EI 364 Vetco Tree Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
Burlington 346 4,200 WROV Uncle John
#3 Vetco Riser System Decommission and wellhead explosive severance.
EW 914 Vetco Tree Thru Tubing Subsea Well Slickline, E-line, cementing, fluid services, and wellhead
Tatham 984 4,000 WROV Uncle John
#2 Vetco Riser System Decommission explosive severance.
EW 915 Vetco Tree Thru Tubing Subsea Well Slickline, E-line, cementing, fluid services, and wellhead
Tatham 945 4,200 WROV Uncle John
#1 Vetco Riser System Decommission explosive severance.
VK 697 Diver/ Dril-Quip Wellhead Subsea Well Decommission of a TA EZSV services, cementing, TCP gun system and
Amerada Hess 689 900 Uncle John
#1 WROV EZSV Riser System well. wellhead explosive severance.
VK 740 Dril-Quip Wellhead Subsea Well Decommission of a TA EZSV services, cementing, TCP gun system and
Amerada Hess 936 600 WROV Uncle John
#1 EZSV Riser System well. wellhead explosive severance.
Cameron Spool
GB 387 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 2,750 WROV Tree Uncle John
SB-1 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 387 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 3,594 WROV Tree Uncle John
SB-2 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 387 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 6,212 WROV Tree Uncle John
SB-3 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 388 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 1,463 WROV Tree Uncle John
SA-1 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 388 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 1,617 WROV Tree Uncle John
SA-2 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 388 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 2,955 WROV Tree Uncle John
SA-3 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 388 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 3,089 WROV Tree Uncle John
A-2 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 388 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 1,100 WROV Tree Uncle John
A-1 Decommission and wellhead explosive severance.
FMC Riser System
FMC Tree
MP 145 Diver/ Set isolation sleeve, Flow or P&A, Slickline, E-line, cementing, coiled tubing, fluid services
Conoco 210 200 Tubing riser W Uncle John
#5 WROV result P&A and wellhead explosive severance.
SenTree 3
FMC Tree
GB 70 #1 Diver/ Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
Newfield 750 3,500 FMC Riser Uncle John
Sea Star WROV Decommission and wellhead explosive severance.
System
FMC Tree
GB 71 #2 Diver/ Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
Newfield 750 489 FMC Riser Uncle John
Sea Star WROV Decommission and wellhead explosive severance.
System
FMC Tree Tubing hanger & tree transfer from
GB 70 #2 Diver/ Slickline, E-line, cementing, coiled tubing, fluid services
Newfield 750 0 FMC Riser previous well, Subsea Well Uncle John
Sea Star WROV and wellhead explosive severance.
System Decommission of a TA well.
National Tree
EHI 327 Diver/ Thru Tubing Subsea Well Slickline, E-line, cementing, fluid services and wellhead
Kerr McGee 211 330 Tubing riser W Uncle John
#4 WROV Decommission explosive severance.
SenTree 3
Permanent abandonment of
18-3/4" W/Head
ST 316 temporarily abandoned well required
Petrobras 550 0 WROV Tubing riser W Uncle John E-line, cementing, coiled tubing, fluid services
#1 drilling 115 feet top cement plug with
SenTree 3
Coil tubing
Subsea Well SCSSV lock out and
VK 783 Vetco Tree
Shell 1,475 2,900 WROV installation of wire line retrievable Uncle John Slickline and pumping services.
Tahoe #4 Vetco Riser System
SCSSV
FMC Tree Thru Tubing Subsea Well
HI A-373 Diver/ Slickline, E-line, cementing, fluid services, and wellhead
Enron 360 3,500 FMC Riser Decommission FlowLine Pigging and Uncle John
#1 WROV explosive severance.
System Decommission
VK 697 Diver/ Dril-Quip Wellhead Subsea Well Decommission of a TA EZSV services, cementing, TCP gun system and
Amerada Hess 689 900 Uncle John
#1 WROV EZSV Riser System well. wellhead explosive severance.
VK 740 Dril-Quip Wellhead Subsea Well Decommission of a TA EZSV services, cementing, TCP gun system and
Amerada Hess 936 600 WROV Uncle John
#1 EZSV Riser System well. wellhead explosive severance.
Cameron Spool
GB 387 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 2,750 WROV Tree Uncle John
SB-1 Decommission and wellhead explosive severance.
FMC Riser System
Cameron Spool
GB 387 Thru Tubing Subsea Well Slickline, E-line, cementing, coiled tubing, fluid services
EEX Corp 2,200 3,594 WROV Tree Uncle John
SB-2 Decommission and wellhead explosive severance.
