Vous êtes sur la page 1sur 4

Global Warming

You Say?
OK, But What About
My Concrete?
by Robert A. Prisby

T here is much discussion and debate about weather.


The real importance is the effect of weather on what
we do and how we deal with it. Summer means
warmer weather and more concrete being placed. This ar-
placed; it is bad. Summer is the time of year when concrete
slab surfaces are at the greatest risk of early surface drying
and when some built-in defects are created.

ticle discusses some of the causes and effects of rapid drying Why should we care?
of concrete slabs in hot-weather conditions and suggests pre- The following is a brief listing of the surface defects related
ventative steps that are low cost and relatively easy to do. to early surface drying:
Concrete hardens by two processes: hydration and dehy- Craze cracking;
dration. Hydration is the chemical reaction between portland Plastic shrinkage cracking (Fig. 1);
cement and water; this is good. Dehydration is simply dry- Curling and warping of pavement slabs;
ing. When dehydration occurs shortly after fresh concrete is Crusting of the surface;

Fig. 1 Plastic
shrinkage cracking,
one of many surface
defects related to early
surface drying.
January 2001 1
Dusting; relative humidity, and wind speed) at ter in the top 1/2 in. (12.7 mm) of the
Difficult finishing or bad appear the time of day during concrete place- 10 x 10 ft (3.05 x 3.05 m) concrete slab
ance because ment. is 5.4 gal. (20.4 L). This water quan-
I cant close the surface, The following is an example of the tity is about 15% of the total volume
It feels like rubber when I try weather affecting surface drying. Two of the top 1/2 in. (12.7 mm).
to trowel it, loads of concrete were delivered at The afternoon placement was ex-
It is setting from the top down, 7:00 a.m. and 1:30 p.m. to place a posed to an evaporation rate more than
It is still jelly underneath, but driveway slab. The weather conditions triple that of the first. It was drying so
the surface is hard (set); on the job site at 7:00 a.m. in western quickly that virtually all of the water
Raveling of sawcuts due to prema - Pennsylvania (August 29, 1999) were in the top 1/2 in. (12.7 mm) would be
ture cutting. 66 F (19 C), wind speed 7 mph (11 kph), evaporated in less than two hours. It
Beyond this listing, early surface and 80% relative humidity when the was hardening through dehydration
drying also contributes to scaling, first truck arrived. All finishing was (drying) and the contractor did not
shrinkage cracking, and poor surface completed by 12:30 p.m. on this first know it. The surface shrinkage strain
durability. I believe that early surface load. Fortunately, the curing com- would be very large at a time when the
drying is a very significant yet prevent- pound was applied before lunch. concrete had virtually no strength to
able factor in many concrete surface A second load arrived at 1:30 p.m., resist this force. The afternoon slab
problems. The previous list of surface and the weather conditions were 76 F was extremely difficult to finish, crust-
defects answers the question: Why (24 C), wind speed 20 mph (32 kph), ing, and at great risk for those surface
should we care? and 39% relative humidity. These defects.
weather conditions might seem ideal The following is a brief description
Why and when does early for concrete placement, but they are of each of the factors affecting evapo-
surface drying occur? not because of rapid evaporation. The ration:
Rapid drying of the concrete occurs by evaporation rate had reached a very Relative humidity When relative
absorption of concrete mixture water dangerous level for the surface of the humidity changes from 90 to 50%,
by a dry subgrade, dry aggregates, or, concrete. The evaporation rate in- the rate of evaporation is increased
most importantly, evaporation of sur- creased from less than 3/4 gal. (2.8 L) five times; a further reduction of
face moisture on a warm, dry, and per hour to 2.5 gal. (9.5 L) per hour 10% increases this rate nine times.
windy day. High drying conditions are for the 10 x 10 ft (3.05 x 3.05 m) slab. Wind speed (Fig. 2) The evapo-
the result of the weather (temperature, Consider that the total mixture wa- ration rate is four times greater when

Fig. 2 Factors affecting evaporation rates (ACI 305R-99).

