Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.

00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
1 DURATION OF PROJECT 455 days Mon 01-09-14 Mon 30-11-15

2 FOUR LANING OF GWALIOR SHIVAPURI SECTION OF 455 days Mon 01-09-14 Mon 30-11-15
NH-3 (FROM KM 0+00 TO KM 125+30)
3 HIGHWAY WORKS 455 days Mon 01-09-14 Mon 30-11-15

4 CONSTRUCTION OF NEW CARRIAGEWAY - 82.75 403 days Mon 01-09-14 Fri 09-10-15
KM
5 UTILITY SHIFTING WORKS 30 days Mon 01-09-14 Wed 01-10-14

6 CLEARING & GRUBBING 90 days Tue 02-09-14 Mon 01-12-14 5SS+1 day

7 EMBANKMENT CONSTRUCTION 357 days Fri 05-09-14 Fri 28-08-15 6SS+3 days

8 SUBGRADE CONSTRUCTION 357 days Fri 12-09-14 Fri 04-09-15 7SS+7 days

9 GSB CONSTRUCTION 357 days Fri 19-09-14 Fri 11-09-15 8SS+7 days

10 WMM CONSTRUCTION 364 days Tue 23-09-14 Tue 22-09-15 9SS+4 days

11 DBM CONSTRUCTION 345 days Thu 23-10-14 Sat 03-10-15 10SS+30 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

1 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
12 BC CONSTRUCTION 345 days Tue 28-10-14 Thu 08-10-15 11SS+5 days

13 HIGHWAY FINISHING WORKS 15 days Thu 24-09-15 Fri 09-10-15 12FF+1 day

14 WIDENING & STRENGTHING OF EXISTING 380 days Thu 02-10-14 Sat 17-10-15
CARRIAGEWAY - 82.75 KM
15 UTILITY SHIFTING WORKS 30 days Thu 02-10-14 Sat 01-11-14 5SS+31 days

16 CLEARING & GRUBBING 90 days Sun 05-10-14 Sat 03-01-15 15SS+3 days

17 EMBANKMENT CONSTRUCTION 330 days Thu 30-10-14 Fri 25-09-15 11SS+7 days

18 SUBGRADE CONSTRUCTION 330 days Thu 06-11-14 Fri 02-10-15 17SS+7 days

19 GSB CONSTRUCTION 330 days Thu 13-11-14 Fri 09-10-15 18SS+7 days

20 WMM CONSTRUCTION 330 days Mon 17-11-14 Tue 13-10-15 19SS+4 days

21 DBM CONSTRUCTION 325 days Mon 24-11-14 Thu 15-10-15 20SS+7 days

22 BC CONSTRUCTION 321 days Sat 29-11-14 Fri 16-10-15 21SS+5 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

2 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
23 HIGHWAY FINISHING WORKS 15 days Fri 02-10-15 Sat 17-10-15 22FF+1 day

24 CONSTRUCTION OF BYPASSES - 36.90 KM 152 days Thu 01-01-15 Tue 02-06-15

25 UTILITY SHIFTING WORKS 97 days Thu 01-01-15 Wed 08-04-15 5SS

26 CLEARING & GRUBBING 30 days Fri 02-01-15 Sun 01-02-15 25SS+1 day

27 EMBANKMENT CONSTRUCTION 120 days Tue 06-01-15 Wed 06-05-15 26SS+4 days

28 SUBGRADE CONSTRUCTION 120 days Sat 10-01-15 Sun 10-05-15 27SS+4 days

29 GSB CONSTRUCTION 120 days Wed 14-01-15 Thu 14-05-15 28SS+4 days

30 WMM CONSTRUCTION 120 days Sun 18-01-15 Mon 18-05-15 29SS+4 days

31 DBM CONSTRUCTION 120 days Sun 25-01-15 Mon 25-05-15 30SS+7 days

32 BC CONSTRUCTION 120 days Fri 30-01-15 Sat 30-05-15 31SS+5 days

33 HIGHWAY FINISHING WORKS 7 days Tue 26-05-15 Tue 02-06-15 32FF+3 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

3 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
34 CONSTRUCTION OF REALIGNMENT- 5.65 KM 90 days Tue 01-09-15 Mon 30-11-15

