SHAPOORJI PALLONJI AND COMPANY P LTD

COMMENT COMPLAINCE REPORT

DATE: REPORT NO: SPCPL/SAMTA/MEP/COMCOM/____/2017-18/SALE - ALPINE

SR NO POINT RAISED AREA PICTURE REMARK CLOSURE DATE PICTURE REMARK

Block Works need 16 th Flr,


Bull mark Required
1 to be completed for Apt-1,
after Block Work
conduit chasing Master Toilet

Lintel Work needs to


Tile Bull Mark
be Constructed with
16th to 22nd Flr, Pending & Wall Bull
2 Block Works for DB
Appt-4 & 3 Mark is required for
Chasing &
DB Installations
Conduiting Works

Lintel Work needs to


Tile Bull Mark
be Constructed with
Pending & Wall Bull
3 Block Works for DB 16 Flr,Appt-2
Mark is required for
Chasing &
DB Installations
Conduiting Works

Block Works with


Lintel needs to be Tile Bull Mark &
4 constructed for 19th Flr Appt-3 Walls Bull Mark is
conduit chasing and required
DB Works

Lintel Work needs to


Tile Bull Mark
be Constructed with
16th to 22th Flr, Pending & Wall Bull
5 Block Works for DB
Appt-2 Mark is required for
Chasing &
DB Installations
Conduiting Works

Mulliens to be filled
since chasing work
6 19th Flr Appt-3 Bull mark Required
may damage the
wall.

Block Work needs


Tiles Bull Mark is
to be constructed 16th Flr,Appt-1,
7 required for Metal
for conduit chasing Common Toilet
box fixing.
works

Seperation Wall
Between Childrens
Wall bull mark is
8 Bedrrom & Master 19th Floor Appt-1
required.
Bedroom needs to
be constructed.

Kitchen Linten Work


needs to be
Tile Bull Mark is
9 constructed will 19th Flr,Apt-2
required
block work for
bracket light points
Linten Work is Tile Bull Mark is
required with block required inside &
10 19th Flr,Apt-2
work for DB Wall Bull Mark is
Chasing activities required Outside
Tower-1 STATUS OF THE ELECTRICAL WORKS DUE TO DEPENDENCIES Date 27-Jun-17
Symbol Descrpition
Stattus Results Complete
x InComplete
NA Not Applicable

Linten Works in Wall Conduiting Wall


Kitchen & Work is in Chasing &
Toilets - DB Progress, Box Fixing Common
Work/Bracket Work Front is Choke Up & DB Wall Master &
Light is Toilet Tile avilable since Repairing Rope Conduitin Installation/L Plaster Common
Flr Appt Pending Bull Mark 20.6.17 Works Pulling g V & LP Wall Construction Dependencies Balance Toilet Wall
Appt-1 x x WIP WIP WIP x x
Appt-2 x x WIP WIP WIP x NA
16th Floor
Appt-3 x x x NA NA
Appt-4 x x WIP x NA NA
Appt-1 x x x x x
Appt-2 x x x x NA
17th Floor
Appt-3 x x x x x- Main Door NA NA
Appt-4 x x x x x- Main Door NA NA
Appt-1 x x x x x
Appt-2 x x x x x- Kitchen Wall NA
18th Floor
Appt-3 x x x x NA NA
Appt-4 x x x x x- DB Wall Broken NA NA
Appt-1 x x x x
Appt-2 x x x x NA
19th Floor
Appt-3 x x x x x- Main Door NA NA
Refuge
Appt-1 x x x x
Appt-2 x x x x x- Kitchen Wall & Bedroom Wall NA
20th Floor
Appt-3 x x x x x- Main Door NA NA
Appt-4 x x x x x- Main Door NA NA
Appt-1 x x x x
Appt-2 x x x x NA
21st Floor
Appt-3 x x x x x- Main Door NA NA
Appt-4 x x x x x- Main Door NA NA
Appt-1 x x x x
Appt-2 x x x x NA
22nd Floor
Appt-3 x x x x x- Main Door NA NA
Appt-4 x x x x x- Main Door NA NA
Tower-2 STATUS OF THE ELECTRICAL WORKS DUE TO DEPENDENCIES Date 27-Jun-17
Symbol Descrpition
Stattus Results Complete
x InComplete
NA Not Applicable

