COMPLETION OF A PROJECT. THIS WILL REQUIRE HAVING A COLLATERAL PROPERTY OR INVESTMENT TO BACK UP THE REQUIREMENTS OF THE SURETY AGENCY. A PERFORMANCE BOND IS USUALLY ISSUED BY A BANK OR AN INSURANCE COMPANY, PERFORMANCE BOND REQUIREMENTS SURETY AND FINANCIAL INSTITUTIONS HAVE DIFFERENT REQUIREMENTS DEPENDING ON THE CAPACITY OF THE CONTRACTOR, THE VOLUME OF THE PROJECT BEING INSURED AND THE PROJECTS CHALLENGES. USUALLY THEY ASK FOR THE FOLLOWING: AT LEAST TWO YEARS OF CPA PREPARED FINANCIAL STATEMENTS. COPY OF THE CONTRACT THAT IS BEING AWARDED. APPLICATION OF THE SURETY. IF YOU OWN REAL ESTATE, IT WILL HELP YOU AND WILL ACCELERATE THE PROCESS. HOW DO THEY WORK? GOVERNMENT REQUIRES PERFORMANCE BONDS AND PAYMENT BONDS FOR PROJECTS TO PROTECT THE TAX PAYERS INVESTMENT. THE PRIVATE SECTOR ALSO REQUIRES THE ISSUANCE OF PERFORMANCE BONDS. COMMON PERFORMANCE AND PAYMENTS BONDS FOR GOVERNMENT PROJECTS CONSIST OF BUILDING BRIDGES AND ROADS. IF THE CONTRACTOR DOES NOT COMPLETE THE PROJECT SPECIFIED IN THE CONTRACT THE SURETY BONDING COMPANY WILL EITHER PAY FOR THE COMPLETION OF THE PROJECT OR HIRE A CONTRACTING FIRM TO COMPLETE THE PROJECT. WHY THE PERFORMANCE BONDS ARE NEEDED?
A PERFORMANCE BOND WILL PROTECT THE OWNER AGAINST
POSSIBLE LOSSES IN A CASE A CONTRACTOR FAILS TO PERFORM, OR IS UNABLE TO DELIVER THE PROJECT AS PER ESTABLISHED AND THE CONTRACT PROVISIONS. SOMETIMES THE CONTRACTOR DEFAULTS OR DECLARES HIMSELF IN BANKRUPTCY, AND THEN IN THOSE SITUATIONS THE SURETY IS RESPONSIBLE TO COMPENSATE THE OWNER FOR THE LOSSES. SUCH COMPENSATION IS DEFINED AS THE AMOUNT COVERED UNDER THE PERFORMANCE BOND. HOW PAYMENT CAN BE GIVEN TO OFFSET DEFAULT?
PAYMENT FROM THE PERFORMANCE BOND IS AVAILABLE ONLY TO
THE PROJECT/PROPERTY OWNER. NO ONE ELSE CAN MAKE CLAIMS AGAINST IT. IN ORDER FOR A PERFORMANCE BOND TO BE EFFECTIVE, THE CONTRACT MUST BE SPECIFIC ABOUT THE WORK TO BE DONE. A CONTRACTOR CANNOT BE HELD ACCOUNTABLE FOR VAGUE DESCRIPTIONS THAT ARE OPEN TO INTERPRETATION. MERITS/DEMERITS OF PERFORMANCE BONDS MERITS OWNER OF A PROJECT IS ASSURED OF THE COMPLETION OF THE PROJECT. OWNER DOES NOT NEED TO INCUR ADDITIONAL COSTS. DEMERITS THE SURETY TRIES TO ESTABLISH-OWNER DID NOT COMPLY WITH THE TECHNICAL CONDITIONS OF A BOND TO AVOID PAYING THE COMPENSATION. SURETY WILL TRY TO PROVE-OWNER MAY HAVE TO SETTLE FOR THE LEAST EXPENSIVE REMEDY TO THE PROBLEM. THE OWNER NEEDS TO QUANTIFY THE LOSSES THAT MIGHT HAVE BEEN SUFFERED WHEN A TRADER OR CONTRACTOR FAILS IN THEIR PERFORMANCE. IF THE OWNER UNDERESTIMATES THE LOSSES AND THE FUTURE COST OF THE COMPLETION OF THE PROJECT IS HIGHER, THE OWNER MAY NOT BE ABLE TO RECOVER THE SHORTFALL FROM THE SURETY. COLLATERAL SECURITY DEFINITION: COLLATERAL SECONDARY, SUBORDINATE, OR SUPPLEMENTARY ITEM ACCOMPANYING A PRIMARY ITEM. EXAMPLE: 1. SPECIFIC ASSET (SUCH AS LAND OR BUILDING) PLEDGED AS A SECONDARY (AND SUBORDINATE) SECURITY BY A BORROWER OR GUARANTOR. 