Académique Documents
Professionnel Documents
Culture Documents
Jawalakhel, Lalitpur
Final Report
On
September 2015,
This document is the project report prepared for the project Soil Investigation Works for the
Design of Residential Building. This document has been submitted by NGC LAB, Lalitpur.
Datasets, Map and other miscellaneous data are produced / developed by Soil Lab, NGC
LAB (P) Ltd., for the project during 2015. These data are owned by Nem Maharjan.
Authorization from the owner is required for the usage and/or publication of the data in part
or whole.
i
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
PROJECT INFORMATION
Name of the Project Soil Investigation Works for the Design of Residential
Building,
SUBMISSION INFORMATION
Date of Submission
Reviewed by
Official Stamp
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
ACKNOWLEDGEMENT
NGC LAB would like to extend special gratitude to Nem Maharjan, for believing in us and
handling this important task to us. We also like to give special gratitude to all the people for
helping & supporting us to complete this job successfully.
All staffs of the NGC LAB, who labored hard in preparing this document, deserve special
thanks. We also express appreciation to the efforts of experts as well as individuals who have
contributed in the preparation of this document by being involved in the various tasks of this
project.
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
EXECUTIVE SUMMARY
Overview and This project involved the Soil Investigation of the soil strata at
Project Aim specific locations of the project area for the Design of Multi-Story
Building. The primary aim of the task was to analyze the bearing
capacity of the underlying soil and thus recommend safe design
parameters for the foundation design of the proposed building.
Outline of Process Initially, a geotechnical professional with his survey team did the
and Planning reconnaissance of the site area. Team members discussed the sites
stage apparent geological conditions and finally fixed the points for the
performance of boring. Altogether, 3 boring points along with their
depths were fixed.
Outline of Actual Following projection of the boring, the borehole locations were
Field work actually plotted on the field as per the points will be allocated within
the building area. Our Drilling team was assigned for this task. As
per the site condition and need of boring, Percussion drilling was
adopted. The machine was safely carried to the field and boring was
performed as per the general practice. Before drilling was carried
out, all the boring points were named distinctly for the identification
from Bore hole No.- 1,2 & 3. All the boreholes were drilled to a depth
of 5 to 10m as per the demand of client. As the drilling was
performed, SPT test up to 1.5m depth was performed and disturbed
samples were taken by using DCPT Barrel. The N-Values obtained
from cone penetration test during field test ranged from 17 to 32. The
samples were properly marked as soon as they were taken and
sealed in air tight plastic bags to preserve the actual moisture
content and transported to the lab as soon as possible.
Outline of Lab After bringing the soil samples from the site, a geotechnical engineer
Tests performed the soil tests in our Soil Lab in accordance to various
codes of practice. Different factors are considered while choosing a
particular samples test results for the analysis of bearing capacity.
Since the soil found at proposed site is mostly cohesion less soil, the
results of the sample that is taken from the depth which would
tentatively be the depth of foundation, is considered. The Lab tests
were specific to gradation analysis, moisture content, specific
gravity, and bulk density test.
Final Test All the tests were performed carefully to get the results as accurate
Outcomes to the field soil condition as possible. There is significantly Silty
Sand and moisture content is 14.41% - 27.39%, sp. gravity of 2.30 -
2.847, bulk unit weight of (12.77 17.76) KN/m3.
Summary of Results Using the test results, the bearing capacity of soil at each borehole
was calculated assuming considerable design parameters i.e. length,
breadth and depth of footing. Hence, depending on the bearing
pressure on the soil.
