TANJUNG AWAR AWAR COAL SHED PROJECT EXECUTION PLAN

2014 2015
No Remarks
OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG
1 ENGINEERING DRAWINGS FINISHED
2 MOBILIZATION AND PREPARING REQUIRED PERMIT Oct 17, '14
3 FABRICATION AREA SITE CLEARING & PREPARATION Oct 20 -Oct 27, '14

SITE TEMPORARY FACILITIES PREPARATION (OFFICE,


4
WAREHOUSE,CANTEEN, FABRICATION WORK SHOP,ETC)
Oct 27 - Nov 10, '14
5 APPOINT SOIL INVESTIGATION THIRD PARTHY Oct 20,'14
6 SOIL INVESTIGATION WORK Oct 20 - Nov 20, 14
7 ISSUED PO FOR PILING Oct 20,'14
ISSUED CONTRACT FOR SOIL BORING AND PILING
8
CONTRACTOR Nov 3,'14
9 BORING AND PILING WORK Nov 10 - Dec 10, 2014
10 FOUNDATION WORK Nov 17 - Dec 17, 2014
10 PROCUREMENT OF PIPING MATERIAL Oct 20 - Nov 20, 14
11 GALVANIZING Oct 27 - Nov 27, '14
12 DELIVERY PIPING MATERIAL TO SITE Nov 3 - Dec 3, '14
13 RAFTER AND GORDING FABRICATION Nov 10, '14 - March 10, '15
13 RAFTER AND GORDING ERECTION Tgl 15 jan' Erection 3 Row mulai Portal H JAN 13 - MAY 13,'15
14 ERECTION OF ROOF May 1 - June 30 '15

15 INSTALATION OF SKY LIGHT AND LIGHTENING PROTECTION


May 15 - June 30 '15