2. THE PRINCIPAL SECURITY IS USUALLY THE BORROWER'S PERSONAL GUARANTY, OR THE CASH FLOW OF A BUSINESS. 3. EXCEPT FOR HIGHLY CREDITWORTHY CUSTOMERS (WHO CAN GET LOANS AGAINST ONLY THEIR SIGNATURES) LENDERS ALWAYS DEMAND A COLLATERAL IF THE PRIMARY SECURITY IS NOT CONSIDERED TO BE RELIABLE OR SUFFICIENT ENOUGH TO RECOVER THE LOAN IN CASE OF A DEFAULT. HOW IT WORKS? A LIEN IS CREATED WHEN THE COLLATERAL IS REGISTERED IN THE PUBLIC RECORDS OFFICE, GIVING THE REGISTERED LENDER PRIORITY OVER OTHER LENDERS ON THE SAME ASSET OR PROPERTY. LENDERS HAVE THE LEGAL RIGHT TO SEIZE AND SELL A COLLATERAL IF THE BORROWER CANNOT PAY BACK THE LOAN AS AGREED. SOMETIMES THE ASSET BEING FINANCED (SUCH AS ACCOUNTS RECEIVABLE, INVENTORY, MACHINERY) IS ITSELF USED AS A COLLATERAL; IN HOME MORTGAGES THE PROPERTY BEING BOUGHT SERVES AS A COLLATERAL. TYPES OF COLLATERAL WHAT TYPES OF COLLATERAL ARE AVAILABLE? ALL FORMS OF PROPERTY, WHETHER TANGIBLE OR INTANGIBLE, INCLUDING: IMMOVEABLE PROPERTY MOVEABLE PROPERTIES, EQUIPMENT/MACHINES/MATEIALS, SHARES AND OTHER SECURITIES, BANK ACCOUNTS, CONTRACTUAL RIGHTS, RECEIVABLES AND INTELLECTUAL PROPERTY CAN BE USED AS COLLATERAL IN INDIA, SUBJECT TO APPLICABLE LAWS AND CONTRACTUAL ARRANGEMENTS. ADVANCE PAYMENT BONDS:WHEN? 1. IF THE CLIENT AGREES TO MAKE AN ADVANCE PAYMENT (SOMETIMES REFERRED TO AS A DOWN PAYMENT) TO A SUPPLIER, A BOND MAY BE REQUIRED TO SECURE THE PAYMENT AGAINST DEFAULT BY THECONTRACTOR. THIS IS REFERRED TO AS AN ADVANCE PAYMENT BOND (APB), ADVANCE PAYMENT GUARANTEE OR ADVANCE STAGE PAYMENT. NATURE? 2. AN ADVANCE PAYMENT BOND WILL NORMALLY BE AN ON-DEMAND BOND, MEANING THAT THE BONDSMAN PAYS THE AMOUNT OF MONEY SET OUT IN THE BOND IMMEDIATELY ON DEMAND, WITHOUT ANY PRECONDITIONS HAVING TO BE MET. THIS IS AS OPPOSED TO A A CONDITIONAL BOND (OR DEFAULT BOND) WHERE THE BONDSMAN IS ONLY LIABLE IF IT HAS BEEN ESTABLISHED THAT THERE HAS BEEN A BREACH OF CONTRACT. TO MEET HIGH PROCUREMENT COSTS 3. TYPICALLY ON A CONSTRUCTION PROJECT AN ADVANCED PAYMENT BOND WILL BE REQUIRED BY THE CLIENT IF THE CONTRACTOR REQUESTS ADVANCE PAYMENT TO HELP THEM MEET SIGNIFICANT START UP ORPROCUREMENT COSTS THAT MAY HAVE TO BE INCURRED BEFORE CONSTRUCTION BEGINS. FOR EXAMPLE WHERE THE CONTRACTOR HAS HAD TO PURCHASE HIGH-VALUE PLANT, EQUIPMENT OR MATERIALS SPECIFICALLY FOR THE PROJECT. CIRCUMSTANCES AND MODE? THE BOND WILL PROTECT THE CLIENT IN THE EVENT THAT THE CONTRACTOR FAILS TO FULFIL ITS CONTRACTUAL OBLIGATIONS, FOR EXAMPLE IF THE CONTRACTOR BECOMES INSOLVENT.
