Weekly Report
June 6-9 ,2017
Prepared by:
Noted:
Approved By:
Accomplishment:
Flooring:
Length = 56m
Width= 5.178m
*From Station 0 + 650 to 0 + 706
Activities:
Equipment:
REMAINI REMARKS
DESCRIPTION DELIVERED USED
NG
12mm 463 - - Reinforcement
C.Purling 20 - - Formworks
Pipe 32 - - Formworks
GI Sheets(6m) 38 - - Barracks roof
Ordinary Plywood 22 - - Barracks Material
150L (May 16)
Diesel (Backhoe 170L (May 18)
636L - -
11) 149L (May19)
167L (May20)
Diesel (Water -
5L - -
Pump)
Diesel (Dump -
70L - -
truck)
Diesel (Backhoe -
266L - -
#15)
Mp3 Greese -
- - -
(Backhoe #15)
G.I. Wire 1 roll - - -
Shovel 5 - - Manual Excavation
Nilon Rope 1 roll - - -
Materials: (Week 1)
REMAINI REMARKS
DESCRIPTION DELIVERED USED
NG
12mm 463(Stock) 303 160 Reinforcement
Diesel (Backhoe -
336L - -
#15)
Concrete
Concrete Mix 50 - -
Pouring(Flooring)
Date: June 06,2017
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Material/s:
Activity/s:
Embankment Excavation
Reinforcement Form Work
Pumping Water out of the bed flooring
Accomplishment/s:
Portion of the Embankment has been excavated (At Station 0+650)
Reinforcement Form work starts at Sta. 0+650
Date: June 07, 2017
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Material/s:
Activity/s:
Continuation Embankment Excavation from Sta. 0+650
Continuation Reinforcement Form Work
Pouring of the concrete in flooring starts at Sta. 0+650
Accomplishment/s:
Portion of the Embankment has been excavated. (At Station 0+640 to Station 0+580 has been
started to excavate)
Portion of the floor has been poured with concrete.
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Material/s:
Activity/s:
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Date: June 09,2017
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring
Material/s:
Activity/s:
Concreting(Floor)
Embankment Excavation
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Construction of San Isidro Small Water
Impounding Project (SWIP)
La Paz, Tarlac
Weekly Report
June 13-16 ,2017
Prepared by:
Noted:
Approved By:
Engr. Michael J. David
Weekly Report
Date June 13-16, 2017
Accomplishment:
Flooring:
Length = 94m (this measure from Station 0+706 to 0+800)
Width= 5.178m
Slope:
Length = 27m ( 27 m was measured between station 0+650 to 0+680)
Width= 4m
Activities:
June 13 June 14 June 15 June 16
Embankment Continuation Continuation Continuation
Excavation (At Station Embankment Embankment Embankment
0+640 to 0 Excavation (At Station Excavation (At Station Excavation (At Station
=580) 0+640 to 0 0+640 to 0 0+640 to 0
=580) =580) =580)
Reinforcement Reinforcement Reinforcement Reinforcement
Formwork (Slope at Formwork (Slope at Formwork (Slope at Formwork (Slope at
0+650) 0+650) 0+650) 0+650)
Concrete Pouring (At Continuation of Continuation of Continuation of
Sta. 0+706) Concrete Pouring (At Concrete Pouring (At Concrete Pouring (At
Sta. 0+706) Sta. 0+706), Concrete Sta. 0+706), Concrete
Pouring (Slope at Pouring (Slope at
0+650) 0+650)
Pumping water out of Pumping water out of Pumping water out of Pumping water out of
the bed flooring the bed flooring the bed flooring the bed flooring
Equipment:
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
5 Skilled
10 Laborer
Equipment/s:
Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring
Material/s:
Activity/s:
Concreting(Floor)
Embankment Excavation
Reinforcement Form Work (Floor & Embankment)
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
10 Laborer
Equipment/s:
Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring
Material/s:
Activity/s:
Concreting(Flooring)
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
5 Skilled
7 Laborer
Equipment/s:
Descriptio
Quantity Working Hours Diesel Oil Activities
n
8:00 12:00 Excavation
Backhoe 1 PM Elevating the
1:00 5:00 PM Ground
8:00 11:00 Draining of the
Water
1 AM water in soil
Pump
1:00 5:00 PM bed/flooring
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Portion of the floor has been poured with concrete.
Portion of the Embankment has been excavated.