Linten Works in Wall


Kitchen & Chasing & Wall
Toilets - DB Box Fixing Construction
Work/Bracket Work is in Progress, Work Choke Up & DB Dependencies,Ki Master & Common
Light is Toilet Tile Front is avilable since Repairing Rope Conduitin Installatio tchen & Main Common Wall Toilet Wall for 2.5
Flr Appt Pending Bull Mark 20.6.17/Wall Bull Mark Status Works Pulling g n/LV & LP Door Plaster Balance BHK
Appt-1 x x x x
Appt-2 x x x NA
16th Floor
Appt-3 x x x NA NA
Appt-4 x x x NA NA
Appt-1 x x x
Appt-2 x x x NA
17th Floor
Appt-3 x x x x NA NA
Appt-4 x x x x NA NA
Appt-1 x x WIP x
Appt-2 x x WIP x NA
18th Floor
Appt-3 x x WIP x NA NA
Appt-4 x x WIP x NA NA
Appt-1 x x x x WIP x x
Appt-2 x x x x WIP x x NA
19th Floor
Appt-3 x x x x WIP x NA NA
Refuge NA
Appt-1 x x x x WIP x
Appt-2 x x x x WIP x NA
20th Floor
Appt-3 x x x x WIP x NA NA
Appt-4 x x x x WIP x NA NA
Appt-1 x x x x x x x
Appt-2 x x x x x x x NA
21st Floor
Appt-3 x x x x x x x NA NA
Appt-4 x x x x x x x NA NA
Appt-1 x x x x x x x
Appt-2 x x x x x x x NA
22nd Floor
Appt-3 x x x x x x x NA NA
Appt-4 x x x x x x x NA NA
Tower-2 STATUS OF THE ELECTRICAL WORKS DUE TO DEPENDENCIES

Stattus Results
Flr Appt

16th
Floor
Appt-1 VPD is not completed, Kitchen GLD choke up is pending,Main Ckt Rope Pulling is Pending

Main Ckt Rope Pulling is Pending, K/n Aq guard pt is pending,Kitchen GLD choke up is pending,
Appt-2 Master Toilet W/m pt to be installed with RCC Chipping , Conduiting & box fixing in NSW

Appt-3 Main Ckt Rope Pulling is Pending, Kitchen Reworks as per CVI

Appt-4 Main Ckt Rope Pulling is Pending, Kitchen Reworks as per CVI,Mater Toilet BL is pending.

17th
Floor
Appt-1 Main Ckt Rope Pulling is Pending,VPD is not completed, Kitchen E/h fan Pt is pending as per CVI
Main Ckt Rope Pulling is Pending,VPD is not completed, Choke for GLD in Kitchen is pending, Deck
area Living Drop Opening is pending, W/m pt is pending in Service Deck,MB Bed Site Control point
Appt-2 Back Box needs to be refixed as alignment is improper.

Main Ckt Rope Pulling is Pending, Kitchen Rework is pending, Kitchen Conduiting work is
Appt-3 incomplete, MB- BL is pending.

Appt-4 Main Ckt Rope Pulling is Pending, K/t Reworks is pending

18th
Floor Main Ckt Rope Pulling is Pending, Kitchen Rework is pending,GLD Choke up is pending, Camera
Appt-1 Point is pending.

Appt-2 Main Ckt Rope Pulling is Pending, Kitchen Rework is pending


Main Ckt Rope Pulling is Pending, Kitchen Reworks is pending with mains conduiting work is
incomplete. CB- 3M & 2 M is needs alignment, SB-1 Entrace Conduiting & Choke Up needs to be
Appt-3 done.

Appt-4 Main Ckt Rope Pulling is Pending Kitchen Reworks is pending