ADVANCE PAYMENT BONDS MUST BE VERY CAREFULLY DRAFTED TO
SET OUT THE CIRCUMSTANCES FOR PAYMENT AND TO MAKE CLEAR THAT THEY ARE ON-DEMAND BONDS. RETENTION MONEY AND DEFECT LIABILITY PERIOD. WHAT? RETENTION MONEY- A SUM DEDUCTED AT EACH MONTHLY PAYMENT NOTICE. WHY? TO PROVIDE THE CLIENT WITH SOME SECURITY THAT THE CONTRACTOR/SUB-CONTRACTOR WILL RETURN TO CORRECT ANY DEFECTS DURING THE DEFECTS LIABILITY PERIOD, OR DEFECTS LIABILITY PERIOD. WHAT IF? THE CONTRACTOR/SUB-CONTRACTOR DOES NOT RETURN TO CORRECT THE DEFECTS THEN THE RETENTION HELD MAY BE USED TO FUND THE PAYMENT OF OTHERS TO CORRECT THE DEFECTS. SO WHAT? IT IS ADVISABLE TO CHECK THE CONTRACT ON THE ABILITY TO DO THIS, AND THE RELEVANT NOTICES THAT SHOULD BE GIVEN TO THE INCUMBENT CONTRACTOR PRIOR TO APPOINTING OTHERS TO UNDERTAKE THE WORKS. AMOUNTS OF RETENTION MONEY
THE LEVEL OF RETENTION HELD IS USUALLY A PERCENTAGE OF THE
VALUE OF THE CONTRACT WORKS.
IT IS GENERALLY APPLIED TO THE VALUE OF THE CONTRACT WORKS,
INCLUDING VARIATIONS AND CHANGES, NOT JUST TO THE CONTRACT SUM.
SOME CONTRACTS ALSO CONTAIN RETENTION FREE AMOUNTS AND
THEREFORE THE CONTRACTOR CAN BE PAID UP TO A CERTAIN SUM PRIOR TO THE RETENTION BEING DEDUCTED. CAP?
SOMETIMES CONTRACTS WILL PLACE A CAP ON THE
MAXIMUM LEVEL OF RETENTION THAT CAN BE DEDUCTED. FOR EXAMPLE, THIS COULD BE THREE TO SIX PER CENT OF THE CONTRACT PRICE/LUMP SUM.