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
Contents
PROJECT INFORMATION............................................................................................................. II
SUBMISSION INFORMATION ....................................................................................................... II
ACKNOWLEDGEMENT ................................................................................................................ III
EXECUTIVE SUMMARY .............................................................................................................. IV
1. INTRODUCTION .................................................................................................................... 6
1.1 BACKGROUND ................................................................................................................... 6
1.2 OBJECTIVE........................................................................................................................ 6
1.3 SCOPE OF W ORK .............................................................................................................. 6
2. METHODOLOGY .................................................................................................................... 7
2.1 FIELD W ORK PROCEDURE ................................................................................................. 7
2.2 LABORATORY TESTS................................................................................................................ 8
6. REFERENCES ...................................................................................................................... 19
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
1. Introduction
1.1 Background
This geotechnical engineering report has been completed for the proposed building to
be constructed at Gwarko, Lalitpur district, Nepal as per the agreement between Nem
Maharjan, Jawalakhel and NGC LAB., Lalitpur. The subsurface at the site was
investigated total of Three borings, designated BH-1, BH-2 & BH-3 was performed to
depths of approximately 10, 5 & 5 m below the existing ground surface. Logs of the
borings with a site location map and boring location plan are included in Appendix A of
this report.
1.2 Objective
The objective of the investigation is to determine the soil formation at the project site so
as to derive engineering parameters for the design of the foundation of the proposed
structures.
The specific objective of this project is:
To do the geotechnical investigation of the site,
To submit soil investigation report including engineering properties, design parameter,
bearing capacity etc.
6|Page
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
2. Methodology
In-situ Tests
Field works involved Percussion Drilling mechanism for drilling and sampling of the
boreholes in the proposed area to the maximum depth of 1.5m from the ground levels
and SPT at 1.5m intervals and are recorded. Borehole logs were prepared at the site on
the basis of the visual observation of the soil obtained from the boreholes. The
boreholes logs are attached to the annexes are later verified by lab test results.
It consists of driving a Split Spoon Sampler with an outside dia. of 50 mm into the soil at
the base of borehole. Driving is accomplished by a drop of hammer weighing 63.5 kg
falling freely through a height of 750 mm onto the drive head. First of all the spoon is
driven 150mm into the soil at the bottom of the borehole. It is then driven further 300mm
and the number of blows (N values) required to drive this distance is recorded.
Table 1 Relation of N value to Relative Density and friction angle for granular soils
7|Page
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
The DCPT is similar to the SPT in test. It is performed by dropping a hammer from a
certain fall height and measuring a penetration depth per blow for each tested depth.
The shape of the dynamic cone is similar to that of the penetrometer used in the DCPT.
In road Design; there is a need to assess the adequacy of the subgrade to behave
satisfactorily beneath a pavement. DCPT can be used to evaluate the mechanical
properties of compacted subgrade soils.
Sampling
Before any sample was taken, the borehole was cleaned up of loose disturbed soil
deposited during drilling operation. The samples which were obtained from bailer and in
the SPT tubes were preserved as representative disturbed samples for finding out
physical properties. The samples thus obtained were placed in airtight double plastic
bags, labeled properly for identification and later transported to the lab for analysis.
Method Used at the Proposed Site:
At the project site, Percussion Drilling was performed by our drilling team, at 3 different
locations within the site, with reference to the Location map . Bore hole locations were,
thus, marked on the ground.
Percussion drilling machine was setup in front of the marked borehole locations and
then, the boring was carried out. Logs of all the bore holes were made on site as boring
proceeded. The logs included visual soil classification, N-value, and ground water level
at the time of boring.
2.2 Laboratory Tests
2.2.1) Gradation Analysis
Sieve analysis is done to determine the presence and distribution of aggregates, by
size, in the soil sample taken from the bore holes.
8|Page
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
The liquid limit (LL) is the water content at which a soil changes from plastic to liquid
behavior. The original liquid limit test of Atterberg's, involved mixing a part of clay in a
round-bottomed porcelain bowl of 1012 cm diameter. A groove was cut through the
part of clay with a spatula, and the bowl was then struck many times.
9|Page
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
10 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
.
Figure 1 Geological map of Nepal (Dahal 2006)
The Himalaya forms a sharp geographic boundary between the high Tibetan plateau of
east-central Asia in the north and the subdued south Asian subcontinent in the south.
This narrow and highly rugged major mountain range of Asia was formed by the latest
mountain building activity in the Earths history. The Himalaya was formed by the
collision of the northward moving Indian plate with the giant Asian landmass. This
convergence builds up the force to push the Himalaya upward as well as horizontally,
thereby making it the most restless mountain range in the world. The orogenic process
is continuous from the collision of Indian plate with the giant Asian landmass and the
mountain is still on making process. This is noticeable by present day northward
movement of India at the rate of 15 mm to 50 mm per year and the occurrences of
11 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
frequent seismic shakes all along the Himalaya and its surroundings. Most part of the
drift is accommodated within the Himalaya by various thrusts as well as rising peaks.
