Vous êtes sur la page 1sur 7

Government of Nepal

Ministry of Federal Affairs and Local Development


Office of District Development Committee
DISTRICT TECHNICAL OFFICE
Chitwan

RATE ANALYSIS FOR Users Committee


Fiscal Year:2073/074
Site Preparation
Surface dressing pots filling, levelling of undulated ground, landscaping all complete work, and Surface levelling
etc.(Survice road)
Analyzed for: 1 m Norms S.N. 1-7
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Labours Unskilled 0.01 no. 525.00 5.25
Grand-Total 5.25

Earthwork/ Sand work


Earthwork excavation in hard soil including disposal upto (1.5m lift & 10m lead).
Analyzed for: 1 m Norms S.N. 2-2
Quantit Rate per
Resources Level / Type Unit Amount Remarks
y unit
Labours Unskilled 0.8 no. 525.00 420.00
Tools & equipments @ 3% of total labour cost 12.60
Sub-Total 432.60

Earth filling & compaction


Earth filling & compaction in 15 cm layers with sprinkling water (Transporting from 10m)
Analyzed for: 1 m Norms S.N. 2-25-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Labours Unskilled 0.5 no. 525.00 262.50
Materials Soil 1.2 Cu.m 0.00 Soil from out of side
Tools & equipments @ 3% of total labour cost 0.00
Sub-Total 262.50

Stone Soling
Dry stone soling
Analyzed for: 1 m Norms S.N. 11-16
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1 no. 740.00 740.00
Labours
Unskilled 3.5 no. 525.00 1837.50
Stone 1.1 m 1650.00 1815.00
Materials
Sand 0.71 m 1600.00 1136.00
Sub-Total 5528.50
Stone Masonry
Random rubble masonry work in 1:6 cement mortar including providing block stone up to 5m height (Transporting from 10m)

Analyzed for: 1 m Norms S.N. 6-1-Ka-3


Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.5 no. 740.00 1110.00 997.5
Labours
Unskilled 5 no. 525.00 2625.00 2350.00
Cement 0.106 MT 13334.00 1413.40 1413.40
Sand 0.47 m 1600.00 752.00 681.50
Materials
Block Stone 1 m 1265.00 1265.00 1500.00
Bond Stone 0.1 m 1265.00 126.50 150.00
Sub-Total 7291.90

Brick Masonry
Brick masonry work in 1:6 cement mortar above ground floor with providing chimney made bricks (Transporting from 30m)

Analyzed for: 1 m Norms S.N. 5-1-Kha-3 & 5-2-Kha


Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 2.2 no. 525.00 1155.00
Bricks 560 no. 14.69 8226.40
Materials Cement 0.07 MT 13334.00 933.38
Sand 0.3 m 1600.00 480.00
Unskilled 0.7 no. 525.00 367.50
Scaffolding
Materials 3% of Labour cost 78.98 78.98
Sub-Total 12351.26

Cement Concrete Work


Cement concrete work in super-structure, deck, slab, beams i ncluding providing materials and haulage distance upto 30m

P.C.C. (1:1.5:3)

Analyzed for: 1 m Norms S.N. 7-4-Kha


Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 0.8 no. 740.00 592.00
Labours
Unskilled 7 no. 525.00 3675.00
Cement 0.4 MT 13334.00 5333.60
Sand 0.425 m 1600.00 680.00
Materials
20mm Aggregate 0.57 m 1935.00 1102.95
10mm Aggregate 0.29 m 1950.00 565.50
Sub-Total 11949.05
Cement concrete work in foundation, floor, walls & abutment (plum concrete) including Supply of materials and
haulage distance upto 30m.
P.C.C. (1:3:6)
Analyzed for: 1 m Norms S.N. 7-1-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 0.30 no. 740.00 222.00
Labours
Unskilled 4.00 no. 525.00 2100.00
Cement 0.22 MT 13334.00 2933.48
Coarse Sand 0.47 m 1600.00 752.00
Materials 20mm River bed Aggregate 0.60 m 1485.00 891.00
10mm River bed Aggregate 0.20 m 1485.00 297.00
225mm Boulder 0.14 m 1650.00 231.00
Sub-Total 7426.48

Steel Work
Curtailment, bent up, placing & binding the MS bar with binding wire as shown in drawings including haulage distance 30m.

Analyzed for: 1 MT Norms S.N. 7-5


Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 12.00 no. 740.00 8880.00
Labours
Unskilled 12.00 no. 525.00 6300.00
MS Bar 1.05 MT 83702.50 87887.63
Materials
Binding Wire 10.00 kg 94.36 943.60
Sub-Total 104011.23
For 1 kg 104.01

Plastering Work
12.5mm thick 1:6 cement sand plaster wall/floor
Analyzed for: 100 m Norms S.N. 12-1-Gha
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 12 no. 740.00 8880.00
Labours
Unskilled 16 no. 525.00 8400.00
Cement 0.382 MT 13334.00 5093.59
Materials
Sand 1.57 m 1600.00 2512.00
Sub-Total 24885.59
For 1 m 248.86

Painting works
Two coat white washing on new surface Wall
Analyzed for: 100 m Norms S.N. 13-1-Kha
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.5 no. 740.00 1110.00
Labours
Unskilled 1.1 no. 525.00 577.50
White Lime 22 kg 26.84 590.48
Materials
Gum 0.88 kg 310.75 273.46
Sub-Total 2551.44
For 1 m 25.51
Painting works
Applying distemper paint
A. Primer
Analyzed for: 100 m Norms S.N. 13-3-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Primer 8 litres 395.50 3164.00
Sub-Total 5694.00
For 1 m 56.94