35 UTILITY SHIFTING WORKS 7 days Tue 01-09-15 Tue 08-09-15 5SS

36 CLEARING & GRUBBING 30 days Wed 02-09-15 Fri 02-10-15 35SS+1 day

37 EMBANKMENT CONSTRUCTION 70 days Fri 04-09-15 Fri 13-11-15 36SS+2 days

38 SUBGRADE CONSTRUCTION 70 days Sun 06-09-15 Sun 15-11-15 37SS+2 days

39 GSB CONSTRUCTION 70 days Tue 08-09-15 Tue 17-11-15 38SS+2 days

40 WMM CONSTRUCTION 70 days Thu 10-09-15 Thu 19-11-15 39SS+2 days

41 DBM CONSTRUCTION 70 days Thu 17-09-15 Thu 26-11-15 40SS+7 days

42 BC CONSTRUCTION 69 days Tue 22-09-15 Mon 30-11-15 41SS+5 days

43 BREAST WALL CONSTRUCTION 85 days Fri 04-09-15 Sat 28-11-15 36SS+2 days

44 HIGHWAY FINISHING WORKS 7 days Sun 22-11-15 Sun 29-11-15 43FF+1 day

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

4 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
45 STRUCTURE WORKS 384 days Mon 01-09-14 Sun 20-09-15

46 BOX CULVERTS - 71 Nos 384 days Mon 01-09-14 Sun 20-09-15

47 EXCAVATION & PCC LAYING 240 days Mon 01-09-14 Wed 29-04-15

48 FOUNDATION 240 days Thu 04-09-14 Sat 02-05-15 47SS+3 days

49 SUBSTRUCTURE 240 days Thu 11-09-14 Sat 09-05-15 48SS+7 days

50 SUPERSTRUCTURE 300 days Thu 25-09-14 Wed 22-07-15 49SS+14 days

51 RETURN WALLS 300 days Thu 11-09-14 Wed 08-07-15 48SS+7 days

52 CRASH BARRIER 300 days Sat 25-10-14 Fri 21-08-15 50FF+30 days

53 FINISHING WORKS 60 days Wed 22-07-15 Sun 20-09-15 52FF+30 days

54 PIPE CULVERTS - 75 Nos 233 days Mon 01-09-14 Wed 22-04-15

55 EXCAVATION & PCC LAYING 180 days Mon 01-09-14 Sat 28-02-15

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

5 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
56 HEAD WALL FIRST LIFT 210 days Wed 03-09-14 Wed 01-04-15 55SS+2 days

57 GRANULAR BED LAYING 210 days Sun 07-09-14 Sun 05-04-15 56SS+4 days

58 LAYING OF NP4 PIPES 210 days Sun 14-09-14 Sun 12-04-15 57SS+7 days

59 HEAD WALL II LIFT 200 days Wed 01-10-14 Sun 19-04-15 58FF+7 days

60 FINSHING WORKS 30 days Mon 23-03-15 Wed 22-04-15 59FF+3 days

61 MINOR BRIDGE - 49 Nos 271 days Mon 01-09-14 Sat 30-05-15

62 EXCAVATION & PCC LAYING 180 days Mon 01-09-14 Sat 28-02-15

63 FOUNDATION 210 days Mon 08-09-14 Mon 06-04-15 62SS+7 days

64 SUBSTRUCTURE 240 days Mon 15-09-14 Wed 13-05-15 63SS+7 days

65 SUPERSTRUCTURE 240 days Mon 22-09-14 Wed 20-05-15 64SS+7 days

66 CRASHBARRIER/HANDRAILS 220 days Sun 19-10-14 Wed 27-05-15 65FF+7 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

6 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
67 FINISHING WORKS 30 days Thu 30-04-15 Sat 30-05-15 66FF+3 days

68 PUP'S - 9 Nos 264 days Mon 01-09-14 Sat 23-05-15

69 EXCAVATION & PCC LAYING 180 days Mon 01-09-14 Sat 28-02-15

70 PUP FOUNDATION 210 days Mon 08-09-14 Mon 06-04-15 69SS+7 days

71 PUP SUBSTRUCTURE 210 days Mon 15-09-14 Mon 13-04-15 70SS+7 days

72 PUP SUPERSTRUCTURE 240 days Mon 22-09-14 Wed 20-05-15 71SS+7 days

73 CRASHBARRIER/HANDRAILS 240 days Thu 25-09-14 Sat 23-05-15 72SS+3 days

74 FINISHING WORKS 10 days Mon 01-09-14 Thu 11-09-14

75 VUP -1 No 87 days Mon 01-09-14 Thu 27-11-14

76 EXCAVATION & PCC LAYING 7 days Mon 01-09-14 Mon 08-09-14

77 VUP FOUNDATION 14 days Mon 08-09-14 Mon 22-09-14 76

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

7 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
78 VUP SUBSTRUCTURE 30 days Thu 11-09-14 Sat 11-10-14 77SS+3 days

