be made in the SDC for same.
The IA shall supply, install, configure and commission the co-located servers in State
Data Center and install system software for application deployment. In addition, the IA shall
Page 10
RFP for Case Management & Tracking System in AG Office MP Volume II
draw out and provision the detailed specifications/requirements for the infrastructure that
needs to be used for hosting the application. The IA shall work with SDC team to understand
the SDC's pre-requisites for deployment of servers, database, application, etc. and provision
the IT infrastructure in such a way that it is acceptable to SDC and complies with the
standards prescribed for the State Data Centre.
State Wide Area Network (SWAN) shall be used as connectivity channel among all
the AG Office and SDC. At present SWAN Connectivity is provided and AG Office Jabalpur.
Same will also be provided in Indore and Gwalior AG office before project sign-off. IA shall
study and understand various provisions and standards prevalent in SWAN and make
necessary provisions in data centers for smooth communication.
SWAN also provides Video Conferencing facility to government office. This VC facility
shall be leveraged in this project. Necessary equipments and connectivity is already
available at AG Office Jabalpur. IA will assess further requirements for VC facility in the AG
Office and submit detailed report including gaps, if any. AG Office will take necessary
decision and accordingly procure gap infrastructure for VC facility. IA will also install and
configure equipments for Video Conferencing using SWAN Network in all the three AG
Office locations i.e. Jabalpur, Indore and Gwalior.
Page 11
RFP for Case Management & Tracking System in AG Office MP Volume II
SWAN Internet
AG Office
High Court
High Court
Data Centre
IA shall provide a detailed report on Data Centre, DR, VC, Networking, client side
hardware and software Setup which will include all the detailed specification of hardware,
brand, warranty, etc. before procurement and installation. AG office technical team shall
study and approve it in context with provision made in this RFP. After getting sign-off from
Technical team, IA will procure the hardware and begin commissioning and installation
work.
The Specifications must be futuristic with at least a five-year horizon to start with
and recommended servers should be able to accommodate any scaling up requirements
necessitated in future. All hardware including, but not limited to the servers procured, shall
be branded and reputed and not locally made products. Please refer Annexure 1 for detailed
specifications.
IA shall submit validation/audit statement from OEM for the products that have
been proposed in the system certifying that solution and sizing of infrastructure proposed
by the IA is relevant and correct with respect to their product.
Page 12
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 14
RFP for Case Management & Tracking System in AG Office MP Volume II
Prepare detailed training plan and all the training manuals to impart trainings to AG
Office Staff and other stakeholders. Training plan will include appropriate training
model, training arrangements and detailed methodology on how the training would
be conducted.
Provide such additional training as they deem necessary in order to ensure that the
training imparted is comprehensive and complete.
Provide Computer Based Training Modules will also be prepared by IA to enable the
users for self-learning.
The development team will transfer all necessary know-how to the project support
team, in such a manner so as to make for a smooth transition. Performance metrics for the
above transition will need to be agreed between the IA and the AG Office to ensure
successful conclusion of this stage. During the operational and maintenance support, a
Helpdesk will be set-up in all the AG Office locations. A central helpdesk will be established
in Jabalpur Head Office of AG for the users to contact in case of any system problems. The IA
will ensure that all necessary measures are taken for the smooth implementation of the
system. The Project maintenance team will be duly prepared and gradually takeover the
work from IA before contractual term is over.
Page 15
RFP for Case Management & Tracking System in AG Office MP Volume II
Systems Manual Detailing the data structure, table, forms and report structures.
User Manual (both online and paper copies) providing detailed instructions on
how to use the software. In addition, it shall describe how to access, submit
inputs to, and interpret outputs from the application.
A data dictionary listing out all the data elements will be prepared.
5.10.1 Web-based Monitoring and Evaluation Tool & SLA Monitoring Tools
6 Project Timelines
The overall implementation of the AG Office Project is envisaged to be completed in
10 months. Keeping in view of very specific and limited functionality of Application, it is
recommended to design, develop, test and implement the application in one phase. The
application will first be deployed in AG Office Jabalpur on Pilot basis. After successful field
testing and user acceptance testing, the application will be deployed in remaining 2 AG
offices i.e. Indore and Gwalior. In the third stage, the application shall go-live with full
deployment. Below timelines are mentioned for Implementation Agency to perform various
activities under given milestones. Time taken by AG Office for evaluation and approval of
deliverables will be excluded from these timelines.
Page 16
RFP for Case Management & Tracking System in AG Office MP Volume II
10 Site Preparation for Data Centres, LAN installation, Client Site T+22
preparation in AG Office Indore and Gwalior.
17 Overall Project Operation and Maintenance Support for 5 years T+38 to T+298
from Go Live Date.
T, as referred above is the date of signing of contract between selected IA and AG Office
Page 17
RFP for Case Management & Tracking System in AG Office MP Volume II
7 Stakeholders Analysis
The major stakeholders of this Project are as follows:
1. Office of the Advocate General, Jabalpur and its circuit offices in Indore and Gwalior.
2. Department of Law, Govt. of MP
3. MP High Court
4. All the State Departments in MP
5. All the Districts and Block
6. All the Govt. Agencies represented by AG Office in High Court.
7. Citizens
8. Department of Information Technology, Govt. of MP
Office of the Advocate General is the single and constitutional agency to provide
legal services to all the departments and agencies of the State Government. Thus, entire
state government is the stakeholder for this project. All the departments, district
administrations, local bodies, etc. interact with AG office for their legal cases and AG office
represent these in the H'ble High Court.
Citizens files petitions/appeals against state government in H'ble High Court and AG
Office respond on such petitions/appeals after necessary consultation with department.
Thus, citizens are also affected by the functioning of AG Office.
Law Department is the parent department for AG office and has many day to day
management related interaction with AG Office. Depart of Information Technology is
providing technical support to the AG office for this project. Roles & responsibilities and
influence level of each stakeholder is as follows:
Office of the Advocate Provide legal services to all the state High
General departments/agencies and represent them in
the H'ble High Court, MP.
Page 18
RFP for Case Management & Tracking System in AG Office MP Volume II
H'ble High Court Issuing daily and weekly cause list. Hearing High
Cases and make Judgement.
Page 19
RFP for Case Management & Tracking System in AG Office MP Volume II
The Project Steering Committee will have the overall responsibility for issuing policy
directives, guidance and coordination for activities related to the project under the
chairmanship of H'ble Advocate General. Secretary of Information Technology Department,
Secretary of Law Department, Representative of General Administration Department,
Registrar IT from High Court, Head SeMT, Head POC, Addl. AG and other key stakeholders
will be the members of Steering Committee. PSC will play key role in the project
implementation and the systemic transformation that the project aims at. It will also
monitor and review the project implementation in coordination with the Project Operations
Committee (POC) and Project Management Unit (PMU). The Steering Committee will be
responsible for:
Vetting of all deliverables of the project and recommend the same for
acceptance by the steering committee
Page 20
RFP for Case Management & Tracking System in AG Office MP Volume II
Coordinating with the relevant officers at all levels for effective implementation
of the project and helping resolve issues requiring high level interventions
Resolve any conflicts and issues that may arise during the implementation of the
project.
The PMU will bear overall responsibility of the Project Management on day to day
basis and remain accountable to POC. Under the guidance of the POC, the PMU will be
responsible for day-to-day activity planning, management, coordination, meeting the
administrative requirements of the Project. The PMU will demonstrate examples of good
practice, and guide and support the various entities involved on all aspects of project
implementation. It also includes, wherever required, efforts to build capacity of the AG
Offices. The PMU shall be a group of Project management, Technology and Change
Management Experts. All the expert consultants of PeMT will remain essential part of PMU.
