Vous êtes sur la page 1sur 32

Construction of San Isidro Small Water

Impounding Project (SWIP)


La Paz, Tarlac

Weekly Report
June 6-9 ,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:

Engr. Roxanne Del Rosario

Approved By:

Engr. Michael J. David


Weekly Report
Date June 6-9, 2017

Accomplishment:

Flooring:
Length = 56m
Width= 5.178m
*From Station 0 + 650 to 0 + 706

Activities:

June 6 June 7 June 8 June 9


Embankment Continuation of Continuation of Continuation of
Excavation Embankment Embankment Embankment
continuation from Sta. Excavation Excavation (Preparing Excavation (Preparing
0+650 the flooring) the flooring & Slope
Reinforcement Start of Concrete Continuation of Continuation of
Formwork starting Pouring (flooring) at Concrete Pouring Concrete Pouring
from Sta. 0+650 Sta. 0+650 (flooring) (At Sta. (Flooring) (From Sta.
0+665) 0+655)
Pumping Water out of Continuation of Continuation of Continuation of
the flooring. Reinforcement Reinforcement Reinforcement
Formwork to continue Formwork to continue Formwork to continue
concrete pouring. concrete pouring. concrete pouring.
- Pumping Water out of Pumping Water out of Pumping Water out of
the bed the bed the bed

Equipment:

Description Total Hours Consumption Activities


Backhoe 45 Embankment Excavation
Water Pump 45 Draining the water out of bed
soil/flooring
MATERIALS ( FROM PREVIOUS WEEK)

REMAINI REMARKS
DESCRIPTION DELIVERED USED
NG
12mm 463 - - Reinforcement
C.Purling 20 - - Formworks
Pipe 32 - - Formworks
GI Sheets(6m) 38 - - Barracks roof
Ordinary Plywood 22 - - Barracks Material
150L (May 16)
Diesel (Backhoe 170L (May 18)
636L - -
11) 149L (May19)
167L (May20)
Diesel (Water -
5L - -
Pump)
Diesel (Dump -
70L - -
truck)
Diesel (Backhoe -
266L - -
#15)
Mp3 Greese -
- - -
(Backhoe #15)
G.I. Wire 1 roll - - -
Shovel 5 - - Manual Excavation
Nilon Rope 1 roll - - -

Materials: (Week 1)
REMAINI REMARKS
DESCRIPTION DELIVERED USED
NG
12mm 463(Stock) 303 160 Reinforcement
Diesel (Backhoe -
336L - -
#15)
Concrete
Concrete Mix 50 - -
Pouring(Flooring)
Date: June 06,2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 PM Excavation
1:00 5:00 PM Elevating the
Ground
Water 1 8:00 11:00 AM Draining of the
Pump 1:00 5:00 PM water in soil
bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel
Oil
12mm 463 240 223
C Purlins 32 - - -
Pipe 32 - - -

Activity/s:
Embankment Excavation
Reinforcement Form Work
Pumping Water out of the bed flooring

Accomplishment/s:
Portion of the Embankment has been excavated (At Station 0+650)
Reinforcement Form work starts at Sta. 0+650
Date: June 07, 2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 11:00 AM Excavation
1:00 5:00 PM Elevating the
Ground
Water 1 8:00 11:00 AM Draining of the
Pump 1:00 5:00 PM water in soil
bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel 284 L
Oil
12mm 223 - 223
C Purlins 32 - - -
Pipe 32 - - -
Concrete Mix - 15 15 -

Activity/s:
Continuation Embankment Excavation from Sta. 0+650
Continuation Reinforcement Form Work
Pouring of the concrete in flooring starts at Sta. 0+650

Accomplishment/s:
Portion of the Embankment has been excavated. (At Station 0+640 to Station 0+580 has been
started to excavate)
Portion of the floor has been poured with concrete.

