Académique Documents
Professionnel Documents
Culture Documents
Authors: Michael Gleeson, [2014] Sean Kelton, [2014] Thomas Considine, [2014] and Tahir Kapoor [2015]
Contents
[hide]
1 Introduction
4 Taxes
5 Depreciation
8 Annualized Costs
10 Conclusion
11 References
Introduction
Once equipment and operating costs are estimated, preliminary cash flow estimations can be
performed to determine if the process is economically viable. When evaluating the long term
economic return of a business, it is important to consider taxes, depreciation and amortization, and
the time value of money. Once all economic factors are estimated, a discounted cash flow analysis
can be used to quantitatively determine the economic return of the process.
The following are "back of the envelope" type calculations for economic return of a project. These
measures are quick and easy because they ignore some of the more complicated parts of evaluating
a project including factors such as depreciation, time value of money and taxes.
Payback Time
The payback time is defined as the period of time (in years) required to break even on the initial
economic investment. It is given by the equation:
Where is the payback time for the project, is the total investment required for the project
and is the average annual cash flow generated by the project. This calculation is used to
determine how quickly the project's fixed costs (i.e. land, machinery, etc.) can be recovered from the
project. A small payback period is desirable for a new project.
Return on Investment
The regular return on investment (ROI) involves complicated tax and depreciation calculations.
However, the pre-tax ROI is much simpler. It is given by the equation:
Where ROI in this case is the pre-tax ROI, C is the pre-tax cash flow generated by the project and I is
the total investment required fro the project. This calculation, as it sounds, is a measure of the
percentage return on the initial investment required for a project (typically the fixed costs, explained
above). A higher ROI is a more profitable project.
Project cash flows, much like it sounds, are the annualized cash flows, or revenue, generated from a
new project. The first year of a project's cash flow is typically negative because the money is spent
on initial investment. At first there will be a small expenditure on research and design expenses from
engineering. Once the design is finished and construction is set to begin the expenditures will rapidly
increase. These expenses may include things such as initial cost of renting or purchasing
space/land, equipment & materials, initial labor to build a plant, etc. All in all research, design,
procurement and construction, all which must be done prior to start up, will typically take 2-4 years.
At this point the project will have reached maximum investment and typically has the most negative
sum of cash flows.
The first year after start up, cash flows begin to become positive, however, the cash flows in the first
year are usually reduced comparatively to years after. This is due to unexpected problems within the
project/process. Typically machine down time, maintenance,etc. will be greatest in this year, causing
the project to run under capacity. After the first year all of the problems within a process have begun
to be discovered and resolved and so the process can run at full capacity with increase cash flows.
From this point on, the only improvements in project cash flows come from process improvements
(i.e. six sigma analysis, etc.), however, by using these techniques project cash flows can become
greater year over year.
Toward the end of the life of a project, cash flows can begin to tail off in magnitude once again due to
outdated equipment, new competition, or other increases in operating costs. Finally when a project is
terminated there is a small additional cash flow related to the recovery from any assets such as
equipment, land, etc. can all be resold or scrapped, however, there will also be some amount of
costs related to deconstruction and land remediation (due to pollution or other harmful project
outputs). Typically the recovered assets outweighs these costs.
A typical cash flow diagram of a project relating the cumulative cash flows over the life of the project
is shown in the figure below.
Figure 1: Cash Flows Diagram. Taken from ChE 351 powerpoint slide 11 (written by Jennifer Cole)
for class instruction. Slides presented on Oct. 5, 2013.
As seen in Figure 1, the cash flows follow the pattern described in the paragraph above. The break
even point of the project is the point at which the cash flows cross the x-axis. The life of the project is
given by the duration of the graph.
Taxes
Chemical production facilities are subject to the same financial levies by the government as all
corporations. Specifically, corporations typically pay income taxes, and may collect incentives based
on state and federal regulations. Detailed tax filings are almost always conducted by the accounting
or financial department of a corporation. When preparing process economics estimations, taxes
should be included, however all final cost estimates reported to management should be prepared by
the appropriate specialist (Douglas, 23).
Corporate Taxes
While tax codes can vary from state to state, and from county to county. Looking at the federal tax
rate is one measure of the tax rate. Federal tax rates for different income are detailed in the table
below. It is important to note that taxes are levied on income only and not on revenue.
0 to 50,000 15%
Many companies have much lower effective tax rates due to tax breaks and loopholes. When
deducting taxes, simply assuming a corporate tax rate of 35% can greatly overestimate the amount
of taxes that a company pays. A better estimation of tax rates would be to find the effective tax rate
of similar publicly traded corporations. The tax rate of any publicly traded company can be found on
their quarterly reports (Form 10-Q) or their annual reports (Form 10-K) filed with the SEC. Below are
some effective tax rates of major chemical companies for 2014 (2013 for The Dow Chemical
Company). [2]
Company WACC
Investment Incentives
Local, state, and federal governments generally encourage capital investments by corporations.