Composition of PMU will be decided by POC in consultation with IA in order to ensure better
coordination and synergy among experts of both sides. Key responsibilities of PMU would
be as follows:
Page 21
RFP for Case Management & Tracking System in AG Office MP Volume II
5. Help in laying down a set of guidelines, following internationally accepted norms and
e-Governance standards, if not present already, for the testing and certification in all
aspects of project development and implementation covering software, hardware
and networking. This includes the processes relating to the design of systems and
sub-systems, coding, testing, business process description, documentation, version
control, security, architecture, performance in relation to compliance with Service
Level Agreement (SLA) metrics, interoperability, scalability, availability and
compliance with all the technical and functional requirements of the Request for
Proposal (RFP) and the agreement.
6. Ensure that all relevant guidelines are being followed and to avoid large-scale
modifications pursuant to testing done after the application is fully developed
IA would be required to deploy a full time project manager for the entire duration of
project. The project manager shall act as the single point of contact for AG Office and the
PMU. The project manager would create a weekly status report based on the agreed upon
format with AG Office and the PMU at the end of each week. The individual would also be
Page 22
RFP for Case Management & Tracking System in AG Office MP Volume II
responsible for escalating all delays in a timely manner. In addition to the Project Manager,
IA has to deploy a sufficient number of staff and technical persons.
Page 23
RFP for Case Management & Tracking System in AG Office MP Volume II
Petitioner or Petitioners
Receiving Window of AG Office High Court
Councel
YES
Receiving Clerk Receives petitions
back from Addl AG. and records
general parameter and forward
the petitions to respective High Court registers the petition and
sections. issues case number
End
Page 24
RFP for Case Management & Tracking System in AG Office MP Volume II
Respondent Department(s)
Appoints OIC and instruct OIC
to report AG office with all the
OIC goes back to his department
necessary factual contents,
evidences and documents.
Return to be
OIC Reports to AG Office and meet with prepared later on?
Return to be
OIC goes to respective department and show prepared right now.
authority slip to take his case file.
AG Office
OIC takes file with notesheet and make an OIC Signs Wakalatnama, Put Stamps on Return, Sign
entry/sign on outward register of Record the Return, Prepare affidavit and notarize it and finally
Room. submit it back to respective section along with file.
OIC Presents the file before Addl. AG/Dy. AG, Section incharge checks all the documents, signs and
who marks the file to a Govt. Advocate. stamps before receiving the file from OIC and make an
entry in Register.
OIC takes the file to the Govt. Advocate, Section serves a copy of return to the petitioner's counsel.
whom the file is marked to.
Page 25
RFP for Case Management & Tracking System in AG Office MP Volume II
Case Hearing
High Court fixes the date Paper printed Cause List received and Cases
of hearing for a petition related Govt. Marked manually.
and publishes it as cause
list daily
If any action Case Files are tied in bunches for each Law
required on file?
officer and delivered at his/her home.
Page 26
RFP for Case Management & Tracking System in AG Office MP Volume II
Yes
End No
Special messanger
Special messenger fills Diary Submission
AG Office finds Case
submits case diary in Form in two copies
Diary on the basis of
bail section and takes
the detail submitted
receipt in duplicate copy
by concerned Thana.
of Form.
Page 27
RFP for Case Management & Tracking System in AG Office MP Volume II
10 System Requirements
The system to be developed by the Implementation Agency (IA) should be able to
deliver at minimum the services listed below. The IA shall implement all the necessary
functional, technical, operational and other supporting requirements to meet these services
levels.
This system will provide following (module wise) office automation and content
management support:
Page 29
RFP for Case Management & Tracking System in AG Office MP Volume II
scrutinize different categories of correspondence time to time. Such categories will later be
defined by AG Office.
Following are the functional specification but not limited to for this module:
Page 30
RFP for Case Management & Tracking System in AG Office MP Volume II
previous records)
Case Category
Respondent Departments/Agencies name (Should support selection of
multiple departments/agencies from list items)
3 System should generate unique document ID for the documents just after scanning, so
that same can be written on the top of correspondence.
5 Should have provision to define authorities/sections to forward all the petitions and
correspondence.
7 Should validate if same document is already exists in the system and if so, display an
appropriate message.
8 Should have provision for user friendly viewing and marking the petitions to concerned
advocates.
9 System should have provision for defining maximum number of petitions to mark to an
advocate in a week.
10 System should suggest names of Govt. Advocates to mark a petition on the basis of
Type/Category of Petition and existing workload on Advocates.
11 Should alert the concerned Advocate or clerk through the system to further process the
application
12 Should have provision for Govt. Advocates to view the petition, write comments, issues
instruction to departments and set time limits.
Page 31
RFP for Case Management & Tracking System in AG Office MP Volume II
13 Should have provision to set various parameters under different categories of cases to
record opinion/remark of Govt. Advocate.
16 System should have provision for respondent departments to login using web interface
on AG Office website and respond on petitions with necessary fact and documentary
evidences.
17 System Should have provision for only quick written communication between
concerned advocates and departments.
All the petitions that receive Case Number from High Court, will get transformed in
Case File. Case file is nothing but consolidation of all the documents i.e. Petition, Vakalat
Nama, Affidavit, Return, Rejoinder, Adjoinder, Notices, Communications, instructions issues,
decision taken, etc. that pertain to a particular Case after registration in High Court. All
these documents will be added in due course of life in case file. Core purpose of this module
is to organize all the contents of a case file in structured manner and provide controlled
access to all the users.
Digital record of all the case files is already available with High Court, which will be
shared with AG Office once the application is ready. AG office application should be able to
synchronize case detail from high court server in real time. High Court has also started
scanning of all the case files. Legacy data (Old case files) will take around 2-3 years to be
scanned completely. New cases (petitions) registered from February 2013, are being
scanned in real time by High Court. In this context, AG Office application should be able to
connect High Court server and fetch scanned copies of case files as and when required.
Case file processing module will record all the case proceedings and trigger relevant
workflows as and when required. These workflows may include issuing notices, calling case
diary from respective thana, compliance of interim court orders, etc. If a case is decided
against govt., concerned department/agencies have only two options i.e. either comply
court order or go for appeal/review. Concerned department takes appropriate decision in
consultation with AG Office and Law Department in this regard. If it is decided not to go for
appeal/review, the Case Processing Module will trigger a separate workflow for compliance
Page 32
RFP for Case Management & Tracking System in AG Office MP Volume II
tracking against court order. Concerned Govt. Advocate will define action points and dead-
lines as per court order in the system. These action points can be accessed by the respective
departments to take necessary action in given time-limit and update status of compliance.
Compliance status will be tracked by MIS module and necessary escalations, alerts,
compliance warnings will be generated accordingly. Following are the functional
specification but not limited to for this module:
2 Should create Case file in the system with Case detail and following scanned documents to
be associated in the course of case proceedings:
Court Processing Documents:
o Vakalatnama
o Affidavit
o Computer Sheet
o etc.
Petition
Petition Enclosures
Rejoinder
Return
Additional Facts and Rulings
Case Correspondence Notices, letters, etc.
Any other
3 Should provided dedicated interface for filing new Case, Appeal, Caveat, etc. by AG Office.
4 Should record following detail but not limited to, in due course of case lifecycle:
OIC Detail,
Case Hearing Details like hearing date, Name of H'ble Justice, name of Govt.
advocate appeared in hearing, etc.
Case proceedings after hearing.
Time limits for further actions and concerned actors.
Case file movement detail.