79 VUP SUPERSTRUCTURE 30 days Sat 11-10-14 Mon 10-11-14 78

80 CRASHBARRIER/HANDRAILS 7 days Mon 10-11-14 Mon 17-11-14 79

81 FINISHING WORKS 10 days Mon 17-11-14 Thu 27-11-14 80

82 MJB AT CH: 53+782 218 days Mon 01-09-14 Tue 07-04-15

83 EXCAVATION & PCC LAYING 30 days Mon 01-09-14 Wed 01-10-14

84 FOUNDATION 30 days Mon 08-09-14 Wed 08-10-14 83SS+7 days

85 SUBSTRUCTURE 150 days Mon 15-09-14 Thu 12-02-15 84SS+7 days

86 RCC GIRDER ERECTION 45 days Mon 12-01-15 Thu 26-02-15 85FF+14 days

87 SUPERSTRUCTURE 60 days Tue 27-01-15 Sat 28-03-15 86FF+30 days

88 CRASHBARRIER / HANDRAILS 7 days Thu 26-03-15 Thu 02-04-15 87FF+5 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

8 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
89 FINISHING WORKS 5 days Thu 02-04-15 Tue 07-04-15 88

90 MJB AT CH: 57+915 220 days Mon 01-09-14 Thu 09-04-15

91 EXCAVATION & PCC LAYING 30 days Mon 01-09-14 Wed 01-10-14

92 FOUNDATION 30 days Mon 08-09-14 Wed 08-10-14 91SS+7 days

93 SUBSTRUCTURE 150 days Mon 15-09-14 Thu 12-02-15 92SS+7 days

94 RCC GIRDER ERECTION 45 days Mon 12-01-15 Thu 26-02-15 93FF+14 days

95 SUPERSTRUCTURE 60 days Tue 27-01-15 Sat 28-03-15 94FF+30 days

96 CRASHBARRIER / HANDRAILS 7 days Sat 28-03-15 Sat 04-04-15 95FF+7 days

97 FINISHING WORKS 5 days Sat 04-04-15 Thu 09-04-15 96

98 MJB AT CH: 61+827 220 days Mon 01-09-14 Thu 09-04-15

99 EXCAVATION & PCC LAYING 30 days Mon 01-09-14 Wed 01-10-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

9 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
100 FOUNDATION 30 days Mon 08-09-14 Wed 08-10-14 99SS+7 days

101 SUBSTRUCTURE 150 days Mon 15-09-14 Thu 12-02-15 100SS+7 days

102 RCC GIRDER ERECTION 45 days Mon 12-01-15 Thu 26-02-15 101FF+14 days

103 SUPERSTRUCTURE 60 days Tue 27-01-15 Sat 28-03-15 102FF+30 days

104 CRASHBARRIER / HANDRAILS 7 days Sat 28-03-15 Sat 04-04-15 103FF+7 days

105 FINISHING WORKS 5 days Sat 04-04-15 Thu 09-04-15 104

106 MJB AT CH: 83+678 273 days Mon 01-09-14 Mon 01-06-15
107 EXCAVATION & PCC LAYING 30 days Mon 01-09-14 Wed 01-10-14

108 FOUNDATION 30 days Fri 31-10-14 Sun 30-11-14 107SS+60 days

109 SUBSTRUCTURE 150 days Fri 07-11-14 Mon 06-04-15 108SS+7 days

110 RCC GIRDER ERECTION 45 days Fri 06-03-15 Mon 20-04-15 109FF+14 days

111 SUPERSTRUCTURE 60 days Sat 21-03-15 Wed 20-05-15 110FF+30 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

10 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
112 CRASHBARRIER / HANDRAILS 7 days Wed 20-05-15 Wed 27-05-15 111FF+7 days

113 FINISHING WORKS 5 days Wed 27-05-15 Mon 01-06-15 112

114 ROB AT CH: 2+050 372 days Mon 01-09-14 Tue 08-09-15

115 PILING WORKS / FOUNDATION WORKS 60 days Mon 01-09-14 Fri 31-10-14

116 SUBSTRUCTURE 180 days Fri 31-10-14 Wed 29-04-15 115

117 PLATE GIRDER ERECTION 60 days Sat 07-03-15 Wed 06-05-15 116FF+7 days

118 SUPERSTRUCTURE 120 days Wed 06-05-15 Thu 03-09-15 117

119 CRASHBARRIER / HANDRAILS 7 days Sat 29-08-15 Sat 05-09-15 118FF+2 days

120 FINISHING WORKS 5 days Thu 03-09-15 Tue 08-09-15 119FF+3 days

121 ROB AT CH: 109+900 342 days Mon 01-09-14 Sun 09-08-15

122 PILING WORKS / FOUNDATION WORKS 60 days Mon 01-09-14 Fri 31-10-14

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

11 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
123 SUBSTRUCTURE 150 days Fri 31-10-14 Mon 30-03-15 122