3.2 Seismicity
Due to Tectonic Forces, Himalayan zones and the neighboring areas are seismically
very active. Most of epicenters of earthquakes are found to be located in the unstable
zones. The frequency and intensity of earthquakes are found at the weakness of the
crust such as major faults, major bends or major acres. Location of Nepal in the
Himalaya along with major tectonic boundary and various longitudinal zones of the
Himalaya are shown in Fig 2.
Seismic hazard map of Nepal is also shown in Fig 3. Figure 3 shows that earthquake
with a peak acceleration of 0.15g may occur in 50 years, making the country very
vulnerable to earthquake.
Figure 2 Location of Nepal in the Himalaya along with major tectonic boundary and various
longitudinal zones of the Himalaya (cited from Bhandary et al. 2013)
12 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
13 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
FS = (CRR / CSR)
Where CRR = cyclic resistance ratio of the soil (obtained from empirical chart of
CRR Vs SPT)
CSR = cyclic stress ratio
= 0.65 (amax/g)* (v/v) *rd
amax = maximum ground acceleration
g = acceleration due to gravity
v = total overburden pressure
v = effective overburden pressure
rd = stress reduction factor
CONCLUSION FROM LIQUEFACTION ANALYSIS:
As per the result obtained from the analysis, we conclude that the soil in the project
area has considerable factor of safety against liquefaction below 2m 2.5m depth. At
bore hole locations 1 the FS was found to be greater than 1 and we recommend laying
of foundation above 2.5m depth.
Despite the considerably medium ground water table (GWT) at each bore hole location
and the presence of sandy soil with gravel, the SPT values obtained during the field test
at each hole was high enough to maintain the resistance of the soil against liquefaction.
Therefore, analyzing all the factors and site conditions, we recommend shallow
foundation for the construction of building at this project location. Therefore, it is
recommended to provide gravel/stone pitching at the depth of about 3.0 meter and the
subsequent laying of building foundation above the gravel/stone pitching for soil
improvement. This is the preferred measure to avoid the chances of uneven
settlement, and liquefaction if there exists any or to be on the safe side
14 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
15 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
5. Bearing capacity
16 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
On the basis of direct shear test, SPT value and allowable settlement the following safe bearing pressures in kN/m2 is recommended.
SummaryofBearingCapacity
17 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
18 | P a g e
Soil Investigation Works for the Design of Residential Building at Gwarko, Lalitpur
6. References
1. Compendium of Indian Standards on Soil Engineering Part 1, Laboratory Testing of Soils
from Civil Engineering Purposes, SP: 36 (Part 1) 1987, Bureau of Indian Standards, new
Delhi.
2. Beca World International (1993), 'Seismic Hazard Mapping and Risk Assessment for
Nepal', Ministry of Housing and Physical Planning, Lalitpur
3. Teng, W.C. (1988), 'Foundation Design', Prentice Hall, New Delhi.
4. Peck, R. B., Hanson, W.E. and Thornburn, T.H. (1974), 'Foundation Engineering', John
Wiley and Sons Inc. 514 p.
5. Terzaghi, K. and Peck, R.B. (1967), 'Soil Mechanics in Engineering Practice', John Wiley
and Sons Inc. 514 p.
6. Simons, N.E. and Menzies, B.K. (1979), 'A short Course in Foundation Engineering', ELBS
and Newnes Butterworth, London, 159 p.
7. Nepal Building Code, (1994), 'Seismic Design of Buildings in Nepal NBC 105 94'.
8. Indian standard CODE OF PRACTICE FOR DETERMINATION OF BREARING CAPACITY OF
SHALLOW FOUNDATIONS IS 6403: 1981
9. Indian standard CODE OF PRACTICE FOR CALCULATION OF SETTLEMENT OF FOUNDA-
TIONS IS 8009 (Part I)
19 | P a g e