Date: June 08,2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel
Oil
12mm 223 63 160
C Purlins 32 - - -
Pipe 32 - - -
Concrete Mix - 20 20 -

Activity/s:
Embankment Excavation
Reinforcement Form Work

Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Date: June 09,2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel
Oil
12mm 160 - - 160
C Purlins 32 - - -
Pipe 32 - - -
Concete Mix - 15 15 -

Activity/s:
Concreting(Floor)
Embankment Excavation

Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Construction of San Isidro Small Water
Impounding Project (SWIP)
La Paz, Tarlac

Weekly Report
June 13-16 ,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:

Engr. Roxanne Del Rosario

Approved By:
Engr. Michael J. David

Weekly Report
Date June 13-16, 2017

Accomplishment:

Flooring:
Length = 94m (this measure from Station 0+706 to 0+800)
Width= 5.178m

Slope:
Length = 27m ( 27 m was measured between station 0+650 to 0+680)
Width= 4m

Activities:
June 13 June 14 June 15 June 16
Embankment Continuation Continuation Continuation
Excavation (At Station Embankment Embankment Embankment
0+640 to 0 Excavation (At Station Excavation (At Station Excavation (At Station
=580) 0+640 to 0 0+640 to 0 0+640 to 0
=580) =580) =580)
Reinforcement Reinforcement Reinforcement Reinforcement
Formwork (Slope at Formwork (Slope at Formwork (Slope at Formwork (Slope at
0+650) 0+650) 0+650) 0+650)
Concrete Pouring (At Continuation of Continuation of Continuation of
Sta. 0+706) Concrete Pouring (At Concrete Pouring (At Concrete Pouring (At
Sta. 0+706) Sta. 0+706), Concrete Sta. 0+706), Concrete
Pouring (Slope at Pouring (Slope at
0+650) 0+650)
Pumping water out of Pumping water out of Pumping water out of Pumping water out of
the bed flooring the bed flooring the bed flooring the bed flooring

Equipment:

Description Total Hours Consumption Activities


Backhoe 45 Embankment Excavation
Draining the water out of bed
Water Pump 45
soil/flooring
Materials:

Description Stock Delivered Used


12mm 160 600 710
GI Wire(Roll) 1 - -
C Purlins 32 - -
Pipe 32 - -
Diesel - 200 L -
Oil - - -
Concrete Mix - 130 cu.m 130 cu.m
Date: June 13, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
5 Skilled
10 Laborer

Equipment/s:

Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I - 1 - -
Wire(Roll)
Diesel
Oil
12mm 160 400 240 320 (12mm bar was
delivered on 06/10)
C Purlins 32 - - -
Pipe 32 - - -
75(5 cu.m This include delivered
Concrete 75(5 cu.m was was on 06-10,06-11 & 06-12,
-
Mix(cu.m) today delivered) today 5cu.m,45cu.m,20cu.m
delivered) respectively

Activity/s:
Concreting(Floor)
Embankment Excavation
Reinforcement Form Work (Floor & Embankment)

Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 14,2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

10 Laborer

Equipment/s:

Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel
Oil
12mm 320 - 220 100
C Purlins 32 - - -
Pipe 32 - - -
Concrete
- 15 15 -
Mix(cu.m)

Activity/s:
Concreting(Flooring)
Embankment Excavation
Reinforcement Form Work

Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 15, 2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll)
Diesel
Oil
12mm 100 - 100 -
C Purlins 32 - - -
Pipe 32 - - -
Concrete
- 15 15 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work

Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 16, 2017

Manpower:

1 Leadman/Foreman 1 checker

1 Backhoe Operator 1 OJT

5 Skilled

7 Laborer

Equipment/s:

Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remaining Remarks


G.I Wire(Roll) - 2 - -
Diesel - 287 L - -
(BackHoe #15)
Oil
12mm steel 100 200 100 200
C Purlins 32 - - -
Pipe 32 - - -
Concrete
- 25 25 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.