Comments and openings.
etc.
5 Should provide comprehensive view of a case file on single screen.
6 Should provide option for marking and forwarding files with in AG Office.
8 Should trigger various workflows as per case proceedings like issuing notices, calling case
diary in bail cases, compliance of interim court orders, etc. (IA will assess need of such
workflows in FRS/SRS and design them)
Page 33
RFP for Case Management & Tracking System in AG Office MP Volume II
9 Should be able to sync with High Court server for fetching details of newly registered cases
and updating existing cases.
10 Should be able to connect high court server for download of scanned documents
associated with concerned cases.
11 Should provide comprehensive facility for viewing list of files along with detail available
with viewer.
12 Should provide facility for adding personal remarks on protected sharing basis on case files.
13 Should provide following pre-defined option (but not limited to) to set time limits for time
tracking:
File return
Call case diary
Obtain certified copies of record
Obtain copy of Court Order
Call OIC
Compliance of Court Orders.
etc.
14 Once decision is taken in a case and final order is uploaded, the system should provide
interface for defining action points with due dates by concerned Govt. Officer with his/her
opinion.
15 Should provide interface for respective departments to see and record compliance status
on each action point.
16 Should provide facility for preparation of written communication or auto filled forms that
are required in day to day work. Such written communication or auto filled forms may be:
Letter to departments for appointment of OIC and preparation of return.
Letter to call OIC.
Wireless message to call case diary (in predefined format)
Duly filled form for obtaining certified copies.
Any other.
17 Should have provision for adding new forms and templates as per requirement.
18 Should have facility to export letter/forms in .Doc format for manual editing.
19 Should have provision for sending letters/forms to their intended receivers by email.
The system will have intelligent algorithms for case allocation for next hearing on the
basis of Roster, case nature, earlier handled by advocates, workload, expertise, status, etc.
System will fetch Cause List from High Court Server and automatically allocate cases to govt.
advocates. Case files will be accessed online by advocates on 24x7 basis. Some relevant
content related to the cases will also be made available on mobile phone.
Page 34
RFP for Case Management & Tracking System in AG Office MP Volume II
After hearing, the advocates will update status in case file. Respondent departments
and agencies will be informed with desired actions at their level and compliances will be
tracked accordingly. If court issues some order in the hearing, dispatch department of AG
office will be informed to obtain a copy of court order. The system will also facilitate to
perform formalities for obtaining court order copies. After obtaining copy of the court
order, the dispatch department will scan and upload it as another content of respective case
file. Following are the functional specification but not limited to for this module:
1 System should have provision to configure Case Allocation roster prepared weekly by AG
Office.
2 System should also have provision to set/define multiple rules for case allocation like:
Case allocation on the basis of experience and expertise of advocate.
Case allocation as per earlier appearance of govt. advocates in respective cases.
Case allocation as per existing workload of Govt. Advocate.
Case distribution among other govt. advocates in case of concerned advocate is
on leave.
Multiple/separate Case allocation rule sets for:
priority/urgent cases,
as per noting done by appropriate authority, or
cases listed for final hearing.
3 System should be able to synchronize daily/weekly cause list with high court server in real
time.
4 System should be able to allocate case in real time they are being listed by high court
server.
6 System should be able to generate real time case allocation report to each section
(especially WP Section) so that respective case files can be extracted from record room as
soon as possible.
Preparation of Return is the task that requires close coordination between Govt.
Advocates and Respondent Departments/agencies. Application will facilitate this
coordination work by providing only return preparation and submission facility. The
application will initiate this process with issuance a Notice to respondent
Page 35
RFP for Case Management & Tracking System in AG Office MP Volume II
2 Should provide authorization code base login for OICs and Respondent departments.
3 Should provide user interface to submit para-wise reply on the petition/rejoinder to the
User department/OIC.
4 Should allow OIC/department to attach scanned copies of evidences and factual contents
with each reply paragraph of return.
5 Should support multiple files to attach with each paragraph and support all relevant file
formats i.e. PDF, JPG, PNG, DOC, etc.
6 Should provide access to see the return prepared by other respondents on same case and
other departments on similar case.
8 Should provide facility for govt advocate to add guiding instruction with each paragraph,
so that departments can see and follow those while preparation of return.
9 Should provide facility to export paragraph wise return in predefined .DOC file template
for further editing.
Page 36
RFP for Case Management & Tracking System in AG Office MP Volume II
At present, there are more than 3 lakh files available in AG Office Jabalpur, Indore
and Gwalior. These files are stored in common racks located in halls, rooms, corridors, etc.
without proper indexing. Storage capacity of these racks and vaults should be properly
indexed to be able to extract files in minimum time. Case File Management Module of the
application will define and track location of each and every file that is stored in racks and
vaults. Following are the functional specification but not limited to for this module:
2 Should automatically generate a sticker for the shelf. System should allow user to print
the sticker
3 Should allow a new directory / appropriate data structure to be created ,for storing data
about each new case, by providing:
Case number
Shelves where the case file has to be placed
4 Should allow the record keeper to search the case file by providing case number/party
name/ year etc.
7 Should attach the storage details to the case records in the system
Page 37
RFP for Case Management & Tracking System in AG Office MP Volume II
11 Should automatically generate a Receipt form for taking / receiving from the staff
13 Should automatically escalate and send alert, if Case file is not returned by the staff with
the in the stipulated return time
15 Should allow record keeper to extend the return date of the record and provide
notes/comments for the same
16 Should be integrated with Case Allocation Module so that record keeper does not have
feed each case number that is listed for next hearing as well as Govt. Advocate to be
issued the file to.
17 Should arrange the Case Number list for next haring in a way, that enables record keeper
to take shortest way to extract multiple files.
18 Should maintain detailed record of inward and outward record/case file movement.
10.1.6 MIS
1.2 Should allow creation and updating of MIS report templates. An indicative list of reports
to be generated is provided below:
MIS reports (Court Wise/AG Office Wise/Department wise/Case Category Wise/
Subject Category wise)
Cases filed in a specified period of time
Cases Disposed of in a specified period of time
Notices issued in a specified period of time
Returns prepared in a specific period of time
Cases listed for final hearing
Cases pending in a specified period of time
Cases pending for hearing.
Page 38
RFP for Case Management & Tracking System in AG Office MP Volume II
1.3 Should allow configuration of the following properties of the MIS reports:
Frequency of generation
Recipient list
2.1 Should automatically generate and email MIS reports as per defined frequency
2.2 Should allow authorized personnel to generate MIS reports as per need (dynamic
reporting)
3 Reports generated should have various formatting, filtering and other features
3.2 Data extracted from the database should be able to be aggregated to form reporting
fields
3.6 Users should be able to customize reports on demand and shall support filtering,
searching and sorting within a report
3.7 Users should be able to save reports so that they need not be re-generated every time
it is viewed
3.8 Should escalate MIS report on non-compliance to as per the escalation matrix
3.9 Should allow to create favourite list of MIS report by authenticated user
3.10 Should allow to configure the mandatory reports with frequency by the user
3.11 Should allow to configure the format with field level detail of the output reports
3.13 Should not allow to modify/delete the data of the MIS report
Page 39
RFP for Case Management & Tracking System in AG Office MP Volume II
To gauge the performance, the digital dashboards shall be designed to allow user
and senior officers to capture specific data points providing a "snapshot" of performance.
Digital dashboards will act as executive information system and allow users to see multiple
performance parameters on single screen and raise alarms/reminders for major events. The
system will track movement and processing of each and every case file as per defined
timelines. System will also support pre-defined rule-sets and algorithms to track files and
generate alerts accordingly in a way that enables AG Office to take necessary action at
appropriate time.
