Vous êtes sur la page 1sur 116

SHERATON HOTEL

BANANI, DHAKA

BILL OF QUANTITIES
Tender Package No: SHD-ASC-PMC-TDO-PA-ID-01
ID WORKS FOR LVL 1 ENTRANCE LOBBY & L-12 MAIN LOBBY

The Employer The Engineer / Project Manager


Unique Hotel & Resorts Limited (SBD) Ascentis India Projects P. Ltd.
Unique Oval, 45 Kemal Ataturk Avenue Gurgaon, Haryana
Banani, Dhaka- 1213, Bangladesh
Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Transfer Lobby @ L-1
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

D DECORATIVE LIGHT WORKS : -

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
DATE 30-05-17
Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Transfer Lobby @ L-1

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :
BasicrateswherevergivenintheBOQareformaterialdeliveredat
siteinclusiveofalltaxesdutiesandleviesasapplicable.Adjustment
ofBasicratestobedoneaspertenderdocument.
TheContractorshallstudydrawings,FFEbooklet,notesbefore
quotingtherates.TheContractorhastosubmitindent(Quantity&
make)forallthematerialsuppliedbyEmployer.
Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedinthe
BOQareindicativeonly,subjectedtochange.
Contractorhastoprepareshopdrawingsforalltheworksandto
ensurethatpanelingisfactoryfinishedtotheextentpossible.

Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.
Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingstomatch
theoverallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQ PA-ID - Transfer Lobby @ L-1 1


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied works as
mentioned below including all required floor preparation/cleaning
before fixing, bedding with cement mortar 1:4 (1 Cement : 4 Coarse
Sand) of minimum 20 mm thick with required lines/levels and slopes,
cleaning after laying of stone, watering, curing etc. complete. Rates
to be applicable for all levels, heights, leads & lifts, shifting / re-
1.1.1
shifting of material from store to the place of fixing. No extra is
payable for additional thickness of bedding to match adjoining floors,
as per directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints with
white cement & matching color pigment, mirror
polishing/honing/other finish (whichever mentioned in following
items) , making of edges, protection of floor with Cello Bubble guard
board and removing the same before handing over etc. complete as
pertheapprovedpatterns,designs,specification&drawings.

Contractor's quoted rates to include the marking of MEP fixtures and


service installations on floors, walls , including making cutouts and
provisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage due to
pattern. Payment will be in Sqm for visible finished floor area only.
Measurement to be verified as per actual site condition. (Note:
Stone will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items)

With18mmthickGreyGranitestoneofpolishedfinishasper
a. ST-101 PS11_PL_005 Sqm 73
approvedsample.
With18mmthickGreyGranitestoneofhonedfinishasperapproved
b. ST-103 PS11_PL_005 Sqm 127
sample.

Itemsameas1.1.1butstonepicestobecutintostripsofvarying
1.1.2
width&tobefixedasperpatternasshownindrawing.

With18mmthickGreyGranitestoneofhonedfinishasperapproved
a. ST-103 PS11_PL_005 Sqm 13
sample.

Itemsameas1.1.1butstonetobefixedindoorthresholdasshown
1.1.3
indrawing.

BOQ PA-ID - Transfer Lobby @ L-1 2


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
With18mmthickGreyGraniteStoneofHonedfinishasper
a. ST-103
approvedsample.
i) 250mmwide PS11_PL_005 Rmt 1
ii) 455mmwide PS11_PL_005 Rmt 10

1.2 Stone Skirting & Cladding


Receiving and fixing of stone in skirting/cladding on Wall/Jamb/allied
works of brick walls / concrete walls / columns as mentioned, in line
and level using backing with 20 mm thick cement mortar 1:3 (1
Cement : 3 Coarse Sand) to the required lines, levels, pattern and
plumbs, pointing the joints with white cement & matching colour
pigment of approved sample as per specification, including all
required surface preparation, cleaning after fixing etc. complete.
Rate to be applicable for all levels, heights, leads & Lifts, shifting / re-
shifting of material from store to the place of fixing. As per directions
and to complete satisfaction of the Project Manager. Contractor has
to perform the work as per the approved pattern, specification &
drawings.

Rate quoted by the contractor to include all labor and materials,


polishing, moulding, making of edges including necessary supports,
marking of MEP fixtures and service installations on floors, walls,
providing cutout & provisions for template like electric points,
junction boxes, switches and power sockets , sanitary fixtures and
accessories etc. complete as per the approved patterns, designs,
specification&drawings.

(No extra will be payable towards additional material wastage due to


pattern. Payment will be as per actual measurement only.
Measurement to be verified as per actual at site.) (Note: Stone will
be supplied by Client free of cost. Reconciliation statement
need to submit for each & every client supplied items)

1.2.1 Skirting
200mmhighskirtingwith18mmthickFlamedGreyGranitestoneof
a. ST-102 PS11_IE_103 Rmt 9
approvedsample.

1.2.2 Cladding
PS11_IE_101,
a. ST-102 With18mmthickFlamedGreyGranitestoneofapprovedsample. Sqm 341
102,103

1.3 Stone Beading Profile

BOQ PA-ID - Transfer Lobby @ L-1 3


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing of stone moulding profile in line and level using
backing with 20 mm thick cement mortar 1:3 (1 Cement : 3 Coarse
Sand) to the required lines, levels, pattern and plumbs, pointing the
joints with white cement & matching colour pigment of approved
sample as per specification, including all required surface
preparation, cleaning after fixing etc. complete. Rate to be applicable
for all levels, heights, leads & Lifts, shifting / re-shifting of material
from store to the place of fixing. As per directions and to complete
satisfaction of the Project Manager. Contractor has to perform the
workaspertheapprovedpattern,specification&drawings.
Rate quoted by the contractor to include all labor and materials,
polishing, making of moulding profile as per pattern etc. all
complete as per the approved patterns, designs, specification &
drawings.
(Note: Stone will be supplied by Client free of cost.
Reconciliation statement need to submit for each & every
client supplied items)

1.3.1 ST-101 75x20mmthickprofilemadeofGreyGranitestoneofpolishfinish. PS11_IE_103 Rmt 9

Addition/deductionforfixingofstonewithchemicaladhesiveinstead
1.4 Sqm RO -
ofcementmortarof1:3(1cement:3coarsesand).

1.5 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made of
stainless steel strip (grade 316) of approved sample at the
MT-101 intersection different types of flooring materials, in line and level, PS11_PL_005 Rmt 18
including anchoring, fixing, cutting, bending,Polishing etc. complete
tothesatisfactionofProjectManager.

SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQ PA-ID - Transfer Lobby @ L-1 4


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling with
G.I. frame work consisting of G.I. 22 gauge main channel
(50x30mm) with molded ends up to 900mm c/c and G.I. 22 gauge
cross channel (20x60mm) at 300mm c/c suspended from the R.C.C.
slab with adjustable G.I. sheet suspenders (in main areas and
narrow strips etc.), applying cast-in-situ plaster of Paris over rabbit
wire mesh fixed to cross runners, including making of cove, groove,
including framework & base ply etc., providing extra framework & ply
NA support/template for electrical fittings, A/C
diffusers,speaker,projector screen and any other cut-outs, making
provision of trap doors ;proving & fixing of wooden shadow battens
(holloc wood, black enamel painted - 25x40mm) at wall
peripheries and ends etc., including scaffolding etc. complete as per
detailed drawings & upto satisfaction of Project manager. (A groove
shall be provided at all the junctions of horizontal and vertical
corners).( Note : The framework may be changed as per site
requirementormanufacture'sspecification.)
Note: surface area to be measured for vertical bands of coves only if
the Vertical height exceeds 200 mm . Within 200 mm verticals , the PS11_PL_003 Sqm 40
Planareatobemeasuredandpaid

2.1.1 NA Itemsameas2.2.1butceilingtobemadeindoubleheightlevel. PS11_PL_003 Sqm 182

PS11_PL_003,
2.1.2 NA Itemsameas2.2.1butmakingoflightcoveasshownindrawing.
PS11_DT_20
a. Size:200x100mmhigh Rmt 3
b. Size:200x75mmhigh Rmt 46

2.2 Gypsum False Ceiling

Contractor/Supplier to submit material sample and technical


specification of the specified item from the manufacture for prior
approvaloftheProjectManager/Architectasnecessary.

BOQ PA-ID - Transfer Lobby @ L-1 5


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all
levels & height including reveal, bulkheads, making coves, all
shaped, sized, profiled to details shown on the drawings. The false
ceiling shall be suspended / fixed to the RCC ceiling / MS structure,
with approved GI framing / suspensions / supports etc. as per
manufacturer's specification or as required. Rate to include cost of all
labors, installations, hardware / like & materials not specified
elsewhere, trims, metal inserts (U Channel) on edges /corner of
ceiling and wall for showing grooves, provision for trap doors,
finishing of joints with proprietary jointing compound, in line and
levels etc. all required for completion and to the PM's approval. Rate
quoted to include all cutouts/templets required for light fixtures,
smoke detectors etc., all complete as per design, drawing,
manufactures specification & satisfaction of project manager.( Note :
VisibleexecutedfalseCeilingAreatobemeasuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures and


Service installations cellings, including making cutouts and provisions
oftemplateswhereverrequired. -

Providing&fixingfalseceilingcomprisingof12.5mthickgypsum
boardfalseceilingasperdetailanddrawing,includingallnecessary
fixingarrangementetc.completeasshownindrawinganddirected
2.2.1 NA bytheProjectManagerincludingmakingverticals,reveals,fillingand Sqm RO -
finishingthetaperedandsquareedgesoftheboardswithjointing
compoundandpapertapeetc.complete(asperrecommended
practicesofIndiaGypsumorequivalent).

2.2.2 NA Itemsameas2.1.1butceilingtobemadeindoubleheightlevel. Sqm RO -

Itemsameas2.1.1butceilingtobemadeofmoistureresistant
2.2.3 NA Sqm RO -
gradeGypboardinsteadofstandardgradeGypboard.

Itemsameas2.1.1butverticalgypsumpartition(Airtightpartition)
2.2.4 NA tobemadeoverfalseceilinglevelasdirectedbytheProject Sqm RO -
manager.
Extraoveritemno2.1.1to2.1.4forproviding&fixingofply
2.2.5 NA Nos RO -
templateofrequiredsizeforlightfixture/otherservicework.

2.3 Mirror Ceiling

BOQ PA-ID - Transfer Lobby @ L-1 6


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of mirror ceiling finished with 6mm Thick clear
mirror pasted over commercial ply fixed to hardwood framing of
minimum 50 x 50mm @ 600 mm c/c including all materials, labour,
MR-101 PS11_PL_003 Sqm 7
wastage, adhesive, nails, screws, making provision of MEP fixtures &
all necessary fixing arrangements etc. complete as per design
drawing&satisfactionofprojectmanager.

2.4 Trap Door

Providing & fixing Trap door made of 12 mm commercial ply &


finished with 6 mm MDF ready to receive paint to match the gypsum
ceiling. The trapdoor edges to be finished with 8mm thick teak wood
lipping. The item is inclusive of making of groove all around the trap
door, any frames with necessary support structure from the ceiling
Sqm 4
for resting the trap door shutters over framework and provision for
accessing units/machines fixed above it and with provision of slots
for return air and a thin black painted GI mesh behind the slots, tools
and tackles etc. required to complete the work to the satisfaction of
theProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint


Providingandapplyingoftwoormorecoatsofemulsionpaintof
approvedqualityandshadeovertwocoatsofprimer,twocoatsof
readymixputty(BirlaWhiteorequivalent)andtouchupputtyif
requiredtoachievesmoothfinish,withoutanyundulationordefects
etc.,completetothelevelrequiredforapremiumhotel;onthe
partitions,walls,ceilingasperspecificationanddrawingincluding
sandpapering,scrapingfillingallholesanddepressions,scaffolding.
Thesurfaceofwallorceilingtobepaintedshallberollerfinishand
preparedtothesatisfactionoftheProjectManagerRatetoinclude
providing&removingbeforepaintingandpeelingoff,after
completionofworkprotectivecovers/membranesonfurnitureorfor
protectingexistingwindowpanesorartwork(ifany)andRemoving
stains(ifany)fromthefloors,doors,windows,ventilators,glass
panes,furniture,platforms,plumbingandotherfixturesetc.all
completeinallrespectasperinstructionofProjectManager.

3.1.1 On ceiling surface


a PT-101 EmulsionPaintofapprovedsample. PS11_PL_003 Sqm 243
b PT-102 EmulsionPaintofapprovedsample. PS11_PL_003 Sqm 9

BOQ PA-ID - Transfer Lobby @ L-1 7


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

3.1.2 On wall surface


a PT-101 EmulsionPaintofapprovedsample. PS11_PL_003 Sqm RO -
b PT-102 EmulsionPaintofapprovedsample. PS11_PL_003 Sqm RO -

3.2 POP Punning on Walls


Providing & applying POP punning on walls upto 8-10 mm thick as
required at site to bring proper line and level for all surfaces as
required including fill in irregularities, making grooves, scaffoldings
etc. complete to achieve a leveled surface and smooth finish ready Sqm 20
forreceivingthepaintdirectlyasdirectedbytheProjectmanager.

3.3 Gypsum Plaster


Providing & applying Gypsum Plaster of approved make as per
manufacturers specifications with suitable bonding agent / admixture
to be directly applied on the walls, RCC Slab, Soffit / Celling Surface
upto 25 ~ 35 mm thick as required including all material. labour,
bonding admixture, surface preparation, adhesive / bond coat, base Sqm RO -
/scratch coat, finishing coat to proper line and level for all surfaces as
required, fill in irregularities etc. complete to achieve a leveled
surface and smooth finish ready for receiving the paint directly as
directedbytheProjectmanager.

SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 D-1 Rest Room Door


Providing&fixingofsingleswingdoorconsistsoffollowings:
Door frame made of 50x230 mm thick 1st class Teak wood fixed to
sub frame/wall with holdfast as directed by Project manger including
making necessary grooves, rebate, chamfering, all necessary fixing
arrangementsetc.completeasperdetaileddrawings.
40 mm thick flush door shutter to be finished with Veneer (Code: WD-
101) as per approved sample pasted on it as shown in drawing. Door
WD-101
shutter to be fixed to frame with 4 Nos hinges of approved sample as
shownindrawing.

BOQ PA-ID - Transfer Lobby @ L-1 8


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
The item includes providing & fixing of all hardware (as per approved
sample) such as concealed door closer, Stainless Steel (Coloured)
Lever Handle Set with lock system, etc. to be fixed including all the
ancillarymaterialcompleteasperdrawing&hardwareschedule.

The item also includes solid teak wood beading of required size,
polishing of veneer, beading & door frame; screws, nails, pins,
adhesive, door seal & all necessary fixing arrangements etc.
completeasperdesign,drawing&satisfactionofProjectManager.
PS11_DD_001,
Overallsize:900x2150mmhigh Nos 1
002

1.2 Reception Backside Door

Item same as above but overall size of Overall size : 1000x2150 mm


PS11_IE_101 Nos 1
highinsteadof900x2150mmhigh.

1.3 Fire Door


Providing and installing in position FIRE DOORS of approved make
with hardwood frame with or without Vision panels, Timber plugs,
6mm countersunk MS bolts, MS holdfasts, etc as shown in detail
drawing .The shutters as mentioned below to be fixed as per the
detail drawings & manufacturers specifications. The fire ratings shall
be as called for and confirming to ASTM/BS standards as per the
detail drawings & manufacturers specifications. This includes
providing and fixing all hardware & accessories of approved make as
indicatedinthedetaildrawing.
With 50 mm thick & 60 min fire rated door including all finishing as
per design, drawing & specification. (Overall size: 1000x2150 mm Nos 2
high)

SUB-TOTAL OF "B-1"

B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Wall Covering


Providing&FixingofwallcoveringofapprovedsamplepastedonPOP
finishedsurfaceorGypsumpanelingsurfacewithadhesiveof
approvedmakeincludingallnecessarysurfacepreparationfor
pastingofwallpaper,straighteningofroll,pattern,fixing,matching
WC-101 PS11_IE_103 Sqm 13
thejoints,providingslotsofcutoutsforMEPworksandallnecessary
arrangementsetc.allcompleteasperthedesign,detaildrawing,
specificationsandtothesatisfactionofProjectManager. (Note:
POP/Gypsum paneling to be paid under separate item.)

BOQ PA-ID - Transfer Lobby @ L-1 9


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
2.2 Veneer Paneling
Providing & fixing of Veneer of approved sample pasted on wooden
base made of commercial ply & hardwood framing of required section
as per pattern shown in drawing including all materials, labour,
wastage, adhesive, nails, screws, teak wood beading/profile, making
2.2.1 WD-101 of groove & light cove, making provision of MEP fixtures, polishing of PS11_IE_101,102 Sqm 41
veneer & wooden beading/profile and all necessary fixing
arrangements etc. all complete as per design drawing & satisfaction
of project manager. (Note: Ply base paneling cost need to be
considerhere.)

Itemsameasabovebutusingaluminumframinginsteadof
2.2.2 WD-101 Sqm RO -
Hardwoodframing.

2.3 Metal Paneling


Providing & fixing of 1.2 mm thick Stainless Steel Sheet of black
mirror finish of approved sample pasted on wooden base made of
commercial ply & hardwood framing of required section as per
pattern shown in drawing including all materials, labour, wastage,
MT-102 PS11_IE_101,102 Sqm 3
adhesive, nails, screws, metal beading/profile, polishing and all
necessary fixing arrangements etc. all complete as per design
drawing & satisfaction of project manager. (Note: Ply base paneling
costneedtobeconsiderhere.)

2.4 Metal Strips


Providing & fixing of metal insert made of Stainless Steel (SS-304)
black mirror finish of approved sample fixed to stone cladding joints
in proper line level including screw, adhesive and all necessary fixing
arrangements etc. complete as per the design, detail drawing,
specificationsandsatisfactionofProjectManager.
PS11_IE_101,
2.4.1 10x6mmthick Rmt 145
102,DT_001
PS11_IE_101,
2.4.2 20x6mmthick Rmt 20
102,DT_001

2.5 Base Paneling with Aluminum framing

BOQ PA-ID - Transfer Lobby @ L-1 10


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Providing & fixing of a base paneling using Aluminum framing of


required section to placed at required spacing and covered with
12mm thick commercial ply in line, level and plumb to receive wall
2.5.1
covering/veneer, including making provision for MEP works, making
light coves, finishing of edges, necessary screws, nails, hardware,
anchorsetc.allcompletetothesatisfactionofProjectManager.

a. Forbasepanelingprojectedupto50mmfromwall. NA Sqm RO -
b. Forbasepanelingprojected50-100mmfromwall. NA Sqm RO -

2.3 Gypsum Paneling for Wall Covering Base


Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one
flange of 34mm and another flange of 36 mm) for vertical members
and U-channels (0.55 mm thick, having equal flanges of 32 mm) for
horizontal members placed at 600 mm centre to centre both ways
with joints staggered to avoid through joints. The frame work is to be
adequately anchored in support having additional framework of
rough wood treated with anti-termite and fire retardant paint for
fixing storages, fire extinguishers paintings, switch boxes, door
frames, wood edge, Artwork etc. complete straight & curved as per
drawing. ( Note : The framework may be changed as per site
requirementormanufacture'sspecification.)
Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board
cladding as per approved sample fixed with dry wall screws of 25mm
at 300mm centre, square and tapered edges of the boards are to be
jointed and finished so as to have a flush look which includes filling
and finishing with jointing compound, fiber tape and two coats of
primer suitable Gyp board, making 1/2" grooves with aluminum
angle on edge as shown in drawing. The external angles of the Sqm 13
paneling having Gyp board has to be protected by using angles,
beads (25x25x0.5) and all exposed edges of Gypboard have to be
protected edge bead 25x12.5x0.5). The item includes all the other
fixing arrangements, cost of scaffolding etc. complete as per design
&drawing.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

BOQ PA-ID - Transfer Lobby @ L-1 11


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
C.1 BUILT-IN FURNITURE WORKS :
Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityasper
TenderDocument.

1.1 Vanity Counter


Providing&fixingofVanityCounterofoverallsize:835x665x500
mmhighconstructedwithfollowingcomponents:
ThebasestructureismadeofBWPplyofrequiredthicknesswithMS
framingofrequiredsection.
Thecountertop,ledgedropisfinishedwithstoneofpolishedfinish
pastedoverwoodenbaseasshownindrawing.
BottomboxingunitfinishedwithStainlessSteelHairlineFinishasper
MT-101 approvedsamplepastedonplybasewithapprovedadhesiveas
shownindrawing.
Theitemincludesbasinholecutting,makingprovisionforMEP
fixtures,polishingofstone,edgemolding/chamfering,allnecessary
hardware,adhesive,primerforMSframing,allothernecessaryfixing
arrangementsetc.allcompleteasperdesign,detaileddrawing&
PS11_IE_103 Nos 1
satisfactionoftheProjectManager.(Note:Stonewillbesuppliedby
Clientfreeofcost.Reconciliationstatementneedtosubmitforeach
&everyclientsupplieditems)

1.2 Vanity Mirror


Providing&FixingofOctagonaltypeVanitymirrorofoverallsize
640x1020mmhighmadeof6mmthkclearmirrorwithstrengthened
Back,pastedoverbackplyofrequiredthicknessincludingmetal
MR-101 PS11_IE_103 Nos 1
trimsallaroundofmirror,screws,nails,adhesive,edgepolishing,
provisionforlightfixtureandallnecessaryfixingarrangementetc.all
completeasperdesign&satisfactionoftheProjectManager.

1.3 Display Unit


Providing & Fixing of Display unit of overall size 1650 x 452 x 2430
mmhighconstructedwithfollowingcomponents:
All the facias,base,shelves are made of commercial ply & finished
WD-101 with Veneer of approved sample on all the visible surfaces as shown
indrawing.
The item includes making provision for MEP fixtures, polishing of
veneer ,wooden beadings, lippings, margins, metal inserts, adhesive,
all hardware as per approved sample, all fixing arrangements etc. all PS11_IE_102 Nos 4
complete as per design, detailed drawing and satisfaction of the
ProjectManager.

1.4 Water Feature ( Back Wall + Trough)

BOQ PA-ID - Transfer Lobby @ L-1 12


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing&fixingofWaterFeature(Backwall&frontwatertrough)
constructedwithfollowingcomponents:(Waterfallmechanismby
others)
Thebackwallofoverallsize:5550x2520mmhighmadeofcement
boardofrequiredthicknesswithmetalframingofrequiredsectionas
shownindrawing.Thewalltobefinishedwith20x20Mosaictileof
TL-101
approvedsamplepastedoncementboardbaseasperpatternas
shownindrawing.150mmwidestoneborderallaroundthepanelto
befixedasshownindrawing.
5550mmlong600mmwide&150mmhighwatertroughtobe
finishedwithsamemosaictileasshownindrawing.
Ledgewalloutsidecladdingtobemadeof18mmthickflamedgrey
granitestoneasshownindrawing.
100mmwideledgewallcopingtobemadeof18mmthickflamed
greygranitestonewithedgemouldingasshownindrawing.
The item includes chamfering/moulding, grinding, butt jointing,
treating the joints with grouts of approved sample, polishing of
stone, making provision of MEP fixtures, adhesive, painting of MS
frame & all necessary fixing arrangements etc. complete as per
design, drawing & satisfaction of Project Manager. (Note: Stone & PS11_IE_101 Nos 1
Tile will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items) (Note: Waterfall mechanism to be supplied & fixied by
other agency).

1.5 Reception Counter


Providing&fixingofReceptionCounterofoverallsize:
2465x800x1100mmhightobemadeasperdesign,drawing& Nos 1
satisfactionofProjectManager.
SUB TOTAL OF "C-1" : -
C.2 LOOSE FURNITURE & AREA RUG WORKS :
Providing&fabricating&placing/fixingofloosefurnitureasper
design,drawing,FFE&allfinishingworkcompleteaspersatisfaction
2.1 ofProjectManager.(Note: stone for loose furniture not to be
supplied by Client. Contractor has to include the cost of stone
for loose furniture)

a. CG-101 CoffeeTableatWaitingArea(Dia1000mmx480(H)mm) AsperFF&E Nos 1

ArmchairsatLobby750(W)x720(H)x830(D)mmincludingthe
b.1 SX-101 AsperFF&E Nos 3
costofFabricasperapprovedsample.

