III. SEQUENCING: Arrange the following activities in sequence and answer properly the no.

of days, it will take with how many people and


how much labor will it cost.
a. b. Works/tasks c. No. of days e. No. of const worker d. Labor cost
1. Install formworks 2
2. mix.pour &cure concrete( 8
columns&beams)
3. Procurement materials 10
4. Staking & batter board layout 2
5. Site clearing 2
6. Carpentry installation of 2
formworks
7. CHB laying 6
8. Excavation 3
9. Install outside services 5
10. Carpentry works roof etc.. 10
11. Tinsmithry 8
12. Bending & erect of steel 6
13. Install & fabricate 10
doors/windows
14. Install lighting 6
15. Install plumbing rough in 5
16. Curing,pouring of concrete 8
(flooring)
17. Wainscoting 5
18. Painting 5
19. Finish & clean out 4
20. Project turn over 1

1. Arrange in sequence all the activities from start to finish, mark them A-T
2. Arrange the events of activities from start to finish
3. Compute number of days it will take to finish the given activity
4. Find the total labor cost of the given activity