2 Concrete International
Fig. 3 A worker
blesses the con-
crete surface a
nonrecommended
practice.

the wind velocity increases from 0 to Knowledge concrete slab. I have seen this success-
10 mph (16 kph), and nine times Watch the Weather Channel the day fully done with inexpensive pressure
greater when the wind velocity in- be fore. Anytime you hear a forecast of washers turned to the maximum mist
creases to 25 mph (40 kph). wind speeds greater than 10 mph (16 kph), or spray setting. The fog (or mist) is
Concrete and air temperature relative humidity less than 50%, or tem- directed into the air above and upwind
When the temperature increases from peratures greater than 85 F (29 C), be of the slab. This fine fog must be car-
50 to 70 F (10 C), evaporation is prepared. ried by the wind over the concrete
doubled; if temperature increases to Know the conditions at your job site surface. The fog will not be able to be
90 F (32 C), evaporation is increased The Weather Channel may be fore- propelled very far through the air. The
four times. casting a 5 mph (8 kph) wind speed, but mist should only be enough to restore
All of these factors combine during if you are placing concrete along a road the sheen to the concrete surface, and
summer weather. The effect can be a while traffic is going by at 50 mph no droplets should impact the surface.
substantial change in evaporation rates (80 kph), a burst of wind blows with Also, specially designed fog mist
between one day and the next or be- every vehicle going by. nozzles are available for approximately
tween morning and afternoon on the Consider changing the placement $20 each. Never use a stream of water.
same day. schedule to a time when the weather is Never use an excess amount of water.
more favorable, typically earlier in the The goal is simply to control the rate of
What can a contractor do? morning. evaporation around the concrete by
Many articles that address this prob- Watch the concrete surface very raising the relative humidity and evapo-
lem have recommended sun shades, closely; the surface should maintain a rative cooling at the concrete surface.
wind screens, fog mists, and evapora- gloss to semigloss water sheen dur- Be ready to quickly apply the curing
tion retardants. In 20 years of job site ing the first few hours. If it quickly loses system. Minimize the time the surface
experience, I have never seen sun its sheen and looks like a flat, dry sur- is left unprotected from the rapid evapo-
shades or wind screens used, even in face, then it is drying too quickly. Take ration. If you are using a curing
equatorial climates. action. compound, consider applying a double
Unfortunately, I have too often seen coating to withstand the rapid drying
a bucket and a blessing brush to re- Equipment exposure.
store the water lost by evaporation Know how to use evaporation retar-
(Fig. 3). Most concrete professionals dants and have them ready to go in a Other concrete areas
understand that water applied by either pressure sprayer next to the concrete The same weather conditions affect
spraying the surface with a garden hose slab. Re-apply this material to maintain concrete highway pavement. Because
or blessing with a cup or a brush prob- the water sheen at the surface. Evapo- paving equipment is used to finish the
ably adds too much water in some ration retardants are different from surface, highway pavements have fewer
areas, not enough in others, and does surface retarders and water-reducing finish concerns. Rapid evaporation can
not address the root cause, which is set-retarding admixtures. Know the dif- be a significant factor in curling,
continued rapid evaporation. ference; surface retarders and retarding rideability, and profile of highway slabs.
The first thing a concrete contractor admixtures will aggravate rapid drying. Fortunately, it is very controllable by
needs to do is have the right knowl- Know how to properly broadcast a the same means discussed previously.
edge and equipment to deal with these fog mist in the area (Fig. 4). Have the A new software program sponsored by
situations ahead of time. fogging equipment set up upwind of the the Federal Highway Administration

January 2001 3
Summary
The good news is that rapid early drying
is preventable. It takes knowledge and a
few low-cost tools. We need to spread the
word so that we actively prevent these
surface defects. ACI 305R Hot Weather
Concreting, is an excellent reference for
additional information. ACIs Flatwork
Finisher Certification program teaches
the ways to handle these conditions.
References
ACI Committee 305, Hot Weather Concreting,
(ACI 305R-99), American Concrete Institute,
Farmington Hills, Mich., 1999, 20 pp.

Selected for reader interest by the editors.

* High-Performance Concrete (HPC) is concrete


that meets special combinations of performance
and uniformity requirements that cannot always be
achieved routinely using conventional constituents
and normal mixing, placing, and curing practices.
Thus, a high-performance concrete is a concrete
in which certain characteristics are developed for
a particular application and environment. Examples
Fig. 4 Fog misting of the concrete surface with a pres- of characteristics that may be considered critical
sure washer. in an application are: ease of placement, compaction without segregation,
early-age strength, long-term mechanical properties, permeability, density,
heat of hydration, toughness, volume stability, and long life in severe envi-
called Hiperpave illustrates this point and other issues af- ronments. ( Editor)
fecting early-age concrete conditions.
Control of rapid evaporation is especially important with ACI member Robert A. Prisby has a BS
high-performance concrete.* High-performance concrete from Pennsylvania State University, over 20
typically has low initial water contents (low w/cm) and typi- years of experience in concrete construc-
cally very low bleeding rates; therefore, it is much more tion, and has served on several national ACI
susceptible and sensitive to these weather conditions. The and ASTM technical committees. He is past
Pennsylvania Department of Transportations AAA mixture president of the Pittsburgh ACI Chapter.
is included in this group of concrete that is sensitive and
susceptible to rapid evaporation.

4 Concrete International

Vous aimerez peut-être aussi