Brief
Department of Public Works announced 2017 Mill and Paving projects which will begin in late
August and continue through September. Streets to be mill and paved are based upon current
road conditions, traffic usage, available funding, citywide needs and other projects impacting
the street. Below is the list of streets for Mill and Paving projects.
Though paving may cause some inconveniences to our public, Public Works tries to keep them
at a minimum and remains confident that the end results will be worth it.
If you have any questions, please call the DPW Residents Unit at (203) 946 7700.

Mill & Paving Projects 2017


LOCATION From To

Legion Avenue Sherman Avenue Orchard Street

Sherman Avenue North Frontage Road Legion Avenue

Dwight Street George Street Legion Avenue

Edgewood Avenue Orchard Street Howe Street

Alston Avenue Chapel Street Edgewood Avenue

Alston Avenue Woodbridge Avenue West Elm Street

Barnett Street Willard Street West Elm Street

Knollwood Drive Laurel Road Ray Road

Winchester Avenue Huntington Street City Line


-2- Paving 2017
Location From To

Woodland Street Winchester Avenue Mansfield Street

Highland Street Whitney Avenue Prospect Street

East Rock Road Whitney Avenue Prospect Street

East Rock Road Livingston Street Whitney Avenue

Willow Street Bridge Deck

Clinton Avenue Middletown Avenue Peck Street

Smith Avenue Cross Street Quinnipiac Avenue

Cross Street Middletown Avenue Smith Avenue

Sherland Avenue Howard Street Clifton Street

Beacon Avenue Main Street Clarendon Street

Frost Street Woodward Avenue Beacon Avenue

Hervey Street Townsend Avenue 700west

Cora Street Cove Street Lighthouse Road

Morris Cove Road Townsend Avenue Bristol Place

Douglass Avenue Townsend Avenue Dead End

Edgemere Road Forbes Avenue Dead End

Long Wharf Drive Sargent Drive Cul-de-sac

Church Street South Amistad South 200 South