ArmchairsatLobby750(W)x720(H)x830(D)mm(Note:Fabric
b.2 SX-101 AsperFF&E Nos RO -
willbesuppliedbyClientfreeofcost.)

BOQ PA-ID - Transfer Lobby @ L-1 13


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
SUB TOTAL OF "C-2" : -
TOTAL OF FURNITURE WORK (C=C1+C2) : -

D DECORATIVE LIGHT WORKS :

FloorLampatLobby(2130(TotalH)x440(LampshadeDia.)x240
1 LX-101 AsperFF&E Nos 1
(LampshadeH.)mm)

TOTAL OF DECORATIVE LIGHT WORK (D) : -

GRAND TOTAL -

BOQ PA-ID - Transfer Lobby @ L-1 14


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Reception Lobby @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

D DECORATIVE LIGHT WORKS : -

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Date: 30-05-17
Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Reception Lobby @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :

BasicrateswherevergivenintheBOQareformaterialdeliveredatsite
inclusiveofalltaxesdutiesandleviesasapplicable.AdjustmentofBasic
ratestobedoneaspertenderdocument.

TheContractorshallstudydrawings,FFEbooklet,notesbeforequoting
therates.TheContractorhastosubmitindent(Quantity&make)forall
thematerialsuppliedbyEmployer.

Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedintheBOQ
areindicativeonly,subjectedtochange.

Contractorhastoprepareshopdrawingsforalltheworksandtoensure
thatpanelingisfactoryfinishedtotheextentpossible.

Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.

Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingstomatchthe
overallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
MarbleSlab:20%
Marblecuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQ PA-ID-LVL 12 Reception Lobby 15


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied works as
mentioned below including all required floor preparation/cleaning before
fixing, bedding with cement mortar 1:4 (1 Cement : 4 Coarse Sand) of
minimum 20 mm thick with required lines/levels and slopes, cleaning
after laying of stone, watering, curing etc. complete. Rates to be
applicable for all levels, heights, leads & lifts, shifting / re-shifting of
1.1.1 material from store to the place of fixing. No extra is payable for
additional thickness of bedding to match adjoining floors, as per
directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints with white
cement & matching color pigment, mirror polishing/honing/other finish
(whichever mentioned in following items) , making of edges, protection
of floor with Cello Bubble guard board and removing the same before
handing over etc. complete as per the approved patterns, designs,
specification&drawings.

Contractor's quoted rates to include the marking of MEP fixtures and


service installations on floors, walls , including making cutouts and
provisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage due to
pattern. Payment will be in Sqm for visible finished floor area only.
Measurement to be verified as per actual site condition. (Note: Stone
will be supplied by Client free of cost. Reconciliation statement
need to submit for each & every client supplied items)

With18mmthickBotticinoClassicstoneofpolishedfinishasper
a. ST-201 PS21_PL_005 Sqm 166
approvedsample.

With16mmthickCreamTravertinostoneofpolishedfinishasper
b. ST-202 PS21_PL_005 Sqm 26
approvedsample.

200mmwidestripswith16mmthickCreamTravertinostoneof
c. ST-202 PS21_PL_005 Sqm 76
polishedfinishasperapprovedsample.

Itemsameas1.1.1butmarbleslabstobecutintopiecesofoverall
1.1.2 size:405x205mm&tobefixedinHerringBonepatternasshownin
drawing.

BOQ PA-ID-LVL 12 Reception Lobby 16


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

With16mmthickCreamTravertinostoneofpolishedfinishasper
a. ST-202 PS21_PL_005 Sqm 22
approvedsample.

Itemsameas1.1.1butstonetobefixedindoorthresholdasshownin
1.1.3
drawing.

With16mmthickCreamTravertinostoneofpolishedfinishasper
a. ST-202
approvedsample.
i) upto300mmwide PS11_PL_005 Rmt 3

1.2 Stone Skirting & Cladding


Receiving and fixing of stone in skirting/cladding on Wall/Jamb/allied
works of brick walls / concrete walls / columns as mentioned, in line and
level using backing with 20 mm thick cement mortar 1:3 (1 Cement : 3
Coarse Sand) to the required lines, levels, pattern and plumbs, pointing
the joints with white cement & matching colour pigment of approved
sample as per specification, including all required surface preparation,
cleaning after fixing etc. complete. Rate to be applicable for all levels,
heights, leads & Lifts, shifting / re-shifting of material from store to the
place of fixing. As per directions and to complete satisfaction of the
Project Manager. Contractor has to perform the work as per the
approvedpattern,specification&drawings.

Rate quoted by the contractor to include all labor and materials,


polishing, moulding, making of edges including necessary supports,
marking of MEP fixtures and service installations on floors, walls,
providing cutout & provisions for template like electric points, junction
boxes, switches and power sockets , sanitary fixtures and accessories
etc. complete as per the approved patterns, designs, specification &
drawings.

(No extra will be payable towards additional material wastage due to


pattern. Payment will be as per actual measurement only. Measurement
to be verified as per actual at site.) (Note: Stone will be supplied by
Client free of cost. Reconciliation statement need to submit for
each & every client supplied items)

1.2.1 Skirting

400mmhighskirtingwith16mmthicktravertinemarbleofpolished PS21_IE_101,102,
a. ST-202 Rmt 67
finishasperapprovedsample. 103

BOQ PA-ID-LVL 12 Reception Lobby 17


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Addition/deductionforfixingofstonewithchemicaladhesiveinsteadof
1.3 Sqm RO -
cementmortarof1:3(1cement:3coarsesand).

1.4 Carpet Flooring

Receiving & laying of Carpet flooring with Woven Axminster Carpet


(80% New Zealand wool, 20% Nylon) as per pattern including flame
retardant underlay of approved sample, grippers ( if required) & all
CA-201 PS11_PL_005 Sqm 51
other fixing arrangement etc. complete as per design drawing &
satisfaction of Project manager. (Note: Carpet will be supplied by Client
freeofcost)

1.5 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made of
stainless steel strip (grade 316) of approved sample at the intersection
different types of flooring materials, in line and level, including
MT-201 anchoring, fixing, cutting, bending, Polishing etc. complete to the PS21_PL_005 Rmt 43
satisfactionofProjectManager.

SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQ PA-ID-LVL 12 Reception Lobby 18


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10-12 mm thick Plaster of Paris false ceiling with
G.I. frame work consisting of G.I. 22 gauge main channel (50x30mm)
with molded ends up to 900mm c/c and G.I. 22 gauge cross channel
(20x60mm) at 300mm c/c suspended from the R.C.C. slab with
adjustable G.I. sheet suspenders (in main areas and narrow strips
etc.), applying cast-in-situ plaster of Paris over rabbit wire mesh fixed
to cross runners, including making of cove, groove, including
framework & base ply etc., providing extra framework & ply
support/template for electrical fittings, A/C diffusers,speaker,projector
2.1.1 NA
screen and any other cut-outs, making provision of trap doors ;proving
& fixing of wooden shadow battens (holloc wood, black enamel
painted - 25x40mm) at wall peripheries and ends etc., including
scaffolding etc. complete as per detailed drawings & upto satisfaction of
Project manager. (A groove shall be provided at all the junctions of
horizontal and vertical corners).( Note : The framework may be changed
aspersiterequirementormanufacture'sspecification.)

Note: surface area to be measured for vertical bands of coves only if the
Vertical height exceeds 200 mm . Within 200 mm verticals , the Plan
areatobemeasuredandpaid PS21_PL_003 Sqm 236

2.1.2 NA Itemsameas2.2.1butceilingtobemadeindoubleheightlevel. Sqm RO -

Itemsameas2.2.1butmakingoflightcovedulyfinished/flatsurface
PS21_PL_003,
2.1.3 NA frominsideforplacementofLEDlight(installationbyothers)asshown
PS21_DT_20
indrawing.
a. Size:120x200mmhigh Rmt 33
b. Size:120x95mmhigh Rmt 17
Extraoveritemno2.1.1to2.1.2forproviding&fixingof12mm
Commercialplywoodtemplateofrequiredsizeforinstallation/support
2.1.4 NA requirementforceilinglightfixture/speakers/chandeliersetc. SQM 25

2.2 Gypsum False Ceiling


Contractor/Supplier to submit material sample and technical
specification of the specified item from the manufacture for prior
approvaloftheProjectManager/Architectasnecessary.

BOQ PA-ID-LVL 12 Reception Lobby 19


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all levels
& height including reveal, bulkheads, making coves, all shaped, sized,
profiled to details shown on the drawings. The false ceiling shall be
suspended / fixed to the RCC ceiling / MS structure, with approved GI
framing / suspensions / supports etc. as per manufacturer's specification
or as required. Rate to include cost of all labors, installations, hardware
/ like & materials not specified elsewhere, trims, metal inserts (U
Channel) on edges /corner of ceiling and wall for showing grooves,
provision for trap doors, finishing of joints with proprietary jointing
compound, in line and levels etc. all required for completion and to the
PM's approval. Rate quoted to include all cutouts/templets required for
light fixtures, smoke detectors etc., all complete as per design, drawing,
manufactures specification & satisfaction of project manager.( Note :
VisibleexecutedfalseCeilingAreatobemeasuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures and


Service installations cellings, including making cutouts and provisions of
templateswhereverrequired.
-

Providing & fixing false ceiling comprising of 12.5m thick gypsum board
false ceiling as per detail and drawing, including all necessary fixing
arrangement etc. complete as shown in drawing and directed by the
2.2.1 NA Project Manager including making verticals,reveals,filling and finishing Sqm RO -
the tapered and square edges of the boards with jointing compound and
paper tape etc. complete (as per recommended practices of India
Gypsumorequivalent).

Itemsameas2.1.1butverticalgypsumpartition(Airtightpartition)to
2.2.2 NA bemadeoverfalseceilinglevelasdirectedbytheProjectmanager. Sqm RO -

Extraoveritemno2.1.1to2.1.2forproviding&fixingofplytemplate
ofrequiredsizeforlightfixture/otherservicework.
2.2.3 NA Nos RO -

2.3 Mirror Ceiling

BOQ PA-ID-LVL 12 Reception Lobby 20


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Providing & fixing of mirror ceiling finished with 6mm Thick clear mirror
pasted over commercial ply fixed to hardwood framing of minimum 50 x
50mm @ 600 mm c/c including all materials, labour, wastage, adhesive,
MI-202 PS11_PL_003 Sqm 30
nails, screws, making provision of MEP fixtures & all necessary fixing
arrangements etc. complete as per design drawing & satisfaction of
projectmanager.

2.4 Trap Door

Providing & fixing Trap door made of 12 mm commercial ply & finished
with 6 mm MDF ready to receive paint to match the gypsum ceiling. The
trapdoor edges to be finished with 8mm thick teak wood lipping. The
item is inclusive of making of groove all around the trap door, any
frames with necessary support structure from the ceiling for resting the Sqm 10
trap door shutters over framework and provision for accessing
units/machines fixed above it and with provision of slots for return air
and a thin black painted GI mesh behind the slots, tools and tackles etc.
requiredtocompletetheworktothesatisfactionoftheProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint


Providingandapplyingoftwoormorecoatsofemulsionpaintof
approvedqualityandshadeovertwocoatsofprimer,twocoatsof
readymixputty(BirlaWhiteorequivalent)andtouchupputtyif
requiredtoachievesmoothfinish,withoutanyundulationordefects
etc.,completetothelevelrequiredforapremiumhotel;onthe
partitions,walls,ceilingasperspecificationanddrawingincludingsand
papering,scrapingfillingallholesanddepressions,scaffolding.The
surfaceofwallorceilingtobepaintedshallberollerfinishand
preparedtothesatisfactionoftheProjectManagerRatetoinclude
providing&removingbeforepaintingandpeelingoff,aftercompletion
ofworkprotectivecovers/membranesonfurnitureorforprotecting
existingwindowpanesorartwork(ifany)andRemovingstains(ifany)
fromthefloors,doors,windows,ventilators,glasspanes,furniture,
platforms,plumbingandotherfixturesetc.allcompleteinallrespectas
perinstructionofProjectManager.

BOQ PA-ID-LVL 12 Reception Lobby 21


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
3.1.1 On ceiling surface
a PT-201 EmulsionPaintofapprovedsample. PS21_PL_003 Sqm 265

3.2 POP Punning on Walls


Providing & applying POP punning on walls upto 8-10 mm thick as
required at site to bring proper line and level for all surfaces as required
including fill in irregularities, making grooves, scaffoldings etc. complete Sqm 50
to achieve a leveled surface and smooth finish ready for receiving the
paintdirectlyasdirectedbytheProjectmanager.

3.3 Gypsum Plaster

Providing & applying Gypsum Plaster of approved make as per


manufacturers specifications with suitable bonding agent / admixture to
be directly applied on the walls, RCC Slab, Soffit / Celling Surface upto
25 ~ 35 mm thick as required including all material. labour, bonding
admixture, surface preparation, adhesive / bond coat, base /scratch Sqm RO -
coat, finishing coat to proper line and level for all surfaces as required,
fill in irregularities etc. complete to achieve a leveled surface and
smooth finish ready for receiving the paint directly as directed by the
Projectmanager.

SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 D-3 Kids Club to Lobby Door

Providing&fixingofsingleswingdoorconsistsoffollowings:

Door frame made of 50x65 mm thick 1st class Teak wood fixed to sub
frame/wall with holdfast as directed by Project manger including making
necessary grooves, rebate, chamfering, all necessary fixing
arrangementsetc.completeasperdetaileddrawings.

BOQ PA-ID-LVL 12 Reception Lobby 22


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

50 mm thick flush door shutter to be finished with Veneer (With WD-201


WD-101, on reception side & WD-401 on Kids Club side) as per approved sample
WD-401 pasted on it as shown in drawing. Door shutter to be fixed to frame with
3Noshingesofapprovedsampleasshownindrawing.

400 mm high stone skirting to be made with 16 mm thick travertine


ST-201 stone of polished finish pasted on door shutter on reception side as
shownindrawing.

The item includes providing & fixing of all hardware (as per approved
sample) such as concealed door closer, Stainless Steel Lever Handle Set
with lock system, etc. to be fixed including all the ancillary material
completeasperdrawing&hardwareschedule.

The item also includes solid teak wood beading of required size,
polishing of veneer, stone, beading & door frame; screws, nails, pins,
adhesive, door seal, making of groove in veneer & all necessary fixing
arrangements etc. complete as per design, drawing & satisfaction of
ProjectManager.

Overallsize:900x2650mmhigh PS21_DS_002 Nos 1

1.2 Door (Reception to office area)

Item same as above but overall size of Overall size : 1000x2650 mm


WD-201 PS21_PL_002 Nos 2
highinsteadof900x2150mmhigh.

1.3 Fire Door


Providing and installing in position FIRE DOORS of approved make with
hardwood frame with or without Vision panels, Timber plugs, 6mm
countersunk MS bolts, MS holdfasts, etc as shown in detail drawing .The
shutters as mentioned below to be fixed as per the detail drawings &
manufacturers specifications. The fire ratings shall be as called for and
confirming to ASTM/BS standards as per the detail drawings &
manufacturers specifications. This includes providing and fixing all
hardware & accessories of approved make as indicated in the detail
drawing.

With 50 mm thick & 60 min fire rated door including all finishing as per
Nos 2
design,drawing&specification.(Overallsize:1800x2650mmhigh)

SUB-TOTAL OF "B-1"

BOQ PA-ID-LVL 12 Reception Lobby 23


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Wall Covering

Providing&FixingofwallcoveringofapprovedsamplepastedonPOP
finishedsurfaceorGypsumpanelingsurfacewithadhesiveofapproved
makeincludingallnecessarysurfacepreparationforpastingof
wallpaper,straighteningofroll,pattern,fixing,matchingthejoints, PS21_IE_101,102,
WC-201 Sqm 105
providingslotsofcutoutsforMEPworksandallnecessaryarrangements 103
etc.allcompleteasperthedesign,detaildrawing,specificationsandto
thesatisfactionofProjectManager. (Note: POP/Gypsum paneling to
be paid under separate item.)

2.2 Veneer Paneling

Providing & fixing of Walnut Veneer of approved sample pasted on


wooden base made of commercial ply & hardwood framing of required
section as per pattern shown in drawing including all materials, labour,
wastage, adhesive, nails, screws, teak wood beading/profile, making of PS21_IE_101,102,
2.2.1 WD-201 Sqm 52
groove & light cove, making provision of MEP fixtures, polishing of 103
veneer & wooden beading/profile and all necessary fixing arrangements
etc. all complete as per design drawing & satisfaction of project
manager.(Note:Plybasepanelingcostneedtoconsiderhere.)

ItemsameasabovebutusingWalnutveneerofmattpolishfinish PS21_IE_101,102,
2.2.2 WD-203 Sqm 35
insteadof20%GlossFinish. 103

Item same as above 2.2.1 & 2.2.2 but using the Aluminum Tube frames
2.2.3 Sqm RO -
insteadofhardwoordframing

2.3 Gypsum Paneling for Wall Covering Base

BOQ PA-ID-LVL 12 Reception Lobby 24


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one
flange of 34mm and another flange of 36 mm) for vertical members and
U-channels (0.55 mm thick, having equal flanges of 32 mm) for
horizontal members placed at 600 mm centre to centre both ways with
joints staggered to avoid through joints. The frame work is to be
adequately anchored in support having additional framework of rough
wood treated with anti-termite and fire retardant paint for fixing
storages, fire extinguishers paintings, switch boxes, door frames, wood
edge, Artwork etc. complete straight & curved as per drawing. ( Note :
The framework may be changed as per site requirement or
manufacture'sspecification.)

Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board
cladding as per approved sample fixed with dry wall screws of 25mm at
300mm centre, square and tapered edges of the boards are to be
jointed and finished so as to have a flush look which includes filling and
finishing with jointing compound, fiber tape and two coats of primer
suitable Gyp board, making 1/2" grooves with aluminum angle on edge
as shown in drawing. The external angles of the paneling having Gyp Sqm 105
board has to be protected by using angles, beads (25x25x0.5) and all
exposed edges of Gypboard have to be protected edge bead
25x12.5x0.5). The item includes all the other fixing arrangements, cost
ofscaffoldingetc.completeasperdesign&drawing.

2.4 Base Paneling with Aluminum framing

Providing & fixing of a base paneling using Aluminum framing of


required section to placed at required spacing and covered with 12mm
thick commercial ply in line, level and plumb to receive wall
covering/veneer, including making provision for MEP works, making light
coves, finishing of edges, necessary screws, nails, hardware, anchors
etc.allcompletetothesatisfactionofProjectManager.

2.4.1 Forbasepanelingprojectedupto50mmfromwall. NA Sqm RO -


2.4.2 Forbasepanelingprojected50-100mmfromwall. NA Sqm RO -

2.5 Fixed Window Glazing at Capsule Lift Wall

BOQ PA-ID-LVL 12 Reception Lobby 25


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing&fixingof3NosWindowGlazingwithFixedtype12mmthick
cleartemperedglassfixedtosolidteakwoodframeofsize250mmx
50mmasperapprovedsampleasshownindrawing.Theitemincludes
PS21_IE_103 Sqm 10
siliconsealantofapprovedmake,fastener,screws,nails,beading,
polishing&allothernecessaryfixingarrangementsetc.completeasper
design,drawing&satisfactionofProjectManager.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityasper
TenderDocument.

1.1 Book Case Display Shelf with Storage Unit


Providing&fixingofBookCaseDisplayShelfwithStorageUnitof
overallsize:8090x440x2500mmhighconstructedwithfollowing
components:

Thedisplayunitbackwall,shelves,partitionstobemadeof30mmthick
WD-202 veneerfinishedpanelsofapprovedsampleasperpatternshownin
drawing.

WD-202 Sidefalsepanelsalsofinishedwithsamepatternasshownindrawing.

Bottomstorageunitalsomadeofsameveneerpanelasshownin
WD-202
drawing.

The item includes providing & fixing of all hardware, hinges & ancillary
materials, making provision for MEP fixtures, making of groove & light
cove, polishing of veneer panels, wooden beadings, lippings, margins, PS21_DT_100 Nos 1
adhesive & all fixing arrangements etc. all complete as per design,
detaileddrawingandsatisfactionoftheProjectManager.

1.2 M-1 Display Shelf Unit (M-1-Type-I)

Providing & Fixing of Glass Display Shelf unit constructed with following
components:

BOQ PA-ID-LVL 12 Reception Lobby 26


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
The base structure is made of 20x20x.. Mm thick stainless steel section
ofhairlinefinish.

All the shelves, unit base, sides & top enclosure to be made of 10 mm
GL-201
thickcleartemperedglassofapprovedsampleasshownindrawing.

The item includes screws, adhesive, polishing, edge grinding, silicone


sealant and all necessary fixing arrangements etc. all complete as per
PS21_DT_110
design, detailed drawing and satisfaction of the Project Manager. (Note:
Planter Box to be paid in separate item)

OverallSize:4240x880x2050mmhigh Nos 1

1.3 M-1 Glass Display Shelf Unit - (M-1-Type-II)


Providing & Fixing of Glass Display Shelf unit constructed with following
components:

The base structure is made of 20x20x.. Mm thick stainless steel section


ofhairlinefinish.

All three vertical sides to be enclosed with 10 mm thick clear tempered


GL-201
glassofapprovedsampleasshownindrawing.

Shelves, intermediate vertical partitions & top enclosure to be made of


same10mmthickcleartemperedglassasshownindrawing.

The item includes screws, adhesive, polishing, edge grinding, silicon


sealant and all necessary fixing arrangements etc. all complete as per
PS21_DT_120
design, detailed drawing and satisfaction of the Project Manager. (Note:
Planter Box to be paid in separate item)

OverallSize:1980x820x1400mmhigh Nos 3

1.4 M-2 Glass Display Shelf Unit - (M-2)


Providing & Fixing of Glass Display Shelf unit constructed with following
components:
The base structure is made of 20x20x.. Mm thick stainless steel section
ofhairlinefinish.

BOQ PA-ID-LVL 12 Reception Lobby 27


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

All three vertical sides to be enclosed with 10 mm thick clear tempered


GL-201
glassofapprovedsampleasshownindrawing.

Shelves, intermediate vertical partition & top enclosure to be made of


GL-201
same10mmthickcleartemperedglassasshownindrawing.

The item includes screws, adhesive, polishing, edge grinding, silicon


sealant and all necessary fixing arrangements etc. all complete as per
PS21_DT_140
design, detailed drawing and satisfaction of the Project Manager. (Note:
Planter Box to be paid in separate item)

OverallSize:1000x820x2060mmhigh Nos 2

1.5 Planter Box (Placed in Display Unit)


Providing&fixingofplanterboxplacedindisplayunitmadeof
followings:
ThebasestructuretobemadeofpowdercoatedMStube&5mmthick
MSplateofsamefinishasperdrawing.
PowdercoatedMSbracketneedtofixasperdrawing.

Theverticalsurfacetobecladdedwith10mmthickclearmirrorasper
MR-202
approvedsamplepastedonbaseasshownindrawing.

The item includes caster wheels (hidden) for moving the planter box in
& out, screws, adhesive, welding, powder coating of MS frame, plate &
all necessary fixing arrangements etc. all complete as per design,
drawing & satisfaction of Project Manager. (Note: drain board, earth
filling & plant to be done by separate vendor)

1.5.1 Overallsize:1000x450x400(placedindisplayunitM-1Type-I)) PS21_DT_111 Nos 4

1.5.2 Overallsize:970x400x400(PlacedindisplayunitM-1Type-II) PS21_DT_120 Nos 3

1.5.3 Overallsize:850x400x400(PlacedindisplayunitM-1Type-II) PS21_DT_120 Nos 3

1.5.4 Overallsize:925x400x400(PlacedindisplayunitM-2) PS21_DT_140 Nos 2

1.6 Reception Pod

BOQ PA-ID-LVL 12 Reception Lobby 28


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing&fixingofReceptionpodunitofoverallsize:
1.6.1
1500x1100x1100mmhighconsistsoffollowings:

Thebasestructuretobemadeofcommercialply&flexyofrequired
thicknesswithhardwoodframingofrequiredsectionasshownin
drawing.