Construction of San Isidro Small Water


Impounding Project (SWIP)
La Paz, Tarlac

Weekly Report
June 19-23 ,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:

Engr. Roxanne Del Rosario

Approved By:
Engr. Michael J. David

Weekly Report
Date June 19-23, 2017

Accomplishment:

Flooring:
Length = 76m (The 60m was measured at station 0+640 to 080, 16m was measure at station 0+640)
Width= 5.178m

Slope:
Length = 113m (113m was measured between Sta. 0+650 to 0+640 & Station 0+660 to 0+720)
Width= 4m

Activities:
June 19 June 20 June 21 June 22 June 23
Embankment Continuation of Continuation of Continuation of Continuation of
Excavation(Prepar Embankment Embankment Embankment Embankment
ing the Flooring At Excavation(Prepar Excavation(Prepar Excavation(Prepar Excavation(Prepar
Station 0+640 to ing the Flooring At ing the Flooring At ing the Flooring At ing the Flooring At
Station 0+580) Station 0+640 to Station 0+640 to Station 0+640 to Station 0+640 to
Station 0+580) Station 0+580) Station 0+580) Station 0+580)
Concrete Continuation of Concrete Concrete Concrete
Pouring(Slope at Concrete Pouring(Slope at Pouring(Slope at Pouring(Slope at
Station Pouring(Slope at Station 0+680) Station 0+700, Station 0+720,
0+660,Slope at to Station 0+660) Flooring at Station Flooring at Station
0+650 to 0+630) 0+640 to 0+580) 0+640 to 0+580)
Pumping water Pumping water Pumping water Pumping water Pumping water
out of the bed out of the bed out of the bed out of the bed out of the bed
flooring(At Station flooring(At Station flooring(At Station flooring(At Station flooring(At Station
0+640) 0+640) 0+640) 0+640) 0+640)
Reinforcement Reinforcement Reinforcement Reinforcement Reinforcement
Formwork(At Formwork(Slope Formwork(Slope Formwork(Slope Formwork(Slope
Station 0+660) At Station 0+660) At Station 0+640 At Station 0+640 At Station 0+640
to 0+580) to 0+580) to 0+580)

Equipment:

Description Total Hours Consumption Activities


Backhoe 45 Embankment Excavation
Water Pump 45 Draining the water out of bed
soil/flooring

MATERIALS ( FROM PREVIOUS WEEK)

DESCRIPTION DELIVERED USED REMAINI REMARKS


NG
Concrete Mix 25 25 - Concrete Pouring
20cu.m(June 17)
5 cu.m(June 18)
12mm steel 400 - - Reinforcement
(delivered on June 17)

Materials: (Week 3)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm 600 468 132 Reinforcement
Shovel 10 - - -
Concrete Mix 50 - - Concrete
Pouring(Flooring)
Diesel (Backhoe 350L - - 150L(June 19)
#15) 200L(June 22)
Diesel (Dump 100L - - -
Truck)
Tansi 4 Roll - - -
Date: June 19, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel 100 L (50L Gamurot
& 50L Domeng
Dump Truck)
150 L (BackHoe #15)
Oil
12mm 200 400 180 420 The delivery of steel was
steel on June 17
C Purlins 32 - - -
Pipe 32 - - -
Concrete - 20 20 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at Sta. 0+650 to 0+630 has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 20, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm 420 - 120 300
steel
C Purlins 32 - - -
Pipe 32 - - -
Concrete - 10 10 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at Station 0+660 to 0+690 has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 21, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm 300 - 136 164
steel
C Purlins 32 - - -
Pipe 32 - - -
Concrete - 20 20 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work

Accomplishment/s:
Slope at 0+690 to 0+710 has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 22, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel 200L (Backhoe #15)
Tansi (Roll) 4
12mm 164 400 246 318
steel
C Purlins 32 - - -
Pipe 32 - - -
Concrete - 25 25 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at 0+710 to 0+730 has been poured with concrete.
Flooring at 0+640 to 0+610 has been poured with concrete.
Portion of the Embankment has been excavated.