OTHER LIMITS OR CAPS MAY BE SET AS TO THE MAXIMUM AMOUNT
OF RETENTION THAT MAY BE DEDUCTED FROM PAYMENTS. THE FIDIC AND NEC FORMS OF CONTRACT DEMONSTRATE THIS. RELEASE OF RETENTION MONEY? IT IS ADVISABLE TO CHECK THE DETAILS OF THE INDIVIDUAL CONTRACTS AS RELEASE IS SLIGHTLY DIFFERENT IN EACH. THE RELEASE OF RETENTION IS DIFFERENT IF THERE IS SECTIONAL COMPLETION, PARTIAL POSSESSION OR THE LIKE UNDER THE CONTRACT. PART RELEASE OF RETENTION MONEY GENERALLY, PART RETENTION RELEASED UPON COMPLETION OF THE WORKS. REMAINDER RELEASED WHEN RECTIFICATION PERIOD OR DEFECTS LIABILITY PERIOD EXPIRES AND THE RELEVANT CERTIFICATION UNDER THE CONTRACT HAS BEEN ISSUED TO CONFIRM THIS. MAJORITY OF CONTRACTS ALLOW FOR PARTIAL RELEASE OF THE RETENTION AT EACH SECTIONAL COMPLETION. MAJORITY OF CONTRACTS ALSO ALLOW FOR PARTIAL RELEASE OF RETENTION UPON PARTIAL POSSESSION BY THE CLIENT/EMPLOYER. FINAL RELEASE OF RETENTION MONEY THE FINAL RELEASE WILL VARY BETWEEN CONTRACTS. MAY BE RELEASED EITHER: AT THE EXPIRY OF THE DEFECTS LIABILITY PERIOD FOR EACH SECTION OR THE EXPIRY OF THE DEFECTS LIABILITY PERIOD FOR THE WORKS AS A WHOLE. SUB-CONTRACTORS SHOULD REVIEW CONTRACTS TO DETERMINE WHEN THE RELEASE IS TRIGGERED. THIS MAY BE BY: COMPLETION OF THE SUB-CONTRACTOR'S WORKS OR THE MAIN CONTRACTOR'S WORKS. IF CONTRACT TERMINATED? CONTRACT BE REVIEWED FOR THE EFFECT UPON RETENTION IN THE EVENT THE CONTRACT IS TERMINATED.
GENERALLY CLAUSES-RELEASE OF RETENTION CEASE
DO APPLY IN EVENT OF TERMINATION BUT MAY VARY DEPENDENT ON THE REASON FOR TERMINATION AND THE CONDITIONS OF CONTRACT. TIMELY RELEASE OF RETENTION MONEY FOR QUANTITY SURVEYORS OR PROJECT MANAGERS RUNNING MULTIPLE CONTRACTS OR PROGRAMMES OF WORK- ADVISABLE TO SET UP A TRACKING PROCESS OF RETENTION FOR CLIENTS AND CONTRACTORS/SUB-CONTRACTORS. AVOID LATE RELEASE OF RETENTION OR A SURPRISE PAYMENT REQUIRED BY A CLIENT/EMPLOYER. INTEREST WILL BECOME DUE FOR LATE RELEASE OF RETENTION MONIES, ONCE CONTRACTUAL PREREQUISITES HAVE BEEN COMPLETED. ALTERNATIVES TO RETENTION MONEY. OPPOSITION FROM CONTRACTORS AND SUBCONTRACTORS TO THE USE OF RETENTION IN MANY AREAS AS THERE IS A VIEW THAT THIS IMPACTS UPON CASH FLOW.
RECENT MOVEMENT FROM CLIENTS AND
EMPLOYERS, PARTICULARLY IN THE PUBLIC SECTOR, TO SUPPORT THIS. ALTERNATIVES TO RETENTION MONEY. REMOVAL OF RETENTION PROVISIONS WITHOUT THE USE OF AN APPROPRIATE BOND IS NOT A DECISION TO BE TAKEN LIGHTLY.