Thetabletoptobefinishedwithapprovedveneerasshownindrawing.

Alltheverticalsurfacetobefinishedwithsameveneerfinishincurved
profileasperpatternasshownindrawing.

Undercounterstorage&drawerunittobefinishedwithMatching
laminateandtheapprovedcolorfeltclothinsidedrawerscompartments
asperHoteloperationsteamrequirementforstationeriesofapproved
sampleasshownindrawing.

20 mm high trim to be finished with stainless steel of hairline finish


pastedonplybaseasshownindrawing.

The item includes making of grove & light cove, making provision of
electrical switch/socket points & conceal the same, providing & fixing of
hardware & ancillary materials like sliding channel, handle, screws;
PS21_DT_140 Nos 3
nails, adhesive, polishing of veneer panel, and all necessary fixing
arrangements etc. all complete as per design, detailed drawing and
satisfactionoftheProjectManager.

1.7 Concierge Desk

Providing&fixingofellipticalConciergeDeskunitofoverallsize:
1.7.1
1770x1100x750mmhighconsistsoffollowings:

Thetabletoptobefinishedwithapprovedveneerasshownindrawing.

Alltheverticalsurfacetobefinishedwithsameveneerpanelincurved
profileasperpatternasshownindrawing.

BOQ PA-ID-LVL 12 Reception Lobby 29


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Undercounterstorage&drawerunittobefinishedwithMatching
laminateandtheapprovedcolorfeltclothinsidedrawerscompartments
asperHoteloperationsteamrequirementforstationeriesofapproved
sampleasshownindrawing.

20 mm high skirting to be finished with stainless steel of hairline finish


pastedonplybaseasshownindrawing.

The item includes making of grove & light cove, making provision of
electrical switch/socket points & conceal the same providing & fixing of
hardware & ancillary materials like sliding channel, handle; screws,
PS21_DT_150 Nos 1
nails, adhesive, polishing of veneer panel, and all necessary fixing
arrangements etc. all complete as per design, detailed drawing and
satisfactionoftheProjectManager.

SUB TOTAL OF "C-1" :

C.2 LOOSE FURNITURE

Providing&fabricating&placing/fixingofloosefurnitureasperdesign,
drawing,FFE&allfinishingworkcompleteaspersatisfactionofProject
2.1
Manager.(Note:stoneforloosefurniturenottobesuppliedbyClient.
Contractorhastoincludethecostofstoneforloosefurniture)

a. CG-201 Sidetableatbookcasezone(420mmx390mmhigh) AsperFF&E Nos 2


Coffeetableatbookcasezone(1800mmx580mmx277mmhigh&
b. CG-202 AsperFF&E Nos 2
12mmthk)

c. CG-203 Sidetableatbookcasezone(Dia450mmx430mmhigh) AsperFF&E Nos 1

Sofaatbookcasezonewithsize(1600mmx1020mmx740mmhigh)
d SX-201 AsperFF&E Nos 2
includingthecostofFabricasperapprovedsample.

d.1 SX-201 ItemSameasabove(d)butFabricissuppliedfreeofcostbyClient AsperFF&E Nos RO -

Armchairatbookcasezonewithsize(665mmx810mmx700mm
e SX-203 AsperFF&E Nos 2
high)includingthecostofFabricasperapprovedsample.

BOQ PA-ID-LVL 12 Reception Lobby 30


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

e.1 SX-203 ItemSameasabove(e)butFabricissuppliedfreeofcostbyClient AsperFF&E Nos RO -

f. SX-204 Benchatbookcasezonewithsize(1244mmx762mmx431mmhigh) AsperFF&E Nos 2

g. SX-205 ReceptionPodchair(686mmx676mmx750mmhigh) AsperFF&E Nos 3

ModularseatinginwaitingloungeincludingthePUleatherremovable
h. SX-206 AsperFF&E Nos 3
covers.

ArmChair-ConciergeDesk(700mmx720mmx750mmhigh)including
i SX-212 AsperFF&E Nos 3
thecostofFabricasperapprovedsample.

i.1 SX-212 ItemSameasabove(i)butFabricissuppliedfreeofcostbyClient AsperFF&E Nos RO -

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

D DECORATIVE LIGHT WORKS :

1 LX-201 Floorlampatwaitinglounge(300mmx1500mmhigh) AsperFF&E Nos 6

2 LX-202 Floorlampatbookcasezone(Dia300mmx370mmx1700mmhigh) AsperFF&E Nos 2

TOTAL OF DECORATIVE LIGHT WORK (D) : -

GRAND TOTAL -

BOQ PA-ID-LVL 12 Reception Lobby 31


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Link Corridor @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

D DECORATIVE LIGHT WORKS : -

E CURTAIN WORKS : -

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Date:
Sheraton Hotel Dhaka
BOQ of ID Work - Link Corridor @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :
BasicrateswherevergivenintheBOQareformaterialdelivered
atsiteinclusiveofalltaxesdutiesandleviesasapplicable.
AdjustmentofBasicratestobedoneaspertenderdocument.

TheContractorshallstudydrawings,FFEbooklet,notesbefore
quotingtherates.TheContractorhastosubmitindent(Quantity&
make)forallthematerialsuppliedbyEmployer.

Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedinthe
BOQareindicativeonly,subjectedtochange.

Contractorhastoprepareshopdrawingsforalltheworksandto
ensurethatpanelingisfactoryfinishedtotheextentpossible.

Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.

Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingsto
matchtheoverallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQ PA-ID-LVL 12 LINK CORRIDOR 32


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied works
as mentioned below including all required floor
preparation/cleaning before fixing, bedding with cement mortar
1:4 (1 Cement : 4 Coarse Sand) of minimum 20 mm thick with
required lines/levels and slopes, cleaning after laying of stone,
watering, curing etc. complete. Rates to be applicable for all
1.1.1 levels, heights, leads & lifts, shifting / re-shifting of material from
store to the place of fixing. No extra is payable for additional
thickness of bedding to match adjoining floors, as per directions
and to complete satisfaction of the Project Manager. Contractor
has to perform the work as per the approved pattern, specification
&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints with
white cement & matching color pigment, mirror
polishing/honing/other finish (whichever mentioned in following
items) , making of edges, protection of floor with Cello Bubble
guard board and removing the same before handing over etc.
complete as per the approved patterns, designs, specification &
drawings.

Contractor's quoted rates to include the marking of MEP fixtures


and service installations on floors, walls , including making cutouts
andprovisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage due
to pattern. Payment will be in Sqm for visible finished floor area
only. Measurement to be verified as per actual site condition.
(Note: Stone will be supplied by Client free of cost.
Reconciliation statement need to submit for each & every
client supplied items)

With18mmthickBotticinoClassicstoneofpolishedfinishasper
a. ST-201 PS22_PL_005 Sqm 272
approvedsample.
200mmwidestripswith16mmthickCreamTravertinostoneof
b. ST-202 PS22_PL_005 Rmt 49
polishedfinishasperapprovedsample.

Itemsameas1.1.1butstonetobefixedindoorthresholdas
1.1.2
shownindrawing.

With18mmthickBotticinoClassicstoneofpolishedfinishasper
a. ST-201
approvedsample.
i) 300mmwide PS22_PL_005 Rmt 3

BOQ PA-ID-LVL 12 LINK CORRIDOR 33


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

With16mmthickCreamTravertinostoneofpolishedfinishasper
b. ST-202
approvedsample.
i) 150mmwide PS22_PL_005 Rmt 5

1.2 Stone Skirting & Cladding


Receiving and fixing of stone in skirting/cladding on
Wall/Jamb/allied works of brick walls / concrete walls / columns as
mentioned, in line and level using backing with 20 mm thick
cement mortar 1:3 (1 Cement : 3 Coarse Sand) to the required
lines, levels, pattern and plumbs, pointing the joints with white
cement & matching colour pigment of approved sample as per
specification, including all required surface preparation, cleaning
after fixing etc. complete. Rate to be applicable for all levels,
heights, leads & Lifts, shifting / re-shifting of material from store
to the place of fixing. As per directions and to complete
satisfaction of the Project Manager. Contractor has to perform the
workaspertheapprovedpattern,specification&drawings.

Rate quoted by the contractor to include all labor and materials,


polishing, moulding, making of edges including necessary
supports, marking of MEP fixtures and service installations on
floors,walls,providingcutout&provisionsfortemplatelikeelectric
points, junction boxes, switches and power sockets , sanitary
fixtures and accessories etc. complete as per the approved
patterns,designs,specification&drawings.

(No extra will be payable towards additional material wastage due


to pattern. Payment will be as per actual measurement only.
Measurement to be verified as per actual at site.) (Note: Stone
will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items)

1.2.1 Skirting
400mmhighskirtingwith16mmthicktravetinemarbleof
a. ST-201 PS22_IE_101,102 Rmt 14
polishedfinishasperapprovedsample.
400mmhighskirtingwith16mmTravertineClassicostoneof
a. ST-206 PS22_IE_101,102 Rmt 9
polishedfinishasperapprovedsample.

1.2.2 Cladding

BOQ PA-ID-LVL 12 LINK CORRIDOR 34


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
With16mmthickTravertineClassicostoneofpolishedfinishas
a. ST-206 PS22_IE_101,102 Sqm 86
perapprovedsample.

Addition/deductionforfixingofstonewithchemicaladhesive
1.3 Sqm RO -
insteadofcementmortarof1:3(1cement:3coarsesand).

1.4 Carpet Flooring


Receiving & laying of Carpet flooring with Woven Axminster Carpet
(80% New Zealand wool, 20% Nylon) as per pattern including
flame retardant underlay of approved sample, grippers ( if
CA-203 PS22_PL_005 Sqm 146
required) & all other fixing arrangement etc. complete as per
design drawing & satisfaction of Project manager. (Note: Carpet
willbesuppliedbyClientfreeofcost)

1.6 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made
of stainless steel strip (grade 316) of approved sample at the
MT-202 intersection different types of flooring materials, in line and level, PS22_PL_005 Rmt 62
including anchoring, fixing, cutting, bending, Polishing etc.
completetothesatisfactionofProjectManager.

SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQ PA-ID-LVL 12 LINK CORRIDOR 35


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling with
G.I. frame work consisting of G.I. 22 gauge main channel
(50x30mm) with molded ends up to 900mm c/c and G.I. 22
gauge cross channel (20x60mm) at 300mm c/c suspended from
the R.C.C. slab with adjustable G.I. sheet suspenders (in main
areas and narrow strips etc.), applying cast-in-situ plaster of
Paris over rabbit wire mesh fixed to cross runners, including
making of cove, groove, including framework & base ply etc.,
providing extra framework & ply support/template for electrical
2.1.1 NA fittings, A/C diffusers,speaker,projector screen and any other cut-
outs, making provision of trap doors ;proving & fixing of wooden
shadow battens (holloc wood, black enamel painted -
25x40mm) at wall peripheries and ends etc., including scaffolding
etc. complete as per detailed drawings & upto satisfaction of
Project manager. (A groove shall be provided at all the junctions of
horizontal and vertical corners).( Note : The framework may be
changedaspersiterequirementormanufacture'sspecification.)

Note: surface area to be measured for vertical bands of coves only


if the Vertical height exceeds 200 mm . Within 200 mm verticals , PS22_PL_003 Sqm 61
thePlanareatobemeasuredandpaid

2.1.2 NA Itemsameas2.3.1butceilingtobemadeindoubleheightlevel. Sqm 365

PS22_PL_003,
2.1.3 NA Itemsameas2.3.1butmakingoflightcoveasshownindrawing.
PS22_DT_20,21
a. Size:120x95mmhigh(upto5mhighceiling) Rmt 9
b. Size:120x95mmhigh(Above5mhighceiling) Rmt 65
Size:120x95mmhighwithmetaledgecapping(upto5mhigh
c. Rmt 7
ceiling)
2.2 Gypsum False Ceiling
Contractor/Supplier to submit material sample and technical
specification of the specified item from the manufacture for prior
approvaloftheProjectManager/Architectasnecessary.

BOQ PA-ID-LVL 12 LINK CORRIDOR 36


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all
levels & height including reveal, bulkheads, making coves, all
shaped, sized, profiled to details shown on the drawings. The false
ceiling shall be suspended / fixed to the RCC ceiling / MS
structure, with approved GI framing / suspensions / supports etc.
as per manufacturer's specification or as required. Rate to include
cost of all labors, installations, hardware / like & materials not
specified elsewhere, trims, metal inserts (U Channel) on edges
/corner of ceiling and wall for showing grooves, provision for trap
doors,finishingofjointswithproprietaryjointingcompound,inline
and levels etc. all required for completion and to the PM's
approval. Rate quoted to include all cutouts/templets required for
light fixtures, smoke detectors etc., all complete as per design,
drawing, manufactures specification & satisfaction of project
manager.( Note : Visible executed false Ceiling Area to be
measuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures


and Service installations cellings, including making cutouts and -
provisionsoftemplateswhereverrequired.

Providing & fixing false ceiling comprising of 12.5m thick gypsum


board false ceiling as per detail and drawing, including all
necessary fixing arrangement etc. complete as shown in drawing
2.2.1 NA and directed by the Project Manager including making PS22_PL_003 Sqm RO -
verticals,reveals,filling and finishing the tapered and square edges
of the boards with jointing compound and paper tape etc.
complete (as per recommended practices of India Gypsum or
equivalent).
Itemsameas2.1.1butverticalgypsumpartition(Airtight
2.2.2 NA partition)tobemadeoverfalseceilinglevelasdirectedbythe Sqm RO -
Projectmanager.

Extraoveritemno2.1.1to2.1.4forproviding&fixingofply
2.2.3 NA templateofrequiredsizeforlightfixture/otherservicework. Nos RO -

2.3 Pelmet

BOQ PA-ID-LVL 12 LINK CORRIDOR 37


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Providing & fixing of wooden pelmet made of 19mm thick


commercial ply and hardwood framing of required section PS22_PL_003,
including base preparation & painting, screws, nails, all necessary PS22_DT_20,
fixing arrangements etc. complete as per design, detailed drawing PS22_IE_101,102,
& satisfaction of Project manager.(Note: Only horizontal surface 103
needtomake&finish,verticalsarepartofseparateitem)

2.3.1 550mmwide(upto5mhighceiling) Rmt RO -


2.3.2 550mmwide(Above5mhighceiling) Rmt RO -

2.4 Mirror Ceiling


Providing & fixing of mirror ceiling finished with 6mm Thick clear
mirror pasted over commercial ply fixed to hardwood framing of
minimum 50 x 50mm @ 600 mm c/c including all materials,
MR-202 PS22_PL_003 Sqm 27
labour, wastage, adhesive, nails, screws, making provision of MEP
fixtures & all necessary fixing arrangements etc. complete as per
designdrawing&satisfactionofprojectmanager.

2.5 Trap Door


Providing & fixing Trap door made of 12 mm commercial ply &
finished with 6 mm MDF ready to receive paint to match the
gypsum ceiling. The trapdoor edges to be finished with 8mm thick
teak wood lipping. The item is inclusive of making of groove all
around the trap door, any frames with necessary support structure
Sqm 10
from the ceiling for resting the trap door shutters over framework
and provision for accessing units/machines fixed above it and with
provision of slots for return air and a thin black painted GI mesh
behind the slots, tools and tackles etc. required to complete the
worktothesatisfactionoftheProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint

BOQ PA-ID-LVL 12 LINK CORRIDOR 38


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providingandapplyingoftwoormorecoatsofemulsionpaintof
approvedqualityandshadeovertwocoatsofprimer,twocoatsof
readymixputty(BirlaWhiteorequivalent)andtouchupputtyif
requiredtoachievesmoothfinish,withoutanyundulationor
defectsetc.,completetothelevelrequiredforapremiumhotel;
onthepartitions,walls,ceilingasperspecificationanddrawing
includingsandpapering,scrapingfillingallholesanddepressions,
scaffolding.Thesurfaceofwallorceilingtobepaintedshallbe
rollerfinishandpreparedtothesatisfactionoftheProject
ManagerRatetoincludeproviding&removingbeforepainting
andpeelingoff,aftercompletionofworkprotectivecovers/
membranesonfurnitureorforprotectingexistingwindowpanesor
artwork(ifany)andRemovingstains(ifany)fromthefloors,
doors,windows,ventilators,glasspanes,furniture,platforms,
plumbingandotherfixturesetc.allcompleteinallrespectasper
instructionofProjectManager.

3.1.1 On ceiling surface


a. PT-201 EmulsionPaintofapprovedsample.(upto5mhighceiling) PS24_PL_003 Sqm 68
b. PT-201 EmulsionPaintofapprovedsample.(above5mhighceiling) PS24_PL_003 Sqm 393

3.1.2 On wall surface


PS24_IE_101,102,
a PT-201 EmulsionPaintofapprovedsample. Sqm 23
103

3.2 Special Paint


Itemsameas3.1butpaintingtobedonewithspecialpaintasper PS24_IE_101,102,
SF-202 Sqm 95
approvedsampleanddesiredpatternasperProjectManager. 103

3.3 POP Punning on Walls


Providing & applying POP punning on walls upto 8-10 mm thick as
required at site to bring proper line and level for all surfaces as
required including fill in irregularities, making grooves, scaffoldings
Sqm 118
etc. complete to achieve a leveled surface and smooth finish ready
forreceivingthepaintdirectlyasdirectedbytheProjectmanager.

3.4 Gypsum Plaster

BOQ PA-ID-LVL 12 LINK CORRIDOR 39


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & applying Gypsum Plaster of approved make as per
manufacturers specifications with suitable bonding agent /
admixture to be directly applied on the walls, RCC Slab, Soffit /
Celling Surface upto 25 ~ 35 mm thick as required including all
material. labour, bonding admixture, surface preparation, Sqm RO -
adhesive / bond coat, base /scratch coat, finishing coat to proper
line and level for all surfaces as required, fill in irregularities etc.
complete to achieve a leveled surface and smooth finish ready for
receivingthepaintdirectlyasdirectedbytheProjectmanager.

SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 Door
Providing&fixingofsingleswingdoorconsistsoffollowings:
Door frame made of 50x125 mm thick 1st class Teak wood fixed
to sub frame/wall with holdfast as directed by Project manger
including making necessary grooves, rebate, chamfering, all
necessary fixing arrangements etc. complete as per detailed
drawings.
45 mm thick flush door shutter to be finished with Veneer as per
approved sample pasted on it as shown in drawing. Door shutter
WD-401
to be fixed to frame with 3 Nos hinges of approved sample as
shownindrawing.
The item includes providing & fixing of all hardware (as per
approved sample) such as concealed door closer, Stainless Steel
Lever Handle Set with lock system, etc. to be fixed including all
the ancillary material complete as per drawing & hardware
schedule.
The item also includes solid teak wood beading of required size,
polishing of veneer, stone, beading & door frame; screws, nails,
pins, adhesive, door seal, making of groove in veneer & all
necessary fixing arrangements etc. complete as per design,
drawing&satisfactionofProjectManager.
Overallsize:900x2650mmhigh PS21_DS_001 Nos RO -

BOQ PA-ID-LVL 12 LINK CORRIDOR 40


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
SUB-TOTAL OF "B-1"

B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Veneer Paneling


Providing & fixing of Walnut Veneer of approved sample pasted on
wooden base made of commercial ply & hardwood framing of
required section as per pattern shown in drawing including all
materials, labour, wastage, adhesive, nails, screws, teak wood
PS22_IE_101,102,
2.1.1 WD-201 beading/profile, making of groove & light cove, making provision Sqm 234
103
of MEP fixtures, polishing of veneer & wooden beading/profile and
all necessary fixing arrangements etc. all complete as per design
drawing & satisfaction of project manager. (Note: Ply base
panelingcostneedtoconsiderhere.)
Item same as above 2.1.1 but using the Aluminum Tube frames
2.1.2 WD-201 Sqm RO -
insteadofhardwoordframing

2.2 Metal Profile/Portal


Providing&fixingofmetalprofileonArtworkwallmadeofmetal
profileofapprovedsamplefixedonexistingbasepaneling
includingallmaterials,labour,wastage,adhesive,nails,screws,
MT-201 PS22_IE_101 Rmt 32
makingofprofileasperpattern,grinding&polishingofprofileand
allnecessaryfixingarrangementsetc.allcompleteasperdesign
drawing&satisfactionofprojectmanager.

2.3 Wall Covering

Providing&Fixingofwallcoveringofapprovedsamplepastedon
POPfinishedsurfaceorGypsumpanelingsurfacewithadhesiveof
approvedmakeincludingallnecessarysurfacepreparationfor
pastingofwallpaper,straighteningofroll,pattern,fixing,
WC-201 matchingthejoints,providingslotsofcutoutsforMEPworksand PS22_IE_102 Sqm 23
allnecessaryarrangementsetc.allcompleteasperthedesign,
detaildrawing,specificationsandtothesatisfactionofProject
Manager.(Note:POP/Gypsumpanelingtobepaidunderseparate
item.)

2.4 Mirror Paneling

BOQ PA-ID-LVL 12 LINK CORRIDOR 41


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of 10 mm thick clear mirror of approved sample
pasted on wooden base made of commercial ply & hardwood
framing of required section as per pattern shown in drawing
including all materials, labour, wastage, adhesive, nails, screws,
2.4.1 MR-202 making of groove & light cove, making provision of MEP fixtures, PS22_IE_101 Sqm 10
polishing edge grinding of mirror and all necessary fixing
arrangements etc. all complete as per design drawing &
satisfactionofprojectmanager.(Note:Plybasepanelingcostneed
toconsiderhere.)

Item same as above but using GL-202 of approved sample instead


2.4.2 GL-202 PS22_IE_101 Sqm 6
ofMR-202.

Item same as 2.4.1 but using 6 mm thick bronze mirror of


2.4.3 MR-201 PS22_IE_101 Sqm 36
approvedsampleinsteadofclearmirrorasshownindrawing.

2.5 Base Paneling with Aluminum framing


Providing & fixing of a base paneling using Aluminum framing of
required section to placed at required spacing and covered with
12mm thick commercial ply in line, level and plumb to receive wall
2.5.1 covering/veneer, including making provision for MEP works,
making light coves, finishing of edges, necessary screws, nails,
hardware, anchors etc. all complete to the satisfaction of Project
Manager.
a. Forbasepanelingprojectedupto50mmfromwall. NA Sqm RO -
b. Forbasepanelingprojected50-100mmfromwall. NA Sqm RO -

2.6 Gypsum Paneling for Wall Covering Base


Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one
flange of 34mm and another flange of 36 mm) for vertical
members and U-channels (0.55 mm thick, having equal flanges of
32 mm) for horizontal members placed at 600 mm centre to
centre both ways with joints staggered to avoid through joints.
The frame work is to be adequately anchored in support having
additional framework of rough wood treated with anti-termite and
fire retardant paint for fixing storages, fire extinguishers paintings,
switch boxes, door frames, wood edge, Artwork etc. complete
straight & curved as per drawing. ( Note : The framework may be
changedaspersiterequirementormanufacture'sspecification.)

BOQ PA-ID-LVL 12 LINK CORRIDOR 42


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board
cladding as per approved sample fixed with dry wall screws of
25mm at 300mm centre, square and tapered edges of the boards
are to be jointed and finished so as to have a flush look which
includes filling and finishing with jointing compound, fiber tape and
two coats of primer suitable Gyp board, making 1/2" grooves with
aluminum angle on edge as shown in drawing. The external angles Sqm 23
of the paneling having Gyp board has to be protected by using
angles, beads (25x25x0.5) and all exposed edges of Gypboard
have to be protected edge bead 25x12.5x0.5). The item includes
all the other fixing arrangements, cost of scaffolding etc. complete
asperdesign&drawing.