Financial incentives afforded to corporations include low interest loans, free capital for research and
development, and tax holidays for new technologies.
Recently, large investment incentives have been provided for green energy technologies. The major
federal program responsible for green investment incentive, comes in the form of a tax credit for
green technologies. Valid until December 31, 2016 the following technologies can be used to claim
tax incentives.
Many other investment incentives are available to companies making large investments, but they are
extremely difficult to estimate and are often very specific depending on location and type of project.
Depreciation
Depreciation, in the colloquial sense, is the loss of value of an item. As it pertains to the chemical
process industry, depreciation is the loss of value due to "wear and tear" of the components and
facilities of the plant. It is important to note that this does not include working capital or land.
Economics of Depreciation
Depreciation can be thought of as a yearly expense that the plant incurs. It can then be considered a
cost, effectively reducing the income and thus the income tax. However, depreciation is not an actual
cash flow. There is no transfer of money.
where is the taxes due; is the gross profit; is the depreciation; and are the taxes due.
Two commons methods of calculating depreciation are discussed in the next sections.
In this method, the depreciable value is written off over the total life of years at a constant
linear rate:
Therefore, the book value , or the initial cost of the item minus the accumulated depreciation
charges, at year , can be defined as:
where is the initial cost of the item.
Therefore we can say that over the three years, the compressor has cost the process a difference of
$750, which can be taken out of the taxable income.
Money that is available now is inherently more valuable than the same amount in the future, because
that money could be used as capital for an investment that earns interest.
Capital that is available in the future is said to be "discounted". The present value of money, which is
discussed in further detail in the coming sections, is a discounted amount of the future value:
Where is the Present value, is the Future value, and is the discount factor.
The discount factor, which takes into account an estimated interest rate gained on present money, is
calculated for every year :
This implies that the a given amount of money in the future has less value as the length of future time
increases, and as the expected amount of interest that current capital could gain increases. See Net
Present Value for more information on this subject.
Of additional interest is the different between the time value of money and inflation. It is important to
note that these two concepts are completely different. Inflation is the yearly rate at which the price of
a certain good will increase (Biegler, 169). Although the mathematics and calculations are similar,
inflation is generally a result of socioeconomic factors increasing the supply of money, and not the
potential interest rate gained on current capital.
where = cash flow in year n and = project lifetime and i is the discount rate as a decimal.
(Towler 407). If the net present value is equal to zero, the return of the project is equal to the return
that the discount rate would provide. (Peters 328). There are several drawbacks to NPV; it does not
measure bang for buck, and it cannot be optimized unless an upper bound is set to the plant size.
where i' is the DCFROR. DCFROR is useful for comparing projects of different sizes and for
comparing projects to other investments. (Towler 408).
Year: 1 2 3 4 5 6 7 8 9 10 11 12
$ $ $ $ $ $ $ $ $ $
Revenue $- $-
38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00
Capital $ $
Expenditure (45.00 (40.00 $ - $- $- $- $- $- $- $- $- $-
s ) )
$ $ $ $ $ $ $ $ $ $
Operating
$- $- (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00
Costs
) ) ) ) ) ) ) ) ) )
$ $ $
Depreciatio $ $ $
$- $- (17.00 (27.20 (16.32 $- $- $- $-
n (9.79) (9.79) (4.90)
) ) )
$ $ $ $ $ $ $ $ $
Taxes $- $- $ 0.35
(2.61) (2.81) (4.70) (4.70) (6.12) (7.54) (7.54) (7.54) (7.54)
$ $
Free Cash $ $ $ $ $ $ $ $ $ $
(45.00 (40.00
Flow 23.39 26.35 23.19 21.30 21.30 19.88 18.46 18.46 18.46 18.46
) )
Annualized Costs
Annualized Cost is another way of comparing capital expenses with future cash flows where the
capital expense is converted into a recurring annual capital charge. It is useful for comparing the cost
of assets with different lifetimes. (Towler 411). This is very similar to the way that mortgages are
amortized over a 15 or 30 year lifetime. Annual payment can be represented as:
where P is the principle investment, n is investment period, and i is the discount rate. The annual
capital charge ratio can be defined as:
It is the fraction of the principle that must be paid each year to recover the investment at the target
interest rate.
Small changes in the discount rate, can cause large fluctuations in future cash flow. When projecting
project cash flows many years in the future it is essential that an accurate discount rate is chosen to
get a reasonable cost estimation. A simple estimation of the discount rate is to set it equal to the
interest rate received from bonds. This simple estimation will often yield a result greatly
under a value needed for a good cost estimations because in the modern financial economy, cash
deposits yield minimal interest rates. Many other forms of higher yielding securities are available to
investors and a good discount rate should combine the interest from many different sources rather
than just cash deposits.
