COMPARACION ENTRE PERFIL Y EXP. TECNICO: MEJORAMIENTO DEL SERVICIO EDUCATIVO EN LA I.E.

N 82077 NIVEL PRIMARIO DEL CASERIO


LA FORTUNA,
DISTRITO DE OTUZCO, PROVINCIA DE OTUZCO - LA LIBERTAD - II ETAPA"

MONTO DE EJECUCION DE LA OBRA - SEGUNDA ETAPA


PERFIL VIABLE EXPEDIENTE TECNICO
ITEM DESCRIPCION Und. Metrado Precio S/. Parcial S/. Und. Metrado Precio S/. Parcial S/.

01 CERCO PERIMETRICO + INGRESO PRINCIPAL 220,056.17 51,643.03


01.02 OBRAS PROVICIONALES * UND 1.00 697.60 697.60 GBL 1.00 714.37 714.37
01.03 TRABAJOS PRELIMINARES ** GBL 1.00 759.46 759.46
01.04 MOVIMIENTO DE TIERRAS * *** UND 1.00 41,274.33 41,274.33 GBL 1.00 160.72 160.72
01.05 OBRAS DE CONCRETO SIMPLE * *** UND 1.00 30,075.98 30,075.98 GBL 1.00 6,691.95 6,691.95
01.06 OBRAS DE CONCRETO ARMADO * *** UND 1.00 74,870.48 74,870.48 GBL 1.00 15,620.15 15,620.15
01.07 MURO DE TABIQUERIA Y ALBAILERIA * UND 1.00 13,107.44 13,107.44 GBL 1.00 13,788.27 13,788.27
01.08 REBOQUES ENCLUIDOS Y MOLDURAS *** UND 1.00 30,939.86 30,939.86 GBL 1.00 3,592.80 3,592.80
01.09 CONTAZOCALOS UND 1.00 4,023.63 4,023.63
01.10 PINTURA *** UND 1.00 14,903.83 14,903.83 GBL 1.00 7,315.31 7,315.31
01.11 CARCO CON MALLA OLIMPICA * *** UND 1.00 3,628.80 3,628.80 GBL 1.00 3,000.00 3,000.00
01.12 OTROS UND 1.00 4,734.35 4,734.35
01.13 FLETE TERRESTRE UND 1.00 1,799.87 1,799.87
02 LOSA MULTIUSOS 47,465.73 72,418.52
02.01 MOVIMIENTO DE TIERRAS * *** UND 1.00 160.50 160.50 GBL 1.00 226.14 226.14
02.02 CONCRETO SIMPLE * *** UND 1.00 37,461.73 37,461.73 GBL 1.00 54,387.65 54,387.65
02.03 VARIOS * *** UND 1.00 436.40 436.40 GBL 1.00 640.58 640.58
02.04 REVOQUES ENCLUIDOS MOLDURAS * *** UND 1.00 5,398.20 5,398.20 GBL 1.00 9,250.27 9,250.27
02.05 CARPINTERIA METALICA * *** UND 1.00 3,158.80 3,158.80 GBL 1.00 6,899.22 6,899.22
02.06 PINTURA * *** UND 1.00 850.10 850.10 GBL 1.00 1,014.66 1,014.66
03 MURO DE CONTENCION 0.00 24,719.56
03.01 MOVIMIENTO DE TIERRAS ** GBL 1.00 772.88 772.88
03.02 MURO CICLOPEO ** GBL 1.00 23,247.65 23,247.65
03.03 VARIOS ** GBL 1.00 699.03 699.03
COSTO DIRECTO S/. 267,521.90 S/. 148,781.11
GASTOS OPERATIVOS (10%) S/. 26,752.19 S/. 14,878.11
UTILIDAD (5%) S/. 13,376.10 S/. 0.00
SUB TOTAL S/. 307,650.19 S/. 163,659.22
IGV (18%) S/. 0.00 S/. 0.00
VALOR REFERENCIAL S/. 307,650.19 S/. 163,659.22
EXPEDIENTE TECNICO S/. 0.00 S/. 0.00
SUPERVISION S/. 15,382.51 S/. 0.00
MITIGACION DE IMPACTO AMBIENTAL S/. 0.00 S/. 0.00

COSTO TOTAL DE INVERSION S/. 323,032.69 S/. 163,659.22


* Actualizacion de Precios
** Nuevas Metas EXPEDIENTE TEC. 163,659.22
*** Mayores Menores Metrados TOTAL 163,659.22

% DE IMPACTO SOBRE EL MONTO DE INVERSION VIABLE -8.26%

PRESUPUSTO PIP VIABLE PIP MODIF. (EXP. TEC.)


1 PPT 1929577 5=(4+2) TOTAL 1770203.52675
PROYECTO
3 I-ETAPA S/. 323,032.69 2 I-ETAPA 163,659.22
4=(1-3) 1606544.30575 6=(5-1) -159373.47325

7=(6/1) % -8.26%