2.7 Glass Railing


Design, fabricate, supply, installation, protection, cleaning and
handover of railing with glass of code GL-202 fixed with effective
depth SS 'U' channel at bottom & stainless steel top railing as per
detail. All design shall be done to meet the performance
requirement mentioned in the technical specification. All exposed PS22_IE_101 Rmt 10
Stainless steel to be SS 316 grade and finish as per architect
selection. The item includes all the ancillary materials like SS
connector, fastener & all necessary fixing arrangements etc.
completeasperdesign,drawing&satisfactionofProjectManager.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityas
perTenderDocument.

1.1 Curved Decorative Screen (Fixed to floor)


Providing&fixingofCurvedDecorativeScreenconsistsof
followings:
Theframeworkismadeofx..x..mmthickbronzemetalof
hairlinefinishasperapprovedsample.Theverticalmemberstobe
MT-201+ claddedwith5mmwidestripsofmmthickprefabricatedveneer
WD-202 panelsasshownindrawing.

BOQ PA-ID-LVL 12 LINK CORRIDOR 43


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
ThePanelstobemadeof1.5mmdiaNylonCord/suitableloom
threadsinmulticolorofapprovedsamplefixedtometalframingas
SF-203 perpatternshownindrawing.
Thewholemetalpanelstobefixedonfloorfirmlywithbaseplate
&fastenerofapprovedsampleasshownindrawing.
The item includes all materials, labors, screws adhesive, polishing
of prefabricated veneer panel, edge grinding & polishing of metal
frame, base plate, fastener and all necessary fixing arrangements
etc. all complete as per design, detailed drawing and satisfaction
oftheProjectManager. PS22_DT_100
i OverallSize:3100mmx3200mmhigh Nos 2
ii OverallSize:1885mmx3200mmhigh Nos 1
iii OverallSize:1770mmx3200mmhigh Nos 1
iv OverallSize:2435mmx3200mmhigh Nos 1

1.2 Curved Decorative Screen (Hanging type)


Itemsameas1.2butdecorativescreentobehangedfromceiling
insteadofmountingonfloorincludingadditionalsupporttohang
fromtrueceilingthroughfalseceiling&allnecessaryfixing
arrangementsetc.allcompleteasperdesign,drawing&
satisfactionofProjectManager. PS22_DT_101
i OverallSize:2514mmx3650mmhigh Nos 1
ii OverallSize:3180mmx3170mmhigh Nos 1
iii OverallSize:1180mmx3170mmhigh Nos 1
iv OverallSize:1918mmx3650mmhigh Nos 2

SUB TOTAL OF "C-1" :

C.2 LOOSE FURNITURE & AREA RUG WORKS :

Providing&fabricating&placing/fixingofloosefurnitureasper
design,drawing,FFE&allfinishingworkcompleteasper
2.1 satisfactionofProjectManager.(Note: stone for loose furniture PS22_PL_001
not to be supplied by Client. Contractor has to include the
cost of stone for loose furniture)

a. CG-201 SideTableatWaitingarea1&2(420mmx390mmhigh) AsperFF&E Nos 2


b. CG-205 ConsoleSeatingarea3&5(1800mmx500mmx960mmhigh) AsperFF&E Nos 2
c. CG-207 CoffeeTableatSeatingarea4(Dia620mmx500mmhigh) AsperFF&E Nos 3
CoffeeTableatWaitingarea2BigSize(920mmx800mmx
CG-208 Nos
d. 320mmhigh) AsperFF&E 1
CoffeeTableatWaitingarea2SmallSize(530mmx730mmx
CG-208 Nos
e. 320mmhigh) AsperFF&E 1
CoffeeTablesatWaitingarea1&Seatingarea3&5BigSize
CG-209 Nos
f. (360mmx360mmx450mmhigh) AsperFF&E 6

BOQ PA-ID-LVL 12 LINK CORRIDOR 44


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
CoffeeTablesatWaitingarea1&Seatingarea3&5SmallSize
CG-209 Nos
g. (360mmx360mmx340mmhigh) AsperFF&E 6
CoffeeTablesatSeatingarea2Bigsize(Dia450mmx450mm
CG-212 Nos
h. high) AsperFF&E 2
CoffeeTablesatSeatingarea2Smallsize(Dia300mmx350mm
CG-212 Nos
i. high) AsperFF&E 2
CG-215 SideTableatSeatingarea2,3&5(Dia500mmx600mmhigh) Nos
j. AsperFF&E 3
k. CG-218 PedestalatLiftLobby(Dia1200mmx750mmhigh) AsperFF&E Nos 1
ArmchairatatWaitingarea1&2(665mmx810mmx700mm
SX-203 Nos
l high)includingthecostofFabricasperapprovedsample. AsperFF&E 7
SX-203 ItemSameAsabove(l)butfabricissuppliedbyclientFreeofcost Nos -
l.1 AsperFF&E RO
SofaatSeatingarea3&5(1700mm(L)x750mm(D)x460mm
SX-207 (SH)x850mm(TH))includingthecostofFabricasperapproved Nos
m sample. AsperFF&E 2
ItemSameAsabove(m)butfabricissuppliedbyclientFreeof
SX-207 Nos -
m.1 cost AsperFF&E RO
ArmchairatSeatingarea3&5(1800mm(L)x750mm(D)x
SX-208 850mm(SH)x450mm(TH))includingthecostofFabricasper Nos
n approvedsample. AsperFF&E 6
ItemSameAsabove(n)butfabricissuppliedbyclientFreeof
SX-208 Nos -
n.1 cost AsperFF&E RO
ArmchairatSeatingarea3&5(900mmx1040mmx630mmhigh)
SX-209 Nos
o includingthecostofFabricasperapprovedsample. AsperFF&E 2
ItemSameAsabove(o)butfabricissuppliedbyclientFreeof
SX-209 Nos -
o.1 cost AsperFF&E RO
ArmchairatSeatingarea4(975mmx740mmx960mmhigh)
SX-210 Nos
p includingthecostofFabricasperapprovedsample. AsperFF&E 6
ItemSameAsabove(p)butfabricissuppliedbyclientFreeof
SX-210 Nos -
p.1 cost AsperFF&E RO
SofaaroundWaitingarea1&2(2730mmx900mmx660mm
SX-213 Nos
q high)includingthecostofFabricasperapprovedsample. AsperFF&E 2
ItemSameAsabove(q)butfabricissuppliedbyclientFreeof
SX-213 Nos -
q.1 cost AsperFF&E RO
ArmchairatWaitingarea2(830mmx960mmx410mm(SH))
SX-214 Nos
r includingthecostofFabricasperapprovedsample. AsperFF&E 1
SX-214 ItemSameAsabove(r)butfabricissuppliedbyclientFreeofcost Nos -
r.1 AsperFF&E RO
SofaatSeatingarea2incurvedshape(2530mmx900mmx
SX-216 1000mmhigh)includingthecostofFabricasperapproved Nos
s sample. AsperFF&E 2
ItemSameAsabove(s)butfabricissuppliedbyclientFreeof
SX-216 Nos -
s.1 cost AsperFF&E RO

BOQ PA-ID-LVL 12 LINK CORRIDOR 45


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
SideTable/OttomanatSeatingarea2(OpenItem)includingthe
SX-217 Nos
t costofFabricasperapprovedsample. AsperFF&E 2
SX-217 ItemSameAsabove(t)butfabricissuppliedbyclientFreeofcost Nos -
t.1 AsperFF&E RO
ArmchairatSeatingarea2(830mmx800mmx750mmhigh)
SX-218 Nos
u includingthecostofFabricasperapprovedsample. AsperFF&E 4
ItemSameAsabove(u)butfabricissuppliedbyclientFreeof
SX-218 Nos -
u.1 cost AsperFF&E RO
ArmchairSeatingarea2,3&5(910mmx95mmx750mmhigh)
SX-219 Nos
v includingthecostofFabricasperapprovedsample. AsperFF&E 6
ItemSameAsabove(v)butfabricissuppliedbyclientFreeof
SX-219 Nos -
v.1 cost AsperFF&E RO

. StorageunitatArtworkWall(4960x350x1060mmhigh) Nos
w. PS22_IE_101 1

. StorageunitatArtworkWall(6480x350x1060mmhigh) Nos
x. PS22_IE_101 1
y. CA-202 AreaRug(3257x4350mm) AsperFF&E Nos 1
z. CA-202 AreaRug(2310x4350mm) AsperFF&E Nos 1

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

D DECORATIVE LIGHT WORKS :

1 LX-203 FloorLampatSeatingarea3&5(Dia500mmx700mmhigh) AsperFF&E Nos 2


2 LX-204 FloorLampatSeatingarea4(650mmx1700mmhigh) AsperFF&E Nos 3
LX-206 FloorLampatWaitingarea1&2(Dia100mmx1700mmhigh) AsperFF&E Nos 4

TOTAL OF DECORATIVE LIGHT WORK (D) : -

E CURTAIN WORKS :

Providing,fabricating&fixingofvenetianblindincludingall
supports,ancillarymaterials&necessaryfixingarrangementsetc.
1
completeasperdesign,drawing,FFE&aspersatisfactionof
ProjectManager.
MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm 150
componentsetc.complete.
ManualVenetianBlindsincludingheadrail&otherancillary
1.2 alternative AsperFF&E Sqm RO -
componentsetc.complete.

BOQ PA-ID-LVL 12 LINK CORRIDOR 46


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving&fixingofvenetianblindincludingallsupports,
ancillarymaterials&necessaryfixingarrangementsetc.complete
2 asperdesign,drawing,FFE&aspersatisfactionofProject
Manager.(Note:Blinds&headrailwillbesuppliedbyClientfree
ofcost.)
MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm RO -
componentsetc.complete.
ManualVenetianBlindsincludingheadrail&otherancillary
1.2 alternative AsperFF&E Sqm RO -
componentsetc.complete.

TOTAL OF CURTAIN WORKS (E) : -

GRAND TOTAL -

BOQ PA-ID-LVL 12 LINK CORRIDOR 47


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Toastina @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

D DECORATIVE LIGHT WORKS : -

E CURTAIN WORKS : -

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Sheraton Hotel Dhaka
BOQ of ID Work - Toastina @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :

BasicrateswherevergivenintheBOQareformaterialdeliveredat
siteinclusiveofalltaxesdutiesandleviesasapplicable.Adjustment
ofBasicratestobedoneaspertenderdocument.

TheContractorshallstudydrawings,FFEbooklet,notesbefore
quotingtherates.TheContractorhastosubmitindent(Quantity&
make)forallthematerialsuppliedbyEmployer.

Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedinthe
BOQareindicativeonly,subjectedtochange.

Contractorhastoprepareshopdrawingsforalltheworksandto
ensurethatpanelingisfactoryfinishedtotheextentpossible.

Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.

Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingstomatch
theoverallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQPA-ID -TOASTINA LOUNGE 48


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied works as
mentioned below including all required floor preparation/cleaning
before fixing, bedding with cement mortar 1:4 (1 Cement : 4 Coarse
Sand) of minimum 20 mm thick with required lines/levels and slopes,
cleaning after laying of stone, watering, curing etc. complete. Rates to
be applicable for all levels, heights, leads & lifts, shifting / re-shifting
1.1.1 of material from store to the place of fixing. No extra is payable for
additional thickness of bedding to match adjoining floors, as per
directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints with
white cement & matching color pigment, mirror
polishing/honing/other finish (whichever mentioned in following
items) , making of edges, protection of floor with Cello Bubble guard
board and removing the same before handing over etc. complete as
pertheapprovedpatterns,designs,specification&drawings.

Contractor's quoted rates to include the marking of MEP fixtures and


service installations on floors, walls , including making cutouts and
provisionsoftemplateswhereverrequired.

No extra will be payable towards additional material wastage due to


pattern. Payment will be in Sqm for visible finished floor area only.
Measurement to be verified as per actual site condition. (Note:
Stone will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items)

With18mmthickBotticinoClassicstoneofpolishedfinishasper
a. ST-201 PS23_PL_005 Sqm 89
approvedsample.

200mmwidestripswith16mmthickTRAVERTINOstoneofpolished
b. ST-202 PS23_PL_005 Rmt 39
finishasperapprovedsample.

300mmwidestripswith16mmthickTRAVERTINOstoneofpolished
c. ST-202 PS23_PL_005 Rmt 11
finishasperapprovedsample.

BOQPA-ID -TOASTINA LOUNGE 49


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Itemsameas1.1.1butstoneslabstobecutintopicesofoverallsize:
1.1.2 405x205mm&tobefixedinHerringBonepatternasshownin
drawing.

With18mmthickSilkGreymarblestoneofpolishedfinishasper
a. ST-203 PS23_PL_005 Sqm 90
approvedsample.

Itemsameas1.1.1butstonetobefixedindoorthresholdasshown
1.1.3
indrawing.

With18mmthickmarblestoneofpolishedfinishasperapproved
a. ST-201
sample.

i) 150mmwide PS23_PL_005 Rmt 1

1.2 Tile Cladding with Cement Mortar


Providing and fixing of cladding on Wall/Jamb/allied works of brick
walls / concrete walls / columns as mentioned, in line and level using
backing with 20 mm thick cement mortar 1:3 (1 Cement : 3 Coarse
Sand) for tile to the required lines, levels, pattern and plumbs, the
joints grouted with matching colour of epoxy grout as per approved
sample & specification, including all required surface preparation,
cleaning after fixing etc. complete. Rate to be applicable for all levels,
heights, leads & Lifts, shifting / re-shifting of material from store to
the place of fixing. As per directions and to complete satisfaction of
the Project Manager. Contractor has to perform the work as per the
approvedpattern,specification&drawings.

Rate quoted by the contractor to include all labor and materials,


making of edges including necessary supports, marking of MEP
fixtures and service installations on floors, walls, providing cutout &
provisions for template like electric points, junction boxes, switches
and power sockets ,sanitary fixtures and accessories etc. complete as
pertheapprovedpatterns,designs,specification&drawings.

(No extra will be payable towards additional material wastage due to


pattern. Payment will be as per actual measurement only.
Measurementtobeverifiedasperactualatsite.)

1.2.1 TL-201 WithDarkGreenTileasperapprovedsample. PS23_IE_102,103 Sqm 32

BOQPA-ID -TOASTINA LOUNGE 50


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Addition/deductionforfixingofstone/tilewithchemicaladhesive
1.3 Sqm RO -
insteadofcementmortarof1:3(1cement:3coarsesand).

1.4 Carpet Flooring

Receiving & laying of Carpet flooring with Woven Axminster Carpet


(80% New Zealand wool, 20% Nylon) as per pattern including flame
retardant underlay of approved sample, grippers ( if required) & all
CA-201 PS23_PL_005 Sqm 23
other fixing arrangement etc. complete as per design drawing &
satisfaction of Project manager. (Note: Carpet will be supplied by
Clientfreeofcost)

1.5 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made of
stainless steel strip (grade 316) of approved sample at the
intersection different types of flooring materials, in line and level,
MT-202 including anchoring, fixing, cutting, bending, Polishing etc. complete PS23_PL_005 Rmt 15
tothesatisfactionofProjectManager.

SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQPA-ID -TOASTINA LOUNGE 51


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling with
G.I. frame work consisting of G.I. 22 gauge main channel
(50x30mm) with molded ends up to 900mm c/c and G.I. 22 gauge
cross channel (20x60mm) at 300mm c/c suspended from the R.C.C.
slab with adjustable G.I. sheet suspenders (in main areas and
narrow strips etc.), applying cast-in-situ plaster of Paris over rabbit
wire mesh fixed to cross runners, including making of cove, groove,
including framework & base ply etc., providing extra framework & ply
support/template for electrical fittings, A/C
2.1.1 NA diffusers,speaker,projector screen and any other cut-outs, making
provision of trap doors ;proving & fixing of wooden shadow battens
(holloc wood, black enamel painted - 25x40mm) at wall peripheries
and ends etc., including scaffolding etc. complete as per detailed
drawings & upto satisfaction of Project manager. (A groove shall be
provided at all the junctions of horizontal and vertical corners).( Note
: The framework may be changed as per site requirement or
manufacture'sspecification.)

Note: surface area to be measured for vertical bands of coves only if


the Vertical height exceeds 200 mm . Within 200 mm verticals , the PS23_PL_003 Sqm 116
Planareatobemeasuredandpaid

2.1.2 NA Itemsameas2.3.1butceilingtobemadeindoubleheightlevel. Sqm 170

PS23_PL_003,
2.1.3 NA Itemsameas2.3.1butmakingoflightcoveasshownindrawing.
PS23_DT_20
a. Size:120x95mmhigh(upto5mhighceiling) Rmt 6
b. Size:120x95mmhigh(Above5mhighceiling) Rmt 42
Extraoveritemno2.1.1&2.1.2forproviding&fixingof12mm
Commercialplywoodtemplateofrequiredsizeforinstallation/
2.1.4 NA supportrequirementforceilinglightfixture/speakers/chandeliers SQM 15
etc.
2.2 Gypsum False Ceiling
Contractor/Supplier to submit material sample and technical
specification of the specified item from the manufacture for prior
approvaloftheProjectManager/Architectasnecessary.

BOQPA-ID -TOASTINA LOUNGE 52


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all
levels & height including reveal, bulkheads, making coves, all shaped,
sized, profiled to details shown on the drawings. The false ceiling shall
be suspended / fixed to the RCC ceiling / MS structure, with approved
GI framing / suspensions / supports etc. as per manufacturer's
specification or as required. Rate to include cost of all labors,
installations, hardware / like & materials not specified elsewhere,
trims, metal inserts (U Channel) on edges /corner of ceiling and wall
for showing grooves, provision for trap doors, finishing of joints with
proprietary jointing compound, in line and levels etc. all required for
completion and to the PM's approval. Rate quoted to include all
cutouts/templets required for light fixtures, smoke detectors etc., all
complete as per design, drawing, manufactures specification &
satisfaction of project manager.( Note : Visible executed false Ceiling
Areatobemeasuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures and


Service installations cellings, including making cutouts and provisions
oftemplateswhereverrequired.
-

Providing & fixing false ceiling comprising of 12.5m thick gypsum


board false ceiling as per detail and drawing, including all necessary
fixing arrangement etc. complete as shown in drawing and directed by
2.2.1 NA the Project Manager including making verticals,reveals,filling and Sqm RO -
finishing the tapered and square edges of the boards with jointing
compound and paper tape etc. complete (as per recommended
practicesofIndiaGypsumorequivalent).

Itemsameas2.1.1butverticalgypsumpartition(Airtightpartition)
2.2.2 NA tobemadeoverfalseceilinglevelasdirectedbytheProjectmanager. Sqm RO -

Extraoveritemno2.1.1to2.1.2forproviding&fixingofply
2.2.3 NA templateofrequiredsizeforlightfixture/otherservicework. Nos RO -

2.3 Pelmet

BOQPA-ID -TOASTINA LOUNGE 53


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Providing & fixing of wooden pelmet made of commercial ply and


hardwood framing of required section including base preparation & PS23_PL_003,
painting, screws, nails, all necessary fixing arrangements etc. PS23_DT_20,
complete as per design, detailed drawing & satisfaction of Project PS23_IE_101,102,
manager.(Note: Only horizontal surface need to make & finish, 103
verticalsarepartofseparateitem)

2.3.1 550mmwide(upto5mhighceiling) Rmt 6


2.3.2 550mmwide(Above5mhighceiling) Rmt 17

Extraoveritemno2.3.1to2.3.3forproviding&fixingofwall
coveringofapprovedsamplepastedonexistingPOPceilingvertical
dropwithadhesiveofapprovedsampleincludingallnecessarysurface
preparationforpastingofwallpaper,straighteningofroll,pattern,
2.3.3 WC-201 fixing,matchingthejoints,providingslotsofcutoutsforMEPworks PS23_IE_103 Sqm 39
andallnecessaryarrangementsetc.allcompleteasperthedesign,
detaildrawing,specificationsandtothesatisfactionofProject
Manager.

2.4 Trap Door

Providing & fixing Trap door made of 12 mm commercial ply &


finished with 6 mm MDF ready to receive paint to match the gypsum
ceiling. The trapdoor edges to be finished with 8mm thick teak wood
lipping. The item is inclusive of making of groove all around the trap
door, any frames with necessary support structure from the ceiling for
Sqm 10
resting the trap door shutters over framework and provision for
accessing units/machines fixed above it and with provision of slots for
return air and a thin black painted GI mesh behind the slots, tools and
tackles etc. required to complete the work to the satisfaction of the
ProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint

BOQPA-ID -TOASTINA LOUNGE 54


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providingandapplyingoftwoormorecoatsofemulsionpaintof
approvedqualityandshadeovertwocoatsofprimer,twocoatsof
readymixputty(BirlaWhiteorequivalent)andtouchupputtyif
requiredtoachievesmoothfinish,withoutanyundulationordefects
etc.,completetothelevelrequiredforapremiumhotel;onthe
partitions,walls,ceilingasperspecificationanddrawingincluding
sandpapering,scrapingfillingallholesanddepressions,scaffolding.
Thesurfaceofwallorceilingtobepaintedshallberollerfinishand
preparedtothesatisfactionoftheProjectManagerRatetoinclude
providing&removingbeforepaintingandpeelingoff,after
completionofworkprotectivecovers/membranesonfurnitureorfor
protectingexistingwindowpanesorartwork(ifany)andRemoving
stains(ifany)fromthefloors,doors,windows,ventilators,glass
panes,furniture,platforms,plumbingandotherfixturesetc.all
completeinallrespectasperinstructionofProjectManager.

3.1.1 On ceiling surface


a. PT-201 EmulsionPaintofapprovedsample.(upto5mhighceiling) PS23_PL_003 Sqm 119
b. PT-201 EmulsionPaintofapprovedsample.(above5mhighceiling) PS23_PL_003 Sqm 149

3.1.2 On wall surface


PS23_IE_101,102,
a PT-201 EmulsionPaintofapprovedsample. Sqm 46
103

3.2 Special Paint


Itemsameas3.1butpaintingtobedonewithspecialpaintasper PS23_IE_101,102,
SF-202 Sqm 85
approvedsampleanddesiredpatternasperProjectManager. 103

3.3 POP Punning on Walls


Providing & applying POP punning on walls upto 8-10 mm thick as
required at site to bring proper line and level for all surfaces as
required including fill in irregularities, making grooves, scaffoldings
etc. complete to achieve a leveled surface and smooth finish ready for Sqm 132
receivingthepaintdirectlyasdirectedbytheProjectmanager.

3.4 Gypsum Plaster

BOQPA-ID -TOASTINA LOUNGE 55


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Providing & applying Gypsum Plaster of approved make as per


manufacturers specifications with suitable bonding agent / admixture
to be directly applied on the walls, RCC Slab, Soffit / Celling Surface
upto 25 ~ 35 mm thick as required including all material. labour,
bonding admixture, surface preparation, adhesive / bond coat, base Sqm RO -
/scratch coat, finishing coat to proper line and level for all surfaces as
required, fill in irregularities etc. complete to achieve a leveled
surface and smooth finish ready for receiving the paint directly as
directedbytheProjectmanager.

SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 D-1 Door

Providing&fixingofsingleswingdoorconsistsoffollowings:

Door frame made of 50x125 mm thick 1st class Teak wood fixed to
sub frame/wall with holdfast as directed by Project manger including
making necessary grooves, rebate, chamfering, all necessary fixing
arrangementsetc.completeasperdetaileddrawings.

45 mm thick flush door shutter to be finished with Veneer as per


approved sample pasted on it as shown in drawing. Door shutter to be
WD-201 fixed to frame with 3 Nos hinges of approved sample as shown in
drawing.

The item includes providing & fixing of all hardware (as per approved
sample) such as concealed door closer, Stainless Steel Lever Handle
Set with lock system, etc. to be fixed including all the ancillary
materialcompleteasperdrawing&hardwareschedule.