B. One coat
Analyzed for: 100 m Norms S.N. 13-3-Kha
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 2 no. 525.00 1050.00
Materials Dry Distemper Powder 6.5 kg 310.75 2019.88
Sub-Total 4549.88
For 1 m 45.50
C. Second coat and every other additional coats
Analyzed for: 100 m Norms S.N. 13-3-Ga
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.8 no. 740.00 1332.00
Labours
Unskilled 1.8 no. 525.00 945.00
Materials Dry Distemper Powder 5 kg 310.75 1553.75
Sub-Total 3830.75
For 1 m 38.31
For one coat on primer 102.44
For two coat on primer 140.75

Flooring works
38mm thick 1:2:4 cement concrete flooring
Analyzed for: 10 m Norms S.N. 11-1-Kha
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.25 no. 740.00 925.00
Labours
Unskilled 2 no. 525.00 1050.00
Cement 0.13 MT 13334.00 1733.42
Materials Sand 0.18 m 1600.00 288.00
12mm Aggregate 0.36 m 1935.00 696.60
Sub-Total 4693.02
For 1 m 469.30
3mm thick cement punning
Analyzed for: 10 m Norms S.N. 11-20
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1 no. 740.00 740.00
Labours
Unskilled 1 no. 525.00 525.00
Materials Cement 53.2 kg 13.33 709.37
Sub-Total 1974.37
For 1 m 197.44

Wood Work
Local wood work for choukosh
Analyzed for: 1 m Norms S.N. 10-1
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 34 no. 740.00 25160.00
Labours
Unskilled 3.4 no. 525.00 1785.00
Local Wood 1.1 m 53558.00 58913.80
Materials Holdfast 92.00 no. 17.75 1633.00
Screw 184.00 no. 1.00 184.00
Sub-Total 87675.80

38 mm thick solid panelled shutter using Sisauml Wood


Analyzed for: 2.114 m (Size 1.07m x 1.982m) Norms S.N. 10-2
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 10 no. 740.00 7400.00
Labours
Unskilled 1 no. 525.00 525.00
Sisaum Wood 0.084 m 130447.20 10957.56
100mm Hinges-Kabja 6 no. 33.90 203.40
150mm Towerbolt-Chheskini 1 no. 67.80 67.80
Materials 340mm Towerbolt 1 no. 169.50 169.50
250mm Locking Set 1 no. 282.50 282.50
6'' Handles 2 no. 56.50 113.00
Screws* 48 LS 1.00 48.00
Sub-Total 19766.76
Rate per m 9350.41

Wood work for beam,column etc.using local wood


Analyzed for: 1 m Norms S.N. 10-17
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 17.65 no. 740.00 13061.00
Labours
Unskilled 1.76 no. 525.00 924.00
Local Wood 1.05 m 53558.00 56235.90
Materials
Nails LS kg 100.00 100.00
Sub-Total 70320.90
Roofing Work
Roofing work by 26 gauge coloured CGI sheets including providing CGI sheets
Analyzed for: 10 m Norms S.N. 9-1
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.1 no. 740.00 814.00
Labours
Unskilled 1.25 no. 525.00 656.25
22*24 C.G.I.Sheet 12 m 633.56 7602.72
8mm Nut Bolt 30 no. 11.30 339.00
Materials
J Hooks 25 no. 20.98 524.50
Bitumen Washer 55 no. 0.34 18.70
Sub-Total 9955.17
For 1 m 995.52

28 gauge colour G. I. plain sheet including supplying of materials, J or L hooks, nut bolts, washers,
Ridge covering with
fixing of C.G.I sheet over roofing members in proper slope and size
Analyzed for: 10 r.m. Norms S.N. 9-2
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 2 no. 740.00 1480.00
Labours
Unskilled 3 no. 525.00 1575.00
Plane Sheet 12 r.m. 417.47 5009.64
Materials
J Hooks 20 no. 20.98 419.60
Sub-Total 8484.24
For 1 rm 848.42

Form Work
Form work for beams, slab in structure including, screening, fitting, oiling, dismantling, removing and transporting up to 30m

A) For Slab
Analyzed for: 10 m Norms S.N. 8-2-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 1.72 no. 740.00 1272.80
Labours
Unskilled 2.57 no. 525.00 1349.25
Wood* 0.06575 m 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 6425.99
For 1 m 642.60
* Assuming timber and ballies will become unserviceable after being used for 8 times

B) For Column-circumfrance upto 2m height


Analyzed for: 10 m Norms S.N. 8-3-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 3.748 no. 740.00 2773.52
Labours
Unskilled 5.622 no. 525.00 2951.55
Wood* 0.06575 m 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 9529.01
For 1 m 952.90
* Assuming timber and ballies will become unserviceable after being used for 8 times
C) For Beam-Depth of beam upto 30cm
Analyzed for: 10 m Norms S.N. 8-4-Ka
Rate per
Resources Level / Type Quantity Unit Amount Remarks
unit
Skilled 4 no. 740.00 2960.00
Labours
Unskilled 6 no. 525.00 3150.00
Wood* 0.06575 m 53558.00 3521.44
Materials
Nails 2.5 kg 113.00 282.50
Sub-Total 9913.94
For 1 m 991.39
* Assuming timber and ballies will become unserviceable after being used for 8 times