124 PLATE GIRDER ERECTION 60 days Thu 05-02-15 Mon 06-04-15 123FF+7 days

125 SUPERSTRUCTURE 120 days Mon 06-04-15 Tue 04-08-15 124

126 CRASHBARRIER / HANDRAILS 7 days Thu 30-07-15 Thu 06-08-15 125FF+2 days

127 FINISHING WORKS 5 days Tue 04-08-15 Sun 09-08-15 126FF+3 days

128 ROB AT CH: 121+040 342 days Wed 01-10-14 Tue 08-09-15

129 PILING WORKS / FOUNDATION WORKS 60 days Wed 01-10-14 Sun 30-11-14

130 SUBSTRUCTURE 150 days Sun 30-11-14 Wed 29-04-15 129

131 PLATE GIRDER ERECTION 60 days Sat 07-03-15 Wed 06-05-15 130FF+7 days

132 SUPERSTRUCTURE 120 days Wed 06-05-15 Thu 03-09-15 131

133 CRASHBARRIER / HANDRAILS 30 days Thu 06-08-15 Sat 05-09-15 132FF+2 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

12 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
134 FINISHING WORKS 10 days Sat 29-08-15 Tue 08-09-15 133FF+3 days

135 TOLL PLAZA CONSTRUCTION - 2 Nos 90 days Sun 01-03-15 Sat 30-05-15
136 CLEARING & GRUBBING 4 days Sun 01-03-15 Thu 05-03-15

137 EMBANKMENT CONSTRUCTION 30 days Wed 04-03-15 Fri 03-04-15 136SS+3 days

138 SUBGRADE CONSTRUCTION 15 days Tue 24-03-15 Wed 08-04-15 137FF+5 days

139 GSB CONSTRUCTION 15 days Sun 29-03-15 Mon 13-04-15 138FF+5 days

140 DLC 15 days Fri 03-04-15 Sat 18-04-15 139SS+5 days

141 CC PAVEMENT 15 days Wed 08-04-15 Thu 23-04-15 140SS+5 days

142 BUILDING WORKS 45 days Wed 15-04-15 Sat 30-05-15 141SS+7 days

143 INSTALLATION WORKS 10 days Sat 25-04-15 Tue 05-05-15 142SS+10 days

144 MISCELLANEOUS WORKS 425 days Mon 01-09-14 Sat 31-10-15

145 REST AREAS 120 days Mon 30-03-15 Tue 28-07-15 3SS+210 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

13 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh
ID Task Task Name Duration Start Finish Predecessors
Mode Apr '14
146 BUSBAYS 120 days Mon 30-03-15 Tue 28-07-15 3SS+210 days

147 TRAFFIC SIGNALES & ROAD APPURTENANCES 60 days Tue 14-04-15 Sat 13-06-15 3SS+225 days

148 ROAD MAINTENANCE DURING CONSTRUCTION 425 days Mon 01-09-14 Sat 31-10-15 3SS
AND SAFTEY
149 DRAINAGE WORKS 150 days Fri 29-05-15 Mon 26-10-15 3SS+270 days

150 REHABILITATION OF BRIDGES 67 days Sat 11-07-15 Wed 16-09-15 148FF-45 days

151 HIGHWAY TRAFFIC MANAGEMENT SYSTEM 425 days Mon 01-09-14 Sat 31-10-15 3SS

152 STREET LIGHTING 93 days Mon 30-03-15 Wed 01-07-15 3SS+210 days

153 FINISHING WORKS 93 days Thu 23-07-15 Sat 24-10-15 3SS+325 days

154 PUNCHLIST ACTIVITIES 33 days Sat 26-09-15 Thu 29-10-15 3SS+390 days

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

14 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

15 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

16 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

17 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

18 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

19 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

20 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

21 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

22 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

23 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

24 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

25 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

26 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

27 of 28
Four Laning of Gwalior-Shivpuri Section of NH-3 from km 15.600 of NH-75 (End of Gwalior bypass) to km 236.00 of NH-3 in the
State of Madhya Pradesh

Jul '14 Oct '14 Jan '15 Apr '15 Jul '15 Oct '15 Jan '16 Apr '16 Jul '16

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Final Construction Prog Summary Manual Summary Rollup Progress

Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

28 of 28