The item also includes solid teak wood beading of required size,
polishing of veneer, stone, beading & door frame; screws, nails, pins,
adhesive, door seal, making of groove in veneer & all necessary fixing
arrangements etc. complete as per design, drawing & satisfaction of
ProjectManager.

Overallsize:900x2650mmhigh PS21_DS_001 Nos 1

BOQPA-ID -TOASTINA LOUNGE 56


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

SUB-TOTAL OF "B-1"

B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Veneer Paneling

Providing & fixing of Walnut Veneer of approved sample pasted on


wooden base made of commercial ply & hardwood framing of required
section as per pattern shown in drawing including all materials,
labour, wastage, adhesive, nails, screws, teak wood beading/profile,
PS23_IE_101,102,
2.1.1 WD-201 making of groove & light cove, making provision of MEP fixtures, Sqm 104
103
polishing of veneer & wooden beading/profile and all necessary fixing
arrangements etc. all complete as per design drawing & satisfaction of
project manager. (Note: Ply base paneling cost need to consider
here.)

Item same as above 2.1.1 but using the Aluminum Tube frames
2.1.2 Sqm RO -
insteadofhardwoordframing

2.2 Wall Covering

Providing&FixingofwallcoveringofapprovedsamplepastedonPOP
finishedsurfaceorGypsumpanelingsurfacewithadhesiveof
approvedmakeincludingallnecessarysurfacepreparationforpasting
ofwallpaper,straighteningofroll,pattern,fixing,matchingthejoints,
WC-201 Sqm RO -
providingslotsofcutoutsforMEPworksandallnecessary
arrangementsetc.allcompleteasperthedesign,detaildrawing,
specificationsandtothesatisfactionofProjectManager. (Note:
POP/Gypsum paneling to be paid under separate item.)

2.3 Base Paneling with Aluminum framing

Providing & fixing of a base paneling using Aluminum framing of


required section to placed at required spacing and covered with
12mm thick commercial ply in line, level and plumb to receive wall
2.3.1
covering/veneer, including making provision for MEP works, making
light coves, finishing of edges, necessary screws, nails, hardware,
anchorsetc.allcompletetothesatisfactionofProjectManager.

a. Forbasepanelingprojectedupto50mmfromwall. NA Sqm RO -
b. Forbasepanelingprojected50-100mmfromwall. NA Sqm RO -

2.6 Gypsum Paneling for Wall Covering Base

BOQPA-ID -TOASTINA LOUNGE 57


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one
flange of 34mm and another flange of 36 mm) for vertical members
and U-channels (0.55 mm thick, having equal flanges of 32 mm) for
horizontal members placed at 600 mm centre to centre both ways
with joints staggered to avoid through joints. The frame work is to be
adequately anchored in support having additional framework of rough
wood treated with anti-termite and fire retardant paint for fixing
storages, fire extinguishers paintings, switch boxes, door frames,
wood edge, Artwork etc. complete straight & curved as per drawing. (
Note : The framework may be changed as per site requirement or
manufacture'sspecification.)

Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board
cladding as per approved sample fixed with dry wall screws of 25mm
at 300mm centre, square and tapered edges of the boards are to be
jointed and finished so as to have a flush look which includes filling
and finishing with jointing compound, fiber tape and two coats of
primer suitable Gyp board, making 1/2" grooves with aluminum angle
on edge as shown in drawing. The external angles of the paneling
Sqm RO
having Gyp board has to be protected by using angles, beads
(25x25x0.5) and all exposed edges of Gypboard have to be protected
edge bead 25x12.5x0.5). The item includes all the other fixing
arrangements, cost of scaffolding etc. complete as per design &
drawing.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityasper
TenderDocument.

1 Banquet Seating (Fixed Sofa)


Providing&fixingoffixedbanquetseatingofoverallsize:
1.1 6610x900x450/900mmhighwithback&sidepartitionconsistsof
followings:

BOQPA-ID -TOASTINA LOUNGE 58


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Basestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.

Seating,arm&backresttobemadeofPUfoamofdensitymin
UP-201 32kg/cum&finishedwithupholstery(Code:UP-201)ofapproved
sampleasshownindrawing.

100mmhighskirtingtobefinishedwithmmthickpre-fabricated
WD203
veneerpanelsasperapprovedsampleasshownindrawing.

Topwoodenprofileoverseatingboothbacktobefinishedwithsame
WD-202
veneerpanelsasshownindrawing.

The item includes all cusions as per approved sample, making of


groove, making provision of MEP fixtures, foam, markin, stitching of
fabric, adhesive, screws, nails, wooden beading with finishing (if
PS23_DT_100 Nos 1
required), polishing of veneer panels and all necessary fixing
arrangements etc. all complete as per design, drawing & satisfaction
ofProjectManager.

1.2 Itemsameasabovebutfabrictobesuppliedbyclientfreeofcost. PS23_DT_100 Nos RO

2 Front Service Counter @ Toastina Lounge Area

Providing&fixingofFrontServiceCounter@ToastinaLoungeareaof
overallsize:3100x900x760/1100mmhighconsistsoffollowings:

BasestructureismadeofBWPplyofrequiredthickness&Aluminum
framingofrequiredsectionasshownindrawing.

600mmwidecountertop,450mmwideledgetop&edgedrops(40-
ST-207 50mm)tobefinishedwithstoneofapprovedsamplepastedon
woodenbasewithedgechamferingasshownindrawing.

Alltheouterverticalfacia,outerfaciaofshutters&drawerfronttobe
WD-203 finishedwithwalnutveneerofmattfinishasperapprovedsample
pastedonplybaseasshownindrawing.

100mmhighskirtingtobefinishedwithbronzemetalofhairline
MT-201 finishasperapprovedsampletobepastedonplybasewithadhesive
asshownindrawing.

BOQPA-ID -TOASTINA LOUNGE 59


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.
The item includes making of groove, making provision of MEP fixtures
& Kitchen equipments, sink hole cutting, chamfering, moulding,
polishing of stone & veneer, providing & fixing of all hardware &
accessories like hinges, sliding channel, handle etc; other ancillary
materials like adhesive, screws, nails, wooden beading with finishing
and all necessary fixing arrangements etc. all complete as per design, PS23_DT_110 Nos 1
drawing & satisfaction of Project Manager. (Note: Stone will be
supplied by Client free of cost. Reconciliation statement need
to submit for each & every client supplied items)

3 Rear Service Counter @ Toastina Lounge Area

Providing&fixingofRearServiceCounter@ToastinaLoungeareaof
overallsize:1890x450x1100mmhighconsistsoffollowings:

BasestructureismadeofBWRplyofrequiredthicknessasshownin
drawing.

450mmwidecountertop&edgedrops(50mm)tobefinishedwith
ST-207 stoneofapprovedsamplepastedonwoodenbasewithedge
chamferingasshownindrawing.

Alltheouterverticalfacia,outerfaciaofshutters&drawerfronttobe
WD-203 finishedwithwalnutveneerofmattfinishasperapprovedsample
pastedonplybaseasshownindrawing.

100mmhighskirtingtobefinishedwithbronzemetalofhairline
MT-201 finishasperapprovedsampletobepastedonplybasewithadhesive
asshownindrawing.

Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.

BOQPA-ID -TOASTINA LOUNGE 60


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
The item includes making of groove, making provision of MEP fixtures
& Kitchen equipments, chamfering, moulding, polishing of stone &
veneer, providing & fixing of all hardware & accessories like hinges,
sliding channel, handle etc; other ancillary materials like adhesive,
screws, nails, wooden beading with finishing and all necessary fixing
PS23_DT_110 Nos 1
arrangements etc. all complete as per design, drawing & satisfaction
of Project Manager. (Note: Stone will be supplied by Client free
of cost. Reconciliation statement need to submit for each &
every client supplied items)

4 Lounge Table near Service Counter


Providing&fixingofLoungeTableServiceCounterofoverallsize:
2290x2310x750mmhighconsistsoffollowings:

TheTabletopismadeofcommercialplyofrequiredthickness&
finishedwithstoneofapprovedsample.Theedgedrop(50mm)also
ST-207
finishedwithsamestonewithchamferingofedgeasshownin
drawing.

Fournosoflegsmadeofsolidwoodwithcurvingasperpattern
WD-202
shownindrawing.

Legcapitals(supportbaseoftabletop)alsomadeofwoodasshown
indrawing.

Theitemincludesmakingofgroove,chamfering,moulding,polishing
ofstone&wood,makingcurvinginwoodlegs,ancillarymaterialslike
adhesive,screws,nails,woodenbeadingwithfinishingandall
necessaryfixingarrangementsetc.allcompleteasperdesign, PS23_DT_110 Nos 1
drawing&satisfactionofProjectManager.(Note: Stone will be
supplied by Client free of cost. Reconciliation statement need
to submit for each & every client supplied items)

5 Display Counter

Providing&fixingofDisplayCounterofoverallsize:2150x900x1100
mmhighconsistsoffollowings:

Basestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.

BOQPA-ID -TOASTINA LOUNGE 61


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Countertop&edgedrops(50mm)tobefinishedwithstoneof
ST-207 approvedsamplepastedonwoodenbasewithedgechamferingas
shownindrawing.

Alltheouterverticalfacia,outerfaciaofshutters&drawerfronttobe
finishedwithwalnutveneerofmattfinishwith20mmwidemetal
WD-203
stripsalongperferiofstorageunit&storageshutterasperapproved
samplepastedonplybaseasshownindrawing.

80mmhighskirtingtobefinishedwithstainlesssteelofhairline
MT-202 finishasperapprovedsampletobepastedonplybasewithadhesive
asshownindrawing.

Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.
Theitemincludesmakingofgroove,makingprovisionofMEPfixtures,
chamfering, moulding, polishing of stone & veneer, providing & fixing
of all hardware & accessories like hinges, handle etc; other ancillary
materials like adhesive, screws, nails, wooden beading with finishing
and all necessary fixing arrangements etc. all complete as per design, PS23_DT_120 Nos 2
drawing & satisfaction of Project Manager. (Note: Stone will be
supplied by Client free of cost. Reconciliation statement need to
submit for each & every client supplied items) (Shelf units will be
paid in separate item)

6 Counter Top Open Shelf Unit


Providing&fixingofDisplayCountertopshelfunitconsistsof
followings:
Thehorizontal&verticalframestobemadeof20x20mmstainless
MT-202
steeltubeofhairlinefinish.

Thehorizontalshelvestobemadeof20mmthickprefabricated
WD-202
veneerpanelsofapprovedsampleasshownindrawing.

80mmhighshelfguardtobemadeof10mmthickcleartempered
GL-201
glassofapprovedsampleasshownindrawing.
The item includes welding, grinding, polishing of metals & veneer
panels, other ancillary materials like adhesive, screws, wooden
beading with finishing and all necessary fixing arrangements etc. all PS23_DT_120
completeasperdesign,drawing&satisfactionofProjectManager.

6.1 Overallsize:1020x350x510mmhigh. Nos 2

BOQPA-ID -TOASTINA LOUNGE 62


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
6.2 Overallsize:1020x350x1050mmhigh Nos 2

7 Preparation Counter
Providing&fixingofPreparationCounteroverallsize:
3960x1130x850mmhighconsistsoffollowings:

BasestructureismadeofBWPplyofrequiredthickness&Aluminum
framingofrequiredsectionasshownindrawing.

Countertop&edgedrops(50mm)tobefinishedwithstoneof
ST-207 approvedsamplepastedonwoodenbasewithedgechamferingas
shownindrawing.

Alltheexposedouterverticalfacia,outerfaciaofshutters&tobe
PL-201 finishedwithHighpressurelaminatepastedonplybaseasshownin
drawing.

80mmhighskirtingtobefinishedwithCreamTravertinostoneof
ST-202 polishfinishasperapprovedsampletobepastedonplybasewith
adhesiveasshownindrawing.

Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.
The item includes making of groove, making provision of MEP fixtures
& Kitchen equipments, sink hole cutting, chamfering, moulding,
polishing of stone, providing & fixing of all hardware & accessories,
hinges; other ancillary materials like adhesive, screws, nails and all
necessary fixing arrangements etc. all complete as per design, PS23_DT_130 Nos 1
drawing & satisfaction of Project Manager. (Note: Stone will be
supplied by Client free of cost. Reconciliation statement need to
submitforeach&everyclientsupplieditems)

8 Service Counter

Providing&fixingofServiceCounter@Toastinaareaofoverallsize:
4240x420x850/1100mmhighconsistsoffollowings:

BasestructureismadeofBWRplyofrequiredthickness&Aluminum
framingofrequiredsectionasshownindrawing.

275mmwidecountertop,200mmwideledgetop&edgedrops
ST-207 (50mm)tobefinishedwithstoneofapprovedsamplepastedon
woodenbasewithedgechamferingasshownindrawing.

BOQPA-ID -TOASTINA LOUNGE 63


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

80mmhighskirtingtobefinishedwithCreamTravertinostoneof
ST-202 polishfinishasperapprovedsampletobepastedonplybasewith
adhesiveasshownindrawing.

The item includes making of groove, making provision of MEP fixtures


& Kitchen equipments, chamfering, moulding, polishing of stone,
providing & fixing of all hardware & accessories like hinges, handle
etc; other ancillary materials like adhesive, screws, nails, wooden
beading with finishing and all necessary fixing arrangements etc. all PS23_DT_130 Nos 1
complete as per design, drawing & satisfaction of Project Manager.
(Note: Stone will be supplied by Client free of cost. Reconciliation
statementneedtosubmitforeach&everyclientsupplieditems)

8 Display shelf over Prep Counter

Providing&fixingofdisplayshelfofoverallsize:4240x300x790mm
highconsistsoffollowings:

TheunitismadeofStainlesssteelofhairlinefinishshelfhanging
MT-202 fromceilingwithsixnosofsupportsmadeofSSofsamefinishas
shownindrawing.
The item includes welding, grinding, polishing of metals, other
ancillary materials like adhesive, screws and all necessary fixing
arrangements etc. all complete as per design, drawing & satisfaction PS23_DT_130 Nos 1
ofProjectManager.

9 Full Height Display Shelf Unit with Under Counter Storage

Providing&fixingoffullheightDisplayShelfUnitOfoverallsize3520
x400x1310mmhighwithUnderCounterStorageconsistsof
followings:

Basestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.

400mmwidestoragecountertop&edgedrops(50mm)tobefinished
ST-207 withstoneofapprovedsamplepastedonwoodenbasewithedge
chamferingasshownindrawing.

BOQPA-ID -TOASTINA LOUNGE 64


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Alltheouterverticalfacia&outerfaciaofshuttersofstorageunitto
WD-203 befinishedwithwalnutveneerofmattfinishasperapprovedsample
pastedonplybaseasshownindrawing.

80mmhighskirtingtobefinishedwithbronzemetalofhairlinefinish
MT-201 asperapprovedsampletobepastedonplybasewithadhesiveas
shownindrawing.

Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.

180mmwideshelves,backwallofshelves,bulkhead(160mmhigh)
MT-202 &soffit(180mmdeep)tobefinishedwithstainlesssteelofhairline
finishasshownindrawing.

The item includes making of groove, making provision of MEP fixtures


& Kitchen equipments, chamfering, moulding, polishing of stone &
veneer, providing & fixing of all hardware & accessories like hinges,
sliding channel, handle etc; welding, grinding other ancillary materials
like adhesive, screws, nails, wooden beading with finishing and all
necessary fixing arrangements etc. all complete as per design, PS23_DT_140 Nos 1
drawing & satisfaction of Project Manager. (Note: Stone will be
supplied by Client free of cost. Reconciliation statement need to
submitforeach&everyclientsupplieditems)

SUB TOTAL OF "C-1" :

C.2 LOOSE FURNITURE :

Providing&fabricating&placing/fixingofloosefurnitureasper
design,drawing,FFE&allfinishingworkcompleteaspersatisfaction
2.1 ofProjectManager.(Note: stone for loose furniture not to be PS23_PL_001
supplied by Client. Contractor has to include the cost of stone
for loose furniture)

a. CG-203 Sidetable(Dia450mmx430mmhigh) AsperFF&E Nos 2


b. CG-205 Console(1800mmx500mmx960mmhigh) AsperFF&E Nos 1
c. CG-205 Console(1200x600x960mmhigh) AsperFF&E Nos 2
d. CG-207 CoffeeTable(Dia620mmx500mmhigh) AsperFF&E Nos 1
e. CG-210 Diningtableround AsperFF&E Nos 3

BOQPA-ID -TOASTINA LOUNGE 65


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
f. CG-211 DiningTable(900mmx900mmx750mmhigh) AsperFF&E Nos 5
g. CG-214 Console(2400mmx600mmx750mmhigh) AsperFF&E Nos 2
h. CG-215 SideTable(Dia500mmx600mmhigh) AsperFF&E Nos 2
i. CG-216 DiningTable(Dia700mmx750mmhigh) AsperFF&E Nos 3
j. CG-221 PulloutStool(600mmx400mmx400mmhigh) AsperFF&E Nos 3

ArmChair(1800mmx750(D)mmx850mm(TH)x450mm(SH))
k SX-208 AsperFF&E Nos 11
includingthecostofFabricasperapprovedsample.

k.1 SX-208 ItemSameAsabove(k)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

ArmChair(900mmx1040mmx630mmhigh)includingthecostof
l SX-209 AsperFF&E Nos 2
Fabricasperapprovedsample.

l.1 SX-209 ItemSameAsabove(l)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

ArmChair(910x950x750mmseatheight400mm)includingthe
m SX-219 AsperFF&E Nos 4
costofFabricasperapprovedsample.

m.1 SX-219 ItemSameAsabove(m)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

ArmChair(910mmx950mmx750mmhigh)includingthecostof
n SX-220 AsperFF&E Nos 2
Fabricasperapprovedsample.

n.1 SX-220 ItemSameAsabove(n)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

Sofa(3000mmx1000mmx760mmhigh)includingthecostof
o SX-221 AsperFF&E Nos 1
Fabricasperapprovedsample.

o.1 SX-221 ItemSameAsabove(o)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

BarStool(500mmx450mmx970mmhigh)includingthecostof
p SX-224 AsperFF&E Nos 7
Fabricasperapprovedsample.

p.1 SX-224 ItemSameAsabove(p)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

D DECORATIVE LIGHT WORKS :

LX-203 Floorlampatseatingarea(Dia500mmx700mmhigh) AsperFF&E Nos 2


LX-207 Floorlampatseatingarea(Dia370mmx570mmhigh) AsperFF&E Nos 1
LX-212 PendentLightatBanquetseatinginToastinaarea(showninelev-3) AsperFF&E Nos 5

BOQPA-ID -TOASTINA LOUNGE 66


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
TOTAL OF DECORATIVE LIGHT WORK (D) : -

E CURTAIN WORKS :

Providing,fabricating&fixingofvenetianblindincludingallsupports,
1 ancillarymaterials&necessaryfixingarrangementsetc.completeas
perdesign,drawing,FFE&aspersatisfactionofProjectManager.

MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm 161
componentsetc.complete.

alternati ManualVenetianBlindsincludingheadrail&otherancillary
1.2 AsperFF&E Sqm RO -
ve componentsetc.complete.

Receiving&fixingofvenetianblindincludingallsupports,ancillary
materials&necessaryfixingarrangementsetc.completeasper
2
design,drawing,FFE&aspersatisfactionofProjectManager.(Note
:Blinds&headrailwillbesuppliedbyClientfreeofcost.)

MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm RO -
componentsetc.complete.

alternati ManualVenetianBlindsincludingheadrail&otherancillary
1.2 AsperFF&E Sqm RO -
ve componentsetc.complete.

TOTAL OF CURTAIN WORKS (E) : -

GRAND TOTAL -

BOQPA-ID -TOASTINA LOUNGE 67


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Bar Lounge @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

D DECORATIVE LIGHT WORKS : -

E CURTAIN WORKS : -

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Sheraton Hotel Dhaka
BOQ of ID Work - Bar Lounge @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :
BasicrateswherevergivenintheBOQareformaterialdeliveredat
siteinclusiveofalltaxesdutiesandleviesasapplicable.Adjustment
ofBasicratestobedoneaspertenderdocument.
TheContractorshallstudydrawings,FFEbooklet,notesbefore
quotingtherates.TheContractorhastosubmitindent(Quantity&
make)forallthematerialsuppliedbyEmployer.
Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedinthe
BOQareindicativeonly,subjectedtochange.
Contractorhastoprepareshopdrawingsforalltheworksandto
ensurethatpanelingisfactoryfinishedtotheextentpossible.

Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.
Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingstomatch
theoverallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQ PA-ID - BAR LOUNGE 68


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied works as
mentioned below including all required floor preparation/cleaning
before fixing, bedding with cement mortar 1:4 (1 Cement : 4 Coarse
Sand) of minimum 20 mm thick with required lines/levels and
slopes, cleaning after laying of stone, watering, curing etc. complete.
Rates to be applicable for all levels, heights, leads & lifts, shifting /
1.1.1
re-shifting of material from store to the place of fixing. No extra is
payable for additional thickness of bedding to match adjoining floors,
as per directions and to complete satisfaction of the Project
Manager. Contractor has to perform the work as per the approved
pattern,specification&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints with
white cement & matching color pigment, mirror
polishing/honing/other finish (whichever mentioned in following
items) , making of edges, protection of floor with Cello Bubble guard
board and removing the same before handing over etc. complete as
pertheapprovedpatterns,designs,specification&drawings.

Contractor's quoted rates to include the marking of MEP fixtures and


service installations on floors, walls , including making cutouts and
provisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage due to
pattern. Payment will be in Sqm for visible finished floor area only.
Measurement to be verified as per actual site condition. (Note:
Stone will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items)

With18mmthickBotticinostoneofpolishedfinishasperapproved
a. ST-201 PS24_PL_005 Sqm 47
sample.
With16mmthickTravertinostoneofpolishedfinishasperapproved
b. ST-202 PS24_PL_005 Sqm 26
sample.
200mmwidestripswith16mmthickCreamTravertinostoneof
c. ST-202 PS24_PL_005 Rmt 36
polishedfinishasperapprovedsample.

Itemsameas1.1.1butstoneslabstobecutintopiecesofoverall
1.1.2 size:405x205mm&tobefixedinHerringBonepatternasshownin
drawing.

With18mmthickSilkGreystoneofpolishedfinishasperapproved
a. ST-203 PS24_PL_005 Sqm 32
sample.

BOQ PA-ID - BAR LOUNGE 69


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

Itemsameas1.1.1butstonetobefixedindoorthresholdasshown
1.1.3
indrawing.

With16mmthickTravertinostoneofpolishedfinishasperapproved
a. ST-202
sample.
i) 150mmwide Rmt RO -

Addition/deductionforfixingofstonewithchemicaladhesive
1.2 Sqm RO -
insteadofcementmortarof1:3(1cement:3coarsesand).

1.3 Carpet Flooring


Receiving & laying of Carpet flooring with Woven Axminster Carpet
(80% New Zealand wool, 20% Nylon) as per pattern including flame
retardant underlay of approved sample, grippers ( if required) & all
CA-203 PS24_PL_005 Sqm 28
other fixing arrangement etc. complete as per design drawing &
satisfaction of Project manager. (Note: Carpet will be supplied by
Clientfreeofcost)

1.4 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made
of stainless steel strip (grade 316) of approved sample at the
MT-202 intersection different types of flooring materials, in line and level, PS24_PL_005 Rmt 17
including anchoring, fixing, cutting, bending, Polishing etc. complete
tothesatisfactionofProjectManager.
SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQ PA-ID - BAR LOUNGE 70


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling with
G.I. frame work consisting of G.I. 22 gauge main channel
(50x30mm) with molded ends up to 900mm c/c and G.I. 22 gauge
cross channel (20x60mm) at 300mm c/c suspended from the R.C.C.
slab with adjustable G.I. sheet suspenders (in main areas and
narrow strips etc.), applying cast-in-situ plaster of Paris over
rabbit wire mesh fixed to cross runners, including making of cove,
groove, including framework & base ply etc., providing extra
2.1.1 NA framework & ply support/template for electrical fittings, A/C
diffusers,speaker,projector screen and any other cut-outs, making
provision of trap doors ;proving & fixing of wooden shadow battens
(holloc wood, black enamel painted - 25x40mm) at wall
peripheries and ends etc., including scaffolding etc. complete as
per detailed drawings & upto satisfaction of Project manager. (A
grooveshallbeprovidedatallthejunctionsofhorizontalandvertical
corners).( Note : The framework may be changed as per site
requirementormanufacture'sspecification.)
Note: surface area to be measured for vertical bands of coves only if
the Vertical height exceeds 200 mm; within 200 mm verticals , the PS24_PL_003 Sqm 47
Planareatobemeasuredandpaid.