3 Should view all the critical information for user in dashboard view.
4 Should show all the escalation of service level to users on dashboard view.
7 Should allow user to navigate from dashboard to corresponding MIS reports/ forms on
user action and also drill down and view various reports.
8 Should be able to provide dashboard view with graphs/ charts/ tables etc.
AG office has fully functional Library in each of the three office locations i.e.
Jabalpur, Indore and Gwalior. Each of such library, there are around 25000 book available.
All of these books are related to Law. Every morning, before hearing, law officers require
studying various books and they approach Library. It is very difficult for Library Management
Unit to serve law officers by searching, extracting and issuing books. Hence, Library
Management module should record all the details of books, present this detail before Law
Officers online, provide them facility to search appropriate books, check their availability in
Library, allow them to make request for book issuance online, alert them for return of books
Page 40
RFP for Case Management & Tracking System in AG Office MP Volume II
if dead line is close, etc. Following are the indicative functional requirements for this
module.
1. Should record details of Books and other library material and generate unique code for
each book.
2 Should have provision for adding, modifying, replacing and deleting books from record.
5 Should print a bar coded sticker to paste on book immediately after registration.
7 Should provide local web based interface for users to search books and availability of
same in the library in real time.
9 Should allow quickly record book information using bar code scanner for issuing and
receiving books from concerned user.
10 Should automatically track issued books as per timelines and rules defined by library
policy.
11 Should be able to send SMS alerts to users who delays in returning books.
1 Should have dedicated AG Office Internet Web Portal for all users and separate Intranet
Portal for each AG Office application access.
Page 41
RFP for Case Management & Tracking System in AG Office MP Volume II
2 The portal shall have security and identity management features like User
authentication, authorization, role based access etc.
5 Instruction kits and online help detailing step by step instructions for using the portal,
form filling & submission, Correction facility for commonly encountered errors etc.
7 Facility to fill and submit para-wise return/response online along with attachments.
10 Shall provide powerful search features through the automatic categorization and
indexing functionality as provided by various portal applications.
11 Portal shall provide consistent look & feel to the users and the standards shall be defined
for content, structure and presentation of the portal and these standards should be
applied and followed throughout the portal.
12 It shall provide data caching at multiple levels including page/sections in the page, which
improves the performance of the portal, in terms of the speed at which content is
delivered to users, by caching frequently accessed information.
13 It should have import/export tools as well as APIs that will allow authorized users to
easily manage content and documents during staging, back-up, offline usage and
deployment.
14 It shall provide activity reporting facility for logging the user behavior and profile
information and also provide canned and ad-hoc reporting capabilities of the raw data.
User demographics and content navigation patterns are common reports that shall be
provided based on activity reporting function.
16 Provide a tool for content management and the tool should allow automatic indexing and
searching portal
17 Shall have a separate link for the important websites: Shall facilitate the add links of the
important websites
Page 42
RFP for Case Management & Tracking System in AG Office MP Volume II
19 Ability to support XML, WML, SOAP by the solution to integrate with other systems
20 Should comply with W3C Accessibility Guidelines and GIGW published by Govt. of India.
The functional specifications of the user administration system are provided below:
2 Shall facilitate the system administrator to Add, Delete, Modify, Password reset, Restrict
etc. For the user profiles
8 Ability to provide access level security for Entry forms at Field level - allow, Read only,
Hide
9 Ability to provide access level security for Entry forms at Transaction level -
allow/deny
10 Ability to provide access level security for reports at Transaction level - allow/ deny
Page 43
RFP for Case Management & Tracking System in AG Office MP Volume II
19 Should support defining of fine-grained access control to service, functionality, file, page,
or objects
21 Should allow creation of new user accounts and should seek the general user inputs (as
required by application solution) for the same.
22 Should validate the inputs provided by the user and display an appropriate error message
if any of the inputs is not valid.
23 Should check if new user id to be created is already in use. If so, an appropriate error
message should be displayed
24 Should create a new user if the inputs provided are valid. The new user created must be
granted access to all the requested services. System should automatically generate a
password for the new user and email the login details to the email id provided or support
passwords based on password policies
25 Should allow deactivation of user accounts. The account entries should only be
passivated and should not be removed from the database on deactivation
28 Should have a self service module in which the user can modify his/her
personal/professional details.
29 The solution should have facilities for enforced-change of password after first-time login
including after password reset, automatic password outage after a fixed period of time,
maintenance of unique passwords that neither resemble login ID nor any of the
previously used passwords (last n passwords), a combination of upper & lower cases,
numbers and special characters, be of sufficient strength and not less than 6 characters
in length, etc.
30 The solution should auto-logout the user after a defined period (pre-configurable) of
non-interaction by the user with the system. All such logouts will cause the system to
save the data as a dirty-form for further work after a fresh login by the same user
Page 44
RFP for Case Management & Tracking System in AG Office MP Volume II
All the above requirements are based on our internal study conducted without
keeping any application platform or ready to deploy product in the mind. These
requirements will be refined further during requirement gathering and system. Sole purpose
of defining functional and application level requirements here is to provide a fair idea on
project complexities and resource/solution requirements to that the prospective bidders
can effectively plan their solutions and present same in the bidding process. .
Overall objective of the Case Management and Tracking System, is to track status of
each file at various stages of the Life Cycle of case files. Broadly, at each stage, the system
will record status of case in three parameters i.e. What to do next, Who will do it and By
what time it should be done. Following is a simple and at glance depiction of various stages
of Case File Life Cycle as well as requirements from new system at each level. Since it is a
high level view, various small processes and minor details are omitted from it.
Page 45
RFP for Case Management & Tracking System in AG Office MP Volume II
System automatically generates alerts by SMS and Email. Dashboard updated on real time basis. AG office tracks
Scrutiny and Preliminary Study departments
Obtaining Case No. from High Court Department see the petition online.
Case File Preparation Record Preliminary screening parameters
Start process of Return Preparation if case Connect Court Server to obtain Case No.
Petition Receiving or Filing is critical nature Initiate necessary workflow
Order Compliance
Compliance
End
Page 46
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 47
RFP for Case Management & Tracking System in AG Office MP Volume II
Application
Front Office Desk Mobile Web Portal
Interface
Internet/Intranet
Date Security
Gateways
Layer Layer
SMTP
SMTP
Gateway
Gateway SMS Gateway SSDG Web Gateway
Data Aggregation
Authentication
Policies, Guidelines and Standards
Presentation
Layer
SMTP
Cache Gateway
Management Content Management Personalization
Authorization
Repository
Content
Library
Service Layer
Single Sign-on
Centralized
Database
CCTNS
External linkages Integration with High Court Server
Jail
Above Figure brings out a conceptual architecture of the system. Please note that
the architecture depicted above is holistic representation on implementation of all
components of Application Framework, and not just of a few components. Implementing
agency will be given opportunity to modify this framework in consultation with AG Office
Technical Team for better fitment with the proposed solution.
Page 48
RFP for Case Management & Tracking System in AG Office MP Volume II
10.3.2 Users
The first user group is the application users. Key requirement of the application users
is shown in table below. The users of Application include all the employees of the AG Office.
AG Office Users AG, Addl. AG and Dy. AG Case tracking and issuing online instructions
More users may be added by IA as per requirement of the solution proposed and as per need
generated during system study.
10.3.4 Gateways
The various gateways act as interfaces to the users and service layer. The gateways
include web gateway, SSDG (State Service Delivery gateway), SMS gateway and SMTP
gateway. These gateways essentially enable the access to AG Office services through access
channels.