Date: June 23, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 8:00 12:00 Excavation
PM Elevating the
1:00 5:00 PM Ground
Water 1 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm 318 - 186 132
steel
C Purlins 32 - - -
Pipe 32 - - -
Concrete - 15 15 -
Mix(cu.m)

Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work

Accomplishment/s:
Flooring at 0+610 to 0+580 has been poured with concrete.
Slope at 0+730 to 0+770 has been poured with concrete.
Portion of the Embankment has been excavated.

Construction of San Isidro Small Water


Impounding Project (SWIP)
La Paz, Tarlac

Weekly Report
June 27-30 ,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:

Engr. Roxanne Del Rosario


Approved By:

Engr. Michael J. David

Accomplishment Report:

No operation due to heavy rainfall, there is high level of flood.


Construction of San Isidro Small Water
Impounding Project (SWIP)
La Paz, Tarlac

Weekly Report
June 3-7,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:

Engr. Roxanne Del Rosario


Approved By:

Engr. Michael J. David

Weekly Report
Date July 3-7, 2017

Accomplishment:

Berm:
Length: 143m (measured from station 0+650 to 0+0793)
Width: 1m

Activities:
July 3 July 4 July 5 July 6 July 7
No operation No operation No operation Concrete pouring No operation
of Berm (At
Station 0+650)

Equipment:

Description Total Hours Consumption Activities


Backhoe -
Water Pump - -

Materials: (Week 5)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm - - - -
- - - - -
Concrete Mix 5 5 - Concrete
Pouring(Berm)
Diesel (Backhoe - - - -
#15)
Diesel (Dump - - - -
Truck)
- - - - -
- - - - -

Construction of San Isidro Small Water


Impounding Project (SWIP)
La Paz, Tarlac

Weekly Report
July 10-14 ,2017

Prepared by:

VELASQUEZ Jr., Marciano M.


OJT

Noted:
Engr. Roxanne Del Rosario

Approved By:

Engr. Michael J. David

Weekly Report
Date July 3-7, 2017

Accomplishment:

Berm:
Length: 143m (measured from station 0+650 to 0+0793)
Width: 1m

Activities:
July 10 July 11 July 12 July 13 July 14
No operation No operation Topping/Sealing Topping/Sealing Topping/Sealing
the crack between the crack between the crack between
station 0+650 station 0+650 station 0+650
Pumping Water Pumping Water Pumping Water
out of the bed out of the bed out of the bed
flooring flooring flooring
Reinforcement Reinforcement Reinforcement
formwork formwork formwork

Equipment:

Description Total Hours Consumption Activities


Backhoe -
Water Pump - -

Materials: (Week 5)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm 400 150 250 Reinforcement
formwork
- - - - -
Concrete Mix - - - -
Cement 5 bags 5 bags - -
- - - - -
- - - - -
- - - - -

Date: July 12, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 - - - -
Water - 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm - 400 40 360
steel
C Purlins 32 - - -
Pipe 32 - - -
Cement - 5 bags 2 3

Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)

Date: July 13, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 - - - -
Water - 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm - 360 50 310
steel
C Purlins 32 - - -
Pipe 32 - - -
Cement 3 bags - 2 1

Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)

Date: July 14, 2017

Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled

Equipment/s:

Descriptio Quantity Working Hours Diesel Oil Activities


n
Backhoe 1 - - - -
Water - 8:00 11:00 Draining of the
Pump AM water in soil
1:00 5:00 PM bed/flooring

Material/s:

Description Stock Delivered Used Remainin Remarks


g
G.I Wire(Roll)
Diesel
Oil
12mm - 310 60 250
steel
C Purlins 32 - - -
Pipe 32 - - -
Cement 3 bags - 2 1

Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)

Vous aimerez peut-être aussi