Weekly Report
June 19-23 ,2017
Prepared by:
Noted:
Approved By:
Engr. Michael J. David
Weekly Report
Date June 19-23, 2017
Accomplishment:
Flooring:
Length = 76m (The 60m was measured at station 0+640 to 080, 16m was measure at station 0+640)
Width= 5.178m
Slope:
Length = 113m (113m was measured between Sta. 0+650 to 0+640 & Station 0+660 to 0+720)
Width= 4m
Activities:
June 19 June 20 June 21 June 22 June 23
Embankment Continuation of Continuation of Continuation of Continuation of
Excavation(Prepar Embankment Embankment Embankment Embankment
ing the Flooring At Excavation(Prepar Excavation(Prepar Excavation(Prepar Excavation(Prepar
Station 0+640 to ing the Flooring At ing the Flooring At ing the Flooring At ing the Flooring At
Station 0+580) Station 0+640 to Station 0+640 to Station 0+640 to Station 0+640 to
Station 0+580) Station 0+580) Station 0+580) Station 0+580)
Concrete Continuation of Concrete Concrete Concrete
Pouring(Slope at Concrete Pouring(Slope at Pouring(Slope at Pouring(Slope at
Station Pouring(Slope at Station 0+680) Station 0+700, Station 0+720,
0+660,Slope at to Station 0+660) Flooring at Station Flooring at Station
0+650 to 0+630) 0+640 to 0+580) 0+640 to 0+580)
Pumping water Pumping water Pumping water Pumping water Pumping water
out of the bed out of the bed out of the bed out of the bed out of the bed
flooring(At Station flooring(At Station flooring(At Station flooring(At Station flooring(At Station
0+640) 0+640) 0+640) 0+640) 0+640)
Reinforcement Reinforcement Reinforcement Reinforcement Reinforcement
Formwork(At Formwork(Slope Formwork(Slope Formwork(Slope Formwork(Slope
Station 0+660) At Station 0+660) At Station 0+640 At Station 0+640 At Station 0+640
to 0+580) to 0+580) to 0+580)
Equipment:
Materials: (Week 3)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm 600 468 132 Reinforcement
Shovel 10 - - -
Concrete Mix 50 - - Concrete
Pouring(Flooring)
Diesel (Backhoe 350L - - 150L(June 19)
#15) 200L(June 22)
Diesel (Dump 100L - - -
Truck)
Tansi 4 Roll - - -
Date: June 19, 2017
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at Sta. 0+650 to 0+630 has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at Station 0+660 to 0+690 has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at 0+690 to 0+710 has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Slope at 0+710 to 0+730 has been poured with concrete.
Flooring at 0+640 to 0+610 has been poured with concrete.
Portion of the Embankment has been excavated.
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Concreting
Embankment Excavation
Reinforcement Form Work
Accomplishment/s:
Flooring at 0+610 to 0+580 has been poured with concrete.
Slope at 0+730 to 0+770 has been poured with concrete.
Portion of the Embankment has been excavated.
Weekly Report
June 27-30 ,2017
Prepared by:
Noted:
Accomplishment Report:
Weekly Report
June 3-7,2017
Prepared by:
Noted:
Weekly Report
Date July 3-7, 2017
Accomplishment:
Berm:
Length: 143m (measured from station 0+650 to 0+0793)
Width: 1m
Activities:
July 3 July 4 July 5 July 6 July 7
No operation No operation No operation Concrete pouring No operation
of Berm (At
Station 0+650)
Equipment:
Materials: (Week 5)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm - - - -
- - - - -
Concrete Mix 5 5 - Concrete
Pouring(Berm)
Diesel (Backhoe - - - -
#15)
Diesel (Dump - - - -
Truck)
- - - - -
- - - - -
Weekly Report
July 10-14 ,2017
Prepared by:
Noted:
Engr. Roxanne Del Rosario
Approved By:
Weekly Report
Date July 3-7, 2017
Accomplishment:
Berm:
Length: 143m (measured from station 0+650 to 0+0793)
Width: 1m
Activities:
July 10 July 11 July 12 July 13 July 14
No operation No operation Topping/Sealing Topping/Sealing Topping/Sealing
the crack between the crack between the crack between
station 0+650 station 0+650 station 0+650
Pumping Water Pumping Water Pumping Water
out of the bed out of the bed out of the bed
flooring flooring flooring
Reinforcement Reinforcement Reinforcement
formwork formwork formwork
Equipment:
Materials: (Week 5)
DESCRIPTION STOCK/DELIVERED USED REMAINI REMARKS
NG
12mm 400 150 250 Reinforcement
formwork
- - - - -
Concrete Mix - - - -
Cement 5 bags 5 bags - -
- - - - -
- - - - -
- - - - -
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)
Manpower:
1 Leadman/Foreman 1 checker
1 Backhoe Operator 1 OJT
25 Laborer/Skilled
Equipment/s:
Material/s:
Activity/s:
Topping/Sealing of the crack in the berm.
Draining of the water out of the bed.
Accomplishment/s:
Portion of the berm has been sealed(Between station 0+650 to 793)