Page 49
RFP for Case Management & Tracking System in AG Office MP Volume II
The communication between AG Office and other actors that communicate with the
Application is performed via Web Services. The presentation layer components extract the
data from the services and presents to the user in a personalized format. When a user
places any service request, these service interfaces invoke the respective applications and
data returned by the application and presented to the user in a readable format.
This layer basically consists of actual modules of the system in the e-enabled
scenario. Conceptually, the system can be conceived as a synthesis of inter-linked
information systems for the AG Office business areas. In other words, each information
system pertaining to a business area would together make the system. Further it is
proposed and is required through this project to roll out a portal that will, in course of time,
emerge as the most preferred point of reference for information on AG Office. To place this
module in the overall context, the portal is identified as Main Module since this would be
module shared among all the other modules and yet have its own development
requirements.
Security is the critical component of the solution architecture. Single Sign On (SSO)
and Role based access are achieved through the identity assertion, credential management
and directory services components. Security layer components should adhere to the
standards for the security management as prescribed in this volume of the RFP.
Applications and users use this layer for the data access; it contains the data access
logic agents and service agents through Data aggregation component. Data management
shall be performed through the document and content repository. The physical data used by
the system resides in this layer.
Policy and guidelines are the guiding principles for the overall Application
architecture. Any component envisaged should strictly adhere to the policies and guidelines
laid out. The solution shall follow open standards and other technology standards
Page 50
RFP for Case Management & Tracking System in AG Office MP Volume II
The application should easily interface with the external systems. External systems
include High Court (e-Courts), Police (CCTNS), Jail, etc. government systems that interact
with the AG Office. Application should be able to interact with various external systems
through application level integration. It should also be interoperable and should comply
with open standards for an easy integration. At present, State Service Delivery Gateway
(SSDG) project is being implemented in Madhya Pradesh, which may take some time to get
fully integrate with department level eGovernance Systems. The application system should
be able to integrate with SSDG in future. SSDG framework is very generic, which may be
studied on NeGP portal.
AG Offices regularly interact with High Court and most of information necessary for
AG Office Application, is generated by High Court. Scanned copy of case files and court
orders shall also be extracted from High Court Database for AG Office Application. Following
data will be extracted or synchronized from High Court Database:
All the cases submitted in the High Court, comprises a "computer sheet" duly filled by the
appellant, applicant or petitioner or by his advocate. This computer sheet contains following
information
Page 51
RFP for Case Management & Tracking System in AG Office MP Volume II
11) Name & State Bar Council Enrollment Number of other advocate (s) signing
vakalatnama,
12) Particulars of the lower Court, Authority or Tribunal etc., i.e.- (a) name, (b)
designation, (c) case, file / order number, (d) date of impugned judgment / order,
13) Whether the appellant, applicant or petitioner is desirous of getting the matter
settled through any of the alternative modes of dispute resolution,
14) Caveat notice, whether received,
15) Name and signature of the advocate filing main case.
Information in above fields, is recorded in High Court computers. All the case records
related to AG Office will be provided by High Court to AG Office in above fields. IA shall
migrate above information in AG Office system. This information will be updated on periodic
basis from High Court Server. This data will become the initial record of all the case files
available in AG Office. IA will be required to update AG Office information from case files in
the additional fields of this data table. Case number will be the unique reference key for all
the updation and correlation with other data to be received from High Court.
AG Office will also require dedicated application interface for Crime and Criminal
Tracking Network System (CCTNS) project for calling case diaries. Similarly, AG Office may
also require an interface for Jail department to call necessary information for court cases.
10.3.11 Hosting
Expected data size is approximately 500 GB for first 2 years in AG Office Jabalpur and
300 GB for first 2 years in AG office Indore and Gwalior each. Approximately 3 GB Data
would be required for AG Office Web portal in SDC. Data is expected to grow at the rate of
20% per year after 2 year. Solution will be scalable enough to accommodate minimum 10
years of data. Hence a provision of 3 TB storage space should be made in the SDC for same.
Page 52
RFP for Case Management & Tracking System in AG Office MP Volume II
Outline the methodology that will be used for testing the system
Define the various levels or types of testing that will be performed for system
Provide necessary checklist/documentation that will be required for testing the
system
Describe any technique that will be used for testing the system
Describe how the testing methodology will confirm to requirements of each of
the functionalities.
Indicate how one will demonstrate to AG Office that all applications installed in
the system have been tested
11.1 INSPECTION
AG Office shall appoint an officer to conduct a thorough physical inspection of all the
products delivered by the supplier to ensure that the delivered equipment is free from
physical damage including but not limited to crushed or broken equipment, missing seals,
opened packages and incomplete shipments. AG Office reserves the right to return the
products to the Supplier at the suppliers expense.
Physical inspection of hardware will also include physical checking, unpacking and
counting of the delivered equipment by AG Office staff in presence of the IA. Supplied
equipments will only be acceptable as correct when each received item corresponds with
the checklist that will be prepared by the IA (and approved by AG Office or its
Page 53
RFP for Case Management & Tracking System in AG Office MP Volume II
representatives) prior to shipment. Any shortfalls in terms of number of items received may
render the delivered equipment incomplete.
Page 54
RFP for Case Management & Tracking System in AG Office MP Volume II
Errors detected during testing should be logged, classified, reviewed, and resolved
prior to release of the software. Software error data that is collected and analyzed during a
development life cycle may be used to determine the suitability of the software product for
release and installation. Test reports should comply with the requirements of the
corresponding test plans.
The acceptance tests must demonstrate that the Implementation Agency has met
each and every requirement specified within the RFP and contract and has delivered an
effective operational system
Page 55
RFP for Case Management & Tracking System in AG Office MP Volume II
Sign off from the competent authority of AG Office after completion of project
activities like installation of hardware, software, data entry, data migration, data
scanning, training, etc.
All required activities as defined in the bid document including all changes
agreed by AG Office are delivered by the Implementation Agency and accepted
by AG Office.
All required system functionality as defined in the bid document including all
changes agreed by AG Office and delivered by the Implementation Agency and
accepted by AG Office.
All required documentation as defined in this bid document including all changes
agreed by AG Office and delivered by the Implementation Agency and accepted
by AG Office.
All required training as defined in this bid document including all changes agreed
by AG Office and delivered by the Implementation Agency and accepted by AG
Office.
All identified shortcomings/defects in the systems have been addressed to
complete satisfaction of AG Office
Certification by a third party testing agency if appointed by AG Office.
The functional/logical acceptance of the system will only be certified when the
proposed system is installed and configured according to the design and that all the detailed
procedures of operating them have been carried out by the Implementation Agency in the
presence of AG Office Staff.
Page 56
RFP for Case Management & Tracking System in AG Office MP Volume II
AG Office shall nominate STQC for conducting audit and certification, upon
intimation by the IA that the system implementation is complete. AG Office will
bear the cost of STQC certification and payment will directly be made to STQC by
AG Office.
The system shall also be audited through a CERT-in enrolled agency for security
audit. This security audit is essential for application hosting in State Data Centre.
Cost of security audit will born by IA.
The agencies nominated by AG Office shall establish appropriate processes for
notifying the IA of any deviations from the norms, standards or guidelines at the
earliest instance, after noticing the same, to enable the IA to take corrective
action.
IA shall extend all support to AG Office nominated Third Party Audit Agency
(TPAA) for all the activities related to audit and certification.
All changes suggested by the audit agency shall be implemented by the IA upon
acceptance and approval by the AG Office.
Third Party Auditor will issue certificate and on basis of same, AG office will issue
completion certificate to IA.