SHOULD BE THOROUGHLY REVIEWED WITH THE
CLIENT/EMPLOYER WITH A CLEAR EXPLANATION OF THE RISKS PRIOR TO PURSUING THIS ROUTE. ALTERNATIVES TO RETENTION MONEY RATHER THAN DEDUCT A PHYSICAL SUM FROM A CONTRACTOR'S INTERIM PAYMENT, POSSIBLE TO PROCURE A RETENTION BOND TO COVER RETENTION THAT WOULD OTHERWISE HAVE BEEN DEDUCTED. RETENTION BONDS GENERALLY ISSUED IN FAVOUR OF CLIENT/EMPLOYER WHO HAS WAIVED HIS RIGHTS, UNDER THE CONTRACT, TO DEDUCTION OF CASH RETENTION AMOUNTS. BONDS GENERALLY SET TO THE STANDARD LEVELS OF RETENTION WHICH WOULD OTHERWISE BE CONTAINED IN THE CONTRACT. MODULE III - DISPUTES AND CLAIMS Salient Contract clauses. Form of Consent and Agreement Possession of site & RFA Condition of Project Site Documentation and Compliance Drawings Contract Duration Milestones Salient Contract clauses Taxes & Duties Changes Valuation of variations Procedure of claims Suspension Events of Default and Termination Salient Contract clauses Construction Programme Payment Schedule / BOQ Certificates and payment Electricity and Water Testing Contd. Salient Contract clauses Mediation Rules Works Delay Damages Extension of Time Defects Liability Change in legislation Guarantees & Insurance Force Majeure NEED FOR DISPUTE AVOIDANCE ? HIGH CONSTRUCTION LITIGATION COSTS. DISPUTES & ADVERSARIAL RELATIONSHIP CAN KILL A PROJECT LITIGANT CONTRACTORS ARE UNWELCOME NON PRODUCTIVE ROOT CAUSE ANALYSIS OF DISPUTES 1. BIDDING/CONTRACT STRUCTURE/TYPE/ DOCUMENTS 2. SCOPE ILL DEFINED 3. UNCERTINTIES-SITE, SOIL, NATURAL CAUSES, UNFORESEEN OBSTRUCTIONS, DESIGNS, CHANGES 4. TOUGH COMPETITION 5. NON FULFILMENT OF OBLIGATIONS 6. NON ADHERENCE TO CONTRACT 7. INEXPERIENCED STAFF & POOR CONTRACT MANAGEMENT 8. DELAYS & LOSSES FACTORS PERTINENT TO CLIENTS FINANCIAL ABILITY/ FINANCIAL ARRANGEMENT FOR THE PROJECT PREVIOUS WORKING RELATIONSHIP CATEGORY ( PUBLIC, PRIVATE) PRIORITY TO CONSTRUCTION TIME SPECIFIED SEQUENCE OF COMPLETION POSSIBLE CHANGES TO INITIAL DESIGN/SCOPE FACTORS PERTINENT TO CONSULTANTS
COMPLETENESS AND TIMELINESS OF PROJECT
INFORMATION BUILD-ABILITY OF DESIGN PROVISION FOR EASE OF COMMUNICATION PREVIOUS WORKING RELATIONSHIPS PRIORITY ON CONSTRUCTION TIME FACTORS PERTINENT TO CONTRACTORS
AVAILABILITY OF SUITABLE MANAGEMENT
TEAM/EQUIPMENT GIVEN FIRM'S CURRENT WORK LOAD. PROGRAMMING CONSTRUCTION WORK. PREVIOUS PERFORMANCE OF SITE MANAGEMENT TEAM NO OF SUB-CONTRACTORS EXTERNAL FACTORS WEATHER REGULATIONS STATUTORY UNDERTAKES ( WATER, GAS, ENVIRONMENTAL ETC..) UNFORESEEN CONDITIONS EXTERNAL FACTORS, MISHAPS, OTHER ACTS OF GOD INTERNAL FACTORS HANDING OVER OF SITE FREE OF ENCUMBRANCES CLEARANCES FROM STATUORY BODIES