2.1.2 NA Itemsameas2.3.1butceilingtobemadeindoubleheightlevel. Sqm 143

PS24_PL_003,
2.1.3 NA Itemsameas2.3.1butmakingoflightcoveasshownindrawing.
PS24_DT_20
a. Size:120x95mmhigh(upto5mhighceiling) Rmt 4
b. Size:120x95mmhigh(Above5mhighceiling) Rmt 44
Extraoveritemno2.1.1&2.1.2forproviding&fixingof12mm
Commercialplywoodtemplateofrequiredsizeforinstallation/
2.1.4 NA SQM 20
supportrequirementforceilinglightfixture/speakers/chandeliers
etc.

2.2 Gypsum False Ceiling


Contractor/Supplier to submit material sample and technical
specification of the specified item from the manufacture for prior
approvaloftheProjectManager/Architectasnecessary.

BOQ PA-ID - BAR LOUNGE 71


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all
levels & height including reveal, bulkheads, making coves, all
shaped, sized, profiled to details shown on the drawings. The false
ceiling shall be suspended / fixed to the RCC ceiling / MS structure,
with approved GI framing / suspensions / supports etc. as per
manufacturer'sspecificationorasrequired.Ratetoincludecostofall
labors, installations, hardware / like & materials not specified
elsewhere, trims, metal inserts (U Channel) on edges /corner of
ceiling and wall for showing grooves, provision for trap doors,
finishing of joints with proprietary jointing compound, in line and
levels etc. all required for completion and to the PM's approval. Rate
quoted to include all cutouts/templets required for light fixtures,
smoke detectors etc., all complete as per design, drawing,
manufactures specification & satisfaction of project manager.(Note :
VisibleexecutedfalseCeilingAreatobemeasuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures and


Service installations cellings, including making cutouts and provisions -
oftemplateswhereverrequired.

Providing & fixing false ceiling comprising of 12.5m thick gypsum


board false ceiling as per detail and drawing, including all necessary
fixing arrangement etc. complete as shown in drawing and directed
2.2.1 NA by the Project Manager including making verticals,reveals,filling and Sqm RO -
finishing the tapered and square edges of the boards with jointing
compound and paper tape etc. complete (as per recommended
practicesofIndiaGypsumorequivalent).

Itemsameas2.1.1butverticalgypsumpartition(Airtightpartition)
2.2.2 NA tobemadeoverfalseceilinglevelasdirectedbytheProject Sqm RO -
manager.

Extraoveritemno2.1.1to2.1.2forproviding&fixingofply
2.2.3 NA Nos RO -
templateofrequiredsizeforlightfixture/otherservicework.

2.3 Pelmet
Providing & fixing of wooden pelmet made of commercial ply and
hardwood framing of required section including base preparation & PS24_PL_003,
painting, screws, nails, all necessary fixing arrangements etc. PS24_DT_20,
complete as per design, detailed drawing & satisfaction of Project PS24_IE_101,
manager.(Note: Only horizontal surface need to make & finish, 102,103
verticalsarepartofseparateitem)
2.3.1 550mmwide(upto5mhighceiling) Rmt 4
2.3.2 550mmwide(Above5mhighceiling) Rmt 17

BOQ PA-ID - BAR LOUNGE 72


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

2.4 Trap Door


Providing & fixing Trap door made of 12 mm commercial ply &
finished with 6 mm MDF ready to receive paint to match the gypsum
ceiling. The trapdoor edges to be finished with 8mm thick teak wood
lipping. The item is inclusive of making of groove all around the trap
door, any frames with necessary support structure from the ceiling
Sqm 10
for resting the trap door shutters over framework and provision for
accessing units/machines fixed above it and with provision of slots
for return air and a thin black painted GI mesh behind the slots,
tools and tackles etc. required to complete the work to the
satisfactionoftheProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint


Providingandapplyingoftwoormorecoatsofemulsionpaintof
approvedqualityandshadeovertwocoatsofprimer,twocoatsof
readymixputty(BirlaWhiteorequivalent)andtouchupputtyif
requiredtoachievesmoothfinish,withoutanyundulationordefects
etc.,completetothelevelrequiredforapremiumhotel;onthe
partitions,walls,ceilingasperspecificationanddrawingincluding
sandpapering,scrapingfillingallholesanddepressions,scaffolding.
Thesurfaceofwallorceilingtobepaintedshallberollerfinishand
preparedtothesatisfactionoftheProjectManagerRatetoinclude
providing&removingbeforepaintingandpeelingoff,after
completionofworkprotectivecovers/membranesonfurnitureor
forprotectingexistingwindowpanesorartwork(ifany)and
Removingstains(ifany)fromthefloors,doors,windows,
ventilators,glasspanes,furniture,platforms,plumbingandother
fixturesetc.allcompleteinallrespectasperinstructionofProject
Manager.

3.1.1 On ceiling surface


a. PT-201 EmulsionPaintofapprovedsample.(upto5mhighceiling) PS24_PL_003 Sqm 49
b. PT-201 EmulsionPaintofapprovedsample.(above5mhighceiling) PS24_PL_003 Sqm 133

3.1.2 On wall surface


PS24_IE_101,
a PT-201 EmulsionPaintofapprovedsample. Sqm 34
102,103

BOQ PA-ID - BAR LOUNGE 73


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

3.2 Special Paint


Itemsameas3.1butpaintingtobedonewithspecialpaintasper PS24_IE_101,
SF-202 Sqm 46
approvedsampleanddesiredpatternasperProjectManager. 102,103

3.3 POP Punning on Walls


Providing & applying POP punning on walls upto 8-10 mm thick as
required at site to bring proper line and level for all surfaces as
required including fill in irregularities, making grooves, scaffoldings
etc. complete to achieve a leveled surface and smooth finish ready Sqm 80
forreceivingthepaintdirectlyasdirectedbytheProjectmanager.

3.4 Gypsum Plaster


Providing & applying Gypsum Plaster of approved make as per
manufacturers specifications with suitable bonding agent / admixture
to be directly applied on the walls, RCC Slab, Soffit / Celling Surface
upto 25 ~ 35 mm thick as required including all material. labour,
bonding admixture, surface preparation, adhesive / bond coat, base Sqm RO -
/scratch coat, finishing coat to proper line and level for all surfaces
as required, fill in irregularities etc. complete to achieve a leveled
surface and smooth finish ready for receiving the paint directly as
directedbytheProjectmanager.

SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 Door
Providing&fixingofsingleswingdoorconsistsoffollowings:
Door frame made of 50x125 mm thick 1st class Teak wood fixed to
sub frame/wall with holdfast as directed by Project manger including
making necessary grooves, rebate, chamfering, all necessary fixing
arrangementsetc.completeasperdetaileddrawings.
45 mm thick flush door shutter to be finished with Veneer as per
approved sample pasted on it as shown in drawing. Door shutter to
WD-201
be fixed to frame with 3 Nos hinges of approved sample as shown in
drawing.

BOQ PA-ID - BAR LOUNGE 74


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
The item includes providing & fixing of all hardware (as per approved
sample) such as concealed door closer, Stainless Steel Lever Handle
Set with lock system, etc. to be fixed including all the ancillary
materialcompleteasperdrawing&hardwareschedule.
The item also includes solid teak wood beading of required size,
polishing of veneer, stone, beading & door frame; screws, nails,
pins,adhesive,doorseal,makingofgrooveinveneer&allnecessary
fixing arrangements etc. complete as per design, drawing &
satisfactionofProjectManager.
Overallsize:900x2650mmhigh PS21_DS_001 Nos RO -

1.2 Fire Door


Providing and installing in position FIRE DOORS of approved make
with hardwood frame with or without Vision panels, Timber plugs,
6mm countersunk MS bolts, MS holdfasts, etc as shown in detail
drawing .The shutters as mentioned below to be fixed as per the
detail drawings & manufacturers specifications. The fire ratings shall
be as called for and confirming to ASTM/BS standards as per the
detail drawings & manufacturers specifications. This includes
providing and fixing all hardware & accessories of approved make as
indicatedinthedetaildrawing.
With 50 mm thick & 60 min fire rated door including all finishing as
per design, drawing & specification. (Overall size: 1500x2650 mm Nos 2
high)

SUB-TOTAL OF "B-1"

B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Veneer Paneling


Providing & fixing of Walnut Veneer of approved sample pasted on
wooden base made of commercial ply & hardwood framing of
required section as per pattern shown in drawing including all
materials, labour, wastage, adhesive, nails, screws, teak wood
PS24_IE_101,
2.1.1 WD-201 beading/profile, making of groove & light cove, making provision of Sqm 53
102,103
MEP fixtures, polishing of veneer & wooden beading/profile and all
necessary fixing arrangements etc. all complete as per design
drawing & satisfaction of project manager. (Note: Ply base paneling
costneedtoconsiderhere.)
Itemsameasabovebutusingaluminummframinginsteadof
2.1.2 WD-201 Sqm RO -
woodenframing.

2.2 Wall Covering

BOQ PA-ID - BAR LOUNGE 75


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing&Fixingofwallcoveringofapprovedsamplepastedon
POPfinishedsurfaceorGypsumpanelingsurfacewithadhesiveof
approvedmakeincludingallnecessarysurfacepreparationfor
pastingofwallpaper,straighteningofroll,pattern,fixing,matching
2.2.1 WC-201 PS24_IE_102 Sqm 14
thejoints,providingslotsofcutoutsforMEPworksandallnecessary
arrangementsetc.allcompleteasperthedesign,detaildrawing,
specificationsandtothesatisfactionofProjectManager. (Note:
POP/Gypsum paneling to be paid under separate item.)
Providing&fixingofwallcoveringofapprovedsamplepastedon
POPceilingverticaldropwithadhesiveofapprovedsampleincluding
allnecessarysurfacepreparationforpastingofwallpaper,
2.2.2 WC-201 straighteningofroll,pattern,fixing,matchingthejoints,providing PS24_IE_103 Sqm 27
slotsofcutoutsforMEPworksandallnecessaryarrangementsetc.
allcompleteasperthedesign,detaildrawing,specificationsandto
thesatisfactionofProjectManager.

2.3 Mirror Paneling


Providing & fixing of 6 mm thick bronze mirror of approved sample
pasted on wooden base made of commercial ply & hardwood framing
of required section as per pattern shown in drawing including all
materials, labour, wastage, adhesive, nails, screws, making of
MR-201 PS24_IE_102 Sqm 72
groove & light cove, making provision of MEP fixtures, polishing edge
grinding of mirror and all necessary fixing arrangements etc. all
complete as per design drawing & satisfaction of project manager.
(Note:Plybasepanelingcostneedtoconsiderhere.)

2.4 Base Paneling with Aluminum framing


Providing & fixing of a base paneling using Aluminum framing of
required section to placed at required spacing and covered with
12mm thick commercial ply in line, level and plumb to receive wall
2.4.1
covering/veneer, including making provision for MEP works, making
light coves, finishing of edges, necessary screws, nails, hardware,
anchorsetc.allcompletetothesatisfactionofProjectManager.
a. Forbasepanelingprojectedupto50mmfromwall. NA Sqm RO -
b. Forbasepanelingprojected50-100mmfromwall. NA Sqm RO -

2.3 Gypsum Paneling for Wall Covering Base

BOQ PA-ID - BAR LOUNGE 76


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one
flange of 34mm and another flange of 36 mm) for vertical members
and U-channels (0.55 mm thick, having equal flanges of 32 mm) for
horizontal members placed at 600 mm centre to centre both ways
with joints staggered to avoid through joints. The frame work is to
be adequately anchored in support having additional framework of
rough wood treated with anti-termite and fire retardant paint for
fixing storages, fire extinguishers paintings, switch boxes, door
frames, wood edge, Artwork etc. complete straight & curved as per
drawing. ( Note : The framework may be changed as per site
requirementormanufacture'sspecification.)
Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board
cladding as per approved sample fixed with dry wall screws of 25mm
at 300mm centre, square and tapered edges of the boards are to be
jointed and finished so as to have a flush look which includes filling
and finishing with jointing compound, fiber tape and two coats of
primer suitable Gyp board, making 1/2" grooves with aluminum
angle on edge as shown in drawing. The external angles of the Sqm 14
paneling having Gyp board has to be protected by using angles,
beads (25x25x0.5) and all exposed edges of Gypboard have to be
protected edge bead 25x12.5x0.5). The item includes all the other
fixing arrangements, cost of scaffolding etc. complete as per design
&drawing.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityasper
TenderDocument.

1.1 Bookcase Display with Storage Unit


Providing&fixingofBookcasedisplayofoverallsize:7800x370x
1.1.1
2650mmhighconsistsoffollowings:
Undercounterstoragetobemadeof20mmthickprefabricated
veneerpanelswithhardwoodframingofrequiredthicknessasshown
indrawing.

BOQ PA-ID - BAR LOUNGE 77


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Backwall,verticalpartitions,openshelves,toppanel,TVpanelunit,
fireplacetoppanelalsomadeofsamepre-fabricatedpanelof
WD-202 approvedsampleasshownindrawing.
Theitemincludesproviding&fixingofallhardware&accessories
likehandle,hingesetc.,makingofgrooves/lightcove,polishingof
pre-fabricatedpanels,woodenbeading,allancillaryfixingmaterials PS24_DT_110 Nos 1
likescrews,nails,adhesiveandallotherrequiredfixing
arrangementsetc.allcompleteasperdesign,drawing&satisfaction
ofProjectManager.(Note:fireplacewillbepaidseparately)

1.2 Front Service Counter (Bar Counter)


Providing&fixingofFrontServiceCounterofoverallsize:
4290x900x760/1100mmhighconsistsoffollowings:
BasestructureismadeofBWPplyofrequiredthickness&Aluminum
framingofrequiredsectionasshownindrawing.
600mmwidecountertop,450mmwideledgetop&edgedrops
ST-207 (50mm)tobefinishedwithstoneofapprovedsamplepastedon
woodenbasewithedgechamferingasshownindrawing.
Barcounterfront&sideverticalfaciastobefinishedwithLeather
Upholsteredpanel(madeofleatherofapprovedsamplecladdedon
UP-202
6mmthickMDFboardasperpattern)fixedtoplybasepanelwith
doublesidedtapeasperdetaildrawing.
Alltheotherouterverticalfacia(outerfaciaofshutters&drawer
WD-203 front)tobefinishedwithwalnutveneerofmattfinishasper
approvedsamplepastedonplybaseasshownindrawing.
100mmhighskirtingtobefinishedwithbronzemetalofhairline
MT-201 finishasperapprovedsampletobepastedonplybasewith
adhesiveasshownindrawing.
Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.
The item includes the cost of leatherite, making of groove, making
provision of MEP fixtures & Kitchen equipment, sink hole cutting,
chamfering,moulding,polishingofstone&veneer,providing&fixing
of all hardware & accessories like hinges, sliding channel, handle etc;
cutting, stitching of leather, other ancillary materials like adhesive,
PS24_DT_100 Nos 1
screws, nails, wooden beading with finishing and all necessary fixing
arrangements etc. all complete as per design, drawing & satisfaction
of Project Manager. (Note: Stone will be supplied by Client free
of cost. Reconciliation statement need to submit for each &
every client supplied items)

1.3 Rear Service Counter

BOQ PA-ID - BAR LOUNGE 78


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing&fixingofRearServiceCounterofoverallsize:
3790x600x1100mmhighconsistsoffollowings:
BasestructureismadeofBWPplyofrequiredthickness&Aluminum
framingofrequiredsectionasshownindrawing.
600mmwidecountertop&edgedrops(50mm)tobefinishedwith
ST-207 stoneofapprovedsamplepastedonwoodenbasewithedge
chamferingasshownindrawing.
Alltheouterverticalfacia,outerfaciaofshutters&drawerfrontto
WD-203 befinishedwithwalnutveneerofmattfinishasperapproved
samplepastedonplybaseasshownindrawing.
80mmhighskirtingtobefinishedwithbronzemetalofhairline
MT-201 finishasperapprovedsampletobepastedonplybasewith
adhesiveasshownindrawing.
Insidefaciaofstorageunit,drawerstobefinishedwithmatching
.. laminatetoveneercolorasperapprovedsampleonplysurfaceas
shownindrawing.
The item includes making of groove, making provision of MEP
fixtures & Kitchen equipment, chamfering, moulding, polishing of
stone & veneer, providing & fixing of all hardware & accessories like
hinges, sliding channel, handle etc; other ancillary materials like
adhesive, screws, nails, wooden beading with finishing and all PS24_DT_100 Nos 1
necessary fixing arrangements etc. all complete as per design,
drawing & satisfaction of Project Manager. (Note: Stone will be
supplied by Client free of cost. Reconciliation statement need
to submit for each & every client supplied items)

1.4 Glass Display Shelf


Providing & Fixing of Glass Display Shelf unit of overall size:
1630x860x2030mmhighconstructedwithfollowingcomponents:
All the verticals, bottom base, top enclosure & shelves to be made of
20 mm thick clear tempered glass of approved sample fixed as per
GL-201 patternshownindrawing.
The item includes adhesive, edge grinding of glass, silicon sealant
and all necessary fixing arrangements etc. all complete as per
PS24_DT_120 Nos 1
design, detailed drawing and satisfaction of the Project Manager.
(Note: Planter Box to be paid in separate item)

1.5 Planter Box (Placed in Display Unit)


Providing&fixingofplanterboxofOverallsize:1000x450x420mm
1.5.1
highplacedindisplayunitmadeoffollowings:
ThebasestructuretobemadeofpowdercoatedMStube&5mm
thickMSplateofsamefinishasperdrawing.
PowdercoatedMSbracketneedtofixasperdrawing.

BOQ PA-ID - BAR LOUNGE 79


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Theverticalsurfacetobecladdedwith10mmthickclearmirroras
MR-202
perapprovedsamplepastedonbaseasshownindrawing.
The item includes caster wheels (hidden) for moving the planter box
in & out, screws, adhesive, welding, powder coating of MS frame,
plate & all necessary fixing arrangements etc. all complete as per PS24_DT_120 Nos 1
design, drawing & satisfaction of Project Manager. (Note: drain
board, earth filling & plant to be done by separate vendor)
Itemsameasabovebutoverallsizeof500x450x420mmhighas
1.5.2 PS24_DT_120 Nos 1
shownindrawing.

SUB TOTAL OF "C-1" :

C.2 LOOSE FURNITURE & AREA RUG WORKS :

Providing&fabricating&placing/fixingofloosefurnitureasper
design,drawing,FFE&allfinishingworkcompleteaspersatisfaction
2.1 ofProjectManager.(Note:stoneforloosefurniturenottobe PS24_PL-001
suppliedbyClient.Contractorhastoincludethecostofstonefor
loosefurniture)

a. CG-201 SideTable(500mmx300mmx390mmhigh) AsperFF&E Nos 2


b. CG-203 Sidetable(Dia516mmx430mmhigh) AsperFF&E Nos 2
c. CG-210 DiningTable(Dia1524x750mmhigh) AsperFF&E Nos 1
d. CG-213 CoffeeTable(1900mmx900mmx400mmhigh) AsperFF&E Nos 1
e. CG-214 Console(2400mmx600mmx750mmhigh) AsperFF&E Nos 1
f. CG-215 SideTable(Dia500mmx600mmhigh) AsperFF&E Nos 2
g. CG-217 CoffeeTable(1400mmx600mmx400mmhigh) AsperFF&E Nos 1
h. CG-218 Pedestal(Dia1200mmx750mmhigh) AsperFF&E Nos 1
i. CG-219 Sidetable(Dia500mmx450mmhigh) AsperFF&E Nos 1
Armchair(830mmwx960mmdx410mmsh)includingthecostof
j SX-215 AsperFF&E Nos 6
Fabricasperapprovedsample.
j.1 SX-215 ItemSameAsabove(j)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO
ArmChair(910mmx950mmx750mmhigh)includingthecostof
k SX-219 AsperFF&E Nos 4
Fabricasperapprovedsample.
k.1 SX-219 ItemSameAsabove(k)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -
ArmChair(910mmx950mmx750mmhigh)includingthecostof
l SX-220 AsperFF&E Nos 4
Fabricasperapprovedsample.
l.1 SX-220 ItemSameAsabove(l)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -
Sofa(3000mmx1000mmx760mmhigh)includingthecostof
m SX-221 AsperFF&E Nos 1
Fabricasperapprovedsample.

BOQ PA-ID - BAR LOUNGE 80


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
m.1 SX-221 ItemSameAsabove(m)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -
Sofa(2250mmwx1130mmdx750mmhigh)includingthecostof
n SX-223 AsperFF&E Nos 1
Fabricasperapprovedsample.
n.1 SX-223 ItemSameAsabove(n)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -
BarStool(500mmx450mmx970mmhigh)includingthecostof
o SX-224 AsperFF&E Nos 6
Fabricasperapprovedsample.
o.1 SX-224 ItemSameAsabove(o)butfabricissuppliedbyclientFreeofcost AsperFF&E Nos RO -

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

D DECORATIVE LIGHT WORKS :

LX-202 Floorlamp(Dia300mmx370mmx1700mmhigh) AsperFF&E Nos 1


LX-203 Floorlamp(Dia500mmx700mmhigh) AsperFF&E Nos 2
LX-207 TableLamp(Dia370mmx570mmhigh) AsperFF&E Nos 3
LX-210 PendentLight(Dia70mmx700mmL) AsperFF&E Set 2

TOTAL OF DECORATIVE LIGHT WORK (D) : -

E CURTAIN WORKS :

Providing,fabricating&fixingofvenetianblindincludingall
supports,ancillarymaterials&necessaryfixingarrangementsetc.
1
completeasperdesign,drawing,FFE&aspersatisfactionof
ProjectManager.
MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm 132
componentsetc.complete.
alternati ManualVenetianBlindsincludingheadrail&otherancillary
1.2 AsperFF&E Sqm RO -
ve componentsetc.complete.

Receiving&fixingofvenetianblindincludingallsupports,ancillary
materials&necessaryfixingarrangementsetc.completeasper
2
design,drawing,FFE&aspersatisfactionofProjectManager.(
Note:Blinds&headrailwillbesuppliedbyClientfreeofcost.)
MotorizedVenetianBlindsincludingheadrail&otherancillary
1.1 DX-201 AsperFF&E Sqm RO -
componentsetc.complete.
alternati ManualVenetianBlindsincludingheadrail&otherancillary
1.2 AsperFF&E Sqm RO -
ve componentsetc.complete.