Page 57
RFP for Case Management & Tracking System in AG Office MP Volume II
In order to effectively perform data assessment and cleaning, it is important that the
data migration team is sufficiently familiar with existing data structures of the source
registers/databases.
The Implementation Agency shall be responsible for digitization of all the records as
specified below. However, Implementation Agency shall be required to estimate the exact
number of registers and quantum of the digitization during assessment of the project
requirements.
The rough estimate of the quantum of work (number of records) for some of the
data elements is mentioned in following Table. Implementation Agency shall
digitize/migrate all case files and service records of AG Offices pertaining to the project.
Bidder should submit data digitization/ migration plan in his/her bid, detailing all the
activities to be performed during the data digitization. Indicative broad activities to be
performed by the Implementation Agency (IA) are as follows
Following table shows the detail of Data Digitization and Migration Requirements
1 Library Books Books Record 75,000 Book record will include Book
Details Name, Publisher, Publishing year,
Category, Type, No. of pages, price,
etc.
Library Book Detail: Estimated size of a record to capture detail of one book is 300
Character.
Case File Proceedings: Estimated size of a record to digitize case proceedings of a single file
is 100 Character. It includes on an average last 5 dates of hearing, Kind of instruction
received from court (if any) in the hearing, Kind of action taken in compliance (if any) after
hearing."
All the original case files remain in custody of respective High Courts. AG Office
maintains a copy of these case files for the purpose of study and processing. Basic
parameters of a case file i.e. Case Number, Petitioners, respondents, case category, subject
matter, filing date, etc. is already digitized by High Court. At present, scanning work of paper
records (of case files) is in process by High Court, which may take 2-3 years to complete. AG
Office will be provided access to this record by High Court. Thus, fresh data entry or
scanning of case files is not required.
Page 59
RFP for Case Management & Tracking System in AG Office MP Volume II
1. Training Team
2. Process & Procedure Team
3. Communication & Other Interventions Team
Effective change agents at the project locations (members of the Change
Management Teams) must possess the skills required to complete the following tasks:
Explain the process and system change and its implications to employees
Focus on the smaller issues of change at AG Office
Solicit and monitor the workforce support for change
Provide honest information regarding the change process
Effective communication mechanism can be an excellent tool for any change
management exercise. During a change process employees are undergoing a transition
phase and are resisting the changing environment for a multitude of reasons. Employees are
the central focus of the change management and communication plan. For successful
project implementation, change management strategies should particularly aim at
supporting those who will be most affected by the change of processes and systems.
Page 60
RFP for Case Management & Tracking System in AG Office MP Volume II
Ensure least resistance from employees with regard to proposed changes in the
processes and systems.
Provide confidence to the employees about the change process and its benefits.
The most common concern of the employees is often "Whats in it for me?"The
communication process should be robust enough to answer the query and provide
employees with the assurance that change is beneficial for them. The following messages
are some of the benefits that employees should gain from Communication and Change
Management exercise:
Page 61
RFP for Case Management & Tracking System in AG Office MP Volume II
Overview of e-Governance
Vision, Objective & Interventions of the Project
Scope of the Project
Proposed Solution
Roles & Responsibilities of officials
Typical workflow envisaged under the Project
Benefits emanating from the project to government officials
The technical trainings are dependent upon the technology finalized and the
implementation plan for the same. Technical Trainings shall mainly be imparted to following
three user groups:
End User: These shall be the groups of employees who will be the actual users of the
technology implemented. End users may vary depending upon the types of users and
the span of control which they will be exercising. End User training will be conducted
when the whole system is ready to be implemented. The aim should be to ensure
that all users of the system are trained at least 2 weeks in advance of the actual
system implementation. End user technical training should be at least 1 days. IA may
increase training duration depending upon the technology implemented.
Process Owner: These will be the employee groups who know the process and can
be termed as "Process Champions". They are aware of the change and can guide
others and help them with issues etc. as and when they crop up. Process Owner
Page 62
RFP for Case Management & Tracking System in AG Office MP Volume II
training should be at-least 1 days which may happen prior or parallel to the process
implementation phase.
Super User Training: Super User Training pertains to the core group who will be the
administrators of the processes, who will grant permissions and give access for extra
modules etc. This user group will need training on certain extra modules which gives
them administrator rights and the usage emphasis as well. There is no minimum
fixed time for this training. IA may decide it as per need and technology
implemented. Ideally, IA should identify Super Users in the initial phase of the
project and involve them in throughout design and development process.
The previous trainings were on general usage of computers, whereas the following training
will happen on the project software itself. This training is for training the operational staff to
enable them posting the data to applications and use the software. This will be a 2 days
training with following contents:
Specific module based training for the concerned process officials on use, working,
authenticity and implementation of access control methods and tools
Implementation Agency should ensure that the knowledge transfer to the staff at AG
Office happens effectively post training, during the project implementation and
maintenance phase as well.
Page 63
RFP for Case Management & Tracking System in AG Office MP Volume II
1. Application maintenance and support services for the solution to meet the
desired service levels
2. Annual Technical Support (ATS) for all the licensed software
3. Warranty & AMC support for all the new hardware procured as part of this RFP
4. Operations and maintenance services for the server and related infrastructure
supplied and commissioned by the IA for the application at the Data Centres.
5. Operations & Maintenance services for Video Conferencing Solution
Page 64
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 65
RFP for Case Management & Tracking System in AG Office MP Volume II
SLA management tool should be able to monitor the all the service levels defined
in the service level agreement.
The proposed solution should provide comprehensive and end-to-end
management of all the components for each service including Network, Systems,
Databases and Application infrastructure.
The proposed SLA management tools should automatically document problems
and interruptions for services and provide the consolidated violations as per the
SLA
The Tool should allow changing the parameters of the measurement and should
allow adding new SLAs on need basis.
SLA management tool should enable the AG Office to have a unified view of the
entire system SLA at single console.
The proposed solution should provide the following performance reports.
o Executive Summary report that gives an overall view of a group of
elements, showing volume and other important metrics for the
technology being viewed.
o Capacity Planning report which provides a view of under-and-over-
utilized elements.
Page 66
RFP for Case Management & Tracking System in AG Office MP Volume II
o Service Level report that shows the elements with the worst availability
and worst response time-the two leading metrics used to monitor SLAs.
o The proposed system must have a built-in report authoring tool which
will enable complete customization flexibility of performance reports.
o The tool should provide an integrated performance view for all the
managed systems and networks along with the various threshold
violations alarms in them. It should be possible to drill-down into the
performance view to execute context specific reports.
The proposed tool should be able to monitor various operating system
parameters such as processors, memory, files, processes, file systems, etc. where
applicable, using agents on the servers to be monitored.
The proposed solution should provide self-monitoring wherein it will track critical
status such as
o CPU utilization
o Memory capacity
o File system space and other important data.
1 System Engineer 1 1 1
Should be qualified as Engineering in Computer
Science or MCA and have at least 2 years of
relevant IT industry experience in the field of
Network / Databases and other related areas. IA
should involve them in all the project activities
since beginning of the project, so that they can
easily take-up and coordinate for Project related
work.
Page 67
RFP for Case Management & Tracking System in AG Office MP Volume II
Public
Confidential
Restricted
Page 68
RFP for Case Management & Tracking System in AG Office MP Volume II
19 Documentation requirements
IA shall be responsible for preparation of documents including User Manuals,
Operations Manual, Administration Manual, Security Manual, Application Support Guide
Page 69
RFP for Case Management & Tracking System in AG Office MP Volume II
and others (if any) as per industry best practices and acceptable standards (e.g. IEEE/ISO
specifications for documentation).