ISSUE OF GOOD FOR CONSTRUCTION DRG POWER PERMITS AND NOC FINALISATION-DESIGN MIX, MATERIALS/SAMPLES, METHOD STATMENT TIMELY SURVEY , LAYOUT AND WORKING DRAWINGS POOR & UNFAIR DOCUMENTATION IN GENERAL, DESIGN- DRAWINGS & SPECS. CASHFLOW/FUNDS-INADEQUATE OR IMPROPER RESOURCES..? INTERNAL FACTORS TIMELY DECISIONS/APPROVALS BILLS CERTIFICATION VARIATIONS-SETTLEMENT OF RATES, EXTRA ITEMS, QUANTITIES, ESCALATION ETC. OTHER SUB CONTRACTORS/AGENCIES POOR PROJECT MANAGEMENT DISPUTE AVOIDANCE PRACTICES
SELECTION OF KEY PERSONNEL (CONTRACTOR,
CONSULTANT AND CLIENT) TEAM APPROACH ULTIMATE GOAL-TIMELY DELIVERY, GOOD QUALITY & REASONABLE PROFIT TO CONTRACTOR STAGES: PRE AWARD AND POST AWARD MACRO AND MICRO PLANNING AND CONTROL GOOD CONTRACT ADMINISTRATION DISPUTE AVOIDANCE PRACTICES-PRE AWARD-PRE TENDER STAGE 1. SURVEY & INVESTIGATIONS 2. DESIGN & SPECS 3. SITE 4. TENDER PROCESS 5. CONTRACT DOCUMENTS 6. STANDARD CONDITIONS OF CONTRACT 7. RISK MANAGEMENT 8. DISPUTE RESOLUTION ARRANGEMENTS 9. BUDGET ESTIMATES DISPUTE AVOIDANCE PRACTICES-PRE AWARD
REALISTIC TIME OF COMPLETION
REALISTIC COST OF PROJECT ADEQUATE TIME FOR SUBMISSION OF BIDS DETAILED SITE INVESTIGATIONS BY CONTRACTORS OWNERS REQUIREMENTS UNAMBIGOUS WELL DEFINED BASE LINE REQUIREMENTS CAPABILITY MATCHING BY CONTRACTORS: RESOURCES FOR THE DURATION, TECHNICAL SPECS, DESIGNS, SCOPE, LEGAL AND ADMIN ISSUES DISPUTE AVOIDANCE PRACTICES-POST AWARD
SITE MANAGEMENT BY CONTRACTOR
ENGINEERS TIMELY TECHNICAL AND CONTRACTUAL DECISIONS/APPROVALS PROJECT DIRECTOR/MANAGER OF CLIENT TO FOLLOW UP APPROVALS FROM STATUORY AUTHORITIES AND VARIATIONS ADDITIONAL ITEMS/FRESH RATES/TIME EXTENSION TEAM WORK HOW?
WORK PROGRAMME-THE KEY TO AVOIDING DELAYS AND
DISPUTES CHANGES AND VARIATIONS TIMELY PAYMENTS GOOD COMMUNICATION PRACTICES PERIODIC REVIEW TRUST GOODWILL AND COOPERATION IMPACT OF DELAY AND DISRUPTIONS CURRENT TIGHT MARKET CONDITIONS, THIN MARGINS, AND STRAINED PROJECT BUDGETS.
ALL STAKEHOLDERS FACE INCREASING
PRESSURE TO COMPLETE PROJECTS ON- TIME AND ON-BUDGET. IMPACT OF DELAY AND DISRUPTIONS DEMANDING CONTRACT TERMS, ONEROUS GOVERNMENT REQUIREMENTS/FINANCIAL INSTITUTIONS AND LEGAL ISSUES IN DEALING WITH THE RISKS OF PROJECT DELAYS. IMPACT OF DELAY AND DISRUPTIONS SUCCESSFUL PROJECT MANAGEMENT DEMANDS MORE CLOSELY PLAN, MONITOR, AND ANALYZE CONSTRUCTION PROGRESS, THE IMPACT OF DESIGN CHANGES, WEATHER ISSUES ETC. INCREASE RISK OF DELAYS AND UNEXPECTED COSTS. STRATEGY DEALING WITH DELAYS AND DISRUPTIONS UNDERSTANDING CRITICAL CONTRACT REQUIREMENTS RELATED TO PLANNING AND SCHEDULING SCHEDULE MANAGEMENT. ANALYZING AND IDENTIFYING THE CAUSE OF ACTUAL OR POTENTIAL DELAYS.