TOTAL OF CURTAIN WORKS (E) : -

BOQ PA-ID - BAR LOUNGE 81


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

GRAND TOTAL -

BOQ PA-ID - BAR LOUNGE 82


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Kids Club @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Sheraton Hotel Dhaka
BOQ of ID Work - Kids Club @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :
BasicrateswherevergivenintheBOQareformaterialdeliveredatsite
inclusiveofalltaxesdutiesandleviesasapplicable.AdjustmentofBasic
ratestobedoneaspertenderdocument.
TheContractorshallstudydrawings,FFEbooklet,notesbeforequotingthe
rates.TheContractorhastosubmitindent(Quantity&make)forallthe
materialsuppliedbyEmployer.
Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedintheBOQ
areindicativeonly,subjectedtochange.
Contractorhastoprepareshopdrawingsforalltheworksandtoensure
thatpanelingisfactoryfinishedtotheextentpossible.
Ratesquotedratesareincludingthetopfinishi.epolish,paintetc.
ContractortoreferthecodesmentionedintheBOQ,thematerial
specificationsandfinishingschedulefortopfinishofthematerial.
Hardwoodframing&plythickness(ifnotmentionedintheitem/drawing)
willbefinalizedbasedontheshopdrawingstomatchtheoverallthickness
offinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring


Receiving and laying of Stone in flooring band/ledge/allied works as
mentioned below including all required floor preparation/cleaning before
fixing, bedding with cement mortar 1:4 (1 Cement : 4 Coarse Sand) of
minimum 20 mm thick with required lines/levels and slopes, cleaning after
laying of stone, watering, curing etc. complete. Rates to be applicable for
1.1.1 all levels, heights, leads & lifts, shifting / re-shifting of material from store
to the place of fixing. No extra is payable for additional thickness of
bedding to match adjoining floors, as per directions and to complete
satisfaction of the Project Manager. Contractor has to perform the work as
pertheapprovedpattern,specification&drawings.

BOQ PA-ID-LVL 12 -KIDS CLUB 83


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Rate quoted by the contractor to include all labor and materials, necessary
chamfering, grinding, butt jointing, filling of joints with white cement &
matching color pigment, mirror polishing/honing/other finish (whichever
mentioned in following items) , making of edges, protection of floor with
Cello Bubble guard board and removing the same before handing over etc.
completeaspertheapprovedpatterns,designs,specification&drawings.

Contractor's quoted rates to include the marking of MEP fixtures and


service installations on floors, walls , including making cutouts and
provisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage due to
pattern. Payment will be in Sqm for visible finished floor area only.
Measurement to be verified as per actual site condition. (Note: Stone
will be supplied by Client free of cost. Reconciliation statement
need to submit for each & every client supplied items)

With18mmthickSilkEmperado(IranianMarble)stoneofpolishedfinish
a. ST-203 PS25_PL_005 Sqm 8
asperapprovedsample.

Itemsameas1.1.1butstonetobefixedindoorthresholdasshownin
1.1.2
drawing.

With18mmthickSilkEmperado(IranianMarble)ofpolishedfinishasper
a. ST-203
approvedsample.
i) 125mmwide PS25_PL_005 Rmt 1
ii) 160mmwide PS25_PL_005 Rmt 2

1.2 Stone Skirting & Cladding


Receiving and fixing of stone in skirting/cladding on Wall/Jamb/allied works
of brick walls / concrete walls / columns as mentioned, in line and level
using backing with 20 mm thick cement mortar 1:3 (1 Cement : 3 Coarse
Sand) to the required lines, levels, pattern and plumbs, pointing the joints
with white cement & matching colour pigment of approved sample as per
specification, including all required surface preparation, cleaning after
fixing etc. complete. Rate to be applicable for all levels, heights, leads &
Lifts, shifting / re-shifting of material from store to the place of fixing. As
per directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

BOQ PA-ID-LVL 12 -KIDS CLUB 84


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Rate quoted by the contractor to include all labor and materials, polishing,
moulding, making of edges including necessary supports, marking of MEP
fixtures and service installations on floors, walls, providing cutout &
provisions for template like electric points, junction boxes, switches and
power sockets , sanitary fixtures and accessories etc. complete as per the
approvedpatterns,designs,specification&drawings.

(No extra will be payable towards additional material wastage due to


pattern. Payment will be as per actual measurement only. Measurement to
be verified as per actual at site.) (Note: Stone will be supplied by
Client free of cost. Reconciliation statement need to submit for
each & every client supplied items)

1.2.1 Skirting
200mmhighskirtingwith18mmthickSilkEmperado(IranianMarble)
a. ST-203 PS25_IE_102 Rmt 12
stoneofpolishedfinishasperapprovedsample.

1.2.2 Cladding
200mmhighskirtingwith18mmthickSilkEmperado(IranianMarble)
a. ST-203 PS25_IE_102 Sqm 10
stoneofpolishedfinishasperapprovedsample.

Addition/deductionforfixingofstonewithchemicaladhesiveinsteadof
1.3 Sqm RO -
cementmortarof1:3(1cement:3coarsesand).

1.4 Stone Moulding


Providing and fixing of stone moulding profile in line and level using
backing with 20 mm thick cement mortar 1:3 (1 Cement : 3 Coarse Sand)
to the required lines, levels, pattern and plumbs, pointing the joints with
white cement & matching colour pigment of approved sample as per
specification, including all required surface preparation, cleaning after
fixing etc. complete. Rate to be applicable for all levels, heights, leads &
Lifts, shifting / re-shifting of material from store to the place of fixing. As
per directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.
Rate quoted by the contractor to include all labor and materials, polishing,
making of moulding profile as per pattern etc. all complete as per the
approvedpatterns,designs,specification&drawings.
(Note: Stone will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied items)

BOQ PA-ID-LVL 12 -KIDS CLUB 85


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
80x20mmthickprofilemadeofSilkEmperado(IranianMarble)stoneof
1.4.1 ST-101 PS25_IE_102 Rmt 12
polishedfinish.

1.5 Vinyl Flooring


ProvidingandFixingof4-6mmthickvinylflooringofapprovedsampleon
existingfloorincludingallrequiredsurfacepreparation,cleaningbefore
fixing,levellingwithselflevellingcompound,backingwithadhesives(if
required)withrequiredlines,plumbsandlevels,jointing,finishingjoints
andgapswithmatchingcolourpigmentedsealants,cleaningafterfixing
etc.complete.Rateshallbeapplicableforalllocations,levels,heights, PS25_PL_005
leads&Lifts,shifting/re-shiftingofmaterialfromstoretotheplaceof
fixing.AsperdirectionsandtocompletesatisfactionoftheProject
Manager.Contractorhastoperformtheworkaspertheapprovedpattern,
installationmethodguidelines&specificationasgivenbymanufacture&
drawings.
1.5.1 VF-201 WithVF-201 Sqm 50
1.5.2 VF-202 WithVF-202 Sqm 25

1.6 Timber Skirting


Providing&fixingoftimberskirtingmadeof400x50mmthicksolidwood
profileasperapprovedsamplefixedonwall/existingbasepanelincluding
adhesive,screws,makingprovisionofMEPworks&otherfixing PS25_IE_101,
1.6.1 Rmt 32
arrangementsetc.allcompleteasperdesign,drawingandsatisfactionof 102,103
projectManger.(BasicRateofskirtingBDT........./RmtFORsite)

Itemsameasabovebutusingofveneerofapprovedsamplepastedonply
1.6.2 Rmt RO -
baseinsteadofsolidwood.

1.7 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish made of
stainless steel strip (grade 316) of approved sample at the intersection
MT-202 different types of flooring materials, in line and level, including anchoring, PS25_PL_005 Rmt 1
fixing, cutting, bending, Polishing etc. complete to the satisfaction of
ProjectManager.
SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS


2.1 POP False Ceiling

BOQ PA-ID-LVL 12 -KIDS CLUB 86


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling with G.I.
frame work consisting of G.I. 22 gauge main channel (50x30mm) with
molded ends up to 900mm c/c and G.I. 22 gauge cross channel
(20x60mm) at 300mm c/c suspended from the R.C.C. slab with
adjustable G.I. sheet suspenders (in main areas and narrow strips etc.),
applying cast-in-situ plaster of Paris over rabbit wire mesh fixed to cross
runners, including making of cove, groove, including framework & base
2.1.1 NA ply etc., providing extra framework & ply support/template for electrical
fittings, A/C diffusers,speaker,projector screen and any other cut-outs,
making provision of trap doors ;proving & fixing of wooden shadow
battens (holloc wood, black enamel painted - 25x40mm) at wall
peripheries and ends etc., including scaffolding etc. complete as per
detailed drawings & upto satisfaction of Project manager. (A groove shall
be provided at all the junctions of horizontal and vertical corners).( Note :
The framework may be changed as per site requirement or manufacture's
specification.)
Note: surface area to be measured for vertical bands of coves only if the
Vertical height exceeds 200 mm . Within 200 mm verticals , the Plan area PS25_PL_003 Sqm 83
tobemeasuredandpaid

Itemsameas2.2.1butceilingtobemadewithMRgradeGypboard PS25_PL_003,
2.1.2 NA Sqm 9
insteadofstandardGypboard. PS_25_DT_20
PS25_PL_003,
2.1.3 NA Itemsameas2.2.1butmakingoflightcoveasshownindrawing.
PS_25_DT_20
Size:120x95mmhigh Rmt 2

2.2 Gypsum False Ceiling


Contractor/Supplier to submit material sample and technical specification
of the specified item from the manufacture for prior approval of the
ProjectManager/Architectasnecessary.

BOQ PA-ID-LVL 12 -KIDS CLUB 87


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all levels &
height including reveal, bulkheads, making coves, all shaped, sized,
profiled to details shown on the drawings. The false ceiling shall be
suspended / fixed to the RCC ceiling / MS structure, with approved GI
framing / suspensions / supports etc. as per manufacturer's specification or
as required. Rate to include cost of all labors, installations, hardware / like
& materials not specified elsewhere, trims, metal inserts (U Channel) on
edges /corner of ceiling and wall for showing grooves, provision for trap
doors, finishing of joints with proprietary jointing compound, in line and
levels etc. all required for completion and to the PM's approval. Rate
quoted to include all cutouts/templets required for light fixtures, smoke
detectors etc., all complete as per design, drawing, manufactures
specification & satisfaction of project manager.( Note : Visible executed
falseCeilingAreatobemeasuredandpaidfor.)
Contractor's quoted rates to include the marking of MEP fixtures and
Service installations cellings, including making cutouts and provisions of
templateswhereverrequired.

Providing & fixing false ceiling comprising of 12.5m thick gypsum board
false ceiling as per detail and drawing, including all necessary fixing
arrangement etc. complete as shown in drawing and directed by the
2.2.1 NA Project Manager including making verticals,reveals,filling and finishing the Sqm RO -
tapered and square edges of the boards with jointing compound and paper
tape etc. complete (as per recommended practices of India Gypsum or
equivalent).
Itemsameas2.1.1butverticalgypsumpartition(Airtightpartition)tobe
2.2.2 NA madeoverfalseceilinglevelasdirectedbytheProjectmanager. Sqm RO -

Extraoveritemno2.1.1to2.1.2forproviding&fixingofplytemplateof
2.2.3 NA Nos RO -
requiredsizeforlightfixture/otherservicework.

2.3 Trap Door


Providing & fixing Trap door made of 12 mm commercial ply & finished
with 6 mm MDF ready to receive paint to match the gypsum ceiling. The
trapdoor edges to be finished with 8mm thick teak wood lipping. The item
is inclusive of making of groove all around the trap door, any frames with
necessary support structure from the ceiling for resting the trap door Sqm 5
shutters over framework and provision for accessing units/machines fixed
above it and with provision of slots for return air and a thin black painted
GI mesh behind the slots, tools and tackles etc. required to complete the
worktothesatisfactionoftheProjectManager.

BOQ PA-ID-LVL 12 -KIDS CLUB 88


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

SUB-TOTAL OF "A-2" -

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint


Providingandapplyingoftwoormorecoatsofemulsionpaintofapproved
qualityandshadeovertwocoatsofprimer,twocoatsofreadymixputty(
BirlaWhiteorequivalent)andtouchupputtyifrequiredtoachievesmooth
finish,withoutanyundulationordefectsetc.,completetothelevel
requiredforapremiumhotel;onthepartitions,walls,ceilingasper
specificationanddrawingincludingsandpapering,scrapingfillingallholes
anddepressions,scaffolding.Thesurfaceofwallorceilingtobepainted
shallberollerfinishandpreparedtothesatisfactionoftheProject
ManagerRatetoincludeproviding&removingbeforepaintingandpeeling
off,aftercompletionofworkprotectivecovers/membranesonfurnitureor
forprotectingexistingwindowpanesorartwork(ifany)andRemoving
stains(ifany)fromthefloors,doors,windows,ventilators,glasspanes,
furniture,platforms,plumbingandotherfixturesetc.allcompleteinall
respectasperinstructionofProjectManager.

3.1.1 On ceiling surface


a. PT-201 EmulsionPaintofapprovedsample. PS25_PL_003 Sqm 83
b. PT-202 EmulsionPaintofapprovedsample. PS25_PL_003 Sqm 9

3.1.2 On wall surface


a PT-201 EmulsionPaintofapprovedsample. Sqm RO -
3.2 POP Punning on Walls
Providing & applying POP punning on walls upto 8-10 mm thick as required
at site to bring proper line and level for all surfaces as required including
fill in irregularities, making grooves, scaffoldings etc. complete to achieve a Sqm 10
leveled surface and smooth finish ready for receiving the paint directly as
directedbytheProjectmanager.

3.3 Gypsum Plaster


Providing & applying Gypsum Plaster of approved make as per
manufacturers specifications with suitable bonding agent / admixture to be
directly applied on the walls, RCC Slab, Soffit / Celling Surface upto 25 ~
35 mm thick as required including all material. labour, bonding admixture,
Sqm RO -
surface preparation, adhesive / bond coat, base /scratch coat, finishing
coat to proper line and level for all surfaces as required, fill in irregularities
etc. complete to achieve a leveled surface and smooth finish ready for
receivingthepaintdirectlyasdirectedbytheProjectmanager.

BOQ PA-ID-LVL 12 -KIDS CLUB 89


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
SUB-TOTAL OF "A-3" -

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 Toilet Door


Providing&fixingofsingleswingdoorconsistsoffollowings:
Door frame made of 50x125 mm thick 1st class Teak wood fixed to sub
frame/wall with holdfast as directed by Project manger including making
necessary grooves, rebate, chamfering, all necessary fixing arrangements
etc.completeasperdetaileddrawings.
45 mm thick flush door shutter to be finished with Veneer as per approved
WD-201 sample pasted on it as shown in drawing. Door shutter to be fixed to frame
with3Noshingesofapprovedsampleasshownindrawing.
The item includes providing & fixing of all hardware (as per approved
sample) such as concealed door closer, Stainless Steel Lever Handle Set
with lock system, etc. to be fixed including all the ancillary material
completeasperdrawing&hardwareschedule.
The item also includes solid teak wood beading of required size, polishing
of veneer, stone, beading & door frame; screws, nails, pins, adhesive, door
seal, making of groove in veneer & all necessary fixing arrangements etc.
completeasperdesign,drawing&satisfactionofProjectManager.
Overallsize:900x2650mmhigh PS25_DS_002 Nos 1

1.2 Kids Club Entry Door


Providing&fixingofAluminumframedGlassdoorconsistsoffollowings:
Door frame made of Aluminum section of required section & finished with
powder coating as per approved sample fixed to wall with fastener of
approvedsample.
Double leaf Glass door shutter to be made of 12 mm thick clear tempered
GL-201 glass of approved sample fixed with top pivot & floor spring as shown in
drawing.
The item includes providing & fixing of all hardware & accessories like floor
spring, top pivot, handle with locking arrangement, edge grinding of glass
& all necessary fixing arrangements etc. complete as per design, drawing &
satisfactionofProjectManager.
Overallsize:1800X2650mmhigh PS25_DS_001 Nos 1

SUB-TOTAL OF "B-1"

BOQ PA-ID-LVL 12 -KIDS CLUB 90


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Wall Covering


Providing&FixingofwallcoveringofapprovedsamplepastedonPOP
finishedsurfaceorGypsumpanelingsurfacewithadhesiveofapproved
makeincludingallnecessarysurfacepreparationforpastingofwallpaper,
straighteningofroll,pattern,fixing,matchingthejoints,providingslotsof PS25_IE_101,
cutoutsforMEPworksandallnecessaryarrangementsetc.allcompleteas 102,103
perthedesign,detaildrawing,specificationsandtothesatisfactionof
ProjectManager. (Note: POP/Gypsum paneling to be paid under
separate item.)
2.1.1 WC-202 WithwallcoveringofCode:WC-202asperapprovedsample. Sqm 18
2.1.2 WC-203 WithwallcoveringofCode:WC-203asperapprovedsample. Sqm 13
2.1.3 WC-204 WithwallcoveringofCode:WC-204asperapprovedsample. Sqm 69

2.2 Laminated Partitions


Providing & fixing of HPL (HIGH PRESSURE LAMINATE) partition with door
of approved make including door hardware, clamps, clips, posts & all
PL-206 PS25_IE_102
necessary supports, fixing arrangements etc. all complete as per drawing,
manufacture'sspecificationandsatisfactionoftheProjectManager.
2.2.1 Fixedpartition Sqm 4
2.2.2 Openablepartition(Door) Sqm 3

2.3 Gypsum Paneling for Wall Covering Base


Framework : Providing and fixing GI Frame work (gypsteel - India
gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick, having one flange
of 34mm and another flange of 36 mm) for vertical members and U-
channels (0.55 mm thick, having equal flanges of 32 mm) for horizontal
members placed at 600 mm centre to centre both ways with joints
staggered to avoid through joints. The frame work is to be adequately
anchored in support having additional framework of rough wood treated
with anti-termite and fire retardant paint for fixing storages, fire
extinguishers paintings, switch boxes, door frames, wood edge, Artwork
etc. complete straight & curved as per drawing. ( Note : The framework
maybechangedaspersiterequirementormanufacture'sspecification.)

BOQ PA-ID-LVL 12 -KIDS CLUB 91


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Skin : Providing and fixing 12.5mm thick (Single layer) Gyp board cladding
as per approved sample fixed with dry wall screws of 25mm at 300mm
centre, square and tapered edges of the boards are to be jointed and
finished so as to have a flush look which includes filling and finishing with
jointing compound, fiber tape and two coats of primer suitable Gyp board,
making 1/2" grooves with aluminum angle on edge as shown in drawing.
The external angles of the paneling having Gyp board has to be protected Sqm RO
by using angles, beads (25x25x0.5) and all exposed edges of Gypboard
have to be protected edge bead 25x12.5x0.5). The item includes all the
other fixing arrangements, cost of scaffolding etc. complete as per design
&drawing.

SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthefurniture&
obtainwrittenapprovalfromappropriateauthorityasperTender
Document.

1.1 Vanity Counter


Providing&fixingofVanityCounterconstructedwithfollowingcomponents
:
ThebasestructureismadeofBWPplyofrequiredthicknesswithMS
framingofrequiredsection.
Thecountertop,(MARBLEBYCLIENT)ledgedropisfinishedwithstoneof
polishedfinishpastedoverwoodenbaseasshownindrawing.
BottomboxingunitfinishedwithStainlessSteelHairlineFinishasper
MT-101 approvedsamplepastedonplybasewithapprovedadhesiveasshownin
drawing.
Theitemincludesbasinholecutting,makingprovisionforMEPfixtures,
polishingofstone,edgemolding/chamfering,allnecessaryhardware,
adhesive,primerforMSframing,allothernecessaryfixingarrangements
etc.allcompleteasperdesign,detaileddrawing&satisfactionofthe
PS25_DT_160,
ProjectManager.(Note: Stone will be supplied by Client free of cost.
Reconciliation statement need to submit for each & every client
supplied items)

1.1.1 OverallSize:730x680x500mmhigh Nos 1

BOQ PA-ID-LVL 12 -KIDS CLUB 92


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

1.2 Vanity Mirror


Providing&FixingofOctagonaltypeVanitymirrorofoverallsize640x1020
mmhighmadeof6mmthkclearmirrorwithstrengthenedBack,pasted
overbackplyofrequiredthicknessincludingmetaltrimsallaroundof
MR-202 PS25_DT_160 1
mirror,screws,nails,adhesive,edgepolishing,provisionforlightfixture
andallnecessaryfixingarrangementetc.allcompleteasperdesign&
satisfactionoftheProjectManager.

1.3 Shoe Rack


Providing&fixingofShoeRackconstructedwithfollowingcomponents:
Allthesides,back,verticals&shelvestobemadeofcommercialply&
hardwoodframingofrequiredsection&finishedwith0.8mmthickGrey
Beigelaminateofmattfinishasperapprovedsamplepastedonplyas
PL-202 shownindrawing.
Theitemalsoincludesscrews,nails,adhesive,PVCtape&allnecessary
fixingarrangementsetc.completeasperperdesign,drawing&satisfaction PS25_DT_100, Nos 1
ofProjectManager.

1.4 Office Supply Cabinet


Providing&fixingofOfficeSupplyCabinetUnitconsistsoffollowing
components:
Thebasestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.
Alltheshelves,storagecountertoptobefinishedwith0.8mmthick
MarineBluelaminateofapprovedsamplepastedonplybaseasshownin
PL-205 drawing.
TheinsidefaciaofstorageunitalsofinishedwithsameBluelaminateas
PL-205 shownindrawing.
Thestorageshuttertobefinishedwith0.8mmthickGreyBeigelaminate
PL-202 ofapprovedsamplepastedonplyasshownindrawing.
Theitemincludesproviding&fixingofalthehardware&accessorieslike
hinges,makingoffingergroove,alltheancillarymaterialslikescrews,
nails,adhesive,PVCtape&allnecessaryfixingarrangementsetc. PS25_DT_110 Nos 1
completeasperperdesign,drawing&satisfactionofProjectManager.
(Note:Backwallwallcoveringtobepaidinseparateitem)

1.5 Book Case - I


Providing&fixingof"L"shapedBookCase-IUnitofoverallsize:
(3560x550x2650mmhigh)+(1275x550x2650mmhigh)consistsof
followingcomponents:
Thebasestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.
Thebackwallisfinishedwith0.8mmthickGreyBeigelaminateof
PL-202 approvedsamplepastedonplybaseasshownindrawing.

BOQ PA-ID-LVL 12 -KIDS CLUB 93


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
PL-202,
PL-203, Alltheshelves,storageshutter,verticalstobefinishedwith0.8mmthick
PL-204, GreyBeige,Sunlight,TorchRed&MarineBluelaminateofapproved
PL-205 samplespastedonplybaseasshownindrawing.
Theinsidefaciaofstorageunitalsofinishedwithsamelaminateasshown
indrawing.
PL-202,
PL-205, Thecircularfeaturetobefinishedwith0.8mmthickgreybeige,Marine
UP-203 bluelaminate&fabricofapprovedsampleasshownindrawing.

Theitemincludeswoodenskirting,providing&fixingofalthehardware&
accessorieslikehinges,makingoffingergroove,alltheancillarymaterials PS25_DT_120 Nos 1
likescrews,nails,adhesive,PVCtape&allnecessaryfixingarrangements
etc.completeasperperdesign,drawing&satisfactionofProjectManager.

1.6 Book Case -II


Providing&fixingof"L"shapedBookCase-IIUnitofoverallsize:
(2350x350x2650mmhigh)+(2110x400x2650mmhigh)consistsof
followingcomponents:
Thebasestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.
PL-202,
PL-203, Alltheshelves,storageshutter,verticals,backwalltobefinishedwith0.8
PL-204, mmthickGreyBeige,Sunlight,TorchRed&MarineBluelaminateof
PL-205 approvedsamplespastedonplybaseasshownindrawing.
Theinsidefaciaofstorageunitalsofinishedwithsamelaminateasshown
indrawing.

Theitemincludeswoodenskirting,providing&fixingofalthehardware&
accessorieslikehinges,makingoffingergroove,alltheancillarymaterials PS25_DT_150 Nos 1
likescrews,nails,adhesive,PVCtape&allnecessaryfixingarrangements
etc.completeasperperdesign,drawing&satisfactionofProjectManager.

1.7 Reception Table


Providing&fixingofReceptionTableofoverallsize:1710x650x900mm
highconsistsoffollowings:
Thebasestructureismadeofcommercialplyofrequiredthickness&
hardwoodframingofrequiredsectionasshownindrawing.
Thecountertoptobefinishedwith0.8mmthickGreyBeigelaminateof
PL-202 approvedsamplepastedonplybaseasshownindrawing.
Alltheexposedverticalfacias,storageshutters,drawerfrontstobe
PL-202, finishedwith0.8mmthickGreyBeige&TorchRedlaminateofapproved
PL-204 samplespastedonplybaseasshownindrawing.
Theinsidefaciaofstorageunitalsofinishedwithsamelaminateasshown
indrawing.