[3]
Generally, WACC is described by the following formula:
where is the number of sources of capital (securities, types of liabilities); is the required rate
of return for security ; and is the market value of all outstanding securities .
The WACC is often simplified to include only debt and equity. Thus it can be written as
where is the total market value of shareholders equity, is the total market value of
debt, is the cost of equity, and is the cost of debt. [4]
Cost of Equity
The cost of equity is analogous to the returns that shareholders expect in return from giving a
company their equity through share purchases.
where is the risk free rate of return that investors in stable securities such as US treasury bonds
can expect. is a commonly used factor describing the companys stocks correlation with the
general market. is the risk premium, the rate of return that investors expect by investing in a
[5]
stock rather than a more stable class of security. A risky company will have a higher risk premium.
Cost of Debt
The cost of debt, , is either a fixed or variable rate that a company pays to a lender. This rate has
been renegotiated and can be easily looked up. Since debt is tax deductible, taxes are often
discounted.
WACC equation
Many of the inputs required to calculate WACC can be easily obtained from a publicly traded
companys financial statements. An example of some WACCs of major chemical companies as of
2/6/15 are shown in the following table. [6]
Company WACC
Year: 1 2 3 4 5 6 7 8 9 10 11 12
$ $ $ $ $ $ $ $ $ $
Revenue $- $-
38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00 38.00
Capital $ $
Expenditure (45.00 (40.00 $ - $- $- $- $- $- $- $- $- $-
s ) )
$ $ $ $ $ $ $ $ $ $
Operating
$- $- (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00 (12.00
Costs
) ) ) ) ) ) ) ) ) )
$ $ $
Depreciatio $ $ $
$- $- (17.00 (27.20 (16.32 $- $- $- $-
n (9.79) (9.79) (4.90)
) ) )
$ $ $ $ $ $ $ $ $
Taxes $- $- $ 0.35
(2.61) (2.81) (4.70) (4.70) (6.12) (7.54) (7.54) (7.54) (7.54)
$ $
Free Cash $ $ $ $ $ $ $ $ $ $
(45.00 (40.00
Flow 23.39 26.35 23.19 21.30 21.30 19.88 18.46 18.46 18.46 18.46
) )
Total Equity,
Total Debt,
Cost of Debt,
Cost of Equity,
Unlike total equity, total debt and the corporate tax rate, the cost of debt and the cost of equity are
not concrete numbers that are reported by most publicly traded companies. The cost of debt can be
calculated by using the amount of interest that a company pays on their total debt while the cost of
equity can be calculated by estimating the risk free rate, the risk premium for a market and the beta
of the company. The risk free rate and the risk premium can vary slightly from model to model, but
the beta is easily obtained from any financial website.
To calculate the cost of debt and the cost of equity we need the following information.
Cost of Debt,
Total Debt,
Interest Payments,
Cost of Equity,
Beta,
Risk Premium,
Many of these variables can be easily obtained by examining Dow Chemicals corporate filings. To
find, , , , and , we can look at Dows annual report for 2014 found via the SEC.
(http://www.sec.gov/Archives/edgar/data/29915/000002991515000011/dow201410k.htm)
To calculate the cost of equity, the risk free rate and the risk premium need to be estimated. US
treasury bonds are typically used as the benchmark for a risk free investment and the yield for a 10
year treasury bond was taken to be the risk free rate. The risk premium was taken to be the average
return of the S&P 500 stock index over the previous 10 years. Finally the beta was obtained from
Yahoo Finance.
Beta 0.75
With all necessary parameters obtained, we can estimate Dow Chemicals WACC:
After WACC is obtained, we can compare the NPV using the WACC as the discount rate vs using the
10 year AA corporate bond rate as the discount rate.
The NPV using the 10 year AA corporate bond rate of 2.78% was found to be 90.73 in the previous
example.
WACC 55.51
Conclusion
Measures of economic return are vital in the design phase of an engineering project. Companies will
perform simulations to project capital and operating cost expenditures along with revenue generation,
and use the resulting data to perform economic analyses, such as NPV, payback period, or
discounted cash flow analysis. Based on the results of this analysis, the project will either be
scrapped or it will be given the go ahead to begin granular design and construction. These measures
of economic return can be very sensitive to the tax rate, discount rate, and other financial factors and
it is very important to provide reasonable values of these parameters to get an accurate economic
return. Measures of economic return provide a quick way for companies to determine the feasibility of
a project, and therefore are extremely valuable.
References
Navigation menu
Log in / create account
Page
Discussion
Read
View source
View history
Go Search
Navigation
Textbook Home
About This Text
Wiki Editing Help
CMS/Blackboard
Recent Changes
Tools
What links here
Related changes
Special pages
Printable version
Permanent link
Page information
This page was last modified on 8 March 2015, at 17:57.