The Implementation Agency must ensure that the Application components being
developed are thoroughly documented with comprehensive manuals and adhere to
standard methodologies in software development as per ISO and/or CMM models. The
documents including but not limited to are:
Quality Assurance Plan Documenting the planned and systematic pattern of all
actions necessary to assure confidence that the software developed will conform
to the AG Office functional and technical requirements.
Interface Control Document Documenting the interface characteristics of one or
more systems and documents agreements between interface owners. It contains
information on both the physical and data element requirements that are
necessary to make the transfer of information between systems feasible.
Test Plan Containing information on the software test environment to be used
for independent testing, the test cases to be performed, and the overall testing
Page 70
RFP for Case Management & Tracking System in AG Office MP Volume II
20 Project Deliverable
The Implementation Agency has to deliver the following deliverables to AG Office as
part of an assurance to fulfill the obligations under the SLA. The table given below may not
be exhaustive and IA is responsible to provide all those deliverables which may be specified
in this RFP but not listed here and those agreed by IA in response to any request from AG
Office. The timelines for producing each of these deliverables will be in line and closely
linked with the overall project timeline as indicated in this RFP. Any conflict with respect to
the project and/or deliverable timelines will have to be resolved by IA in consultation with
AG Office and/or its designated agencies and approved by AG Office. Thereafter the
approved timelines will have to be adhered to by IA, unless specified otherwise.
S.N. Deliverables
Page 71
RFP for Case Management & Tracking System in AG Office MP Volume II
5. Technical / System Design Document (HLD and LLD) including but not limited to
o Logical and Physical Data base Design
o Application architecture, deployment architecture, network
architecture diagrams, security architecture etc.
o Component, and Deployment Views of the Application
o Collaboration, Class diagrams in the UML notations
o Security and Features
o Performance Features
o Interface / Control Design Features
Traceability Matrix
Document on Testing Approach for Application, along with the test cases and
test results.
8 Security policy
Standard Operating Procedures
11 Project Documentation
Page 72
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 73
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 74
RFP for Case Management & Tracking System in AG Office MP Volume II
21.5 SPECIFICATIONS
1. Specification for Data Centre Hardware/Software
Compliance
Type Details
(Y/N)
Latest generation Intel Xeon E5-4620 (2.2GHz/8-core/16MB/95W)
Processor Processor or Equivalent AMD Processor with same or higher Specint rating ,
based on Intel/AMD series chipset. Server Should be scalabe to 4 Processor.
128 GB Memory scalable to at least upto 1TB, using DDR3 Load Reduced
DIMM (LRDIMM) memory modules. Proposed memory should support
Memory
reliably identify and verify whether installed memory has passed the rigorous
OEM qualification and testing process to increase system reliability
Hard disk 2 * 600 GB hot plug SFF SAS drives.
Page 75
RFP for Case Management & Tracking System in AG Office MP Volume II
drive with
carrier
Storage Integrated PCIe 3.0/PCIe 2.0 SAS Raid Controller with RAID 0, 1 with 512MB
Controller of Flash backed write cache onboard.
Networking Dual port 10Gbps network port which supports partitioning up to 4*
features Ethernet ports per 10Gbps port
Interfaces Minimum of 1 * internal USB 2.0 port and
ACPI 2.0
Microsoft Logo certifications
USB 2.0 Support
IMPI 2.0
Secure Digital 2.0
TMP 1.2 Support
Industry IEEE (specific IEEE standards depending on Ethernet adapter card(s) installed)
Standard Advanced Encryption Standard (AES)
Compliance Triple Data Encryption Standard (3DES)
SNMP
SSL 2.0
DMTF Systems Management Architecture for Server Hardware Command
Line Protocol (SMASH CLP)
Active Directory v1.0
PCIe 3.0/2.0
Microsoft Windows 2008 R2
Microsoft Windows 2008 (32 bit and 64 bit)
Microsoft Windows Server 2008 Standard Edition (32 bit and 64 bit)
Microsoft Windows Server 2008 Enterprise Edition (32 bit and 64 bit)
Red Hat Enterprise Linux 5.7 (32 bit and 64 bit)
OS Support
Red Hat Enterprise Linux 6.0 (32 bit and 64 bit)
SUSE LINUX Enterprise Server 11 (32 bit and 64 bit)
SUSE LINUX Enterprise Server 10 (32 bit and 64 bit)
VMware ESX 4.1
VMware ESXi 5.0
Essential tools, drivers, agents to setup, deploy and maintain (not the OS)
Provisioning
the server should be embedded inside the server.
Compliance
Type Details
(Y/N)
2 nos of Intel Xeon E5-2640 v2 (2.0GHz/8-core/20MB/95W)
Processor or Equivalent AMD Processor with same or higher Specint
rating.
64 GB memory scalable to at least upto 512GB, using DDR3
Memory
Load Reduced DIMM (LRDIMM) memory modules.
Advanced ECC with multi-bit error protection supporting
Memory
technologies of memory mirroring and memory lockstep mode
Protection
or Equivalent Technology
Storage Integrated PCIe 3.0/2.0 based SAS Raid Controller with RAID 0, 1
Controller with 512MB of Flash backed write cache onboard.
Networking Dual port 10Gbps network port which supports partitioning up
features to 4* Ethernet ports per 10Gbps port
Page 76
RFP for Case Management & Tracking System in AG Office MP Volume II
Compliance
Type Details
(Y/N)
Intel Xeon E5-2640 v2 (2.0GHz/8-core/20MB/95W) or
Processor
Equivalent AMD Processor with same or higher Specint rating.
32 GB DIMMS scalable to at least upto 512GB, using DDR3 Load
Memory
Reduced DIMM (LRDIMM) memory modules.
Memory Advanced ECC with multi-bit error protection supporting
Protection technologies of memory mirroring and memory lockstep mode
Hard disk
drive with 2 * 300 GB hot plug SFF SAS drives.
carrier
Storage Integrated PCIe 3.0/2.0 based SAS Raid Controller with RAID 0, 1
Controller with 512MB of Flash backed write cache onboard.
Networking Dual port 10Gbps network port which supports partitioning up
features to 4* Ethernet ports per 10Gbps port
Page 77
RFP for Case Management & Tracking System in AG Office MP Volume II
Page 78
RFP for Case Management & Tracking System in AG Office MP Volume II
The indicative general configurations for the server and other are provided below.
The specifications are indicative and the Successful Bidder must fine-tune and provide
detailed specifications and numbers as per requirements of the system proposed. The
Successful Bidder should also propose the specifications of any additional servers and other
hardware, if required for the system.
Features common for all hardware items
All components shall be rated for continuous operation.
Availability of spares and support for the system for the complete period of the
contract.
The Bidder shall provide all other H/W items that are not explicitly mentioned
herein but are required to fulfill the intended specifications by the Bidder in the
bid.
The Specifications parameters are indicative and any item of higher rating will be
preferred.
All servers (systems) shall be of same make.
The server farms for all the critical components in the architecture including web,
application, database, DNS etc shall build redundancy in servers (with primary and
backup servers) in high-availability mode, which facilitates server backup. The
primary and backup servers, can be implemented in either active-active or active-
passive mode. But, the sizing of each server or total number of servers
implemented for the solution shall ensure no performance degradation, even if a
particular server is unavailable.
No item should be offered whose end-of-sale has been declared by the OEM or has
been declared to be under phase out.
Page 79
RFP for Case Management & Tracking System in AG Office MP Volume II
All events and changes applied to the device configurations shall be audited and
logged.