BOQ PA-ID-LVL 12 -KIDS CLUB 94


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Theitemincludesskirting,providing&fixingofalthehardware&
accessorieslikehinges,locks,slidingchannels,knobs,makingoffinger
groove,makingprovisionofMEPworks,alltheancillarymaterialslike PS25_DT_130 Nos 1
screws,nails,adhesive,PVCtape&allnecessaryfixingarrangementsetc.
completeasperperdesign,drawing&satisfactionofProjectManager.

1.8 Computer Game Table


Providing&fixingof"L"shaped,curvedfront,CornertypeComputerGame
tableofoverallsize:(3850+2970)x(570/290)x730mmhighconsistsof
followings:
50mmthicktabletopofvariablewidth(variesfrom290mmto570mm
wide)madeofcommercialplyofrequiredthickness&hardwoodframingof
requiredsectiontobefinishedwith0.8mmthickMarineBluelaminateas
PL-205 shownindrawing.
Thetablebottomfaciaallfinishedwithsamelaminateasshownin
drawing.
3noslegsupportstobemadeofbronzemetalofhairlinefinishasper
MT-201 approvedsampletobefixedasshownindrawing.
TheitemincludesmakingprovisionofMEPworks,alltheancillarymaterials
likescrews,nails,adhesive,PVCtape&allnecessaryfixingarrangements PS25_DT_140 Nos 1
etc.completeasperperdesign,drawing&satisfactionofProjectManager.
SUB TOTAL OF "C-1" : -

C.2 LOOSE FURNITURE & AREA RUG WORKS :

Providing&fabricating&placing/fixingofloosefurnitureasperdesign,
drawing,FFE&allfinishingworkcompleteaspersatisfactionofProject
2.1 PS25_PL_001
Manager.(Note:stoneforloosefurniturenottobesuppliedbyClient.
Contractorhastoincludethecostofstoneforloosefurniture)
ChairatComputerGamingArea&ReceptionincludingthecostofFabricas
2.1.1 SX-225 NA Nos 6
perapprovedsample.
LeatheredArmchairatreceptionincludingthecostofFabricasper
2.1.2 SX-212 NA Nos 1
approvedsample.
2.1.3 SX-227 TablenearouterBookCase1 NA Nos 5
2.1.4 SX-228 FloorSeatingNearTVincludingthecostofFabricasperapprovedsample. NA Nos 3
SofaatWaitingareanearentryincludingthecostofFabricasper
2.1.5 SX-226 NA Nos 1
approvedsample.

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

BOQ PA-ID-LVL 12 -KIDS CLUB 95


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
GRAND TOTAL (A+B+C) : -

BOQ PA-ID-LVL 12 -KIDS CLUB 96


Sheraton Hotel Dhaka
BOQ of ID Work - Public Area - Public Toilet @ L-12
Summary

S. No. Description Amount Remarks

A HARD FINISHING WORK -

B MILL WORKS -

FURNITURE WORKS (BUILT-IN &


C -
LOOSE)

TOTAL -
Labour Cess
VAT
Service Tax
Any Other Tax
GRAND TOTAL -
Date: 30-05-17
Sheraton Hotel Dhaka
BOQ of ID Work - Public Toilet @ L-12

S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Notes :
BasicrateswherevergivenintheBOQareformaterialdelivered
atsiteinclusiveofalltaxesdutiesandleviesasapplicable.
AdjustmentofBasicratestobedoneaspertenderdocument.

TheContractorshallstudydrawings,FFEbooklet,notesbefore
quotingtherates.TheContractorhastosubmitindent(Quantity
&make)forallthematerialsuppliedbyEmployer.

Stone/tiles/woodnomenclaturei.etype,sizeetc.mentionedin
theBOQareindicativeonly,subjectedtochange.

Contractorhastoprepareshopdrawingsforalltheworksandto
ensurethatpanelingisfactoryfinishedtotheextentpossible.
Ratesquotedratesareincludingthetopfinishi.epolish,paint
etc.ContractortoreferthecodesmentionedintheBOQ,the
materialspecificationsandfinishingschedulefortopfinishofthe
material.
Hardwoodframing&plythickness(ifnotmentionedinthe
item/drawing)willbefinalizedbasedontheshopdrawingsto
matchtheoverallthicknessoffinishedproduct.
ThewastagepercentageofClientsupplieditemsasfollowsfor
reconciliationpurpose:
Marble:20%
MarbleCuttosize:10%
Granite:10%
Tile:8%

A HARD FINISHING WORK

A.1 FLOORING, SKIRTING & CLADDING WORKS

1.1 Stone Flooring

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 97


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Receiving and laying of Stone in flooring band/ledge/allied
works as mentioned below including all required floor
preparation/cleaning before fixing, bedding with cement mortar
1:4 (1 Cement : 4 Coarse Sand) of minimum 20 mm thick with
required lines/levels and slopes, cleaning after laying of stone,
watering, curing etc. complete. Rates to be applicable for all
1.1.1 levels, heights, leads & lifts, shifting / re-shifting of material
from store to the place of fixing. No extra is payable for
additional thickness of bedding to match adjoining floors, as per
directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

Rate quoted by the contractor to include all labor and materials,


necessary chamfering, grinding, butt jointing, filling of joints
with white cement & matching color pigment, mirror
polishing/honing/other finish (whichever mentioned in following
items) , making of edges, protection of floor with Cello Bubble
guard board and removing the same before handing over etc.
complete as per the approved patterns, designs, specification &
drawings.

Contractor's quoted rates to include the marking of MEP fixtures


and service installations on floors, walls , including making
cutoutsandprovisionsoftemplateswhereverrequired.
No extra will be payable towards additional material wastage
due to pattern. Payment will be in Sqm for visible finished floor
area only. Measurement to be verified as per actual site
condition. (Note: Stone will be supplied by Client free of
cost. Reconciliation statement need to submit for each &
every client supplied items)

With18mmthickCremastoneofpolishedfinishasper
a. ST-203 PS26_PL_005 Sqm 55
approvedsample.

Itemsameas1.1.1butstonetobefixedindoorthresholdas
1.1.2
shownindrawing.

With18mmthickCremastoneofpolishedfinishasper
a. ST-203
approvedsample.
i) 125mmwide PS26_PL_005 Rmt 1
i) 135mmwide PS26_PL_005 Rmt 1
i) 150mmwide PS26_PL_005 Rmt 1

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 98


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

1.2 Stone Skirting & Cladding


Receiving and fixing of stone in skirting/cladding on
Wall/Jamb/allied works of brick walls / concrete walls / columns
as mentioned, in line and level using backing with 20 mm thick
cement mortar 1:3 (1 Cement : 3 Coarse Sand) to the required
lines, levels, pattern and plumbs, pointing the joints with white
cement & matching colour pigment of approved sample as per
specification, including all required surface preparation, cleaning
after fixing etc. complete. Rate to be applicable for all levels,
heights, leads & Lifts, shifting / re-shifting of material from store
to the place of fixing. As per directions and to complete
satisfaction of the Project Manager. Contractor has to perform
theworkaspertheapprovedpattern,specification&drawings.

Rate quoted by the contractor to include all labor and materials,


polishing, moulding, making of edges including necessary
supports, marking of MEP fixtures and service installations on
floors, walls, providing cutout & provisions for template like
electric points, junction boxes, switches and power sockets ,
sanitary fixtures and accessories etc. complete as per the
approvedpatterns,designs,specification&drawings.

(No extra will be payable towards additional material wastage


due to pattern. Payment will be as per actual measurement only.
Measurement to be verified as per actual at site.) (Note: Stone
will be supplied by Client free of cost. Reconciliation
statement need to submit for each & every client supplied
items)

1.2.1 Skirting
200mmhighskirtingwith18mmthickCremastoneofpolished PS26_IE_101,1
a. ST-204 Rmt 61
finishasperapprovedsample. 02,103,104

1.2.2 Cladding
With18mmthickCremastoneofpolishedfinishasper PS26_IE_101,1
a. ST-204 Sqm 48
approvedsample. 02,103,104

Addition/deductionforfixingofstonewithchemicaladhesive
1.3 Sqm RO -
insteadofcementmortarof1:3(1cement:3coarsesand).

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 99


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
1.4 Stone Moulding
Providing and fixing of stone moulding profile in line and level
using backing with 20 mm thick cement mortar 1:3 (1 Cement :
3 Coarse Sand) to the required lines, levels, pattern and plumbs,
pointing the joints with white cement & matching colour pigment
of approved sample as per specification, including all required
surface preparation, cleaning after fixing etc. complete. Rate to
be applicable for all levels, heights, leads & Lifts, shifting / re-
shifting of material from store to the place of fixing. As per
directions and to complete satisfaction of the Project Manager.
Contractor has to perform the work as per the approved pattern,
specification&drawings.

Rate quoted by the contractor to include all labor and materials,


polishing, making of moulding profile as per pattern etc. all
complete as per the approved patterns, designs, specification &
drawings.
(Note: Stone will be supplied by Client free of cost.
Reconciliation statement need to submit for each & every
client supplied items)

PS26_IE_101,
1.4.1 ST-204 80x20mmthickprofilemadeofCremastoneofpolishedfinish. Rmt 61
102,103,104

1.5 SS Inlay
Providing and fixing SS inlay/dividing strip of approved finish
made of stainless steel strip (grade 316) of approved sample at
MT-202 the intersection different types of flooring materials, in line and Rmt RO -
level, including anchoring, fixing, cutting, bending, Polishing etc.
completetothesatisfactionofProjectManager.

SUB TOTAL OF "A-1" -

A.2 FALSE CEILING WORKS

2.1 POP False Ceiling

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 100


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing of10 mm thick Plaster of Paris false ceiling
with G.I. frame work consisting of G.I. 22 gauge main channel
(50x30mm) with molded ends up to 900mm c/c and G.I. 22
gauge cross channel (20x60mm) at 300mm c/c suspended from
the R.C.C. slab with adjustable G.I. sheet suspenders (in main
areas and narrow strips etc.), applying cast-in-situ plaster of
Paris over rabbit wire mesh fixed to cross runners, including
making of cove, groove, including framework & base ply etc.,
2.1.1 NA providing extra framework & ply support/template for electrical NA Sqm RO -
fittings, A/C diffusers,speaker,projector screen and any other cut-
outs, making provision of trap doors ;proving & fixing of
wooden shadow battens (holloc wood, black enamel painted -
25x40mm) at wall peripheries and ends etc., including
scaffolding etc. complete as per detailed drawings & upto
satisfaction of Project manager. (A groove shall be provided at
all the junctions of horizontal and vertical corners).( Note : The
framework may be changed as per site requirement or
manufacture'sspecification.)
Note: surface area to be measured for vertical bands of coves
only if the Vertical height exceeds 200 mm . Within 200 mm PS26_PL_003 Sqm 56
verticals,thePlanareatobemeasuredandpaid

Itemsameas2.1.1butmakingoflightcoveasshownin PS26_PL_003,
2.1.2 NA
drawing. PS23_DT_20
a. Size:120x95mmhigh Rmt 12
2.2 Gypsum False Ceiling
Contractor/Supplier to submit material sample and technical
specification of the specified item from the manufacture for
priorapprovaloftheProjectManager/Architectasnecessary.

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 101


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing and fixing suspended Gypsum Board false ceiling at all
levels & height including reveal, bulkheads, making coves, all
shaped, sized, profiled to details shown on the drawings. The
false ceiling shall be suspended / fixed to the RCC ceiling / MS
structure, with approved GI framing / suspensions / supports
etc. as per manufacturer's specification or as required. Rate to
include cost of all labors, installations, hardware / like &
materials not specified elsewhere, trims, metal inserts (U
Channel) on edges /corner of ceiling and wall for showing
grooves, provision for trap doors, finishing of joints with
proprietary jointing compound, in line and levels etc. all required
for completion and to the PM's approval. Rate quoted to include
all cutouts/templets required for light fixtures, smoke detectors
etc., all complete as per design, drawing, manufactures
specification & satisfaction of project manager.( Note : Visible
executedfalseCeilingAreatobemeasuredandpaidfor.)

Contractor's quoted rates to include the marking of MEP fixtures


and Service installations cellings, including making cutouts and -
provisionsoftemplateswhereverrequired.

Providing & fixing false ceiling comprising of 12.5m thick gypsum


board false ceiling as per detail and drawing, including all
necessary fixing arrangement etc. complete as shown in drawing
2.2.1 NA and directed by the Project Manager including making Sqm RO -
verticals,reveals,filling and finishing the tapered and square
edges of the boards with jointing compound and paper tape etc.
complete (as per recommended practices of India Gypsum or
equivalent).
Itemsameas2.1.1butceilingtobemadewithMRgradeGyp
2.2.2 NA Sqm RO -
boardinsteadofstandardGypboard.

Itemsameas2.1.1butverticalgypsumpartition(Airtight
2.2.3 NA partition)tobemadeoverfalseceilinglevelasdirectedbythe Sqm RO -
Projectmanager.

Extraoveritemno2.1.1to2.1.3forproviding&fixingofply
2.2.4 NA templateofrequiredsizeforlightfixture/otherservicework. Nos RO -

2.3 Trap Door

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 102


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & fixing Trap door made of 12 mm commercial ply &
finished with 6 mm MDF ready to receive paint to match the
gypsum ceiling. The trapdoor edges to be finished with 8mm
thick teak wood lipping. The item is inclusive of making of
groove all around the trap door, any frames with necessary
support structure from the ceiling for resting the trap door Sqm 6
shutters over framework and provision for accessing
units/machines fixed above it and with provision of slots for
return air and a thin black painted GI mesh behind the slots,
tools and tackles etc. required to complete the work to the
satisfactionoftheProjectManager.

SUB-TOTAL OF "A-2"

A.3 PAINTING & POP PUNNING WORKS

3.1 Emulsion Paint


Providingandapplyingoftwoormorecoatsofemulsionpaint
ofapprovedqualityandshadeovertwocoatsofprimer,two
coatsofreadymixputty(BirlaWhiteorequivalent)andtouch
upputtyifrequiredtoachievesmoothfinish,withoutany
undulationordefectsetc.,completetothelevelrequiredfora
premiumhotel;onthepartitions,walls,ceilingasper
specificationanddrawingincludingsandpapering,scraping
fillingallholesanddepressions,scaffolding.Thesurfaceofwall
orceilingtobepaintedshallberollerfinishandpreparedto
thesatisfactionoftheProjectManagerRatetoincludeproviding
&removingbeforepaintingandpeelingoff,aftercompletionof
workprotectivecovers/membranesonfurnitureorfor
protectingexistingwindowpanesorartwork(ifany)and
Removingstains(ifany)fromthefloors,doors,windows,
ventilators,glasspanes,furniture,platforms,plumbingand
otherfixturesetc.allcompleteinallrespectasperinstructionof
ProjectManager.
3.1.1 On ceiling surface
a. PT-202 EmulsionPaintofapprovedsample. PS26_PL_003 Sqm 61

3.1.2 On wall surface


a PT-202 EmulsionPaintofapprovedsample. Sqm RO -

3.3 POP Punning on Walls

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 103


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Providing & applying POP punning on walls upto 8-10 mm thick
as required at site to bring proper line and level for all surfaces
as required including fill in irregularities, making grooves, Sqm 25
scaffoldings etc. complete to achieve a leveled surface and
smooth finish ready for receiving the paint directly as directed
bytheProjectmanager.
3.4 Gypsum Plaster
Providing & applying Gypsum Plaster of approved make as per
manufacturers specifications with suitable bonding agent /
admixture to be directly applied on the walls, RCC Slab, Soffit /
Celling Surface upto 25 ~ 35 mm thick as required including all
material. labour, bonding admixture, surface preparation,
Sqm RO -
adhesive / bond coat, base /scratch coat, finishing coat to proper
line and level for all surfaces as required, fill in irregularities
etc. complete to achieve a leveled surface and smooth finish
ready for receiving the paint directly as directed by the Project
manager.
SUB-TOTAL OF "A-3"

TOTAL OF HARD FINISH WORK (A = A1+A2+A3) -

B MILL WORKS

B.1 DOOR & OTHER ALLIED WORKS

1.1 Handicapped Toilet Door


Providing&fixingofsingleswingdoorconsistsoffollowings:
Door frame made of 50x125 mm thick 1st class Teak wood
fixed to sub frame/wall with holdfast as directed by Project
manger including making necessary grooves, rebate,
chamfering, all necessary fixing arrangements etc. complete as
perdetaileddrawings.
45 mm thick flush door shutter to be finished with Veneer as per
approved sample pasted on it as shown in drawing. Door shutter
WD-201 to be fixed to frame with 3 Nos hinges of approved sample as
shownindrawing.
The item includes providing & fixing of all hardware (as per
approved sample) such as concealed door closer, Stainless Steel
Lever Handle Set with lock system, etc. to be fixed including all
the ancillary material complete as per drawing & hardware
schedule.

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 104


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
The item also includes solid teak wood beading of required size,
polishing of veneer, stone, beading & door frame; screws, nails,
pins, adhesive, door seal, making of groove in veneer & all
necessary fixing arrangements etc. complete as per design,
drawing&satisfactionofProjectManager.
Overallsize:1000x2650mmhigh PS26_DS_001 Nos 1

1.2 Janitor Room Door


ItemsameasabovebutthedoortobefixedinJanitorroom. PS26_DS_001 Nos 1

1.3 Staff Room Door


ItemsameasabovebutthedoortobefixedinStaffroom. PS26_DS_001 Nos 1

1.4 Concealed Shaft Door


Item same as above but door shutter thickness is 35 mm &
shutter finished with paint inside & wallpaper on outside facia. (
Nos 1
Note: wall paper will be paid under separate item) overall size :
400x2650mmhigh

SUB-TOTAL OF "B-1"

B.2 PARTITION, PANELING & OTHER ALLIED WORKS

2.1 Wall Covering


Providing&Fixingofwallcoveringofapprovedsamplepastedon
POPfinishedsurfaceorGypsumpanelingsurfacewithadhesive
ofapprovedmakeincludingallnecessarysurfacepreparationfor
pastingofwallpaper,straighteningofroll,pattern,fixing,
PS26_IE_101,1
WC-202 matchingthejoints,providingslotsofcutoutsforMEPworksand Sqm 96
02,103,104
allnecessaryarrangementsetc.allcompleteasperthedesign,
detaildrawing,specificationsandtothesatisfactionofProject
Manager. (Note: POP/Gypsum paneling to be paid under
separate item.)

2.2 Laminated Partitions


Providing & fixing of High Pressure Laminate partition with door
of approved make including door hardware, clamps, clips, posts
PL-201 & all necessary supports, fixing arrangements etc. all complete PS26_DS_001
as per drawing, manufacture's specification and satisfaction of
theProjectManager.
2.2.1 Fixedpartition Sqm 27
2.2.2 Openablepartition(Door) Sqm 9

2.3 Gypsum Paneling for Wall Covering Base

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 105


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
Framework : Providing and fixing GI Frame work (gypsteel -
India gypsum/Ultra) of 50 mm boxed studs ( 0.55 mm thick,
having one flange of 34mm and another flange of 36 mm) for
vertical members and U-channels (0.55 mm thick, having equal
flanges of 32 mm) for horizontal members placed at 600 mm
centre to centre both ways with joints staggered to avoid
through joints. The frame work is to be adequately anchored in
support having additional framework of rough wood treated with
anti-termite and fire retardant paint for fixing storages, fire
extinguishers paintings, switch boxes, door frames, wood edge,
Artwork etc. complete straight & curved as per drawing. ( Note :
The framework may be changed as per site requirement or
manufacture'sspecification.)
Skin : Providing and fixing 12.5mm thick (Single layer) Gyp
board cladding as per approved sample fixed with dry wall
screws of 25mm at 300mm centre, square and tapered edges of
the boards are to be jointed and finished so as to have a flush
look which includes filling and finishing with jointing compound,
fiber tape and two coats of primer suitable Gyp board, making
1/2" grooves with aluminum angle on edge as shown in drawing. Sqm 71
The external angles of the paneling having Gyp board has to be
protected by using angles, beads (25x25x0.5) and all exposed
edges of Gypboard have to be protected edge bead
25x12.5x0.5). The item includes all the other fixing
arrangements, cost of scaffolding etc. complete as per design &
drawing.
SUB TOTAL OF "B-2" : -

TOTAL OF MILL WORK ( B = B1+B2 ) : -

C FURNITURE WORKS

C.1 BUILT-IN FURNITURE WORKS :


Note:ContractorneedtosubmittheShop Drawingsofallthe
furniture&obtainwrittenapprovalfromappropriateauthorityas
perTenderDocument.

1.1 Vanity Counter


Providing&fixingofVanityCounterconstructedwithfollowing
1.1.1
components:
ThebasestructureismadeofBWPplyofrequiredthicknesswith
MSframingofrequiredsection.

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 106


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.
ThecountertopmadeofCompositewhitemarble(suppliedby
client)ledgedropisfinishedwithstoneofpolishedfinishpasted
overwoodenbaseasshownindrawing.
BottomboxingunitfinishedwithStainlessSteelHairlineFinish
MT-101 asperapprovedsamplepastedonplybasewithapproved
adhesiveasshownindrawing.
Theitemincludesbasinholecutting,makingprovisionforMEP
fixtures,polishingofstone,edgemolding/chamfering,all
necessaryhardware,adhesive,primerforMSframing,allother
necessaryfixingarrangementsetc.allcompleteasperdesign,
PS26_DT_100,
detaileddrawing&satisfactionoftheProjectManager.(Note:
PS26_IE_101
Stone will be supplied by Client free of cost.
Reconciliation statement need to submit for each & every
client supplied items)

OverallSize:1140x670x500mmhigh(AtMaleToilet) Nos 2
OverallSize:4540x670x500mmhigh(AtFemaleToilet) Nos 1

Itemsameasabove1.1.1butvanitycountertobemade PS26_DT_110,
1.1.2
withoutbottomboxingasshownindrawing. PS26_IE_104
OverallSize:900x470x150mmhigh(AtHandicappedToilet) Nos 1

1.2 Luggage Counter


Itemsameasabove1.1.1butthecountertobemadeexcluding PS26_DT_110,
basinholecuttingshownindrawing. PS26_IE_104
OverallSize:1020x370x850mmhigh Nos 2

1.3 Vanity Mirror


Providing&FixingofOctagonaltypeVanitymirrorofoverallsize
640x1020mmhighmadeof6mmthkclearmirrorwith
strengthenedBack,pastedoverbackplyofrequiredthickness PS26_DT_100,
includingmetaltrimsallaroundofmirror,screws,nails, 110; Nos 9
MR-202
adhesive,edgepolishing,provisionforlightfixtureandall PS26_IE_104
necessaryfixingarrangementetc.allcompleteasperdesign&
satisfactionoftheProjectManager.

1.3 Urinal Partition


Providing & fixing of urinal partition of overall size (390mm x
810mm high mm high made of 18-20 mm thick stone of
approved sample fixed to wall with SS bracket of approved PS26_DT_120,
sample. The item includes bracket, screws, fastener, adhesive PS26_IE_101
and all necessary fixing arrangements etc. all complete as per
design,detaileddrawingandsatisfactionoftheProjectManager. Nos 3

SUB TOTAL OF "C-1" : -

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 107


S.
Code Item Description Drawing No. Unit Quantity Rate Amount Remarks
No.

C.2 LOOSE FURNITURE & AREA RUG WORKS :

Providing&fabricating&placing/fixingofloosefurnitureasper
2.1 design,drawing,FFE&allfinishingworkcompleteasper
satisfactionofProjectManager.
NIL

SUB TOTAL OF "C-2" : -

TOTAL OF FURNITURE WORK (C=C1+C2) : -

GRAND TOTAL (A+B+C) : -

BOQ-PA-ID-LVL 12 PUBLIC TOILETS 108

Vous aimerez peut-être aussi