FMC Riser System
1
Gulf of Mexico Riser Based Plug and Abandon Well History
FMC Tree
HI 370 Subsea well decommissioning tree E-line, cementing, Slickline, fluid services, Coil tubing,
Kerr McGee 380 0 WROV FMC Riser Q4000
#1 recovery and flowline abandonment well head explosives
System
Vetco Tree
HI 378 Subsea well decommissioning tree E-line, cementing, Slickline, fluid services, Coil tubing,
Kerr McGee 330 0 WROV Vetco Riser Q4000
#1 recovery and flowline abandonment well head explosives
System
EI 309C Re-entry of platform P&A wells to E-line, cementing, Slickline, fluid services, Coil tubing,
Forest Oil 350 0 WROV Drill Pipe Riser Q4000
(6 wells) carry out final isolation of the wells. well head explosives
7-3/8 Intervention Subsea well decommissioning tree Slickline, E-line, cementing, coiled tubing, fluid services,
Chevron GC 136#7
1100 1000 WROV Riser System recovery, installation of EZSV and Q4000 EZSV c/w TCP gun and wellhead severance
Texaco Shasta
Cameron Spool mechanical cutting of wellhead. w/mechanical cutting.
Ewing Bank Vetco Wellhead Re-enter subsea well, complete upper Perforating, cementing, mechanical and explosive
EOG 380 0 WROV Q4000
827#1 EZSV Riser System P&A cut and remove wellhead cutting.
7-3/8 Intervention
GC 516#1 Secure lower zone, open upper zone Slickline, pumping and testing services, with coil tubing
ENI 3815 7000 WROV Riser System Q4000
Yosemite by manipulation of sliding sleeves and e-line as standby.
Cameron Spool
7-3/8 Intervention
GC 472 Secure lower zone, open upper zone Slickline, pumping and testing services, with coil tubing
ENI 3815 7000 WROV Riser System Q4000
King Kong by manipulation of sliding sleeves and e-line as standby.
Cameron Spool
Dril Quip subsea
EB 114 Abandon well and remove PLET. Slickline, eline, pumping cementing EZSV and wellhead
Unocal 712 650 WROV tree with drillpipe tie Q4000
#4 Production zone already isolated cutting. CT annulus hook up for circulation
back riser
Chevron VK 864 DrilQuip Wellhead Final abandonment of T&A wells Well head tooling, EZSV and drill guns, Slickline, E-
850 0 WROV Q4000
Texaco #1 EZSV Riser System including wellhead removal 15 bml Line, pumping
Chevron GB 191 Vetco Wellhead Final abandonment of T&A well Well head tooling, EZSV and drill guns, Slickline, E-
660 0 WROV Q4000
Texaco #1 EZSV Riser System including wellhead removal 15 BML Line, pumping
2
Gulf of Mexico Riser Based Plug and Abandon Well History
3
Gulf of Mexico Riser Based Plug and Abandon Well History
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell GC 200 #4 Troika 2600 2 WROV Analysis and Decommission
7 3/8" IRS 2012 and specialized tooling.
Cameron HXT Well Q4000 Slick Line, pumping, coil tubing, coil tubing fishing and
ERT GC 237 T 3 2060 2 WROV Casing Pressure /T&A
Ops 7 3/8" IRS 2012 milling tools, tree personnel and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell GB 341 Habanero 2015 2 WROV Decommission
7 3/8" IRS 2012 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Anadarko EB 688 #7 3795 2 WROV P&A
7 3/8" IRS 2012-2013 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Anadarko EB 688 #6 3788 2 WROV P&A
7 3/8" IRS 2013 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Anadarko EB 688 #8 3786 2 WROV P&A
7 3/8" IRS 2013 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Anadarko AT 37 7919 2 WROV P&A
7 3/8" IRS 2013 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell MC 810 UI 2 3943 2 WROV T&A
7 3/8" IRS 2013 and specialized tooling.
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell MC 810 PI 1 3853 2 WROV T&A
7 3/8" IRS 2013 and specialized tooling.
FMC Tree, Custom Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell GC 20 Gyrfalcon 880 2 WROV T&A
TRT 2013 and specialized tooling.
MC 899 A5 FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell 4393 2 WROV P&A
Crosby 7 3/8" IRS 2013 and specialized tooling.
4
Gulf of Mexico Riser Based Plug and Abandon Well History
FMC HXT Well Ops Q4000 E-Line, Slick Line, pumping, coil tubing, tree personnel
LLOG GB 378 SS03 2045 2 WROV P&A
7 3/8" IRS 2013 and specialized tooling.
Q4000
MC 810 P7 E-Line, Slick Line, pumping, coil tubing, tree personnel
Shell 3645 2 WROV Well Ops 7 3/8" IRS P&A 2013 /
Princess and specialized tooling.
2014