The proposed devices shall provide support for alerting the proposed solution and
also provide support for syslog and SNMP.
The proposed devices shall support roles based access controls and assignment/
delegation of privileged access.
The device shall be capable of supporting configuration that will disable in-secure
services or network services that should not be required for use.
Unattended access or idle connections to the proposed devices shall have time-
outs after a time interval of 5minutes.
The proposed devices shall support IPV 4 and IPV6 both.
The devices shall allow out of band access for management and administrative
functions.
The IA shall put in place all necessary information security controls when out of
band access is not required.
The proposed devices shall be capable of being managed by Command Line
Interface and SSH.
The proposed devices shall support configuration of the Network Time Protocol
(NTP).
The proposed switches shall support configuration of File Transfer Protocol (FTP),
Trivial File Transfer Protocol (TFTP) or Secure Copy (SCP) enabled file transfers.
The proposed switches shall support local and remote port mirroring features.
The proposed devices shall support an easy-to-use management interface using a
graphical user interface.
The proposed devices shall have remote monitoring capabilities to monitor for
device and port status.
The proposed devices shall support real time notification user access to
management console system.
The proposed devices should provide support for at least 128 bit Secure Sockets
Layer (SSL) encryption.
Compliance
Type Details
(Y/N)
Intel Core i5-650, 2.93 GHz, 4 MB L3 Cache and 1066 MHz FSB /
CPU
AMD Phenom II X2 555, 6 MB L3 Cache, 4000 MHz HT or higher
Chipset Intel 5 series / AMD or better
Memory 2 GB 1066 MHz or higher DDR2 RAM with 4 GB Expandability
Page 80
RFP for Case Management & Tracking System in AG Office MP Volume II
Hard Disk
500 GB Serial ATA HDD.
drive
Monitor 17" TFT (or above upto 19") Digital Color LED/LCD Monitor
Keyboard Bilingual (Hindi & English) Keyboard with 104 or higher keys
Mouse USB Optical Mouse, Two button Scroll
6 USB Ports (with at least 2 in front), 1 Serial, Audio ports for
Ports
microphone and headphone in front.
Cabinet Mini Tower
DVD ROM
8X or better DVD Writer
Drive
Networking 10/100/1000 on board integrated Network Port with remote
facility booting facility remote system installation, remote wake up.
Product Windows 7 & Linux Certification. However UL and FCC
Certifications Certification is preferable
ISO 9001-14001, ISO 9001-2008, Should be in the list of Top
OEM 5 Desktop brands as per IDC report published for India
Certifications during year 2010. However Greenpeace international
certification is preferable
Power Screen Blanking, Hard Disk and System Idle Mode in Power
Management On, Set up Password, Power supply SMPS Surge protected.
Compliance
Type Details
(Y/N)
Speed 28 PPM Legal (21.5 x 35.5) or higher
Processor 400 MHz or higher
Resolution Min. 1200 x 1200 dpi
Duty Cycle Min. 50,000 page / month
Memory 64 MB or higher
Interface USB 2.0 (High Speed) with USB Cable
Network Yes (10/100Mbps)
Duplex Yes
Paper support A4
Page 81
RFP for Case Management & Tracking System in AG Office MP Volume II
Compliance
Type Details
(Yes/No)
Resolutions 600x600 ( in DPI)
Speed 40 PPM or more
Document Feeder ADF and Flat Bed
Document size Minimum A4 through Flat Bed. Legal paper through ADF
Document feed
75 sheets legal size
tray capacity
Duty Cycle 1500 pages
Page 82
RFP for Case Management & Tracking System in AG Office MP Volume II
Compliance
Type Details
(Yes/No)
Printing Method Direct Thermal Transfer and Thermal Transfer Printing
Resolution 200 DPI or higher.
Memory 8 MB Flash and 16 MB DRAM or better
Print Speed 8 inch per second or better
Max. Print width 4 inch or higher
Must have USB 2.0 or higher with RS-232C serial port and
Connectivity
bi-direction parallel interface
Fixed reflective sensor, adjustable transmissive sensor
Media Sensors
media characteristics
Ribbon Length 450 meter per roll or higher
Ribbon Type Resin, (Should also support wax type ribbon)
Media Type Continuous, die-cut, tags
Operating
0 to 40 degree Celsius
temperature
Operating
20-85% non-condensing
Humidity
Graphic Support User defined fonts and graphics
Barcode Should be able to print 1D barcodes on sticky paper.
Display Should have 240X128 pixel display or more
Programmable
Should have programmable key.
key
Compliance
Type Description (Y/ N)
Page 83
RFP for Case Management & Tracking System in AG Office MP Volume II
Capacity 1 KVA
PWM using MOSFET / IGBT ( Indicate the make,
Technology capacity and other technical details of the
MOSFET/IGBT)
A. MAINS MODE
1. AC INPUT
1. Voltage 160 to 270Volts
2. Frequency 50 Hz + 3 Hz
2. AC OUTPUT
200V to 245V (with AVR). The output voltage should be
within 200V to 245V range at any point of time during
input window of 160V to 270V. Please mention type of
1. Voltage Window AVR.
2. Frequency Sync to Mains
B. INVERTER MODE (Output)
230 volts + 5% during all condition in inverter mode like
1. Voltage
Full load to no load, backup period etc.
2. Frequency 50 Hz + 0.5 Hz
3. Load Power Factor 0.6 (Lag)
4. Output Load 600W for 1 KVA
5. Wave Form Quasi Sine wave
6. Inverter Efficiency 65 % (on full rated capacity of UPS at 0.6 load PF)
7. Total Harmonic
Distortion 22%
Battery Bank
1. BATTERY VRLA (Sealed Maintenance Free )
2. Minimum Battery
20 minutes on full load
Backup
3. Battery End Cell > 10.5V (None of the Battery should be discharge
Voltage below 10.5V)
4. Battery Cabinet Inbuilt
UPS cabinet should of minimum 1mm thick material and
5. UPS Cabinet should be free from sharp edge, scratches, nicks, &
burs etc.
PROTECTIONS
Electronic current limit in inverter mode & Fuse/MCB in
1. Short Circuit
mains mode.
2. Surge/Spikes Through Line Filters
Page 84
RFP for Case Management & Tracking System in AG Office MP Volume II
Compliance
Type Details
(Y/N)
IEEE 802.3 Ethernet, IEEE 802.3u Fast Ethernet,
Standards IEEE 802.3x Flow Control, Compatible with all major
network software.
Network
RJ 45 UTP - 10/100BaseT
Interface
Switching
Store and forward
Method
Switch Fabric 4.8 Gbps
Page 85
RFP for Case Management & Tracking System in AG Office MP Volume II
Compliance
Details
(Y/N)
19 Wall mount, 9 U height
Proper ventilated with One Fan, One Cable Manager, Power Distribution Unit of 6
No. (5 and 5 Amp) Sockets with surge protection, Mounting Accessories,
Compliance
Type Details
(Yes/No)
24 or 12 port patch panel as per requirement,
Type Unshielded Twisted Pair, Category 6, ANSI/TIA/EIA 568-
B.2.1
Category Category 6
Circuit Identification Port Labeling for port identification on each of 24-ports
Scheme
Port Identification Labels on each of 24/48-ports (to be included in supply)
Height 1 U (1.75 inches)
Modular Jack 750 mating cycles
Compliance
Type Details
(Yes/No)
1-port, Shuttered, White, with surface box for surface
Type
mount applications, Category 6,TIA/EIA 568-b Category
Material ABS/Polycarbonate
No. of ports One
Protection Shutters
Identification To be supplied with label for port identification
Page 86